espersor de asfalto
0.25
e = 0.25
n´= 1.70
DATOS:
Ancho = 4.1 m
Luz Libre L = 22.8 m
Tren de Cargas = HL-93
Cajuela C = 0.6 m
f´c = 280 kg/cm^2
fy = 4200 kg/cm^2
Carga muerta de la baranda = 80 kg-ml
Carga viva de la baranda = 150 kg/ml
Espesor de asfalto e = 0m
Piso terminado = 0.1 tn/m^2
Número de Vigas = 3
1. PRESIMENSIONAMIENTO
1.1. Predimensionamiento de la Viga
a) Luz de Cálculo de la viga
L´ = L + c = 23.40
S´= 2.05
b) Ancho de la Viga
b = 0.02L´*(√S´)
b= 0.67007 m Usaremos b = 70.00 cm
S = S´- b = 1.35 m
c) Peralte de la Viga
Según MTC
e = (S+3000)/30 =
e= 1350 + 3000
30
e= 14.5 cm Usaremos = 20.5 cm 25
2. DISEÑO DE LA LOSA
2.1 Ancho Efectivo de las Franjas Longitudinales
EN VOLADOS
Peso Propio = 0.5 x 2.5 x 1 = 1.25
P.Piso Term= 0.1 x 1 = 0.10
D2 = 1.35 Tn/m
b) Carga Viva
S/C = 0.36 x 1 = 0.36 Tn/m
PD 0.26
PL 0.15
I= 0.33
Barandas Barandas
PD = 0.26 D2 = 1.35 D2 = 1.35 PD = 0.26 Tn/m
PL = 0.15 L2 = 0.36 L2 = 0.36 PL = 0.15 Tn/m
D1 = 0.625
S/C vehicular
S´= 0.95 S´= 2.05 S´= 2.05 S´= 0.95 Luz entre ejes
a) En Tramos Intermedios
Por Carga Muerta
MD = D1S^2 = 0.625 1.35 ^2 = 0.11391 Tn/m
10 10
Para eje tandem = 5.6 tn
Por S/C Vehicular 7.4 = Peso del Neumático
ML = 0.8(S+0.6)P = 0.8 1.35 + 0.6 7.4 = 1.18 Tn-m
9.75 9.75
b) En Tramos en Volados
Por Carga Muerta
(-)MD = D2S^2 + PDS´ = 1.35 0.600 ^2 + 0.26 0.600 = 0.399 Tn-m
2 2
3.20 Tn-m
Mu = 1.598 Tn-m
a) Por Servicio
2𝑀𝑠
𝑑𝑚𝑖𝑛 =
𝑓𝑐. 𝑘. 𝐽. 𝑏
MS = MD + ML + MI = 0.11391 + 1.18 + 0.39
MS = 1.69 Tn-m
𝐸𝑠 2 x 10^6 = 8
𝑛= =
𝐸𝑐 15000√f´c
𝑘 1 - 0.372 = 0.87592
𝐽=1 − =
3 3
As = 4.83 a= 0.81
As = 4.10 a= 0.68
As = 4.09 a= 0.68
As = 4.09 a= 0.68
As = 4.09 cm²
Espaciamiento
As = 2.73 a= 0.45
As = 2.03 a= 0.34
As = 2.03 a= 0.34
As = 2.03 a= 0.34
As = 2.73 cm²
Espaciamiento
𝐷𝑆
𝑉𝐷 = = 0.11391 1.35 = 0.077 Tn
2 2
4.8
3.40
E= 5.16 m (VIA)
P = 14.78 = 2.86
E 5.16
d) Corte Ultimo
Vu = n(1.25VD + 1.75VL + 1.75VI)
Vu = 1.10 x( 1.25 x 0.08 + 1.75 x 4.21 + 1.75 x 1.39 )
Vu = 10.91 Tn
1.95 m
0.70 m
0.25
0.25
1.7
0.95 1.03
b) Carga Viva
PL L2 ml
Carga Viva en Vereda = 0.36 x 1 = 0.36
Carga Viva en Baranda = 0.15 = 0.15
0.51 Tn/m Carga Viva de la Baranda
R = 2P 2.05 R = 2P
RA X 23.40 -X
X+ 4.3 19.10 -X
RA = 9.45 − 0.3802 X
