HOJA METRADO DE ARQUITECTURA - BLOQUE A

"RECONSTRUCCION DEL SERVICIO DE EDUCACION PRIMARIA EN LA INSTITUCION


PROYEC
EDUCATIVA Nº20174 DEL DISTRITO DE PACARAN - PROVINCIA DE CAÑETE -
TO :
DEPARTAMENTO DE LIMA"
UBICACI
PACARAN - CAÑETE - LIMA
ÓN:
02 ARQUITECTURA
02.01 MUROS, TABIQUES DE ALBAÑILERIA
02.01.01 Muro de Ladrillo KK de Soga C:A 1:4 de 24 X 13 X 9 cm M2
Ubicación Unids largo ancho altura Area Sub total TOTAL
BLOQUE A
Primer nivel
EJE B-B 1.00 13.00 1.20 15.60
1.00 1.40 3.59 5.03
EJE A-A 1.00 18.10 3.59 64.98
EJE 1-1,7-7 2.00 5.55 3.59 39.85
EJE 3-3,5-5 2.00 5.25 3.59 37.70
Segundo nivel
EJE B-B 1.00 13.00 1.20 15.60
1.00 1.40 3.59 5.03
EJE A-A 1.00 18.10 3.59 64.98
EJE 1-1,7-7 2.00 5.55 3.59 39.85
EJE 3-3,5-5 2.00 5.25 3.59 37.70
PASADIZO 1.00 24.45 1.20 29.34
1.00 1.30 1.20 1.56
azotea
2.00 24.45 1.20 58.68
1.00 8.50 1.20 10.20
+7 % desperdicio 426.08
29.83 455.90 455.90

02.01.02 alambre ·08 de refuerzo horizontal en muros KG 19.51

02.01.03 juntas de tecnopor e=1" ML


Ubicación Unids largo ancho altura ml Sub total TOTAL
primer nivel
25.00 3.59 89.75
segundo nivel
25.00 3.59 89.75
179.50 179.50

02.02 REVOQUES Y REVESTIMIENTOS


02.02.01 Tarrajeo en interiores mezcla C:A - 1:5 M2
Ubicación Unids largo ancho altura Area Sub total TOTAL
Primer nivel
EJE B-B 1.00 13.00 1.20 15.60
1.00 1.40 3.59 5.03
EJE A-A 1.00 18.10 3.59 64.98
EJE 1-1,7-7 2.00 5.55 3.59 39.85
EJE 3-3,5-5 2.00 5.25 3.59 37.70
Segundo nivel
EJE B-B 1.00 13.00 1.20 15.60
1.00 1.40 3.59 5.03
EJE A-A 1.00 18.10 3.59 64.98
EJE 1-1,7-7 2.00 5.55 3.59 39.85
EJE 3-3,5-5 2.00 5.25 3.59 37.70
PASADIZO 1.00 24.45 1.20 29.34
1.00 1.30 1.20 1.56
azotea
2.00 24.45 1.20 58.68
1.00 8.50 1.20 10.20
+7 % desperdicio 426.08
29.83 455.90 455.90
02.02.02 Tarrajeo en exteriores mezcla C:A - 1:5 M2
Ubicación Unids largo ancho altura Area Sub total TOTAL
Primer nivel
EJE B-B 1.00 13.00 1.20 15.60
1.00 1.40 3.59 5.03
EJE A-A 1.00 18.10 3.59 64.98
EJE 1-1 1.00 5.55 3.59 19.92
Segundo nivel
EJE B-B 1.00 13.00 1.20 15.60
1.00 1.40 3.59 5.03
EJE A-A 1.00 18.10 3.59 64.98
EJE 1-1 1.00 5.55 3.59 19.92
PASADIZO 1.00 24.45 1.20 29.34
1.00 1.30 1.20 1.56
azotea
2.00 24.45 1.20 58.68
1.00 8.50 1.20 10.20
+7 % desperdicio 310.84
21.76 332.60 332.60

02.02.03 Tarrajeo en Columnas C:A - 1:5 M2


Ubicación Unids largo ancho altura Area Sub total TOTAL
primer piso
4.00 2.30 3.89 35.79
10.00 2.90 3.89 112.81
segundo piso
4.00 2.30 3.29 30.27
10.00 2.90 3.29 95.41
+7 % desperdicio 274.28
19.20 293.48 293.48

02.02.04 Tarrajeo en Columnetas C:A - 1:5 M2


Ubicación Unids largo ancho altura Area Sub total TOTAL
PRIMER PISO 15.00 0.50 1.20 9.00
20.00 0.50 3.00 30.00
SEGUNDO PISO
25.00 0.50 1.20 15.00
20.00 0.50 3.00 30.00
AZOTEA
28.00 0.50 0.85 11.90
95.90
+5 % desperdicio 4.80 100.70 100.70

02.02.05 Tarrajeo en Vigas, mezcla C:A - 1:5 M2


Ubicación Unids largo ancho altura Area Sub total TOTAL
PISO 1
2.00 26.70 1.05 56.07
2.00 8.50 1.55 26.35
2.00 8.50 1.40 23.80
1.00 26.70 0.70 18.69
PISO 2
2.00 26.70 1.05 56.07
2.00 8.50 1.55 26.35
2.00 8.50 1.40 23.80
1.00 26.70 0.70 18.69
+7 % desperdicio 249.82
17.49 267.31 267.31

02.02.06 Tarrajeo en Viguetas, mezcla C:A - 1:5 M2


Ubicación Unids largo ancho altura Area Sub total TOTAL
PISO 1
Viguetas a 1.00 14.34 0.30 4.30
6.00 3.05 0.30 5.49
4.00 2.07 0.30 2.48
2.00 2.02 0.30 1.21
PISO 2
Viguetas a 1.00 14.34 0.30 4.30
6.00 3.05 0.30 5.49
4.00 2.07 0.30 2.48
2.00 2.02 0.30 1.21
PASADIZO 2.00 26.70 0.30 16.02
AZOTEA
2.00 26.70 0.30 16.02
1.00 9.50 0.30 2.85
+5 % desperdicio 61.87
3.09 64.96 64.96

02.02.07 Vestiduras de Derrames en Vanos mezcla 1:5 M


Ubicación Cantid. largo ancho altura Sub total TOTAL
BLOQUE A
P1 6.00 8.68 52.08
V-1 2.00 11.60 23.20
V-2 6.00 7.80 46.80
V-3 6.00 9.60 57.60
V-4 6.00 8.80 52.80
V-5 4.00 11.80 47.20
+5 % desperdicio 279.68
13.98 293.66 293.66

02.02.08 bruñas de 1x1cm x 5mm M


Ubicación Cantid. largo ancho altura Sub total TOTAL
PISO 1 6.00 7.90 47.40
6.00 4.06 24.36
6.00 7.68 46.08
2.00 17.78 35.56
4.00 12.58 50.32
8.00 12.78 102.24
PISO 2 6.00 7.90 47.40
6.00 4.06 24.36
6.00 7.68 46.08
2.00 17.78 35.56
4.00 12.58 50.32
8.00 12.78 102.24
PASADIZO 0.00
12.00 7.90 94.80
1.00 5.00 5.00
AZOTEA 0.00
24.00 7.90 189.60
6.00 7.90 47.40
948.72 948.72

02.03 CIELO RASOS


02.03.01 Cielorrasos con Tarrajeo con Mezcla de Cemento sobre Losa Aligerada M2
Ubicación unids largo ancho altura Area Sub total TOTAL
PISO 1
6.00 8.05 4.00 193.20
PISO 2
6.00 8.05 4.00 193.20
+7 % desperdicio 386.40
27.05 413.45 413.45

02.04 PISOS Y PAVIMENTOS


02.04.01 CONTRAPISOS
02.04.01. Contrapiso - Concreto P/ f'c=175 kg/cm2 e=10 cm M2
Ubicación unids largo ancho altura Area Sub total TOTAL
PRIMER PISO
aulas 1,2,3 6.00 7.10 4.20 178.92
SEGUNDO PISO
aulas 4,5,6 6.00 7.10 4.20 178.92
pasadizo 1.00 26.55 1.65 43.81
+7 % desperdicio 401.65
28.12 429.76 429.76

02.04.01 PISOS
02.04.01. Piso de porcelanato de 60 x 60cm alto transito M2
Ubicación Cantid. largo ancho altura Area Sub total TOTAL
PRIMER PISO
aulas 1,2,3 6.00 7.10 4.20 178.92
SEGUNDO PISO
aulas 4,5,6 6.00 7.10 4.20 178.92
pasadizo 1.00 26.55 1.65 43.81
+7 % desperdicio 401.65
28.12 429.76 429.76

02.05 OTROS
02.05.01 Canaleta pluvial en piso a media caña con acabado y bruñado M
Ubicación Cantid. largo ancho altura Sub total TOTAL
AZOTEA
2.00 26.55 53.10

+7 % desperdicio 53.10
3.72 56.82 56.82

02.06 CONTRAZOCALOS
02.06.01 Contrazocalo de Porcelanato de H=7cm M
Ubicación Cantid. largo ancho altura Longitud Sub total TOTAL
1 PISO
aulas 1,2,3 3.00 40.95 122.85
2 PISO
aulas 4,5,6 3.00 40.95 122.85
pasadizo 1.00 26.54 26.54
1.00 1.93 1.93
+5 % desperdicio 274.17
13.71 287.88 287.88

02.07 COBERTURAS
02.07.01 cobertura con ladrillo pastelero con mortero M2
Ubicación Cantid. largo ancho altura Longitud Sub total TOTAL
AZOTEA
1.00 26.55 9.20 244.26
+5 % desperdicio 244.26
12.21 256.47 256.47

02.07.02 Impermeabilizante de techo con pintura asfaltica M2


Ubicación Cantid. largo ancho altura Longitud Sub total TOTAL
AZOTEA
1.00 26.55 9.20 244.26
+5 % desperdicio 244.26
12.21 256.47 256.47

02.08 CARPINTERIA DE MADERA


02.08.01 Suministro e instalacion de puerta de madera cedro M2
Ubicación Cantid. largo ancho altura Area Sub total TOTAL
P1 6.00 1.00 2.45 14.70 14.70 14.70

02.09 CARPINTERIA METALICA Y HERRERIA


02.09.01 Protector metalico para ventanas M2
Ubicación Cantid.
largo ancho altura Area Sub total TOTAL
Vanos
V-1 2.00 3.50 2.30 16.10
V-2 6.00 1.60 2.30 22.08
V-3 6.00 3.50 0.80 16.80
V-4 6.00 3.60 0.80 17.28
V-5 4.00 3.60 2.30 33.12
105.38 105.38

02.10 CERRAJERIA
02.10.01 Bisagras aluminizada capuchina pesada de 4" x 4" PZA
Ubicación Cantid. unidades Total Sub total TOTAL
BLOQUE A
P1 6.00 3.00 18.00 18.00 18.00

02.11 CERRADURAS
02.11.01 Cerradura Tipo Forte 3 golpes PZA
Ubicación Cantid. unidades Total Sub total TOTAL
BLOQUE A
P1 6.00 1.00 6.00 6.00 6.00

02.12 VIDRIOS, CRISTALES Y SIMILARES


02.12.01 Vidrio templado de 6mm p/sistema directo M2
Ubicación Cantid. largo ancho altura total Sub total TOTAL
V-1 2.00 3.50 2.30 16.10
V-2 6.00 1.60 2.30 22.08
V-3 6.00 3.50 0.80 16.80
V-4 6.00 3.60 0.80 17.28
V-5 4.00 3.60 2.30 33.12
105.38 105.38

