PRECIOS UNITARIOS

RENGLON UNIDAD CANTIDAD PRE. UNIT TOTAL


PRELIMINARES M2 73.26
BODEGA Y GUARDIANIA UNIDAD 1.00

MATERIALES Y EQUIPO
BODEGA Y GUARDIANIA UNIDAD 1.00
PARALES UNIDAD 24.00 Q 25.00 Q 600.00
LAMINAS 12" UNIDAD 24.00 Q 134.00 Q 3,216.00
CLAVOS DE 3' LIBRA 2.00 Q 10.00 Q 20.00
CLAVO DE LAMINA LIBRA 2.00 Q 15.00 Q 30.00
BISAGRAS UNIDAD 2.00 Q 15.00 Q 30.00
CANDADO UNIDAD 1.00 Q 60.00 Q 60.00
CADENA PIE 3.00 Q 25.00 Q 75.00
SANITARIO UNIDAD 1.00 Q 500.00 Q 500.00
TOTAL DE MATERIALES Q 4,531.00

MANO DE OBRA
BODEGA Y GUARDIANIA DIA 2.00 Q 525.00 Q 1,050.00
LIMPIEZA Y CHAPEO M2 73.26 Q 9.00 Q 659.34
NIVELACION DE TERRENO M2 73.26 Q 15.00 Q 1,098.90
TRAZO Y ESTAQUEO M2 73.26 Q 8.00 Q 586.08
TOTAL MANO DE OBRA Q 3,394.32

FLETES
TOTAL DE FLETES UNIDAD 1.00 Q 150.00 Q 150.00

COSTE DIRECTO (MATERIAL Y EQUIPO + FLETE + MANO DE OBRA) Q 8,075.32


COSTO INDIRECTO Q 2,826.36
COSTO TOTAL Q 10,901.68
COSTO UNITARIO Q 148.81
PRECIOS UNITARIOS
RENGLON UNIDAD CANTIDAD PRE. UNIT TOTAL
CIMIENTO CORRIDO ML 57.50

MATERIALES Y EQUIPO
CEMENTO SACO 46.00 Q 80.00 Q 3,680.00
ARENA M3 4.60 Q 150.00 Q 690.00
PIEDRIN 1/2" M3 4.60 Q 260.00 Q 1,196.00
ALAMBRE DE AMARRE LIBRA 18.00 Q 8.00 Q 144.00
VARILLA DE 3/8" VARILLA 46.00 Q 31.00 Q 1,426.00
SILLETAS UNIDAD 116.00 Q 2.00 Q 232.00
BAILARINA DIA 1.00 Q 300.00 Q 300.00
BASE (CASCAJO) M3 2.30 Q 150.00 Q 345.00
CEMENTO (CASCAJO) SACO 3.00 Q 80.00 Q 240.00
TOTAL DE MATERIALES Q 8,253.00

MANO DE OBRA
CIMIENTO CORRIDO ML 35.00 Q 90.00 Q 3,150.00
Q - Q -
Q - Q -
Q - Q -
TOTAL MANO DE OBRA Q 3,150.00

FLETES
FLETES VIAJE 1.00 Q 150.00 Q 150.00

COSTE DIRECTO (MATERIAL Y EQUIPO + FLETE + MANO DE OBRA) Q 11,553.00


COSTO INDIRECTO Q 4,043.55
COSTO TOTAL Q 15,596.55
COSTO UNITARIO Q 271.24
PRECIOS UNITARIOS
RENGLON UNIDAD CANTIDAD PRE. UNIT TOTAL
ZAPATAS UNIDAD 2.50

MATERIALES Y EQUIPO
CEMENTO SACO 25.00 Q 80.00 Q 2,000.00
ARENA M3 2.50 Q 150.00 Q 375.00
PIEDRIN 1/2" M3 2.50 Q 260.00 Q 650.00
ALAMBRE DE AMARRE LIBRA 20.00 Q 8.00 Q 160.00
VARILLA DE 1/2" VARILLA 30.00 Q 55.00 Q 1,650.00
SILLETAS UNIDAD 40.00 Q 2.00 Q 80.00
BASE (CASCAJO) M3 1.00 Q 150.00 Q 150.00
CEMENTO (CASCAJO) SACO 2.00 Q 80.00 Q 160.00
TOTAL DE MATERIALES Q 5,225.00

