PROYECTO: "MEJORAMIENTO DEL PARQUE CENTRAL DEL GRUPO 16 DEL AA.

GRUPO 16 DEL AA.HH UPIS HUASCAR, COMUNA 12, DISTRITO DE SAN JUAN DE LURIGANCHO - PROVINCIA DE LIMA - DEPARTAMENTO DE LIMA"

Cliente: MUNICIPALIDAD DISTRITAL DE SAN JUAN DE LURIGANCHO


Lugar: LIMA - LIMA - SAN JUAN DE LURIGANCHO

CRONOGRAMA VALORIZADO DE AVANCE DE OBRA

P. Unit. Parcial
Item Descripción Und Metrado Mes 1 Mes 2 TOTAL
S/. S/.

Parcial % Parcial % TOTAL %

01 OBRAS PROVISIONALES 1,953.33 1,953.33 100.00% 0.00 0.00% 1,953.33 100.00%

01.01 ALQUILER DE ALMACEN, OFICINA Y BAÑO mes 1.5 400 600.00 600.00 100.00% 0.00 0.00% 600.00 100.00%

01.02 CARTEL DE OBRA 3.60x7.20 und 1 1353.33 1,353.33 1,353.33 100.00% 0.00 0.00% 1,353.33 100.00%

02 TRABAJOS PRELIMINARES 621.27 621.27 100.00% 0.00 0.00% 621.27 100.00%

02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y HERRAMIENTAS glb 1 500 500.00 500.00 100.00% 0.00 0.00% 500.00 100.00%

02.02 TRAZO Y REPLANTEO m2 178.34 0.68 121.27 121.27 100.00% 0.00 0.00% 121.27 100.00%

03 CERCO METÁLICO PARA JARDINES 86,088.74 79,130.22 91.92% 6,958.52 8.08% 86,088.74 100.00%

03.01 MOVIMIENTO DE TIERRAS 817.81 817.81 100.00% 0.00 0.00% 817.81 100.00%

03.01.01 EXCAVACION A MANO EN TERRENO NORMAL m3 11.44 37.93 433.92 433.92 100.00% 0.00 0.00% 433.92 100.00%

03.01.02 ELIMINACION DE MATERIAL EXCEDENTE HASTA 25 Km m3 13.72 27.98 383.89 383.89 100.00% 0.00 0.00% 383.89 100.00%

03.02 CONCRETO SIMPLE 3,146.00 3,146.00 100.00% 0.00 0.00% 3,146.00 100.00%

03.02.01 CONCRETO F'C=140 KG/CM2 m3 11.44 275.00 3,146.00 3,146.00 100.00% 0.00 0.00% 3,146.00 100.00%

03.03 CARPINTERIA METALICA 82,124.93 75,166.41 91.53% 6,958.52 8.47% 82,124.93 100.00%

03.03.01 REJA METALICA PARA JARDIN m2 784.70 95.79 75,166.41 75,166.41 100.00% 0.00 0.00% 75,166.41 100.00%

03.03.02 PUERTA METALICA m2 13.20 182.28 2,406.10 0.00 0.00% 2,406.10 100.00% 2,406.10 100.00%

03.03.03 LOGOTIPO DE ACERO SEGUN DISEÑO und 94.00 48.43 4,552.42 0.00 0.00% 4,552.42 100.00% 4,552.42 100.00%

04 AREAS RECREATIVAS 12,775.89 12,775.89 100.00% 0.00 0.00% 12,775.89 100.00%

04.01 MOVIMIENTO DE TIERRAS 4,944.74 4,944.74 100.00% 0.00 0.00% 4,944.74 100.00%
PROYECTO: "MEJORAMIENTO DEL PARQUE CENTRAL DEL GRUPO 16 DEL AA.HH UPIS HUASCAR, COMUNA 12, DISTRITO DE SAN JUAN DE LURIGANCHO - PROVINCIA DE LIMA - DEPARTAMENTO DE LIMA"

Cliente: MUNICIPALIDAD DISTRITAL DE SAN JUAN DE LURIGANCHO


Lugar: LIMA - LIMA - SAN JUAN DE LURIGANCHO

CRONOGRAMA VALORIZADO DE AVANCE DE OBRA

P. Unit. Parcial
Item Descripción Und Metrado Mes 1 Mes 2 TOTAL
S/. S/.

Parcial % Parcial % TOTAL %

04.01.01 CORTE A NIVEL DE SUB RASANTE CON MAQUINARIA m3 36.41 12.84 467.50 467.50 100.00% 0.00 0.00% 467.50 100.00%

04.01.02 ELIMINACION DE MATERIAL EXCEDENTE HASTA 25 Km m3 43.69 27.98 1,222.45 1,222.45 100.00% 0.00 0.00% 1,222.45 100.00%