02.13 PINTURA
02.13.01 Pintura latex en muros interiores 02 manos M2
Ubicación Unids largo ancho altura Area Sub total TOTAL
BLOQUE A
Primer nivel
EJE B-B 1.00 13.00 1.20 15.60
1.00 1.40 3.59 5.03
EJE A-A 1.00 18.10 3.59 64.98
EJE 1-1,7-7 2.00 5.55 3.59 39.85
EJE 3-3,5-5 2.00 5.25 3.59 37.70
Segundo nivel
EJE B-B 1.00 13.00 1.20 15.60
1.00 1.40 3.59 5.03
EJE A-A 1.00 18.10 3.59 64.98
EJE 1-1,7-7 2.00 5.55 3.59 39.85
EJE 3-3,5-5 2.00 5.25 3.59 37.70
PASADIZO 1.00 24.45 1.20 29.34
1.00 1.30 1.20 1.56
azotea
2.00 24.45 1.20 58.68
1.00 8.50 1.20 10.20
+7 % desperdicio 426.08
29.83 455.90 455.90

02.13.02 Pintura latex en muros exteriores 02 manos M2


Ubicación Unids largo ancho altura Area Sub total TOTAL
Primer nivel
EJE B-B 1.00 13.00 1.20 15.60
1.00 1.40 3.59 5.03
EJE A-A 1.00 18.10 3.59 64.98
EJE 1-1 1.00 5.55 3.59 19.92
Segundo nivel
EJE B-B 1.00 13.00 1.20 15.60
1.00 1.40 3.59 5.03
EJE A-A 1.00 18.10 3.59 64.98
EJE 1-1 1.00 5.55 3.59 19.92
PASADIZO 1.00 24.45 1.20 29.34
1.00 1.30 1.20 1.56
azotea
2.00 24.45 1.20 58.68
1.00 8.50 1.20 10.20
+7 % desperdicio 310.84
21.76 332.60 332.60

02.13.03 Pintura latex en columnas, Columnetas, derrames 2 manos M2


Ubicación Unids largo ancho altura Area Sub total TOTAL
COLUMNAS
PRIMER PISO
4.00 2.30 3.89 35.79
10.00 2.90 3.89 112.81
SEGUNDO PISO
4.00 2.30 3.29 30.27
10.00 2.90 3.29 95.41
COLUMNETAS
PRIMER PISO 15.00 0.50 1.20 9.00
20.00 0.50 3.00 30.00
SEGUNDO PISO
25.00 0.50 1.20 15.00
20.00 0.50 3.00 30.00
AZOTEA
28.00 0.50 0.85 11.90
DERRAMES
P1 6.00 8.68 0.15 7.81
V-1 2.00 11.60 0.15 3.48
V-2 6.00 7.80 0.15 7.02
V-3 6.00 9.60 0.15 8.64
V-4 6.00 8.80 0.15 7.92
V-5 4.00 11.80 0.15 7.08
+7 % desperdicio 412.13
28.85 440.98 440.98

02.13.04 Pintura latex en vigas y viguetas, derrames 2 manos M2


Ubicación Unids largo ancho altura Area Sub total TOTAL
VIGAS
PISO 1
2.00 26.70 1.05 56.07
2.00 8.50 1.55 26.35
2.00 8.50 1.40 23.80
1.00 26.70 0.70 18.69
PISO 2 0.00
2.00 26.70 1.05 56.07
2.00 8.50 1.55 26.35
2.00 8.50 1.40 23.80
1.00 26.70 0.70 18.69
VIGUETAS
PISO 1
Viguetas a 1.00 14.34 0.30 4.30
6.00 3.05 0.30 5.49
4.00 2.07 0.30 2.48
2.00 2.02 0.30 1.21
PISO 2
Viguetas a 1.00 14.34 0.30 4.30
6.00 3.05 0.30 5.49
4.00 2.07 0.30 2.48
2.00 2.02 0.30 1.21
PASADIZO 2.00 26.70 0.30 16.02
AZOTEA
2.00 26.70 0.30 16.02
1.00 9.50 0.30 2.85
+7 % desperdicio 311.69
21.82 333.50 333.50
02.14 PINTURA DE CIELOS RASOS
02.14.01 Pintura Latex en Cielorraso 02 manos M2
Ubicación unids largo ancho altura Area Sub total TOTAL
PISO 1
ENTRE EJE A, B, C, D, E, F, G. 6.00 8.05 4.00 193.20
PISO 2
ENTRE EJE A, B, C, D, E, F, G. 6.00 8.05 4.00 193.20
+7 % desperdicio 386.40
27.05 413.45 413.45

02.15 PINTURA EN MADERA


02.15.01 Pintura en puertas de madera con barniz 2 manos M2
Ubicación Cantid. caras ancho altura Area Sub total TOTAL
BLOQUE A
P1 6.00 1.00 2.45 14.70
+7 % desperdicio 14.70
1.03 15.73 15.73

02.16 VARIOS
02.16.01 Juntas c/tecknoport y jebe microporoso e=1" M
Ubicación Cantid. long ancho altura Longitud Sub total TOTAL
primer nivel
25.00 3.59 89.75
segundo nivel
25.00 3.59 89.75
179.50 179.50

02.16.02 Tachos de polietileno para reciclaje UND


Ubicación Cantid. long ancho altura und Sub total TOTAL
BLOQUE A
Aulas 6.00 6.00 6.00 6.00

02.16.03 Junta/lamina metalica de 4"x3/16" para separacion sismica entre bloqueM


Ubicación Cantid. long ancho altura Longitud Sub total TOTAL
BLOQUE A
2.00 3.89 7.78 7.78 7.78

02.16.04 tapa junta/metalica en pisos M


Ubicación Unids largo ancho altura Sub total TOTAL
BLOQUE A
2.00 3.50 7.00 7.00 7.00

02.16.05 tapa junta/metalica en techo M


Ubicación Cantid. long ancho altura Longitud Sub total TOTAL
BLOQUE A
2.00 3.89 7.78 7.78 7.78

02.16.06 pantalla acrilica de 4m x 1.20m inc. Instalacion UND


Ubicación Cantid. long ancho altura Longitud Sub total TOTAL
BLOQUE A
Aulas 6.00 6.00 6.00 6.00

02.16.07 Limpieza final de obra M2


Ubicación Cantid. long ancho altura Longitud Sub total TOTAL
BLOQUE A
1.00 26.70 7.40 197.58 197.58 197.58

02.16.08 cortinas plegables lavables inc coporte UND


Ubicación Unids largo ancho altura Sub total TOTAL
BLOQUE A 12.00 12.00 12.00
HOJA METRADO DE ARQUITECTURA - BLOQUE B

"RECONSTRUCCION DEL SERVICIO DE EDUCACION PRIMARIA EN LA INSTITUCION


PROYEC
EDUCATIVA Nº20174 DEL DISTRITO DE PACARAN - PROVINCIA DE CAÑETE -
TO :
DEPARTAMENTO DE LIMA"
UBICACI
PACARAN - CAÑETE - LIMA
ÓN:
02 ARQUITECTURA
02.01 MUROS, TABIQUES DE ALBAÑILERIA
02.01.01 Muro de Ladrillo KK de Soga C:A 1:4 de 24 X 13 X 9 cm
Ubicación Unids largo ancho altura Area
BLOQUE B
PRIMER NIVEL
SS.HH
EJE A-A 1.00 5.11 2.49 12.72
EJE B-B 1.00 2.15 3.29 7.07
EJE B'-B' 2.00 2.20 3.29 14.48
EJE 8-8 1.00 5.15 3.29 16.94
EJE 8'-8' 1.00 10.70 3.29 35.20
EJE 9-9 1.00 5.15 3.29 16.94
ESCALERA
EJE A-A 1.00 3.20 3.29 10.53
1.00 3.30 3.29 10.86
SALA DE USOS MULTIPLES
EJE 10-10 1.00 5.15 3.29 16.94
EJE 15-15 1.00 3.44 3.29 11.32
EJE A-A 1.00 14.97 2.49 37.28
EJE B-B 1.00 7.66 3.29 25.20
1.00 5.87 1.20 7.04
CUARTO DE MAQUINAS - S.H
EJE C'-C' 1.00 3.15 3.29 10.36
2.00 1.90 2.49 9.46
EJE C-C 1.00 5.96 3.29 19.61
EJE 13-13, 15-15 2.00 0.72 3.29 4.74
EJE 13'-13' 1.00 2.40 3.29 7.90
SALA DE PROFESORES
EJE 13-13 1.00 0.40 3.29 1.32
1.00 1.62 1.20 1.94
EJE 15-15 1.00 3.25 2.49 8.09
EJE D-D 1.00 6.20 3.29 20.40
COCINA
EJE 13-13 1.00 0.90 3.29 2.96
1.00 1.90 1.20 2.28
EJE 15-15 1.00 3.90 2.49 9.71
EJE E-E 1.00 6.50 3.29 21.39
SEGUNDO NIVEL
SS.HH
EJE A-A 1.00 5.11 2.49 12.72
EJE B-B 1.00 2.15 3.29 7.07
EJE B'-B' 2.00 2.20 3.29 14.48
EJE 8-8 1.00 5.15 3.29 16.94
EJE 8'-8' 1.00 10.70 3.29 35.20
EJE 9-9 1.00 5.15 3.29 16.94
ESCALERA
EJE A-A 1.00 3.20 3.29 10.53
1.00 3.30 3.29 10.86
AULA DE INNOVACION
EJE 10-10 1.00 5.15 3.29 16.94
EJE 13-13 1.00 4.45 3.29 14.64
EJE A-A 1.00 9.23 2.49 22.98
EJE B-B 1.00 1.86 3.29 6.12
1.00 5.15 1.20 6.18
CUARTO DE CONECTIVIDAD
EJE A-A 1.00 2.93 2.49 7.30
EJE B-B 1.00 2.93 3.29 9.64
EJE 13'-13' 1.00 7.10 3.29 23.36
DEPOSITO
EJE B'-B' 1.00 2.55 3.29 8.39
EJE A-A 1.00 2.82 3.29 9.28
EJE 15-15 1.00 5.15 3.29 16.94
BIBLIOTECA ESCOLAR
EJE 13-13 1.00 0.75 3.29 2.47
1.00 4.78 1.20 5.74
EJE 15-15 1.00 6.75 2.49 16.81
EJE D-D 1.00 6.20 3.29 20.40
DIRECCION
EJE 13-13 1.00 0.85 3.29 2.80
1.00 2.22 1.20 2.66
EJE 15-15 1.00 3.85 2.49 9.59
EJE E-E 1.00 6.50 3.29 21.39
PASADIZO
1.00 1.95 1.20 2.34
1.00 11.90 1.20 14.28
1.00 20.05 1.20 24.06
AZOTEA
1.00 21.92 1.20 26.30
1.00 6.77 1.20 8.12
1.00 21.11 1.20 25.33
1.00 22.12 1.20 26.54
1.00 11.44 1.20 13.73
1.00 12.90 1.20 15.48
+5 % desperdicio
42.36

02.01.02 alambre ·08 de refuerzo horizontal en muros

02.01.03 juntas de tecnopor e=1"


Ubicación Unids largo ancho altura ml
primer nivel
44.00 3.59 157.96
segundo nivel
38.00 3.59 136.42

