SOLICITUD DE MATERIALES ESPECIFICOS SEGÚN CALENDARIO

DE UTILIZACION DE MATERIALES

MONOMIO 02 : AAM
Valor sin IGV Valor con IGV
Cod. Insumo UND CANT P.UNIT
S/. S/.
ACERO (IU: 03) 183,849.72
030032 FIERRO CORRUGADO PROMEDIO kg 54,592.07 2.83 154,495.56 183,849.72

AGREGADO GRUESO (IU: 05) 237,286.04


053102 MATERIAL DE CANTERA m3 96,273.05 1.50 144,409.58 171,847.40
050221 PIEDRA GRANDE m3 251.19 55.00 13,815.45 16,440.39
040000 ARENA FINA m3 549.00 75.00 41,175.00 48,998.25

MADERA (IU: 43) 76,813.99


430025 MADERA PARA ENCOFRADO p2 19,619.93 3.29 64,549.57 76,813.99

MONOMIO 03 : ACD
Valor sin IGV Valor con IGV
Cod. Insumo UND CANT P.UNIT
S/. S/.
ASFALTO (IU: 13) 962,263.55
130006 ASFALTO RC-250 gln 106,398.00 7.60 808,624.83 962,263.55

CEMENTO (IU: 03) 544,147.48


210000 CEMENTO PORTLAND TIPO I bls 27,899.13 16.39 457,266.79 544,147.48
MONTOS MAXIMOS PARA ADELANTO DE MATERIALES

MM= S_VAL x C x ( Ima / Imo) K = 0.125 (Mr / Mo) + 0.051 (AAMr / AAMo) + 0.221 (ACDVr / ACDo) + 0.408 (MMr / MMo) + + 0.195 (Ir / Io)

CONTRATO : A.D.P. Nº 0019-2009/ORA


OBRA : MEJORAMIENTO DEL CIRCUITO VIAL CHUPACA - SICAYA - VICSO - ACO - MITO, L = 22+044 - PROVINCIAS DE CHUPACA, HUANCAYO, CONCEPCION - JUNIN
PROPIETARIO : GOBIERNO REGIONAL JUNIN
CONTRATISTA : CONSORCIO VIAL
SUPERVISIÓN : GOBIERNO REGIONAL JUNIN

Monto contratado (C/IGV) S/.9,102,777.60


Fecha del Pto Base May-10
Saldo por valorizar programado (C/IGV) S/.9,102,777.60
Fecha de Solicitud Feb-11
AREA GEOGRAFICA : 3 0.515

MON SIM DESCRIPCION IND C % May-10 Feb-11 MONTOS MAXIMOS MONTOS ADELANTO A SALDOS MAXIMOS
% OTORGADO
Io Ia (S/.) SOLICITADOS (S/.) OTORGAR (S/.) (S/.)

01 M MANO DE O. INC. LEYES SOCIALES 47 0.125 100.00% 415.58 430.83 1,179,601.30 1,179,601.30
02 AAM ACERO DE CONSTRUCCION CORRUGADO 03 0.051 39.22% 518.10 517.58 181,892.83 183,849.72 181,892.83 2.00% 0.00
AGREGADO GRUESO 05 0.051 45.10% 335.82 438.98 273,689.94 237,286.04 237,286.04 2.61% 36,403.90
MADERA NACIONAL PARA ENCOF. Y CARPINT. 43 0.051 15.68% 684.87 736.11 78,239.26 76,813.99 76,813.99 0.84% 1,425.27
03 ACD ASFALTO 13 0.221 49.32% 1265.36 1265.36 992,177.27 962,263.55 962,263.55 10.57% 29,913.72
CEMENTO PORTLAND TIPO I 21 0.221 27.15% 357.75 357.75 546,180.31 544,147.48 544,147.48 5.98% 2,032.83
DOLAR 29 0.221 23.53% 361.46 358.95 470,069.25 470,069.25
04 MM MAQUINARIA Y EQUIPO NACIONAL 48 0.408 30.88% 334.68 332.35 1,138,878.28 1,138,878.28
MAQUINARIA Y EQUIPO IMPORTADO 49 0.408 69.12% 244.28 240.97 2,532,286.80 2,532,286.80
05 I INDICE GENERAL DE PRECIOS AL CONSUMIDOR 39 0.195 100.00% 351.51 354.67 1,790,998.88 1,790,998.88

TOTALES S/. 9,184,014.12 S/. 2,004,360.77 S/. 2,002,403.88 22.00% 7,181,610.24

MM = Monto Maximo de materiales


S_VAL = Saldo por Valorizar
C = Coeficiente del Monomio
Ima = Indice del Material a lafecha del Adelanto (se considera el indice del mes de Diciembre, por no salir publicado a la fecha el indice de Enero y Febrero)