BODEGA Y GUARDIANIA UNIDAD 1.00
PARALES UNIDAD 24.00 Q 25.00 Q 600.00
LAMINAS 12" UNIDAD 24.00 Q 134.00 Q 3,216.00
CLAVOS DE 3' LIBRA 2.00 Q 10.00 Q 20.00
CLAVO DE LAMINA LIBRA 2.00 Q 15.00 Q 30.00
BISAGRAS UNIDAD 2.00 Q 15.00 Q 30.00
CANDADO UNIDAD 1.00 Q 60.00 Q 60.00
CADENA PIE 3.00 Q 25.00 Q 75.00
SANITARIO UNIDAD 1.00 Q 500.00 Q 500.00
TOTAL DE MATERIALES Q 4,531.00
MANO DE OBRA
BODEGA Y GUARDIANIA DIA 2.00 Q 525.00 Q 1,050.00
LIMPIEZA Y CHAPEO M2 73.26 Q 9.00 Q 659.34
NIVELACION DE TERRENO M2 73.26 Q 15.00 Q 1,098.90
TRAZO Y ESTAQUEO M2 73.26 Q 8.00 Q 586.08
TOTAL MANO DE OBRA Q 3,394.32
FLETES
TOTAL DE FLETES UNIDAD 1.00 Q 150.00 Q 150.00
MATERIALES Y EQUIPO
CEMENTO SACO 46.00 Q 80.00 Q 3,680.00
ARENA M3 4.60 Q 150.00 Q 690.00
PIEDRIN 1/2" M3 4.60 Q 260.00 Q 1,196.00
ALAMBRE DE AMARRE LIBRA 18.00 Q 8.00 Q 144.00
VARILLA DE 3/8" VARILLA 46.00 Q 31.00 Q 1,426.00
SILLETAS UNIDAD 116.00 Q 2.00 Q 232.00
BAILARINA DIA 1.00 Q 300.00 Q 300.00
BASE (CASCAJO) M3 2.30 Q 150.00 Q 345.00
CEMENTO (CASCAJO) SACO 3.00 Q 80.00 Q 240.00
TOTAL DE MATERIALES Q 8,253.00
MANO DE OBRA
CIMIENTO CORRIDO ML 35.00 Q 90.00 Q 3,150.00
Q - Q -
Q - Q -
Q - Q -
TOTAL MANO DE OBRA Q 3,150.00
FLETES
FLETES VIAJE 1.00 Q 150.00 Q 150.00
MATERIALES Y EQUIPO
CEMENTO SACO 25.00 Q 80.00 Q 2,000.00
ARENA M3 2.50 Q 150.00 Q 375.00
PIEDRIN 1/2" M3 2.50 Q 260.00 Q 650.00
ALAMBRE DE AMARRE LIBRA 20.00 Q 8.00 Q 160.00
VARILLA DE 1/2" VARILLA 30.00 Q 55.00 Q 1,650.00
SILLETAS UNIDAD 40.00 Q 2.00 Q 80.00
BASE (CASCAJO) M3 1.00 Q 150.00 Q 150.00
CEMENTO (CASCAJO) SACO 2.00 Q 80.00 Q 160.00
TOTAL DE MATERIALES Q 5,225.00
MANO DE OBRA
ZAPATAS UNIDAD 9.00 Q 120.00 Q 1,080.00
Q - Q -
Q - Q -
Q - Q -
TOTAL MANO DE OBRA Q 1,080.00
FLETES
FLETES UNIDAD 1.00 Q 150.00 Q 150.00
MATERIALES Y EQUIPO
MANO DE OBRA
LEVANTADO DE BLOCK DE 0.14 * 0.19 * 0.39 DE 50 KG/CM2 M2 23.00 Q 75.00 Q 1,725.00
Q - Q -
Q - Q -
Q - Q -
TOTAL MANO DE OBRA Q 1,725.00
FLETES
FLETES VIAJE 1.00 Q 400.00 Q 400.00
MATERIALES Y EQUIPO