02.02 REVOQUES Y REVESTIMIENTOS


02.02.01 Tarrajeo primario para recibir enchapes
Ubicación Unids largo ancho altura area
SS.HH
EJE A-A 1.00 5.11 2.40 12.26
EJE B-B 1.00 2.15 2.40 5.16
EJE B'-B' 2.00 2.20 2.40 10.56
EJE 8-8 1.00 5.15 2.40 12.36
EJE 8'-8' 1.00 10.70 2.40 25.68
EJE 9-9 1.00 5.15 2.40 12.36
COCINA
EJE 13-13 1.00 0.90 2.40 2.16
1.00 1.90 2.40 4.56
EJE 15-15 1.00 3.90 2.40 9.36
EJE E-E 1.00 6.50 2.40 15.60
+7 % desperdicio
7.70

02.02.02 Tarrajeo en interiores mezcla C:A - 1:5


Ubicación Unids largo ancho altura Area
BLOQUE B
PRIMER NIVEL
ESCALERA
EJE A-A 2.00 3.20 3.29 21.06
2.00 3.30 3.29 21.71
SALA DE USOS MULTIPLES
EJE 10-10 1.00 5.15 3.29 16.94
EJE 15-15 1.00 3.44 3.29 11.32
EJE A-A 1.00 14.97 2.49 37.28
EJE B-B 1.00 7.66 3.29 25.20
1.00 5.87 1.20 7.04
CUARTO DE MAQUINAS - S.H
EJE C'-C' 1.00 3.15 3.29 10.36
2.00 1.90 2.49 9.46
EJE C-C 2.00 5.96 3.29 39.22
EJE 13-13, 15-15 2.00 0.72 3.29 4.74
EJE 13'-13' 1.00 2.40 3.29 7.90
SALA DE PROFESORES
EJE 13-13 1.00 0.40 3.29 1.32
1.00 1.62 1.20 1.94
EJE 15-15 1.00 3.25 2.49 8.09
EJE D-D 2.00 6.20 3.29 40.80
COCINA
EJE 13-13 1.00 0.90 3.29 2.96
1.00 1.90 1.20 2.28
EJE 15-15 1.00 3.90 2.49 9.71
EJE E-E 1.00 6.50 3.29 21.39
SEGUNDO NIVEL
ESCALERA
EJE A-A 2.00 3.20 3.29 21.06
2.00 3.30 3.29 21.71
AULA DE INNOVACION
EJE 10-10 1.00 5.15 3.29 16.94
EJE 13-13 2.00 4.45 3.29 29.28
EJE A-A 1.00 9.23 2.49 22.98
EJE B-B 1.00 1.86 3.29 6.12
1.00 5.15 1.20 6.18
CUARTO DE CONECTIVIDAD
EJE A-A 1.00 2.93 2.49 7.30
EJE B-B 1.00 2.93 3.29 9.64
EJE 13'-13' 2.00 7.10 3.29 46.72
DEPOSITO
EJE B'-B' 2.00 2.55 3.29 16.78
EJE A-A 1.00 2.82 3.29 9.28
EJE 15-15 1.00 5.15 3.29 16.94
BIBLIOTECA ESCOLAR
EJE 13-13 1.00 0.75 3.29 2.47
1.00 4.78 1.20 5.74
EJE 15-15 1.00 6.75 2.49 16.81
EJE D-D 2.00 6.20 3.29 40.80
DIRECCION
EJE 13-13 1.00 0.85 3.29 2.80
1.00 2.22 1.20 2.66
EJE 15-15 1.00 3.85 2.49 9.59
EJE E-E 1.00 6.50 3.29 21.39
PASADIZO
1.00 1.95 1.20 2.34
1.00 11.90 1.20 14.28
1.00 20.05 1.20 24.06
AZOTEA
1.00 21.92 1.20 26.30
1.00 6.77 1.20 8.12
1.00 21.11 1.20 25.33
1.00 22.12 1.20 26.54
1.00 11.44 1.20 13.73
1.00 12.90 1.20 15.48
+7 % desperdicio
55.31

02.02.03 Tarrajeo en exteriores mezcla C:A - 1:5


Ubicación Unids largo ancho altura Area
BLOQUE A
PRIMER NIVEL
SS.HH
EJE A-A 1.00 5.11 2.49 12.72
EJE B-B 1.00 2.15 3.29 7.07
EJE B'-B' 2.00 2.20 3.29 14.48
EJE 8-8 1.00 5.15 3.29 16.94
1.00 3.30 3.29 10.86
SALA DE USOS MULTIPLES
EJE 10-10 1.00 5.15 3.29 16.94
EJE 15-15 1.00 3.44 3.29 11.32
EJE A-A 1.00 14.97 2.49 37.28
EJE B-B 1.00 7.66 3.29 25.20
1.00 5.87 1.20 7.04
CUARTO DE MAQUINAS - S.H
EJE C'-C' 1.00 3.15 3.29 10.36
2.00 1.90 2.49 9.46
EJE 13-13, 15-15 2.00 0.72 3.29 4.74
SALA DE PROFESORES
EJE 13-13 1.00 0.40 3.29 1.32
1.00 1.62 1.20 1.94
EJE 15-15 1.00 3.25 2.49 8.09
COCINA
EJE 13-13 1.00 0.90 3.29 2.96
1.00 1.90 1.20 2.28
EJE 15-15 1.00 3.90 2.49 9.71
EJE E-E 1.00 6.50 3.29 21.39
SEGUNDO NIVEL
SS.HH
EJE A-A 1.00 5.11 2.49 12.72
EJE B-B 1.00 2.15 3.29 7.07
EJE 8-8 1.00 5.15 3.29 16.94
AULA DE INNOVACION
EJE A-A 1.00 9.23 2.49 22.98
EJE B-B 1.00 1.86 3.29 6.12
1.00 5.15 1.20 6.18
CUARTO DE CONECTIVIDAD
EJE A-A 1.00 2.93 2.49 7.30
DEPOSITO
EJE A-A 1.00 2.82 3.29 9.28
EJE 15-15 1.00 5.15 3.29 16.94
BIBLIOTECA ESCOLAR
EJE 13-13 1.00 0.75 3.29 2.47
1.00 4.78 1.20 5.74
EJE 15-15 1.00 6.75 2.49 16.81
DIRECCION
EJE 13-13 1.00 0.85 3.29 2.80
1.00 2.22 1.20 2.66
EJE 15-15 1.00 3.85 2.49 9.59
EJE E-E 1.00 6.50 3.29 21.39
PASADIZO
1.00 1.95 1.20 2.34
1.00 11.90 1.20 14.28
1.00 20.05 1.20 24.06
AZOTEA
1.00 21.92 1.20 26.30
1.00 6.77 1.20 8.12
1.00 21.11 1.20 25.33
1.00 22.12 1.20 26.54
1.00 11.44 1.20 13.73
1.00 12.90 1.20 15.48
+7 % desperdicio
38.87

02.02.04 Tarrajeo en Columnas C:A - 1:5


Ubicación Unids largo ancho altura Area
PRIMER PISO
C-1 8.00 2.80 3.89 87.14
C-2 8.00 3.30 3.89 102.70
C-3 4.00 3.60 3.89 56.02
SEGUNDO PISO
C-1 8.00 2.80 3.29 73.70
C-2 8.00 3.30 3.29 86.86
C-3 4.00 3.60 3.29 47.38
AZOTEA
C-1 4.00 2.80 3.29 36.85
+7 % desperdicio
34.34

02.02.05 Tarrajeo en Columnetas C:A - 1:5


Ubicación Unids largo ancho altura Area
PRIMER PISO
Ca 11.00 0.50 0.95 5.23
50.00 0.50 3.00 75.00
SEGUNDO PISO
15.00 0.50 0.95 7.13
50.00 0.50 3.00 75.00
AZOTEA
Ca 30.00 0.50 0.95 14.25

+5 % desperdicio 8.83

02.02.06 Tarrajeo en Vigas, mezcla C:A - 1:5


Ubicación Unids largo ancho altura Area
PISO 1
2.00 32.33 1.10 71.13
2.00 15.00 1.10 33.00
3.00 8.40 1.30 32.76
3.00 7.65 1.30 29.84
3.00 5.60 1.40 23.52
1.00 34.68 0.70 24.28
PISO 2
2.00 32.33 1.10 71.13
2.00 15.00 1.10 33.00
3.00 8.40 1.30 32.76
3.00 9.70 1.30 37.83
3.00 5.60 1.40 23.52
1.00 49.12 0.70 34.38
AZOTEA
2.00 7.40 1.10 16.28
2.00 4.55 1.10 10.01
+7 % desperdicio
33.14

02.02.07 Tarrajeo en Viguetas, mezcla C:A - 1:5


Ubicación Unids largo ancho altura Area
PISO 1
4.00 7.00 0.30 8.40
2.00 26.73 0.30 16.04
5.00 6.70 0.30 10.05
2.00 18.40 0.30 11.04
PISO 2

4.00 7.00 0.30 8.40


2.00 26.73 0.30 16.04
5.00 6.70 0.30 10.05
2.00 18.40 0.30 11.04
AZOTEA
1.00 11.75 0.30 3.53
1.00 21.78 0.30 6.53
1.00 28.08 0.30 8.42
1.00 9.50 0.30 2.85
1.00 12.90 0.30 3.87
1.00 22.42 0.30 6.73
+5 % desperdicio
6.15

02.02.08 Vestiduras de Derrames en Vanos mezcla 1:5


Ubicación Cantid. largo ancho altura
BLOQUE B
P2 3.00 8.02 24.06
P4 2.00 8.22 16.44
P6 6.00 7.08 42.48
P7 8.00 8.20 65.60
P8 3.00 5.10 15.30
V5 1.00 4.80 4.80
V6 2.00 13.20 26.40
V7 1.00 8.85 8.85
V8 1.00 9.20 9.20
V9 1.00 10.00 10.00
V10 2.00 8.00 16.00
V11 1.00 9.74 9.74
V12 2.00 5.40 10.80
V13 2.00 6.20 12.40
V14 1.00 9.20 9.20
V15 1.00 9.30 9.30
V21 1.00 4.00 4.00
V22 2.00 13.20 26.40
V23 1.00 8.86 8.86
V24 1.00 9.20 9.20
V25 3.00 10.00 30.00
V26 2.00 8.00 16.00
V27 1.00 6.80 6.80
V28 1.00 6.00 6.00
V29 1.00 10.50 10.50
V30 1.00 7.40 7.40
V31 1.00 9.30 9.30
+5 % desperdicio
21.25

02.02.09 bruñas de 1x1cm x 5mm


Ubicación Cantid. largo ancho altura
PISO 1
16.00 18.08 289.28
32.00 12.74 407.68
PISO 2
16.00 18.08 289.28
32.00 12.74 407.68
AZOTEA
40.00 8.40 336.00

02.02.10 gradas acabado pulido de piso con mortero 1:2 x 1.5 cm de espesor
Ubicación Cantid. largo ancho altura area
ESCALERA 1
24.00 1.80 0.30 12.96
24.00 1.80 0.17 7.13
ESCALERA 2
24.00 1.80 0.30 12.96
24.00 1.80 0.17 7.13
+5 % desperdicio
2.01

02.02.11 descansos acabado pulido de piso con mortero 1:2 x 1.5 cm de espesor
Ubicación Cantid. largo ancho altura area
ESCALERA 1
1.00 3.75 1.80 6.75
ESCALERA 2
1.00 3.75 1.80 6.75
+5 % desperdicio
0.68

