Reporte de Avance de la Contratista

Código del Proyecto AC-12-576


Denominación del EXTENSION DE RED A RAMAL TUPAC AMARU
Proyecto

Periodo Desde: 9/5/2016 Al: 9/11/2016

1. AVANCE POR ENTREGABLE

Avance Acum.
Nro. Hito Criterio de Avance UN Total de Obra % Avance de Obra
de Obra

1 CALICATA Calicata/Calicata total. Und. 74.00 96.00 77.08%


Metro lineal de Corte/
2 CORTE, ROTURA ml. 2957.00 4750.00 62.25%
Metro lineal Total.
Metro lineal excavado/
3 EXCAVACIÓN ml. 3175.00 4750.00 66.84%
Metro lineal Total.
Metro lineal bajado de
4 TENDIDO DE TUBERIA AC ml. 3175.00 4750.00 66.84%
tuberia/ Metro lineal Total.
Junta realizada / Junta
5 SOLDADURA Und. 269.00 408.00 65.93%
Total.

6 ENSAYOS NO DESTRUCTIVOS END realizado/ END Total. Und. 264.00 404.00 65.35%

Mantas realizadas/ Manta


7 MANTAS Und. 243.00 408.00 59.56%
Total.
Metros lineal Pre-tapado
8 PRE-TAPADO AC Realizado/ Metro lineal ml. 3127.00 4750.00 65.83%
Pre-tapado Total.
Metro lineal Tapado
9 TAPADO Realizado/ Metro lineal ml. 3330.00 4750.00 70.11%
Tapado Total.
Metro lineal con
10 REPOSICIÓN reposición / Metro lineal ml. 2869.00 4750.00 60.40%
con reposción Total.
PRUEBA HIDRAULICA Y/O
13 0% /100% % 0.00 100% 0.00%
NEUMATICA

14 LIMPIEZA Y SECADO 0% /100% % 0.00 100% 0.00%

INSTALACION DE VALVULA EN
15 0% /100% % 0.00 100% 0.00%
CÁMARA

16 HOT TAP Y/O EMPALME 0% /100% % 0.00 100% 0.00%

17 LIMPIEZA FINAL 0% /100% % 0.00 100% 0.00%

2. CRONOGRAMA CON AVANCE DE OBRA

% Avance de Obra
100.00%
90.00%
80.00%
70.00%
60.00%
50.00%
40.00%
30.00%
20.00%
10.00%
0.00%
CALICATACORTE, ROTURA
EXCAVACIÓN
TENDIDO DE TUBERIA
SOLDADURA
AC
ENSAYOS NO DESTRUCTIVOS
MANTASPRE-TAPADO AC TAPADO PRUEBA
REPOSICIÓN
HIDRAULICA Y/O
LIMPIEZA
INSTALACION
NEUMATICA
Y SECADO
DE VALVULA
HOT TAP
ENY/O
CÁMARA
EMPALME
LIMPIEZA FINAL

% Avance de Obra
3. RECURSOS UTILIZADOS
Cantidad de trabajadores directos
Cantidad de trabajadores subcontratados
4. AVANCE DEL PROYECTO POR SEMANA
4.1 Indicadores
Sem 32 33 34 35 36 37
% Avance Programado 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
% Avance Real 54.17% 54.17% 54.17% 55.98% 57.93% 59.99%
4.2 Curva S del proyecto

Curva S
6; 7; 9; 99.00%
97.00%
98.00%
95.00%
100.00%
90.00%
90.00% 4; 85.00%
3; 80.00%
80.00% 75.00%
1; 70.00%
70.00% 52; 65.00%
60.00% 59.99%
57.93%
60.00% 50; 55.00% 54.17%
54.17%
53.92%
51.69% 54.17%
54.17%
54.17%
54.17%
54.17%
54.17%
54.17%
54.17%
54.17%
54.17%55.98%
54.17%
54.17%
49; 50.00% 49.44%
47.57%
46.80%
50.00% 48; 45.00% 45.14%
44.00%
42.72%
42.65%
42.29%
40.00% 40.31%
38.85%
38.73%
38.06%
40.00% 46; 35.00% 36.48%
35.68%
35.49%
35.10%
45; 30.00% 27.35% 32.23%
29.82%
30.00% 44; 25.00% 23.22%
25.58%
20.00% 47;48; 18.55%
16.98%
20.00% 41; 42; 15.00%
44; 46;
45; 14.18%
11.76%
11.00%
10.00%
42;43; 9.95%
7.70% 20.69%
39;40;
10.00% 40; 5.00%
41; 4.15%
2.58%
2.00%0.87%
0.00%
3940414243444546474849505152 1 2 3 4 5 6 7 8 9 10111213141516171819202122232425262728293031323334353637
AVANCE PROGRAMADO AVANCE REAL

5. AVANCE DE BAJADA DE TUBERIA POR SEMANA (solo para extensiones de red)


5.1 Indicadores
Sem 32 33 34 35 36 37
% Avance Programado 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
% Avance Real 56.82% 56.82% 56.82% 56.82% 58.40% 60.40%
5.2 Curva S del proyecto

Curva S con tendido de tubería con reposición


10;11;
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100.00%
88% 9; 88%
90.00%
80.00% 6; 7;
76%76%
4;
68%68%
70.00% 2; 3;
60%60% 60.40%
56.82%
56.82%
56.82%
56.82%
56.82%
56.82%
56.82%
56.82%
56.82%
56.82%
56.82%
56.82%
56.82%58.40%
56.82%
56.82%
60.00% 52;
52%52% 52.61%
51.14%
49.14%
48.46%
46.51%
50.00% 50;51;
44%44% 43.45%
43.45%
43.45%
43.45%
48;
49;
36%
36% 35.56%
35.56% 38.82%
36.51%
36.51%
35.56% 38.82%
38.82%
40.00% 31.98%
46;
28%28% 28.61%
25.45%
30.00% 22.93%
22.93%
20%45; 20%
48; 18.08%
18.08%
20.00% 43;45;
46;
10%11.62%
47;
11.62%
11.62%
10% 44; 9.43%
10.00%39; 42;43; 7.01% 18.08%
4.27%
0%40;
0.00%
40;
41;
0.00%
41;
0%
0.00%
0%
0.00%
3940414243444546474849505152 1 2 3 4 5 6 7 8 9 10111213141516171819202122232425262728293031323334353637
AVANCE PROGRAMADO AVANCE REAL

Toda impresión o copia de este documento que este fuera del entorno de la carpeta M/Documentos Normativos no garantiza que
sea el VIGENTE.
F-COO-110_V1 Fecha de vigencia: 24/06/2014 Pagina 1 de 1