MANO DE OBRA
ZAPATAS UNIDAD 9.00 Q 120.00 Q 1,080.00
Q - Q -
Q - Q -
Q - Q -
TOTAL MANO DE OBRA Q 1,080.00

FLETES
FLETES UNIDAD 1.00 Q 150.00 Q 150.00

COSTE DIRECTO (MATERIAL Y EQUIPO + FLETE + MANO DE OBRA) Q 6,455.00


COSTO INDIRECTO Q 2,259.25
COSTO TOTAL Q 8,714.25
COSTO UNITARIO Q 3,485.70
PRECIOS UNITARIOS
RENGLON UNIDAD CANTIDAD PRE. UNIT TOTAL
LEVANTADO DE BLOCK DE 0..14*0.190.39 DE 50KG/CM2 M2 23.00

MATERIALES Y EQUIPO

BLOCK DE 0.14 * 0.19 * 0.39 DE 50 KG/CM2 UNIDAD 300.00 Q 6.00 Q 1,800.00


CEMENTO SACO 5.00 Q 80.00 Q 400.00
ARENA M3 0.50 Q 150.00 Q 75.00
CAL SACO 1.25 Q 32.00 Q 40.00
Q - Q -
Q - Q -
Q - Q -
TOTAL DE MATERIALES Q 2,315.00

MANO DE OBRA
LEVANTADO DE BLOCK DE 0.14 * 0.19 * 0.39 DE 50 KG/CM2 M2 23.00 Q 75.00 Q 1,725.00
Q - Q -
Q - Q -
Q - Q -
TOTAL MANO DE OBRA Q 1,725.00

FLETES
FLETES VIAJE 1.00 Q 400.00 Q 400.00

COSTE DIRECTO (MATERIAL Y EQUIPO + FLETE + MANO DE OBRA) Q 4,440.00


COSTO INDIRECTO Q 1,554.00
COSTO TOTAL Q 5,994.00
COSTO UNITARIO Q 260.61
PRECIOS UNITARIOS
RENGLON UNIDAD CANTIDAD PRE. UNIT TOTAL
LEVANTADO DE SOLERA DE HUMEDAD ML 57.50

MATERIALES Y EQUIPO
CEMENTO SACO 17.30 Q 80.00 Q 1,384.00
ARENA M3 1.73 Q 150.00 Q 259.50
PIEDRIN M3 1.73 Q 260.00 Q 449.80
ALAMBRE DE AMARRE LIBRA 21.00 Q 8.00 Q 168.00
VARILLA DE 3/8" UNIDAD 41.00 Q 35.00 Q 1,435.00
VARILLAS DE 1/4" UNIDAD 29.00 Q 13.15 Q 381.35
MADERA DOCENA 2.00 Q 600.00 Q 1,200.00
Q - Q -
TOTAL DE MATERIALES Q 5,277.65

MANO DE OBRA
SOLERA DE HUMEDAD DE 0.15 * 0.20 * 35 ML ML 57.50 Q 50.00 Q 2,875.00
Q - Q -
Q - Q -
Q - Q -
TOTAL MANO DE OBRA Q 2,875.00

FLETES
FLETES VIAJE 1.00 Q 400.00 Q 400.00

COSTE DIRECTO (MATERIAL Y EQUIPO + FLETE + MANO DE OBRA) Q 8,552.65


COSTO INDIRECTO Q 2,993.43
COSTO TOTAL Q 11,546.08
COSTO UNITARIO Q 200.80
PRECIOS UNITARIOS
RENGLON UNIDAD CANTIDAD PRE. UNIT TOTAL
COLUMNA TIPO A DE 0.20*0.15 UNIDAD 10.00

MATERIALES Y EQUIPO
CEMENTO SACO 10.20 Q 80.00 Q 816.00
ARENA M3 1.02 Q 150.00 Q 153.00
PIEDRIN M3 1.00 Q 260.00 Q 260.00
ALAMBRE DE AMARRE LIBRA 15 Q 8.00 Q 120.00
VARILLA DE 3/8" UNIDAD 24 Q 35.00 Q 840.00
VARILLAS DE 1/4" UNIDAD 34 Q 13.15 Q 447.10
MADERA DOCENA 1.5 Q 600.00 Q 900.00
TOTAL DE MATERIALES Q 3,536.10

MANO DE OBRA
ARMADO DE COLUMNA TIPO A UNIDAD 10.00 Q 55.00 Q 550.00
Q - Q -
Q - Q -
Q - Q -
TOTAL MANO DE OBRA Q 550.00

FLETES
FLETES VIAJE 1.00 Q 400.00 Q 400.00

COSTE DIRECTO (MATERIAL Y EQUIPO + FLETE + MANO DE OBRA) Q 4,486.10


COSTO INDIRECTO Q 1,570.14
COSTO TOTAL Q 6,056.24
COSTO UNITARIO Q 605.62
PRECIOS UNITARIOS
RENGLON UNIDAD CANTIDAD PRE. UNIT TOTAL
COLUMNA TIPO B DE 0.15x0.15x3.40M UNIDAD 10.00