02.02.12 revestimiento de ceramica de 45x45cm - mesa de cocina


Ubicación Cantid. largo ancho altura area
COCINA
1.00 3.50 0.60 2.10
1.00 3.30 0.60 1.98
1.00 1.48 0.60 0.89
+5 % desperdicio
0.25

02.03 CIELO RASOS


02.03.01 Cielorrasos con Tarrajeo con Mezcla de Cemento sobre Losa Aligerada
Ubicación unids largo ancho altura Area
PISO 1
1.00 8.40 6.40 53.76
1.00 3.75 1.80 6.75
1.00 8.40 4.14 34.78
1.00 8.40 4.20 35.28
1.00 5.35 1.80 9.63
1.00 4.20 1.80 7.56
1.00 2.45 1.80 4.41
1.00 3.40 1.80 6.12
1.00 7.65 5.35 40.93
1.00 7.65 4.20 32.13
1.00 7.65 4.25 32.51
1.00 7.65 6.60 50.49
PISO 2
1.00 8.40 6.40 53.76
1.00 3.75 1.80 6.75
1.00 8.40 4.14 34.78
1.00 8.40 4.20 35.28
1.00 5.35 1.80 9.63
1.00 4.20 1.80 7.56
1.00 2.45 1.80 4.41
1.00 3.40 1.80 6.12
1.00 7.65 5.35 40.93
1.00 7.65 0.78 5.97
1.00 7.65 4.20 32.13
1.00 7.65 0.57 4.36
1.00 7.65 4.25 32.51
1.00 7.65 0.38 2.91
1.00 7.65 6.60 50.49
1.00 7.65 0.15 1.15
AZOTEA
1.00 6.60 3.75 24.75
+7 % desperdicio
46.75

02.04 PISOS Y PAVIMENTOS


02.04.01CONTRAPISOS
02.04.01. Contrapiso - Concreto P/ f'c=175 kg/cm2 e=10 cm
Ubicación unids largo ancho altura Area
PRIMER PISO
SS.HH 1.00 area cad= 18.05 18.05
1.00 area cad= 19.27 19.27
1.00 area cad= 7.35 7.35
USO MULTIPLES 1.00 area cad=146.51 146.51
S.H DISCAPACITADOS 1.00 area cad= 7.12 7.12
CUARTO DE MAQ. 1.00 area cad= 11.92 11.92
SALA DE PROFESORES 1.00 area cad= 34.18 34.18
COCINA 1.00 area cad= 46.95 46.95
SEGUNDO PISO
SS.HH 1.00 area cad= 18.05 18.05
1.00 area cad= 19.27 19.27
1.00 area cad= 7.35 7.35
INNOVACION 1.00 area cad= 88.86 88.86
CONECTIVIDAD 1.00 area cad= 28.63 28.63
DEPOSITO 1.00 area cad= 18.16 18.16
BIBLIOTECA 1.00 area cad= 80.34 80.34
DIRECCION 1.00 area cad= 46.95 46.95
PASADIZO 1.00 area cad= 71.71 71.71
+7 % desperdicio
46.95

02.04.01PISOS
02.04.01. Piso de porcelanato de 60 x 60cm alto transito
Ubicación Cantid. largo ancho altura Area
PRIMER PISO
SS.HH 1.00 area cad= 18.05 18.05
1.00 area cad= 19.27 19.27
1.00 area cad= 7.35 7.35
USO MULTIPLES 1.00 area cad=146.51 146.51
S.H DISCAPACITADOS 1.00 area cad= 7.12 7.12
CUARTO DE MAQ. 1.00 area cad= 11.92 11.92
SALA DE PROFESORES 1.00 area cad= 34.18 34.18
COCINA 1.00 area cad= 46.95 46.95
SEGUNDO PISO
SS.HH 1.00 area cad= 18.05 18.05
1.00 area cad= 19.27 19.27
1.00 area cad= 7.35 7.35
INNOVACION 1.00 area cad= 88.86 88.86
CONECTIVIDAD 1.00 area cad= 28.63 28.63
DEPOSITO 1.00 area cad= 18.16 18.16
BIBLIOTECA 1.00 area cad= 80.34 80.34
DIRECCION 1.00 area cad= 46.95 46.95
PASADIZO 1.00 area cad= 71.71 71.71
+7 % desperdicio
46.95
02.05 OTROS
02.05.01 Canaleta pluvial en piso a media caña con acabado y bruñado
Ubicación Cantid. largo ancho altura
AZOTEA
2.00 22.10 44.20
1.00 21.92 21.92
1.00 17.87 17.87
+7 % desperdicio
5.88

02.06 ZOCALOS Y CONTRAZOCALOS


02.06.01 zocalo de porcelanato de 60 x 60cm-ss.hh - cocina
Ubicación Cantid. largo ancho altura area
SS.HH
EJE A-A 1.00 5.11 2.40 12.26
EJE B-B 1.00 2.15 2.40 5.16
EJE B'-B' 2.00 2.20 2.40 10.56
EJE 8-8 1.00 5.15 2.40 12.36
EJE 8'-8' 1.00 10.70 2.40 25.68
EJE 9-9 1.00 5.15 2.40 12.36
COCINA
EJE 13-13 1.00 0.90 2.40 2.16
1.00 1.90 2.40 4.56
EJE 15-15 1.00 3.90 2.40 9.36
EJE E-E 1.00 6.50 2.40 15.60
+7 % desperdicio
7.70

02.06.01 Contrazocalo de Porcelanato de H=7cm


Ubicación Cantid. largo ancho altura Longitud
PRIMER PISO
1.00 65.35 65.35
1.00 21.07 21.07
1.00 7.10 7.10
2.00 11.10 22.20
2.00 15.10 30.20
2.00 25.00 50.00
2.00 28.30 56.60
SEGUNDO PISO
1.00 45.65 45.65
1.00 22.70 22.70
1.00 17.50 17.50
1.00 43.50 43.50
1.00 28.30 28.30
pasadizo 1.00 77.45 77.45
+5 % desperdicio
24.38

02.07 COBERTURAS
02.07.01 cobertura con ladrillo pastelero con mortero
Ubicación Cantid. largo ancho altura Longitud
AZOTEA
1.00 444.80 444.80
+5 % desperdicio
22.24

02.07.02 impermeabilizante de techo con pintura asfaltica


Ubicación Cantid. largo ancho altura Longitud
AZOTEA
1.00 444.80 444.80
+5 % desperdicio
22.24

02.08 CARPINTERIA DE MADERA


02.08.01 Suministro e instalacion de puerta de madera cedro
Ubicación Cantid. largo ancho altura Area
P-2 3.00 1.00 3.51 10.53
P-4 2.00 1.20 3.51 8.42
P-6 6.00 1.00 3.04 18.24

02.08.02 puerta de melamine e=18mm con estructura de aluminio - baños


Ubicación Cantid. largo ancho altura Area
BLOQUE B
P-3 12.00 0.70 1.80 15.12

02.08.03 puerta mueble de cocina de melamine e=18mm, 2 hojas


Ubicación Cantid. largo ancho altura Area
3.00 3.49 0.70 7.33

02.08.04 separador con plancha de melamine e=18mm - baños


Ubicación Cantid. largo ancho altura Area
BLOQUE B
SS.HH 2.00 10.20 1.80 36.72
02.08.05 mueble de cocina alto
Ubicación Cantid. largo ancho altura
BLOQUE B
cocina 1.00 12.80 12.80

02.08.06 mueble de cocina bajo


Ubicación Cantid. largo ancho altura
BLOQUE B
cocina 1.00 8.20 8.20

02.09 CARPINTERIA METALICA Y HERRERIA


02.09.01 barandas metalicas de proteccion para escalera 2"
Ubicación Cantid. largo ancho altura
ESCALERA 1 2.00 10.40 20.80
2.00 3.40 6.80
ESCALERA 2 2.00 10.40 20.80
2.00 3.40 6.80

02.09.02 barra de apoyo de acero inox. Para discapacitados


Ubicación Cantid. largo ancho altura
SS.HH
2.00 5.40 10.80
1.00 4.40 4.40

02.09.03 Protector metalico para ventanas


Ubicación Cantid.
largo ancho altura Area
Vanos
VENTANAS 1-2 PISO
V-5 1.00 1.60 0.80 1.28
V-6 2.00 5.80 0.80 9.28
V-7 1.00 3.62 0.80 2.90
V-8 1.00 3.80 0.80 3.04
V-9 1.00 3.80 1.20 4.56
V-10 2.00 3.20 0.80 5.12
V-11 1.00 3.20 1.67 5.34
V-12 2.00 1.90 0.80 3.04
V-13 2.00 1.90 1.20 4.56
V-14 1.00 3.80 0.80 3.04
V-15 1.00 3.85 0.80 3.08
V-21 1.00 1.20 0.80 0.96
V-22 2.00 5.80 0.80 9.28
V-23 1.00 3.63 0.80 2.90
V-24 1.00 3.80 0.80 3.04
V-25 3.00 3.80 1.20 13.68
V-26 2.00 3.20 0.80 5.12
V-27 1.00 2.20 1.20 2.64
V-28 1.00 1.80 1.20 2.16
V-29 1.00 4.05 1.20 4.86
V-30 1.00 2.50 1.20 3.00
V-31 1.00 3.85 0.80 3.08

02.09.04 mesa de trabajo de acero inoxidable industrial para cocina


Ubicación Cantid. largo ancho altura
COCINA
2.00 2.00

02.10 CERRAJERIA
02.10.01 Bisagras aluminizada capuchina pesada de 4" x 4"
Ubicación Cantid. unidades Total
BLOQUE B
P-2 3.00 3.00 9.00
P-4 2.00 3.00 6.00
P-6 6.00 3.00 18.00
P-7 8.00 3.00 24.00
P-8 3.00 3.00 9.00

02.11 CERRADURAS
02.11.01 Cerradura Tipo Forte 3 golpes
Ubicación Cantid. unidades Total
BLOQUE B
P-2 3.00 1.00 3.00
P-4 2.00 1.00 2.00
P-6 6.00 1.00 6.00
P-7 8.00 1.00 8.00
P-8 3.00 1.00 3.00

02.11.02 Cerrojo de 2" para puertas


Ubicación Cantid. unidades Total
BLOQUE B
P-3 6.00 1.00 6.00
02.12 VIDRIOS, CRISTALES Y SIMILARES
02.12.01 Vidrio templado de 6mm p/sistema directo
Ubicación Cantid. largo ancho altura total
VENTANAS 1-2 PISO
V-5 1.00 1.60 0.80 1.28
V-6 2.00 5.80 0.80 9.28
V-7 1.00 3.62 0.80 2.90
V-8 1.00 3.80 0.80 3.04
V-9 1.00 3.80 1.20 4.56
V-10 2.00 3.20 0.80 5.12
V-11 1.00 3.20 1.67 5.34
V-12 2.00 1.90 0.80 3.04
V-13 2.00 1.90 1.20 4.56
V-14 1.00 3.80 0.80 3.04
V-15 1.00 3.85 0.80 3.08
V-21 1.00 1.20 0.80 0.96
V-22 2.00 5.80 0.80 9.28
V-23 1.00 3.63 0.80 2.90
V-24 1.00 3.80 0.80 3.04
V-25 3.00 3.80 1.20 13.68
V-26 2.00 3.20 0.80 5.12
V-27 1.00 2.20 1.20 2.64
V-28 1.00 1.80 1.20 2.16
V-29 1.00 4.05 1.20 4.86
V-30 1.00 2.50 1.20 3.00
V-31 1.00 3.85 0.80 3.08