CEMENTO SACO 17.30 Q 80.00 Q 1,384.00
ARENA M3 1.73 Q 150.00 Q 259.50
PIEDRIN M3 1.73 Q 260.00 Q 449.80
ALAMBRE DE AMARRE LIBRA 21.00 Q 8.00 Q 168.00
VARILLA DE 3/8" UNIDAD 41.00 Q 35.00 Q 1,435.00
VARILLAS DE 1/4" UNIDAD 29.00 Q 13.15 Q 381.35
MADERA DOCENA 2.00 Q 600.00 Q 1,200.00
Q - Q -
TOTAL DE MATERIALES Q 5,277.65
MANO DE OBRA
SOLERA DE HUMEDAD DE 0.15 * 0.20 * 35 ML ML 57.50 Q 50.00 Q 2,875.00
Q - Q -
Q - Q -
Q - Q -
TOTAL MANO DE OBRA Q 2,875.00
FLETES
FLETES VIAJE 1.00 Q 400.00 Q 400.00
MATERIALES Y EQUIPO
CEMENTO SACO 10.20 Q 80.00 Q 816.00
ARENA M3 1.02 Q 150.00 Q 153.00
PIEDRIN M3 1.00 Q 260.00 Q 260.00
ALAMBRE DE AMARRE LIBRA 15 Q 8.00 Q 120.00
VARILLA DE 3/8" UNIDAD 24 Q 35.00 Q 840.00
VARILLAS DE 1/4" UNIDAD 34 Q 13.15 Q 447.10
MADERA DOCENA 1.5 Q 600.00 Q 900.00
TOTAL DE MATERIALES Q 3,536.10
MANO DE OBRA
ARMADO DE COLUMNA TIPO A UNIDAD 10.00 Q 55.00 Q 550.00
Q - Q -
Q - Q -
Q - Q -
TOTAL MANO DE OBRA Q 550.00
FLETES
FLETES VIAJE 1.00 Q 400.00 Q 400.00
MATERIALES Y EQUIPO
CEMENTO SACO 6.30 Q 80.00 Q 504.00
ARENA M3 0.63 Q 150.00 Q 94.50
PIEDRIN M3 0.63 Q 260.00 Q 163.80
ALAMBRE DE AMARRE LIBRA 11 Q 8.00 Q 88.00
VARILLA DE 3/8" UNIDAD 20 Q 35.00 Q 700.00
VARILLAS DE 1/4" UNIDAD 16 Q 13.15 Q 210.40
MADERA DOCENA 2 Q 600.00 Q 1,200.00
TOTAL DE MATERIALES Q 2,960.70
MANO DE OBRA
ARMADO DE COLUMNA TIPO B UNIDAD 10.00 Q 50.00 Q 500.00
Q - Q -
Q - Q -
Q - Q -
TOTAL MANO DE OBRA Q 500.00
FLETES
FLETES VIAJE 1.00 Q 400.00 Q 400.00
MATERIALES Y EQUIPO
CEMENTO SACO 6.72 Q 80.00 Q 537.60
ARENA M3 0.67 Q 150.00 Q 100.50
PIEDRIN M3 0.67 Q 260.00 Q 174.20
ALAMBRE DE AMARRE LIBRA 9 Q 8.00 Q 72.00
VARILLA DE 3/8" UNIDAD 16 Q 35.00 Q 560.00
VARILLAS DE 1/4" UNIDAD 15 Q 13.15 Q 197.25
MADERA DOCENA 2 Q 600.00 Q 1,200.00
TOTAL DE MATERIALES Q 2,841.55
MANO DE OBRA
ARMADO DE COLUMNA TIPO C UNIDAD 10.00 Q 55.00 Q 550.00
Q - Q -
Q - Q -
Q - Q -
TOTAL MANO DE OBRA Q 550.00
FLETES
FLETES VIAJE 1.00 Q 400.00 Q 400.00
MATERIALES Y EQUIPO
CEMENTO SACO 19.00 Q 80.00 Q 1,520.00
ARENA M3 1.90 Q 150.00 Q 285.00