04.01.03 CONFORMACION Y COMPACTACION DE SUBRASANTE C/EQUIPO m2 364.07 8.94 3,254.79 3,254.79 100.00% 0.00 0.00% 3,254.79 100.00%

04.02 SUMINISTRO DE GRASS SINTETICO 7,831.15 7,831.15 100.00% 0.00 0.00% 7,831.15 100.00%

04.02.01 SUMINISTRO E INSTALACION DE GRASS SINTÉTICO m2 364.07 21.51 7,831.15 7,831.15 100.00% 0.00 0.00% 7,831.15 100.00%

05 VARIOS 10,573.17 482.43 4.56% 10,090.74 95.44% 10,573.17 100.00%

05.01 MANTENIMIENTO DE MINIGIMNASIO glb 1 482.43 482.43 482.43 100.00% 0.00 0.00% 482.43 100.00%

05.02 MANTENIMIENTO DE JUEGOS PARA NIÑOS glb 1 555.52 555.52 0.00 0.00% 555.52 100.00% 555.52 100.00%

05.03 MANTENIMIENTO DE TACHOS DE BASURA und 20 12.97 259.40 0.00 0.00% 259.40 100.00% 259.40 100.00%

05.04 MANTENIMIENTO DE POSTES DE ILUMINACION und 30 17.56 526.80 0.00 0.00% 526.80 100.00% 526.80 100.00%

05.05 MANTENIMIENTO DE BANCAS DE CONCRETO und 41 42.13 1,727.33 0.00 0.00% 1,727.33 100.00% 1,727.33 100.00%

05.06 REPOSICIÓN DE FAROLAS EN POSTES DE ILUMINACION und 30 106.63 3,198.90 0.00 0.00% 3,198.90 100.00% 3,198.90 100.00%

05.07 DESMONTAJE DE TACHOS DE BASURA und 7 14.44 101.08 0.00 0.00% 101.08 100.00% 101.08 100.00%

05.08 SUMINISTRO E INSTALACION DE TACHO DE BASURA und 7 410.67 2,874.69 0.00 0.00% 2,874.69 100.00% 2,874.69 100.00%

05.09 PODIO und 1 847.02 847.02 0.00 0.00% 847.02 100.00% 847.02 100.00%

06 SEGURIDAD Y SALUD 800.00 0.00 0.00% 800.00 100.00% 800.00 100.00%

ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE


06.01 glb 1 800 800.00 0.00 0.00% 800.00 100.00% 800.00 100.00%
SEGURIDAD Y SALUD EN EL TRABAJO

07 PLAN DE MANEJO AMBIENTAL 500.00 0.00 0.00% 500.00 100.00% 500.00 100.00%
PROYECTO: "MEJORAMIENTO DEL PARQUE CENTRAL DEL GRUPO 16 DEL AA.HH UPIS HUASCAR, COMUNA 12, DISTRITO DE SAN JUAN DE LURIGANCHO - PROVINCIA DE LIMA - DEPARTAMENTO DE LIMA"

Cliente: MUNICIPALIDAD DISTRITAL DE SAN JUAN DE LURIGANCHO


Lugar: LIMA - LIMA - SAN JUAN DE LURIGANCHO

CRONOGRAMA VALORIZADO DE AVANCE DE OBRA

P. Unit. Parcial
Item Descripción Und Metrado Mes 1 Mes 2 TOTAL
S/. S/.

Parcial % Parcial % TOTAL %

07.01 MITIGACION DE IMPACTO AMBIENTAL glb 1 500 500.00 250.00 50.00% 250.00 50.00% 500.00 100.00%

Costo Directo S/. 113,312.40 94,963.14 83.81% 18,349.26 16.19% 113,312.40 100.00%

Gastos Generales 10.00% S/. 11,331.24 9,496.31 83.81% 1,834.93 16.19% 11,331.24 100.00%

Utilidad 10.00% S/. 11,331.24 9,496.31 83.81% 1,834.93 16.19% 11,331.24 100.00%

Sub-Total S/. 135,974.88 113,955.76 83.81% 22,019.12 16.19% 135,974.88 100.00%

Impuesto General a las Ventas 18.00% S/. 24,475.48 20,512.04 83.81% 3,963.44 16.19% 24,475.48 100.00%

Total Final S/. 160,450.36 134,467.80 83.81% 25,982.56 16.19% 160,450.36 100.00%