02.13 PINTURA
02.13.01 Pintura latex en muros interiores 02 manos
Ubicación Unids largo ancho altura Area
PRIMER NIVEL
ESCALERA
EJE A-A 2.00 3.20 3.29 21.06
2.00 3.30 3.29 21.71
SALA DE USOS MULTIPLES
EJE 10-10 1.00 5.15 3.29 16.94
EJE 15-15 1.00 3.44 3.29 11.32
EJE A-A 1.00 14.97 2.49 37.28
EJE B-B 1.00 7.66 3.29 25.20
1.00 5.87 1.20 7.04
CUARTO DE MAQUINAS - S.H
EJE C'-C' 1.00 3.15 3.29 10.36
2.00 1.90 2.49 9.46
EJE C-C 2.00 5.96 3.29 39.22
EJE 13-13, 15-15 2.00 0.72 3.29 4.74
EJE 13'-13' 1.00 2.40 3.29 7.90
SALA DE PROFESORES
EJE 13-13 1.00 0.40 3.29 1.32
1.00 1.62 1.20 1.94
EJE 15-15 1.00 3.25 2.49 8.09
EJE D-D 2.00 6.20 3.29 40.80
COCINA
EJE 13-13 1.00 0.90 3.29 2.96
1.00 1.90 1.20 2.28
EJE 15-15 1.00 3.90 2.49 9.71
EJE E-E 1.00 6.50 3.29 21.39
SEGUNDO NIVEL
ESCALERA
EJE A-A 2.00 3.20 3.29 21.06
2.00 3.30 3.29 21.71
AULA DE INNOVACION
EJE 10-10 1.00 5.15 3.29 16.94
EJE 13-13 2.00 4.45 3.29 29.28
EJE A-A 1.00 9.23 2.49 22.98
EJE B-B 1.00 1.86 3.29 6.12
1.00 5.15 1.20 6.18
CUARTO DE CONECTIVIDAD
EJE A-A 1.00 2.93 2.49 7.30
EJE B-B 1.00 2.93 3.29 9.64
EJE 13'-13' 2.00 7.10 3.29 46.72
DEPOSITO
EJE B'-B' 2.00 2.55 3.29 16.78
EJE A-A 1.00 2.82 3.29 9.28
EJE 15-15 1.00 5.15 3.29 16.94
BIBLIOTECA ESCOLAR
EJE 13-13 1.00 0.75 3.29 2.47
1.00 4.78 1.20 5.74
EJE 15-15 1.00 6.75 2.49 16.81
EJE D-D 2.00 6.20 3.29 40.80
DIRECCION
EJE 13-13 1.00 0.85 3.29 2.80
1.00 2.22 1.20 2.66
EJE 15-15 1.00 3.85 2.49 9.59
EJE E-E 1.00 6.50 3.29 21.39
PASADIZO
1.00 1.95 1.20 2.34
1.00 11.90 1.20 14.28
1.00 20.05 1.20 24.06
AZOTEA
1.00 21.92 1.20 26.30
1.00 6.77 1.20 8.12
1.00 21.11 1.20 25.33
1.00 22.12 1.20 26.54
1.00 11.44 1.20 13.73
1.00 12.90 1.20 15.48
+7 % desperdicio
55.31

02.13.02 Pintura latex en muros exteriores 02 manos


Ubicación Unids largo ancho altura Area
PRIMER NIVEL
SS.HH
EJE A-A 1.00 5.11 2.49 12.72
EJE B-B 1.00 2.15 3.29 7.07
EJE B'-B' 2.00 2.20 3.29 14.48
EJE 8-8 1.00 5.15 3.29 16.94
1.00 3.30 3.29 10.86
SALA DE USOS MULTIPLES
EJE 10-10 1.00 5.15 3.29 16.94
EJE 15-15 1.00 3.44 3.29 11.32
EJE A-A 1.00 14.97 2.49 37.28
EJE B-B 1.00 7.66 3.29 25.20
1.00 5.87 1.20 7.04
CUARTO DE MAQUINAS - S.H
EJE C'-C' 1.00 3.15 3.29 10.36
2.00 1.90 2.49 9.46
EJE 13-13, 15-15 2.00 0.72 3.29 4.74
SALA DE PROFESORES
EJE 13-13 1.00 0.40 3.29 1.32
1.00 1.62 1.20 1.94
EJE 15-15 1.00 3.25 2.49 8.09
COCINA
EJE 13-13 1.00 0.90 3.29 2.96
1.00 1.90 1.20 2.28
EJE 15-15 1.00 3.90 2.49 9.71
EJE E-E 1.00 6.50 3.29 21.39
SEGUNDO NIVEL
SS.HH
EJE A-A 1.00 5.11 2.49 12.72
EJE B-B 1.00 2.15 3.29 7.07
EJE 8-8 1.00 5.15 3.29 16.94
AULA DE INNOVACION
EJE A-A 1.00 9.23 2.49 22.98
EJE B-B 1.00 1.86 3.29 6.12
1.00 5.15 1.20 6.18
CUARTO DE CONECTIVIDAD
EJE A-A 1.00 2.93 2.49 7.30
DEPOSITO
EJE A-A 1.00 2.82 3.29 9.28
EJE 15-15 1.00 5.15 3.29 16.94
BIBLIOTECA ESCOLAR
EJE 13-13 1.00 0.75 3.29 2.47
1.00 4.78 1.20 5.74
EJE 15-15 1.00 6.75 2.49 16.81
DIRECCION
EJE 13-13 1.00 0.85 3.29 2.80
1.00 2.22 1.20 2.66
EJE 15-15 1.00 3.85 2.49 9.59
EJE E-E 1.00 6.50 3.29 21.39
PASADIZO
1.00 1.95 1.20 2.34
1.00 11.90 1.20 14.28
1.00 20.05 1.20 24.06
AZOTEA
1.00 21.92 1.20 26.30
1.00 6.77 1.20 8.12
1.00 21.11 1.20 25.33
1.00 22.12 1.20 26.54
1.00 11.44 1.20 13.73
1.00 12.90 1.20 15.48
+7 % desperdicio
38.87

02.13.03 Pintura latex en columnas, Columnetas, derrames 2 manos


Ubicación Unids largo ancho altura Area
COLUMNAS
PRIMER PISO
C-1 8.00 2.80 3.89 87.14
C-2 8.00 3.30 3.89 102.70
C-3 4.00 3.60 3.89 56.02
SEGUNDO PISO
C-1 8.00 2.80 3.29 73.70
C-2 8.00 3.30 3.29 86.86
C-3 4.00 3.60 3.29 47.38
AZOTEA
C-1 4.00 2.80 3.29 36.85
COLUMNETAS
PRIMER PISO
Ca 11.00 0.50 0.95 5.23
50.00 0.50 3.00 75.00
SEGUNDO PISO
15.00 0.50 0.95 7.13
50.00 0.50 3.00 75.00
AZOTEA
Ca 30.00 0.50 0.95 14.25
VESTIDURAS
P2 3.00 8.02 0.15 3.61
P4 2.00 8.22 0.15 2.47
P6 6.00 7.08 0.15 6.37
P7 8.00 8.20 0.15 9.84
P8 3.00 5.10 0.15 2.30
V5 1.00 4.80 0.15 0.72
V6 2.00 13.20 0.15 3.96
V7 1.00 8.85 0.15 1.33
V8 1.00 9.20 0.15 1.38
V9 1.00 10.00 0.15 1.50
V10 2.00 8.00 0.15 2.40
V11 1.00 9.74 0.15 1.46
V12 2.00 5.40 0.15 1.62
V13 2.00 6.20 0.15 1.86
V14 1.00 9.20 0.15 1.38
V15 1.00 9.30 0.15 1.40
V21 1.00 4.00 0.15 0.60
V22 2.00 13.20 0.15 3.96
V23 1.00 8.86 0.15 1.33
V24 1.00 9.20 0.15 1.38
V25 3.00 10.00 0.15 4.50
V26 2.00 8.00 0.15 2.40
V27 1.00 6.80 0.15 1.02
V28 1.00 6.00 0.15 0.90
V29 1.00 10.50 0.15 1.58
V30 1.00 7.40 0.15 1.11
V31 1.00 9.30 0.15 1.40

+7 % desperdicio 51.17

02.13.04 Pintura latex en vigas y viguetas 2 manos


Ubicación Unids largo ancho altura Area
VIGAS
PISO 1
2.00 32.33 1.10 71.13
2.00 15.00 1.10 33.00
3.00 8.40 1.30 32.76
3.00 7.65 1.30 29.84
3.00 5.60 1.40 23.52
1.00 34.68 0.70 24.28
PISO 2
2.00 32.33 1.10 71.13
2.00 15.00 1.10 33.00
3.00 8.40 1.30 32.76
3.00 9.70 1.30 37.83
3.00 5.60 1.40 23.52
1.00 49.12 0.70 34.38
AZOTEA
2.00 7.40 1.10 16.28
2.00 4.55 1.10 10.01
VIGUETAS
PISO 1
4.00 7.00 0.30 8.40
2.00 26.73 0.30 16.04
5.00 6.70 0.30 10.05
2.00 18.40 0.30 11.04
PISO 2 0.00
4.00 7.00 0.30 8.40
2.00 26.73 0.30 16.04
5.00 6.70 0.30 10.05
2.00 18.40 0.30 11.04
AZOTEA
1.00 11.75 0.30 3.53
1.00 21.78 0.30 6.53
1.00 28.08 0.30 8.42
1.00 9.50 0.30 2.85
1.00 12.90 0.30 3.87
1.00 22.42 0.30 6.73
+7 % desperdicio
41.75

02.14 PINTURA DE CIELOS RASOS


02.14.01 Pintura Latex en Cielorraso 02 manos
Ubicación unids largo ancho altura Area
PISO 1
1.00 8.40 6.40 53.76
1.00 3.75 1.80 6.75
1.00 8.40 4.14 34.78
1.00 8.40 4.20 35.28
1.00 5.35 1.80 9.63
1.00 4.20 1.80 7.56
1.00 2.45 1.80 4.41
1.00 3.40 1.80 6.12
1.00 7.65 5.35 40.93
1.00 7.65 4.20 32.13
1.00 7.65 4.25 32.51
1.00 7.65 6.60 50.49
PISO 2
1.00 8.40 6.40 53.76
1.00 3.75 1.80 6.75
1.00 8.40 4.14 34.78
1.00 8.40 4.20 35.28
1.00 5.35 1.80 9.63
1.00 4.20 1.80 7.56
1.00 2.45 1.80 4.41
1.00 3.40 1.80 6.12
1.00 7.65 5.35 40.93
1.00 7.65 0.78 5.97
1.00 7.65 4.20 32.13
1.00 7.65 0.57 4.36
1.00 7.65 4.25 32.51
1.00 7.65 0.38 2.91
1.00 7.65 6.60 50.49
1.00 7.65 0.15 1.15
AZOTEA
1.00 6.60 3.75 24.75
+7 % desperdicio
46.75

02.15 PINTURA EN MADERA


02.15.01 Pintura en puertas de madera con barniz 2 manos
Ubicación Cantid. caras ancho altura Area
BLOQUE A
P-2 3.00 1.00 3.51 10.53
P-4 2.00 1.20 3.51 8.42
P-6 6.00 1.00 3.04 18.24
P-7 8.00 1.20 3.50 33.60
P-8 3.00 0.90 2.10 5.67
+7 % desperdicio
5.35

