PROD A PROD B PROD C PROD D TOTAL

requerimiento diario 300 240 180 60 780


Cantidad de Paquete 15 15 15 15 60
N kanbas 20 16 12 4 52
pitch 17 17 17 17

Reduccion de paquetes 5 4 3 1

INCREMENTO DEL PITCH PRODUCTO


6:00 6:17 A 300 A
6:17 6:34 A
6:34 6:51 A
6:51 7:08 A
7:08 7:25 A
7:25 7:42 B
7:42 7:59 B
7:59 8:16 B
8:16 8:33 B
8:33 8:50 C
8:50 9:07 C
9:07 9:24 C
9:24 9:41 D
9:41 9:58 A
9:58 10:15 A
10:15 10:32 A
10:32 10:49 A
10:49 11:06 A
11:06 11:23 B
11:23 11:40 B
11:40 11:57 B
11:57 12:14 B
12:14 12:54 DESCANSO
12:54 13:11 C
13:11 13:28 C
13:28 13:45 C
13:45 14:02 D CAMBIO DE TURNO
14:02 14:19 A
14:19 14:36 A
14:36 14:53 A
14:53 15:10 A
15:10 15:27 A
15:27 15:44 B
15:44 16:01 B
16:01 16:18 B
16:18 16:35 B
16:35 16:52 C
16:52 17:09 C
17:09 17:26 C
17:26 17:43 D
17:43 18:23 DESCANSO
18:23 18:40 A
18:40 18:57 A
18:57 19:14 A
19:14 19:31 A
19:31 19:48 A
19:48 20:05 B
20:05 20:22 B
20:22 20:39 B
20:39 20:56 B
20:56 21:13 C
21:13 21:30 C
21:30 21:47 C
21:47 22:04 D
turnos 2
duracion turno 8 horas REDUCCION DE PAQUETE = NUMERO KANBANS / CANTIDAD DE PRO
descanso 40 minutos

tiempo disponible 880 minutos

tatk time 1.12820513 minutos


takt time 67.6923077 segundos
NBANS / CANTIDAD DE PRODUCTOS
0.035
DPMO 70000
D 7
O 5 DPO 0.07
U 20
1000000 YIELD 0.93

NIVEL SIGMA 2.96