ii)
λP = 3.97073 λP = 3.97 λP´ = 0.95512 9.00 ≤ x ≤ 19.1
9.00 4.3
RA X 23.40 −X
X+ 4.3 19.1 −X
X − 9.0 32.4 −X
23.4
RA = 10.25 − 0.3802 X
ML = 41.66 Tn-m
Eje Tandem
X 23.40 − X
RA
x + 1.2 22.20 −X
x 23.40 - x
23.40
RA = 21.83 - 0.96X
Mo = 21.83 - 0.96X X = 0
M= 21.83X - 0.96X^2 = 0
23.40
d) Por Impacto
x= 0.3
RA = (x=3) = 21.54 0.54 = 5.78 Tn
2 Número de ruedas
22.8
d) POR IMPACTO
As = 109.31 a= 27.6
As = 98.42 a= 24.8
As = 97.64 a= 24.6
As = 97.58 a= 24.6
0.7 𝑓´𝑐
𝐴𝑠 𝑚í𝑛 = 𝑏𝑑 = 36.1158 cm^2 → 4 Ø 1" + 5 Ø 3/4" ok 0.75ʆb = 0.02125
𝑓𝑦
𝐴𝑠 𝑚á𝑥 = 0.75ʆ𝑏. 𝑏. 𝑑 = 275.19 cm^2 ok
S= 28
84.61
h/2 = 97.5
10 Ø 1" = 61.2
12.89
4 10 Ø 1" = 61.2
dc = 9.08 cm
S≤ 300 mm
250
𝑆 ≤ 300 = 357.14
𝑓𝑠
S= 28 cm ≤ 35.7143 cm ok
NECESITA ESTRIBOS
Vs = Vn - Vc = 120.59 - 114.85
0.85
Vs = Vn - Vc = 27.02 Tn
c) Verificación de la Sección
Vs = 27.02 Tn ≤ 2.1√f´c.bw.d
≤ 2.1 x√ 280 x 70 x 185
≤ 455.06 Tn ok
Vs = 27.02 Tn ≤ 2.1√f´c.bw.d
≤ 1.1 x√ 280 x 70 x 185
≤ 238.36 Tn
Smáx = d/2 = 92.5
ó
60 cm
Espaciamiento "S"
Usaremos: 1/2" @ 20 cm
S= 20 cm < S= 44.23 cm ok
Si Usamos: S= 30 cm
Vn = Vc + Vs
Vn = 114.85 + 66.82 = 181.67 Tn
Si Usamos S= 40 cm
Vu = 120.59
Vu = 154.42
(S= 30 )
Vu = 140.22
(S= 40 )
S= 20
S= 30
S = 40
11.4 m
0.8 0.6 10 m
Relación de Triángulos
Para S = 20 cm
120.59 = 154.42
11.4 11.4 - d
d= -3.2 m
Para S = 30 cm
154.42 = 140.22
7.24 7.24 - d
d= 0.67 m
Para S = 40 cm
1.95 m
0.70 m
0.25
0.25
1.7
1.025 1.025
a) Carga Muerta
b) Carga Viva
PL L2 ml
Carga Viva en Vereda = 0.36 x 1 = 0.36
Carga Viva en Baranda = 0.15 1 = 0.15
0.51 Tn/m
λ = 0.32944 P
λ= 0.32944
RA X 23.4 -X
X+ 4.3 19.1 -X
RA = 5.80 − 0.23343 X
ii)
λP = 2.43787 λP = 2.44 λP´ = 0.58641 9.00 ≤ x ≤ 19.1
9.00 4.3
RA X 23.4 −X
X+ 4.3 19.1 −X
X − 9.0 32.4 −X
23.4
RA = 6.29 − 0.23343 X
ML = 25.58 Tn-m
Eje Tandem
X 23.4 − X
RA
x + 1.2 22.2 −X
x 23.4 - x
23.4
RA = 21.83 - 0.96X
Mo = 21.83 - 0.96X X = 0
M= 21.83X - 0.96X^2 = 0
23.4
d) Por Impacto
x
x= 0.3 + 4.3 = 4.6
RA (x=4.53) = 5.22 = VL
x= 0.3
22.8
d) POR IMPACTO
As = 109.31 a= 27.6
As = 98.42 a= 24.8
As = 97.64 a= 24.6
As = 97.58 a= 24.6
0.7 𝑓´𝑐
𝐴𝑠 𝑚í𝑛 = 𝑏𝑑 = 36.1158 cm^2 → 4 Ø 1" + 5 Ø 3/4" ok 0.75ʆb = 0.02125
𝑓𝑦
𝐴𝑠 𝑚á𝑥 = 0.75ʆ𝑏. 𝑏. 𝑑 = 275.19 cm^2 ok