02.16 VARIOS
02.16.01 Juntas c/tecknoport y jebe microporoso e=1"
Ubicación Cantid. long ancho altura Longitud
BLOQUE B
primer nivel
48.00 3.59 172.32
segundo nivel
32.00 3.59 114.88

02.16.02 Tachos de polietileno para reciclaje


Ubicación Cantid. long ancho altura und
BLOQUE B
Aulas 24.00 24.00

02.16.03 Junta/lamina metalica de 4"x3/16" para separacion sismica entre bloque


Ubicación Cantid. long ancho altura Longitud
BLOQUE B
6.00 3.89 23.34

02.16.04 tapa junta/metalica en pisos


Ubicación Unids largo ancho altura
BLOQUE B
6.00 3.50 21.00

02.16.05 tapa junta/metalica en techo


Ubicación Cantid. long ancho altura Longitud
BLOQUE B
6.00 3.89 23.34

02.16.06 pantalla acrilica de 4m x 1.20m inc. Instalacion


Ubicación Cantid. long ancho altura Longitud
BLOQUE B
Aulas 12.00 12.00

02.16.07 Limpieza final de obra


Ubicación Cantid. long ancho altura Longitud
BLOQUE B
1.00 52.00 8.45 439.40

02.16.08 cantonera estriada para escalera 2"


Ubicación Cantid. long ancho altura Longitud
BLOQUE B
24.00 1.80 43.20

02.16.09 cortinas plegables lavables inc coporte


Ubicación Unids largo ancho altura
BLOQUE B 17.00
02.16.10 espejo empotrado sin bisel 6mm color plata
Ubicación Unids largo ancho altura
BLOQUE B 12.00

02.16.11 estructura de apoyo para ovalines


Ubicación Unids largo ancho altura
BLOQUE B 16.00 0.80 0.40 5.12
QUE B

MARIA EN LA INSTITUCION
ROVINCIA DE CAÑETE -

M2
Sub total TOTAL
847.24
889.60 889.60

KG 68.00

ML
Sub total TOTAL

294.38 294.38

M2
Sub total TOTAL

110.06
117.77 117.77

M2
Sub total TOTAL
790.07
845.38 845.38

M2
Sub total TOTAL
555.28
594.15 594.15

M2
Sub total TOTAL
490.62
524.97 524.97

M2
Sub total TOTAL

176.60
185.43 185.43

M2
Sub total TOTAL

473.43
506.57 506.57

M2
Sub total TOTAL
122.99
129.13 129.13

M
Sub total TOTAL
425.03
446.28 446.28

M
Sub total TOTAL

1,729.92 ###

M2
Sub total TOTAL

40.18
42.18 42.18

M2
Sub total TOTAL

13.50
14.18 14.18

M2
Sub total TOTAL

4.97
5.22 5.22

M2
Sub total TOTAL

667.82
714.57 714.57

M2
Sub total TOTAL
670.67
717.62 717.62

M2
Sub total TOTAL

670.67
717.62 717.62
M
Sub total TOTAL

83.99
89.87 89.87

M2
Sub total TOTAL

110.06
117.77 117.77

M
Sub total TOTAL
487.62
512.00 512.00

M2
Sub total TOTAL

444.80
467.04 467.04

M2
Sub total TOTAL

444.80
467.04 467.04

M2
Sub total TOTAL

37.19 37.19

M2
Sub total TOTAL

15.12 15.12

M2
Sub total TOTAL

7.33 7.33

M2
Sub total TOTAL

36.72 36.72
M
Sub total TOTAL

12.80 12.80

M
Sub total TOTAL

8.20 8.20

M
Sub total TOTAL

55.20 55.20

M
Sub total TOTAL

15.20 15.20

M2

Sub total TOTAL


95.96 95.96

UND
Sub total TOTAL

2.00 2.00

PZA
Sub total TOTAL

66.00 66.00

PZA
Sub total TOTAL

22.00 22.00

PZA
Sub total TOTAL

6.00 6.00
M2
Sub total TOTAL

95.96 95.96

M2
Sub total TOTAL
790.07
845.38 845.38

M2
Sub total TOTAL
555.28
594.15 594.15

M2
Sub total TOTAL
730.98
782.15 782.15

M2
Sub total TOTAL
596.41
638.16 638.16

M2
Sub total TOTAL
667.82
714.57 714.57

M2
Sub total TOTAL

76.46
81.82 81.82

M
Sub total TOTAL
287.20 287.20

UND
Sub total TOTAL

24.00 24.00

M
Sub total TOTAL

23.34 23.34

M
Sub total TOTAL

21.00 21.00

M
Sub total TOTAL

23.34 23.34

UND
Sub total TOTAL

12.00 12.00

M2
Sub total TOTAL

439.40 439.40

M2
Sub total TOTAL

43.20 43.20

UND
Sub total TOTAL
17.00 17.00
UND
Sub total TOTAL
12.00 12.00

M2
Sub total TOTAL
5.12 5.12
HOJA METRADO DE ARQUITECTURA - CISTERNA

"RECONSTRUCCION DEL SERVICIO DE EDUCACION PRIMARIA EN LA INSTITUCION


PROYEC
EDUCATIVA Nº20174 DEL DISTRITO DE PACARAN - PROVINCIA DE CAÑETE -
TO :
DEPARTAMENTO DE LIMA"
UBICACI
PACARAN - CAÑETE - LIMA
ÓN:
02 ARQUITECTURA
02.01 REVOQUES Y REVESTIMIENTOS
02.01.01 tarrajeo con impermeabilizantes de fondo - piso
Ubicación Unids largo ancho altura Area
CISTERNA
1.00 2.70 2.50 6.75
+7 % desperdicio
0.47

02.01.02 tarrajeo con impermeabilizantes de muros


Ubicación Unids largo ancho altura Area
CISTERNA
1.00 2.70 1.00 2.70
1.00 2.50 1.00 2.50
+7 % desperdicio
0.36

02.01.03 tarrajeo con impermeabilizantes de losa - techo


Ubicación Unids largo ancho altura Area
CISTERNA
1.00 2.70 2.50 6.75
+7 % desperdicio
0.47

02.01.04 aplicación de primera capa de xipes concentrado p/impermeabilizacion int


Ubicación Unids largo ancho altura Area
CISTERNA
1.00 2.70 1.00 2.70
1.00 2.50 1.00 2.50
+5 % desperdicio 0.26

02.01.05 aplicación de segunda capa de xipes concentrado p/impermeabilizacion in


Ubicación Unids largo ancho altura Area
CISTERNA
1.00 2.70 1.00 2.70
1.00 2.50 1.00 2.50
+5 % desperdicio
0.26
02.02 CARPINTERIA METALICA Y HERRERIA
02.02.01 escalera para gato tubo de FºGº 11/2"x1!. Acceso a cisterna
Ubicación Cantid.
largo ancho altura und
Vanos
CISTERNA 1.00 1.00

02.02.02 tapa metalica para cisterna de 60x60m


Ubicación Cantid.
largo ancho altura und
Vanos
CISTERNA 1.00 1.00

02.16 VARIOS
02.16.08 Limpieza final de obra
Ubicación Cantid. long ancho altura Longitud
CISTERNA
1.00 2.70 2.50 6.75
TERNA

MARIA EN LA INSTITUCION
ROVINCIA DE CAÑETE -

M2
Sub total TOTAL

6.75
7.22 7.22

M2
Sub total TOTAL

5.20
5.56 5.56

M2
Sub total TOTAL

6.75
7.22 7.22

M2
Sub total TOTAL

5.20
5.46 5.46

M2
Sub total TOTAL

5.20
5.46 5.46
UND

Sub total TOTAL

1.00 1.00

UND

Sub total TOTAL

1.00 1.00

M2
Sub total TOTAL

6.75 6.75
HOJA METRADO DE ARQUITECTURA - TANQUE ELEVADO

"RECONSTRUCCION DEL SERVICIO DE EDUCACION PRIMARIA EN LA INSTITUCION


PROYEC
EDUCATIVA Nº20174 DEL DISTRITO DE PACARAN - PROVINCIA DE CAÑETE -
TO :
DEPARTAMENTO DE LIMA"
UBICACI
PACARAN - CAÑETE - LIMA
ÓN:
02 ARQUITECTURA
02.01 MUROS, TABIQUES DE ALBAÑILERIA
02.01.01 Muro de Ladrillo KK de Soga C:A 1:4 de 24 X 13 X 9 cm
Ubicación Unids largo ancho altura Area
TANQUE ELEV.
2.00 2.95 2.20 12.98
2.00 2.75 2.20 12.10
+7 % desperdicio
1.76

02.01.02 alambre ·08 de refuerzo horizontal en muros

02.01.03 juntas de tecnopor e=1"


Ubicación Unids largo ancho altura ml
TANQUE ELEV.
8.00 2.20 17.60

02.02 REVOQUES Y REVESTIMIENTOS


02.02.01 Tarrajeo en interiores mezcla C:A - 1:5
Ubicación Unids largo ancho altura Area
TANQUE ELEV.
2.00 2.95 2.20 12.98
2.00 2.75 2.20 12.10
+7 % desperdicio
1.76

02.02.02 Tarrajeo en exteriores mezcla C:A - 1:5


Ubicación Unids largo ancho altura Area
TANQUE ELEV.
2.00 2.95 2.20 12.98
2.00 2.75 2.20 12.10
+7 % desperdicio
1.76

02.02.03 Tarrajeo en Columnas C:A - 1:5


Ubicación Unids largo ancho altura Area
TANQUE ELEV.
C-1 4.00 1.60 9.24 59.14
+7 % desperdicio
4.14

02.02.04 Tarrajeo en Vigas, mezcla C:A - 1:5


Ubicación Unids largo ancho altura Area
TANQUE ELEV.
16.00 1.93 0.50 15.44
16.00 2.10 0.50 16.80
+7 % desperdicio
2.26

02.02.05 Vestiduras de Derrames en Vanos mezcla 1:5


Ubicación Cantid. largo ancho altura
TANQUE ELEV.
P1 1.00 5.40 5.40
+5 % desperdicio
0.27

02.02.06 tarrajeo con impermeablizantes de fondo - piso


Ubicación Cantid. largo ancho altura
TANQUE ELEV.
1.00 2.95 2.75 8.11

02.02.07 tarrajeo con impermeablizantes de muros


Ubicación Cantid. largo ancho altura
TANQUE ELEV.
2.00 2.95 1.70 10.03
2.00 2.75 1.70 9.35

02.02.08 tarrajeo con impermeablizantes de losa - techo


Ubicación Cantid. largo ancho altura
TANQUE ELEV.
1.00 2.95 2.75 8.11

02.02.09 aplicación de primera capa de xipes concentrado p/impermeabilizacion int


Ubicación Cantid. largo ancho altura
TANQUE ELEV.
1.00 2.95 1.70 5.02
1.00 2.75 1.70 4.68

02.02.10 aplicación de segunda capa de xipes concentrado p/impermeabilizacion in


Ubicación Cantid. largo ancho altura
TANQUE ELEV.
1.00 2.95 1.70 5.02
1.00 2.75 1.70 4.68