MATERIALES Y EQUIPO
CEMENTO SACO 6.30 Q 80.00 Q 504.00
ARENA M3 0.63 Q 150.00 Q 94.50
PIEDRIN M3 0.63 Q 260.00 Q 163.80
ALAMBRE DE AMARRE LIBRA 11 Q 8.00 Q 88.00
VARILLA DE 3/8" UNIDAD 20 Q 35.00 Q 700.00
VARILLAS DE 1/4" UNIDAD 16 Q 13.15 Q 210.40
MADERA DOCENA 2 Q 600.00 Q 1,200.00
TOTAL DE MATERIALES Q 2,960.70

MANO DE OBRA
ARMADO DE COLUMNA TIPO B UNIDAD 10.00 Q 50.00 Q 500.00
Q - Q -
Q - Q -
Q - Q -
TOTAL MANO DE OBRA Q 500.00

FLETES
FLETES VIAJE 1.00 Q 400.00 Q 400.00

COSTE DIRECTO (MATERIAL Y EQUIPO + FLETE + MANO DE OBRA) Q 3,860.70


COSTO INDIRECTO Q 1,351.25
COSTO TOTAL Q 5,211.95
COSTO UNITARIO Q 521.19
PRECIOS UNITARIOS
RENGLON UNIDAD CANTIDAD PRE. UNIT TOTAL
COLUMNA TIPO C DE 0.15x0.10x3.40M UNIDAD 16.00

MATERIALES Y EQUIPO
CEMENTO SACO 6.72 Q 80.00 Q 537.60
ARENA M3 0.67 Q 150.00 Q 100.50
PIEDRIN M3 0.67 Q 260.00 Q 174.20
ALAMBRE DE AMARRE LIBRA 9 Q 8.00 Q 72.00
VARILLA DE 3/8" UNIDAD 16 Q 35.00 Q 560.00
VARILLAS DE 1/4" UNIDAD 15 Q 13.15 Q 197.25
MADERA DOCENA 2 Q 600.00 Q 1,200.00
TOTAL DE MATERIALES Q 2,841.55

MANO DE OBRA
ARMADO DE COLUMNA TIPO C UNIDAD 10.00 Q 55.00 Q 550.00
Q - Q -
Q - Q -
Q - Q -
TOTAL MANO DE OBRA Q 550.00

FLETES
FLETES VIAJE 1.00 Q 400.00 Q 400.00

COSTE DIRECTO (MATERIAL Y EQUIPO + FLETE + MANO DE OBRA) Q 3,791.55


COSTO INDIRECTO Q 1,327.04
COSTO TOTAL Q 5,118.59
COSTO UNITARIO Q 319.91
PRECIOS UNITARIOS
RENGLON UNIDAD CANTIDAD PRE. UNIT TOTAL
LEVANTADO DE MURO CON BLOCK 0.14 * 0.19 0.39 DE 50 KG/ M2 97.53

MATERIALES Y EQUIPO
CEMENTO SACO 19.00 Q 80.00 Q 1,520.00
ARENA M3 1.90 Q 150.00 Q 285.00
CAL SACO 5.00 Q 32.00 Q 160.00
BLOCK UNIDAD 1268 Q 6.00 Q 7,608.00
Q - Q -
Q - Q -
Q - Q -
TOTAL DE MATERIALES Q 9,573.00

MANO DE OBRA
LEVANTADO DE BLOCK M2 97.53 Q 75.00 Q 7,314.75
Q - Q -
Q - Q -
Q - Q -
TOTAL MANO DE OBRA Q 7,314.75

FLETES
FLETES VIAJE 1.00 Q 400.00 Q 400.00

COSTE DIRECTO (MATERIAL Y EQUIPO + FLETE + MANO DE OBRA) Q 17,287.75


COSTO INDIRECTO Q 6,050.71
COSTO TOTAL Q 23,338.46
COSTO UNITARIO Q 239.30
PRECIOS UNITARIOS
RENGLON UNIDAD CANTIDAD PRE. UNIT TOTAL
LEVANTADO DE SOLERA INTERMEDIA 1ER NIVEL ML 51.06

