DRILLING ENGINEERING I

DRILLING RIG
SELECTION CRITERIA
The selection procedure to follow is the next:
1. Design the well
2. Establish various loads expected during drilling and testing and use
the highest.
3. Compare the ratings of the rigs with the design loads.
4. Select the appropriate rig and its components.
RIG REQUIREMENTS - HOSTING
 Drilling line
RIG REQUIREMENTS - HOSTING
 Power developed in the hook

Power requirements at drawworks

Torque requirements at drawworks

Safety factor
RIG REQUIREMENTS - HOSTING
 Hosting efficiency

Where,
Carga estática del taladro [lb], Número de líneas ensartadas al bloque viajero
Carga sobre el gancho [lb], Tensión de la línea muerta [lb], Tensión de la línea
rápida [lb] Eficiencia de levantamiento, Velocidad de la línea rápida [ft/min],
Velocidad del gancho [ft/min], Velocidad de rotación del malacate [rpm],
Diámetro del tambor del malacate [ft], Potencia en el gancho [hp], Potencia del
malacate [hp], Torque del malacate [ft.lb], Factor de seguridad, Carga de
ruptura de la línea de perforación [lb], Factor de fricción de polea y línea por
cada polea (1.09 para cojinetes planos o 1.04 para cojinetes esféricos)
RIG REQUIREMENTS - HOSTING
Componentes Factor de seguridad
Cable del taladro 3
Línea a tierra 3
Línea de perforación rotaria 3
Otra línea de levantamiento 3
Línea de levantamiento del
2.5
mástil
Línea de perforación durante
2
corrida del Casing
Tensión extra para liberar
herramienta u 2
otras operaciones ocasionales
RIG REQUIREMENTS - ROTARY
 Power required at the rotary table.
RIG REQUIREMENTS -
CIRCULATION
 • Theorical flow rate at duplex pump 90% ef

• Theorical flow rate at triplex pump 95% ef

• Volumetric efficiency

• Hydraulic power
RIG REQUIREMENTS -
CIRCULATION
•  Required power at motor

• Duplex-triplex pump factor

Mechanic efficiency is around 85% due to the power lost at the components.

Where:

Caudal teórico [gpm], Strokes por minuto [strokes/min, Longitud del Stroke [in],
Diámetro de la camisa [in], Diámetro del pistón [in], Caudal real [gpm], Presión de
descarga [psi], Eficiencia volumétrica, Eficiencia mecánica, Eficiencia compuesta (V-
belt=0.97; chains=0.95; torque converter=0.7-0.9), Potencia del motor [hp], Factor de
bomba [bbl/stroke], Número de cilindros
RIG REQUIREMENTS - BOP
Blowout preventer
It can be specified as:
5M – 13 5/8 – SRRA

Where:
5M= working pressure rate
13 5/8= preventer inside diameter
S= drilling spool
R=ram preventers
A=annular preventer
RIG REQUIREMENTS –
GENERATORS
• The energy requirement for a drilling rig could be between 1500 and
3000 hp and be generated by 3 to 5 generators.
• Power should cover all the equipment requirement at the drilling rig
systems.
• It is calculated as the sum of power required at each system.
RIG REQUIREMENTS –
SUBSTRUCTURE
 
Rig load are calculated considering the worst situation, which can
be the following criteria:
• It is running the heaviest casing string and the string get stuck at the
TD, so maximum overpull is applied.
• All drilling pipe stands are on the drilling floor.
• Worst case load

Static load
RIG REQUIREMENTS –
SUBSTRUCTURE
•  Dynamic load

Where:
Peor caso de carga en el taladro [lb], Peso de la tubería en el taladro [lb],
Carga del Casing con pega [lb], Longitud de la tubería de perforación [ft] Peso
de la tubería de perforación [lb/ft], Longitud del BHA (Drill Collar + BHA) de
perforación [ft], Peso del BHA (Drill Collar + BHA) de perforación [lb/ft],
Longitud de HWDP [ft], WHWDP= Peso del HWDP [lb/ft], LSC= Longitud del
Casing en pega [ft], WCSG= Peso del Casing [lb/ft]
Overpullmax= La tensión aplicada para liberar la sarta de una pega [lb],
Hosting= Peso del bloque viajero más el peso del Top Drive y demás equipos
del sistema de levantamiento [lb], DDL= Carga dinámica del taladro [lb], F=
Carga sobre el gancho [lb], t= Tensión de la línea muerta [lb], ta= Tensión de la
línea rápida [lb].