02.02.11 bruñas de 1x1 de 5mm


Ubicación Cantid. largo ancho altura
TANQUE ELEV.
8.00 12.00 1.70 163.20

02.03 CIELO RASOS


02.03.01 tarrajeo en cielo raso mezcla c:a 1:5 e=1.5cm
Ubicación Cantid. largo ancho altura
TANQUE ELEV.
1.00 2.95 2.75 8.11

02.04 PISOS Y PAVIMENTOS


02.04.01CONTRAPISOS
02.04.01. Contrapiso - Concreto P/ f'c=175 kg/cm2 e=10 cm
Ubicación unids largo ancho altura Area
TANQUE ELEV.
1.00 2.95 2.75 8.11
+7 % desperdicio
0.57

02.04.01PISOS
02.04.01. Piso de porcelanato de 60 x 60cm alto transito
Ubicación Cantid. largo ancho altura Area
TANQUE ELEV.
1.00 2.95 2.75 8.11
+7 % desperdicio
0.57

02.05 CONTRAZOCALOS
02.05.01 Contrazocalo de Porcelanato de H=7cm
Ubicación Cantid. largo ancho altura Longitud
TANQUE ELEV.
1.00 11.40 11.40
+5 % desperdicio
0.57
02.06 COBERTURAS
02.06.01 cobertura con ladrillo pastelero con mortero
Ubicación Cantid. largo ancho altura Longitud
TECHO TANQ.
1.00 2.95 2.75 8.11
+5 % desperdicio
0.41

02.06.02 Impermeabilizante de techo con pintura asfaltica


Ubicación Cantid. largo ancho altura Longitud
TECHO TANQ.
1.00 2.95 2.75 8.11
+5 % desperdicio
0.41

02.07 CARPINTERIA METALICA Y HERRERIA


02.07.01 escalera para gato tubo de FºGº 11/2"x1!. Acceso a cisterna
Ubicación Cantid.
largo ancho altura und
Vanos
TANQUE ELEV. 1.00 1.00

02.07.02 tapa metalica para cisterna de 60x60m


Ubicación Cantid.
largo ancho altura und
Vanos
TANQUE ELEV. 1.00 1.00

02.07.03 puerta metalica


Ubicación Cantid.
largo ancho altura und
Vanos
TANQUE ELEV. 1.00 1.00

02.08 PINTURA
02.08.01 Pintura latex en muros interiores 02 manos
Ubicación Unids largo ancho altura Area
TANQUE ELEV.
2.00 2.95 2.20 12.98
2.00 2.75 2.20 12.10
+7 % desperdicio
1.76

02.08.02 Pintura latex en muros exteriores 02 manos


Ubicación Unids largo ancho altura Area
TANQUE ELEV.
2.00 2.95 2.20 12.98
2.00 2.75 2.20 12.10
+7 % desperdicio
1.76

02.08.03 Pintura latex en columnas, Columnetas, derrames 2 manos


Ubicación Unids largo ancho altura Area
TANQUE ELEV.
C-1 4.00 1.60 9.24 59.14
+7 % desperdicio
4.14

02.08.04 Pintura latex en vigas y viguetas, derrames 2 manos


Ubicación Unids largo ancho altura Area
TANQUE ELEV.
16.00 1.93 0.50 15.44
16.00 2.10 0.50 16.80
+7 % desperdicio
2.26

02.09 PINTURA DE CIELOS RASOS


02.09.01 Pintura Latex en Cielorraso 02 manos
Ubicación unids largo ancho altura Area
TANQUE ELEVADO
1.00 2.95 2.75 8.11
+7 % desperdicio
0.57

02.10 VARIOS
02.10.01 Juntas c/tecknoport y jebe microporoso e=1"
Ubicación Cantid. long ancho altura Longitud
TANQUE ELEVADO
4.00 2.20 8.80

02.10.02 Limpieza final de obra


Ubicación Cantid. long ancho altura Longitud
TANQUE ELEVADO
1.00 2.95 2.75 8.11
ELEVADO

MARIA EN LA INSTITUCION
ROVINCIA DE CAÑETE -

M2
Sub total TOTAL

25.08
26.84 26.84

KG 1.50

ML
Sub total TOTAL

17.60 17.60

M2
Sub total TOTAL

25.08
26.84 26.84

M2
Sub total TOTAL

25.08
26.84 26.84

M2
Sub total TOTAL
59.14
63.28 63.28

M2
Sub total TOTAL

32.24
34.50 34.50

M
Sub total TOTAL

5.40
5.67 5.67

M2
Sub total TOTAL

8.11 8.11

M2
Sub total TOTAL

19.38 19.38

M2
Sub total TOTAL

8.11 8.11

M2
Sub total TOTAL

9.69 9.69

M2
Sub total TOTAL

9.69 9.69

M2
Sub total TOTAL

163.20 163.20

M2
Sub total TOTAL

8.11 8.11

M2
Sub total TOTAL

8.11
8.68 8.68

M2
Sub total TOTAL

8.11
8.68 8.68

M
Sub total TOTAL

11.40
11.97 11.97
M2
Sub total TOTAL

8.11
8.52 8.52

M2
Sub total TOTAL

8.11
8.52 8.52

UND

Sub total TOTAL

1.00 1.00

UND

Sub total TOTAL

1.00 1.00

UND

Sub total TOTAL

1.00 1.00

M2
Sub total TOTAL

25.08
26.84 26.84

M2
Sub total TOTAL
25.08
26.84 26.84

M2
Sub total TOTAL

59.14
63.28 63.28

M2
Sub total TOTAL

32.24
34.50 34.50

M2
Sub total TOTAL

8.11
8.68 8.68

M
Sub total TOTAL

8.80 8.80

M2
Sub total TOTAL

8.11 8.11
HOJA METRADO DE ARQUITECTURA - CERCO PERIMETRICO

"RECONSTRUCCION DEL SERVICIO DE EDUCACION PRIMARIA EN LA INSTITUCIO


PROYEC
EDUCATIVA Nº20174 DEL DISTRITO DE PACARAN - PROVINCIA DE CAÑETE -
TO :
DEPARTAMENTO DE LIMA"
UBICACI
PACARAN - CAÑETE - LIMA
ÓN:
02 ARQUITECTURA
02.01 MUROS, TABIQUES DE ALBAÑILERIA
02.01.01 Muro de Ladrillo KK de Soga C:A 1:4 de 24 X 13 X 9 cm
Ubicación Unids largo ancho altura Area
CERCO
1.00 2.92 2.35 6.86
3.00 2.67 2.35 18.82
1.00 1.38 2.35 3.24
43.00 3.00 2.35 303.15
3.00 2.21 2.35 15.58
1.00 3.59 2.35 8.44
1.00 2.53 2.35 5.95
1.00 1.74 2.35 4.09
1.00 1.01 2.35 2.37
1.00 1.27 2.35 2.98
1.00 2.43 2.35 5.71
1.00 2.27 2.35 5.33
1.00 1.96 2.35 4.61
4.00 2.73 2.35 25.66
+7 % desperdicio
28.90

02.01.02 alambre ·08 de refuerzo horizontal en muros

02.01.03 juntas de tecnopor e=1"


Ubicación Unids largo ancho altura ml

19.00 2.35 44.65

02.02 REVOQUES Y REVESTIMIENTOS


02.02.01 Tarrajeo en interiores mezcla C:A - 1:5
Ubicación Unids largo ancho altura Area
1.00 2.92 2.35 6.86
3.00 2.67 2.35 18.82
1.00 1.38 2.35 3.24
43.00 3.00 2.35 303.15
3.00 2.21 2.35 15.58
1.00 3.59 2.35 8.44
1.00 2.53 2.35 5.95
1.00 1.74 2.35 4.09
1.00 1.01 2.35 2.37
1.00 1.27 2.35 2.98
1.00 2.43 2.35 5.71
1.00 2.27 2.35 5.33
1.00 1.96 2.35 4.61
4.00 2.73 2.35 25.66
+7 % desperdicio
28.90

02.02.02 Tarrajeo en exteriores mezcla C:A - 1:5


Ubicación Unids largo ancho altura Area
1.00 2.92 2.35 6.86
3.00 2.67 2.35 18.82
1.00 1.38 2.35 3.24
43.00 3.00 2.35 303.15
3.00 2.21 2.35 15.58
1.00 3.59 2.35 8.44
1.00 2.53 2.35 5.95
1.00 1.74 2.35 4.09
1.00 1.01 2.35 2.37
1.00 1.27 2.35 2.98
1.00 2.43 2.35 5.71
1.00 2.27 2.35 5.33
1.00 1.96 2.35 4.61
4.00 2.73 2.35 25.66
+7 % desperdicio
28.90

02.02.03 Tarrajeo en Columnas C:A - 1:5


Ubicación Unids largo ancho altura Area
C-1 83.00 1.00 2.75 228.25
C-2 3.00 1.29 2.75 10.64
C-3 1.00 1.63 2.75 4.48
+7 % desperdicio
17.04

02.02.04 Tarrajeo en Vigas, mezcla C:A - 1:5


Ubicación Unids largo ancho altura Area
2.00 3.42 0.25 1.71
2.00 9.27 0.25 4.64
2.00 1.88 0.25 0.94
2.00 3.55 0.25 1.78
2.00 7.72 0.25 3.86
2.00 3.83 0.25 1.92
2.00 16.30 0.25 8.15
2.00 52.35 0.25 26.18
2.00 1.26 0.25 0.63
2.00 1.52 0.25 0.76
2.00 53.06 0.25 26.53
2.00 16.92 0.25 8.46
2.00 4.98 0.25 2.49
2.00 20.50 0.25 10.25
2.00 3.20 0.25 1.60
+7 % desperdicio
6.99

02.02.05 bruñas de 1x1cm x 5mm


Ubicación Cantid. largo ancho altura
63.00 10.70 674.10

02.03 COBERTURAS
02.03.01 cobertura con ladrillo pastelero con mortero
Ubicación Cantid. largo ancho altura Longitud

1.00 201.00 201.00


+5 % desperdicio
10.05

02.04 PINTURA
02.04.01 Pintura latex en muros interiores 02 manos
Ubicación Unids largo ancho altura Area
1.00 2.92 2.35 6.86
3.00 2.67 2.35 18.82
1.00 1.38 2.35 3.24
43.00 3.00 2.35 303.15
3.00 2.21 2.35 15.58
1.00 3.59 2.35 8.44
1.00 2.53 2.35 5.95
1.00 1.74 2.35 4.09
1.00 1.01 2.35 2.37
1.00 1.27 2.35 2.98
1.00 2.43 2.35 5.71
1.00 2.27 2.35 5.33
1.00 1.96 2.35 4.61
4.00 2.73 2.35 25.66
+7 % desperdicio
28.90

02.04.02 Pintura latex en muros exteriores 02 manos


Ubicación Unids largo ancho altura Area
1.00 2.92 2.35 6.86
3.00 2.67 2.35 18.82
1.00 1.38 2.35 3.24
43.00 3.00 2.35 303.15
3.00 2.21 2.35 15.58
1.00 3.59 2.35 8.44
1.00 2.53 2.35 5.95
1.00 1.74 2.35 4.09
1.00 1.01 2.35 2.37
1.00 1.27 2.35 2.98
1.00 2.43 2.35 5.71
1.00 2.27 2.35 5.33
1.00 1.96 2.35 4.61
4.00 2.73 2.35 25.66
+7 % desperdicio
28.90