MATERIALES Y EQUIPO
CEMENTO SACOS 16.00 Q 80.00 Q 1,280.00
ARENA M3 1.60 Q 150.00 Q 240.00
PIERDIN M3 1.60 Q 260.00 Q 416.00
ALAMBRE DE AMARRE LBS 18.20 Q 8.00 Q 145.60
HIERRO 1/4 UNIDAD 26 Q 13.15 Q 341.90
HIERRO 3/8 UNIDAD 36 Q 35.00 Q 1,260.00
MADERA DOCENA 1.5 Q 600.00 Q 900.00
Q - Q -
TOTAL DE MATERIALES Q 4,583.50

MANO DE OBRA
LEVANTADO DE SOLERA INTERMEDIA ML 51.06 Q 50.00 Q 2,553.00
Q - Q -
Q - Q -
Q - Q -
TOTAL MANO DE OBRA Q 2,553.00

FLETES
FLETES VIAJE 1.00 Q 400.00 Q 400.00

COSTE DIRECTO (MATERIAL Y EQUIPO + FLETE + MANO DE OBRA) Q 7,536.50


COSTO INDIRECTO Q 2,637.77
COSTO TOTAL Q 10,174.28
COSTO UNITARIO Q 199.26
PRECIOS UNITARIOS
RENGLON UNIDAD CANTIDAD PRE. UNIT TOTAL
LEVANTADO DE SOLERA CORONA 1ER NIVEL ML 57.50

MATERIALES Y EQUIPO
CEMENTO SACOS 18.00 Q 80.00 Q 1,440.00
ARENA M3 1.80 Q 150.00 Q 270.00
PIERDIN M3 1.80 Q 260.00 Q 468.00
ALAMBRE DE AMARRE LBS 21.00 Q 8.00 Q 168.00
HIERRO 1/4 UNIDAD 29 Q 13.15 Q 381.35
HIERRO 3/8 UNIDAD 41 Q 35.00 Q 1,435.00
MADERA DOCENA 2 Q 600.00 Q 1,200.00
ANDAMIOS DIA 6 Q 20.00 Q 120.00
TOTAL DE MATERIALES Q 5,482.35

MANO DE OBRA
LEVANTADO DE SOLERA CORONA ML 57.50 Q 50.00 Q 2,875.00
Q - Q -
Q - Q -
Q - Q -
TOTAL MANO DE OBRA Q 2,875.00

FLETES
FLETES VIAJE 1.00 Q 400.00 Q 400.00

COSTE DIRECTO (MATERIAL Y EQUIPO + FLETE + MANO DE OBRA) Q 8,757.35


COSTO INDIRECTO Q 3,065.07
COSTO TOTAL Q 11,822.42
COSTO UNITARIO Q 205.61
PRECIOS UNITARIOS
RENGLON UNIDAD CANTIDAD PRE. UNIT TOTAL
LOSA DE PRIMER NIVEL M2 55.55

MATERIALES Y EQUIPO
CEMENTO SACOS 123.00 Q 80.00 Q 9,840.00
ARENA M3 12.30 Q 150.00 Q 1,845.00
PIERDIN M3 12.30 Q 260.00 Q 3,198.00
ALAMBRE DE AMARRE LBS 75.00 Q 8.00 Q 600.00
HIERRO DE 3/8" UNIDAD 195 Q 35.00 Q 6,825.00
CLAVO LBS 18 Q 10.00 Q 180.00
TABLA RENTADA DOCENA 4.5 Q 75.00 Q 337.50
TABLA COMPRADA DOCENA 2 Q 600.00 Q 1,200.00
PARALES RENTA DOCENA 1.5 Q 75.00 Q 112.50
PARALES COMPRA DOCENA 9 Q 600.00 Q 5,400.00
SILLETAS UNIDAD 200 Q 2.00 Q 400.00
Q -
VIBRADOR DIA 1 Q 300.00 Q 300.00
TOTAL DE MATERIALES Q 30,238.00

MANO DE OBRA
ARMADO DE LOSA M2 55.55 Q 125.00 Q 6,943.75
COLADO DE LOSA SACO 123.00 Q 33.33 Q 4,099.59
Q - Q -
Q - Q -
TOTAL MANO DE OBRA Q 11,043.34

FLETES
FLETES VIAJE 1.00 Q 400.00 Q 400.00

COSTE DIRECTO (MATERIAL Y EQUIPO + FLETE + MANO DE OBRA) Q 41,681.34


COSTO INDIRECTO Q 14,588.47
COSTO TOTAL Q 56,269.81
COSTO UNITARIO Q 1,012.96