S= 28
84.61
h/2 = 97.5
10 Ø 1" = 61.2
12.89
4 10 Ø 1" = 61.2
dc = 9.08 cm
S≤ 300 mm
250
𝑆 ≤ 300 = 357.14
𝑓𝑠
S= 28 cm ≤ 35.7143 cm ok
NECESITA ESTRIBOS
Vs = Vn - Vc = 99.05 - 114.85
0.85
Vs = Vn - Vc = 1.68 Tn
c) Verificación de la Sección
Vs = 1.68 Tn ≤ 2.1√f´c.bw.d
≤ 2.1 x√ 280 x 70 x 185
≤ 455.06 Tn ok
Vs = 1.68 Tn ≤ 2.1√f´c.bw.d
≤ 1.1 x√ 280 x 70 x 185
≤ 238.36 Tn
Smáx = d/2 = 92.5
ó
60 cm
Espaciamiento "S"
Usaremos: 1/2" @ 20 cm
S= 20 cm < S= 44.23 cm ok
Si Usamos: S= 30 cm
Vn = Vc + Vs
Vn = 114.85 + 66.82 = 181.67 Tn
Si Usamos S= 40 cm
Vu = 99.05
Vu = 154.42
(S= 30 )
Vu = 140.22
(S= 40 )
S= 20
S= 30
S = 40
22.8 m
99.05 = 154.42
22.8 22.8 - d
d= -12.7 m
Para S = 30 cm
154.42 = 140.22
7.24 7.24 - d
d= 0.67 m
Para S = 40 cm
DISEÑO DE LA BARANDA
h´ = 0.75
0.5
0.5 0.25
Lt = L´ + 2C + N°(v) x h´
𝐿´ + 2𝑐
𝑁° 𝑣 = = 22.8 + 2 x 0.6 = 30.00 = 30
𝑒 0.8
Metrado de Cargas
Carga Vertical
Wv = 150 + 7.75 = 157.75 kg/m
Carga Horizontal
WH = 225 kg/m
Tubo de = 3"
𝑊𝐿2
+ 𝑀𝐷 = =
14
𝑊𝐿2
− 𝑀𝐿 = =
10
Verificación de la Sección
Ƴt = 800 kg/cm^2
I= ¶ ( 8.12 ^4 - 7.62 ^4 )
64
I= 47.90 cm^4
Vr = ¶ x R x t x T
t= 0.25 cm
T= 60 kg/cm^2
R= 4.06 cm
Vr = ¶ x 4.06 x 0.25 x 60
Vr = 191.32 kg
Corte Actuante
Vmayor
Vact = WL 1.15
2
Vact = 103.5 kg
DISEÑO DE LA COLUMNETA
0.25
Fuerzas Actuantes
Corte Resistente
Vr = ¶ x R x t x T
t= 0.25 cm
T= 60 kg/cm^2
R= 4.06 cm
Vr = ¶ x 4.06 x 0.25 x 60
Vr = 191.32 kg
Por Flexión
𝛾𝑚á𝑥 . 𝐼
𝑀𝑚á𝑥 = = 94.39 kg-m > 90 kg-m ok
𝐶
DISEÑO DE DIAFRAGMA
1) Predimensionamiento
60 y 80%
h= 1.95 x 0.6
h= 1.17 = 0.85
b= 0.85 = 0.425 trabajamos con = 45
2
23.40 m
3.71 0.35
4.06
Diseño de Diafragmas
Intermedios
Metrado de Cargas
Peso Propio = 0.85 x 0.35 x 2.5 = 0.74 Tn/m
Momento de Diseño
(+) Mu = Mpp + Tv = 0.44 + 4.54038 = 4.98 Tn-m
Por Corte
Corte por Peso Propio
𝐿
𝑉𝑢 𝑝𝑝 = 1.4𝑊𝑝
2
Vu pp = 1.4 x 0.74 x 2.05 = 1.07 Tn-m
2
𝑇𝑢
𝑉𝑢 = 𝑉𝑢 𝑝𝑝 + = 1.07 + 4.54038 = 3.28 Tn
𝑆 2.05
Diseño Por Flexión
Mu = 4.98 Tn-m
b= 35 cm
d= 79 cm
a= 26.3333
As = Mu a= As.fy
Øfy(d - a/2) 0.85.f´c.b
As = 2.00 a= 1.01
As = 1.68 a= 0.85
As = 1.68 a= 0.85
As = 1.68 a= 0.85
0.7 𝑓´𝑐
𝐴𝑠 𝑚í𝑛 = 𝑏𝑑 = 7.71 cm^2 → 3 Ø 1" + 3 Ø 3/4" falso 0.75ʆb = 0.02125
𝑓𝑦
𝐴𝑠 𝑚á𝑥 = 0.75ʆ𝑏. 𝑏. 𝑑 = 58.75 cm^2 ok