02.04.03 Pintura latex en columnas 2 manos


Ubicación Unids largo ancho altura Area
C-1 83.00 1.00 2.75 228.25
C-2 3.00 1.29 2.75 10.64
C-3 1.00 1.63 2.75 4.48
+7 % desperdicio
17.04

02.04.04 Pintura latex en vigas 2 manos


Ubicación Unids largo ancho altura Area
2.00 3.42 0.25 1.71
2.00 9.27 0.25 4.64
2.00 1.88 0.25 0.94
2.00 3.55 0.25 1.78
2.00 7.72 0.25 3.86
2.00 3.83 0.25 1.92
2.00 16.30 0.25 8.15
2.00 52.35 0.25 26.18
2.00 1.26 0.25 0.63
2.00 1.52 0.25 0.76
2.00 53.06 0.25 26.53
2.00 16.92 0.25 8.46
2.00 4.98 0.25 2.49
2.00 20.50 0.25 10.25
2.00 3.20 0.25 1.60
+7 % desperdicio
6.99

02.05 VARIOS
02.05.01 Juntas c/tecknoport y jebe microporoso e=1"
Ubicación Cantid. long ancho altura Longitud
21.00 3.00 63.00

02.05.02 Limpieza final de obra


Ubicación Cantid. long ancho altura Longitud
1.00 31.70 0.70 22.19
ERIMETRICO

MARIA EN LA INSTITUCION
ROVINCIA DE CAÑETE -

M2
Sub total TOTAL

412.80
441.70 441.70

KG 103.00

ML
Sub total TOTAL

44.65 44.65

M2
Sub total TOTAL
412.80
441.70 441.70

M2
Sub total TOTAL

412.80
441.70 441.70

M2
Sub total TOTAL

243.38
260.41 260.41

M2
Sub total TOTAL
99.88
106.87 106.87

M
Sub total TOTAL

674.10 674.10

M
Sub total TOTAL

201.00
211.05 211.05

M2
Sub total TOTAL

412.80
441.70 441.70

M2
Sub total TOTAL
412.80
441.70 441.70

M2
Sub total TOTAL

243.38
260.41 260.41

M2
Sub total TOTAL

99.88
106.87 106.87

M
Sub total TOTAL

63.00 63.00

M2
Sub total TOTAL
22.19 22.19
HOJA METRADO DE ARQUITECTURA - PORTICOS

"RECONSTRUCCION DEL SERVICIO DE EDUCACION PRIMARIA EN LA INSTITUCION


PROYEC
EDUCATIVA Nº20174 DEL DISTRITO DE PACARAN - PROVINCIA DE CAÑETE -
TO :
DEPARTAMENTO DE LIMA"
UBICACI
PACARAN - CAÑETE - LIMA
ÓN:
02 ARQUITECTURA
02.01 MUROS, TABIQUES DE ALBAÑILERIA
02.01.01 Muro de Ladrillo KK de Soga C:A 1:4 de 24 X 13 X 9 cm
Ubicación Unids largo ancho altura Area
PORTICO PRINCIPAL
1.00 2.45 2.55 6.25
PORTICO SECUNDARIO 2
1.00 0.60 2.35 1.41
+7 % desperdicio
0.54

02.01.02 alambre ·08 de refuerzo horizontal en muros

02.01.03 juntas de tecnopor e=1"


Ubicación Unids largo ancho altura ml

6.00 2.35 14.10

02.02 REVOQUES Y REVESTIMIENTOS


02.02.01 Tarrajeo en interiores mezcla C:A - 1:5
Ubicación Unids largo ancho altura Area
PORTICO PRINCIPAL
1.00 2.45 2.55 6.25
PORTICO SECUNDARIO 2
1.00 0.60 2.35 1.41
+7 % desperdicio
0.54

02.02.02 Tarrajeo en exteriores mezcla C:A - 1:5


Ubicación Unids largo ancho altura Area
PORTICO PRINCIPAL
1.00 2.45 2.55 6.25
PORTICO SECUNDARIO 2
1.00 0.60 2.35 1.41
+7 % desperdicio
0.54

02.02.03 Tarrajeo en Columnas C:A - 1:5


Ubicación Unids largo ancho altura Area
PORTICO P-1
C-1 3.00 1.00 2.55 7.65
2.00 1.00 3.70 7.40
PORTICO SECUNDARIO P-2-P-3
C-1 3.00 1.00 2.30 6.90
4.00 1.00 2.90 11.60
+7 % desperdicio
2.35

02.02.04 Tarrajeo en Vigas, mezcla C:A - 1:5


Ubicación Unids largo ancho altura Area
PORTICO PRINCIPAL 4.00 7.73 0.30 9.28
4.00 2.02 0.30 2.42
PORTICO SECUNDARIO 02
2.00 2.11 0.30 1.27
2.00 1.50 0.30 0.90
PORTICO SECUNDARIO 03
2.00 5.68 0.30 3.41
2.00 2.92 0.30 1.75
+7 % desperdicio
1.33

02.02.05 Tarrajeo en losa - techo, mezcla C:A - 1:5


Ubicación Unids largo ancho altura Area
PORTICO PRINCIPAL
1.00 7.69 0.85 6.54
PORTICO SECUNDARIO 02
1.00 1.50 1.20 1.80
PORTICO SECUNDARIO 03
1.00 2.92 1.20 3.50
+7 % desperdicio
0.83

02.02.06 bruñas de 1x1cm x 5mm


Ubicación Cantid. largo ancho altura
2.00 10.70 21.40

02.03 COBERTURAS
02.03.01 cobertura con ladrillo pastelero con mortero
Ubicación Cantid. largo ancho altura Longitud
1.00 15.50 15.50
+5 % desperdicio
0.78
02.04 PINTURA
02.04.01 Pintura latex en muros interiores 02 manos
Ubicación Unids largo ancho altura Area
PORTICO PRINCIPAL
1.00 2.45 2.55 6.25
PORTICO SECUNDARIO 2
1.00 0.60 2.35 1.41
+7 % desperdicio
0.54

02.04.02 Pintura latex en muros exteriores 02 manos


Ubicación Unids largo ancho altura Area
PORTICO PRINCIPAL 0.00
1.00 2.45 2.55 6.25
PORTICO SECUNDARIO 2 0.00
1.00 0.60 2.35 1.41
+7 % desperdicio
0.54

02.04.03 Pintura latex en columnas 2 manos


Ubicación Unids largo ancho altura Area
PORTICO P-1
C-1 3.00 1.00 2.55 7.65
2.00 1.00 3.70 7.40
PORTICO SECUNDARIO P-2-P-3
C-1 3.00 1.00 2.30 6.90
4.00 1.00 2.90 11.60
+7 % desperdicio
2.35

02.04.04 Pintura latex en vigas 2 manos


Ubicación Unids largo ancho altura Area
PORTICO PRINCIPAL 4.00 7.73 0.30 9.28
4.00 2.02 0.30 2.42
PORTICO SECUNDARIO 02
2.00 2.11 0.30 1.27
2.00 1.50 0.30 0.90
PORTICO SECUNDARIO 03
2.00 5.68 0.30 3.41
2.00 2.92 0.30 1.75
+7 % desperdicio
1.33

02.04.05 Pintura latex en losa - techo 2 manos


Ubicación Unids largo ancho altura Area
PORTICO PRINCIPAL
1.00 7.69 0.85 6.54
PORTICO SECUNDARIO 02
1.00 1.50 1.20 1.80
PORTICO SECUNDARIO 03
1.00 2.92 1.20 3.50
+7 % desperdicio
0.83

02.04.06 Pintura letras porticos de ingreso


Ubicación Unids largo ancho altura Area
PORTICO PRINCIPAL
1.00 1.00 1.00 1.00
PORTICO SECUNDARIO 02
1.00 1.00 1.00 1.00
PORTICO SECUNDARIO 03
1.00 1.00 1.00 1.00
+7 % desperdicio
0.21

02.05 CARPINTERIA METALICA Y HERRERIA


02.05.01 porton de ingreso principal metalico de 2,55x3.00m
Ubicación Unids largo ancho altura und
PORTICO PRINCIPAL
1.00 1.00

02.05.02 porton de ingreso metalico de 2,55x1.00m


Ubicación Unids largo ancho altura und
PORTICOS SECUNDAR 02
1.00 1.00

02.05.03 porton de ingreso metalico de 2,30x2.40m


Ubicación Unids largo ancho altura und
PORTICOS SECUNDAR 03
1.00 1.00

02.06 VARIOS
02.06.01 Juntas c/tecknoport y jebe microporoso e=1"
Ubicación Cantid. long ancho altura Longitud
3.00 3.00 9.00
02.06.02 Limpieza final de obra
Ubicación Cantid. long ancho altura Longitud
1.00 15.50 0.70 10.85

02.07 SEÑALETICAS
02.07.01 señales de identificacion de puertas de salida
Ubicación Cantid. long ancho altura Longitud
60.00 60.00

02.07.02 señales de identificacion de zona segura


Ubicación Cantid. long ancho altura Longitud
60.00 60.00

02.07.03 señales direccional de salida derecha - izquierda


Ubicación Cantid. long ancho altura Longitud
60.00 60.00

02.07.04 señal ubicación extintor


Ubicación Cantid. long ancho altura Longitud
10.00 10.00

02.07.05 señal salida accesible de emergencia


Ubicación Cantid. long ancho altura Longitud
60.00 60.00

02.07.06 señal antencion de riesgo electrico


Ubicación Cantid. long ancho altura Longitud
30.00 30.00

02.07.07 extintor contra incendio pqs abc 12 kg


Ubicación Cantid. long ancho altura Longitud
10.00 10.00

02.07.08 señalizacion de seguridad en piso


Ubicación Cantid. long ancho altura Longitud
60.00 60.00

02.07.09 indicativa escalera


Ubicación Cantid. long ancho altura Longitud
10.00 10.00
TICOS

MARIA EN LA INSTITUCION
ROVINCIA DE CAÑETE -

M2
Sub total TOTAL

7.66
8.19 8.19

KG 2.00

ML
Sub total TOTAL

14.10 14.10

M2
Sub total TOTAL

7.66
8.19 8.19

M2
Sub total TOTAL

7.66
8.19 8.19

M2
Sub total TOTAL

33.55
35.90 35.90

M2
Sub total TOTAL

19.03
20.36 20.36

M2
Sub total TOTAL

11.84
12.67 12.67

M
Sub total TOTAL

21.40 21.40

M
Sub total TOTAL

15.50
16.28 16.28
M2
Sub total TOTAL

7.66
8.19 8.19

M2
Sub total TOTAL

7.66
8.19 8.19

M2
Sub total TOTAL

33.55
35.90 35.90

M2
Sub total TOTAL

19.03
20.36 20.36

M2
Sub total TOTAL

11.84
12.67 12.67

M2
Sub total TOTAL

3.00
3.21 3.21

UND
Sub total TOTAL

1.00 1.00

UND
Sub total TOTAL

1.00 1.00

UND
Sub total TOTAL

1.00 1.00

M
Sub total TOTAL
9.00 9.00

M2
Sub total TOTAL

10.85 10.85

UND
Sub total TOTAL

60.00 60.00

UND
Sub total TOTAL

60.00 60.00

UND
Sub total TOTAL

60.00 60.00

UND
Sub total TOTAL

10.00 10.00

UND
Sub total TOTAL

60.00 60.00

UND
Sub total TOTAL

30.00 30.00

UND
Sub total TOTAL

10.00 10.00

UND
Sub total TOTAL
60.00 60.00

UND
Sub total TOTAL

10.00 10.00