CAL SACO 5.00 Q 32.00 Q 160.00
BLOCK UNIDAD 1268 Q 6.00 Q 7,608.00
Q - Q -
Q - Q -
Q - Q -
TOTAL DE MATERIALES Q 9,573.00
MANO DE OBRA
LEVANTADO DE BLOCK M2 97.53 Q 75.00 Q 7,314.75
Q - Q -
Q - Q -
Q - Q -
TOTAL MANO DE OBRA Q 7,314.75
FLETES
FLETES VIAJE 1.00 Q 400.00 Q 400.00
MATERIALES Y EQUIPO
CEMENTO SACOS 16.00 Q 80.00 Q 1,280.00
ARENA M3 1.60 Q 150.00 Q 240.00
PIERDIN M3 1.60 Q 260.00 Q 416.00
ALAMBRE DE AMARRE LBS 18.20 Q 8.00 Q 145.60
HIERRO 1/4 UNIDAD 26 Q 13.15 Q 341.90
HIERRO 3/8 UNIDAD 36 Q 35.00 Q 1,260.00
MADERA DOCENA 1.5 Q 600.00 Q 900.00
Q - Q -
TOTAL DE MATERIALES Q 4,583.50
MANO DE OBRA
LEVANTADO DE SOLERA INTERMEDIA ML 51.06 Q 50.00 Q 2,553.00
Q - Q -
Q - Q -
Q - Q -
TOTAL MANO DE OBRA Q 2,553.00
FLETES
FLETES VIAJE 1.00 Q 400.00 Q 400.00
MATERIALES Y EQUIPO
CEMENTO SACOS 18.00 Q 80.00 Q 1,440.00
ARENA M3 1.80 Q 150.00 Q 270.00
PIERDIN M3 1.80 Q 260.00 Q 468.00
ALAMBRE DE AMARRE LBS 21.00 Q 8.00 Q 168.00
HIERRO 1/4 UNIDAD 29 Q 13.15 Q 381.35
HIERRO 3/8 UNIDAD 41 Q 35.00 Q 1,435.00
MADERA DOCENA 2 Q 600.00 Q 1,200.00
ANDAMIOS DIA 6 Q 20.00 Q 120.00
TOTAL DE MATERIALES Q 5,482.35
MANO DE OBRA
LEVANTADO DE SOLERA CORONA ML 57.50 Q 50.00 Q 2,875.00
Q - Q -
Q - Q -
Q - Q -
TOTAL MANO DE OBRA Q 2,875.00
FLETES
FLETES VIAJE 1.00 Q 400.00 Q 400.00
MATERIALES Y EQUIPO
CEMENTO SACOS 123.00 Q 80.00 Q 9,840.00
ARENA M3 12.30 Q 150.00 Q 1,845.00
PIERDIN M3 12.30 Q 260.00 Q 3,198.00
ALAMBRE DE AMARRE LBS 75.00 Q 8.00 Q 600.00
HIERRO DE 3/8" UNIDAD 195 Q 35.00 Q 6,825.00
CLAVO LBS 18 Q 10.00 Q 180.00
TABLA RENTADA DOCENA 4.5 Q 75.00 Q 337.50
TABLA COMPRADA DOCENA 2 Q 600.00 Q 1,200.00
PARALES RENTA DOCENA 1.5 Q 75.00 Q 112.50
PARALES COMPRA DOCENA 9 Q 600.00 Q 5,400.00
SILLETAS UNIDAD 200 Q 2.00 Q 400.00
Q -
VIBRADOR DIA 1 Q 300.00 Q 300.00
TOTAL DE MATERIALES Q 30,238.00
MANO DE OBRA
ARMADO DE LOSA M2 55.55 Q 125.00 Q 6,943.75
COLADO DE LOSA SACO 123.00 Q 33.33 Q 4,099.59
Q - Q -
Q - Q -
TOTAL MANO DE OBRA Q 11,043.34
FLETES
FLETES VIAJE 1.00 Q 400.00 Q 400.00