Está en la página 1de 3

Civil Works Construction for Depot Building 105-108-111-112

Id EDT Nombre de tarea Duración Comienzo Fin Costo Predecesoras Semestre 2, 2024
F M A M J J A S
1 1 Civil Works Construction for Depot Building 105-108-111-112 99 días mié 13/03/24 6: vie 9/08/24 5:00 p$8.235.101.202 0%

2 1.1 INICIO DE PROYECTO 99 días mié 13/03/24 6: vie 9/08/24 5:00 p$8.235.101.202 0%

3 1.1.1 firma del contrato 0 días mié 13/03/24 6:0mié 13/03/24 6:00$0 13/03

4 1.1.2 Depot-Building 105 98 días mié 13/03/24 7: jue 8/08/24 5:00 $4.143.867.444 0%

5 1.1.2.1 Groundworks and earthworks systems 52 días mié 13/03/24 7: jue 30/05/24 5:00$2.475.223.261 0%

6 1.1.2.1.1 Earthworks excavating systems 45 días mié 13/03/24 7:0mar 21/05/24 5:0 $586.362.852 3 0%

7 1.1.2.1.2 Earthworks filling systems 47 días mié 20/03/24 7:0jue 30/05/24 5:00$1.888.860.409 6CC+5 días 0%

8 1.1.2.2 Concrete foundation systems 83 días lun 8/04/24 7:00jue 8/08/24 5:00 $837.284.392 0%

9 1.1.2.2.1 Concrete foundation pads 83 días lun 8/04/24 7:00jue 8/08/24 5:00 p$803.357.635 7CC+10 días 0%

10 1.1.2.2.2 Reinforcing steel 78 días lun 8/04/24 7:00mié 31/07/24 5:00$33.926.758 9CC 0%

11 1.1.2.3 Reinforced concrete beam systems 63 días mar 7/05/24 7:0jue 8/08/24 5:00 $407.344.688 0%

12 1.1.2.3.1 Concrete beams 63 días mar 7/05/24 7:00jue 8/08/24 5:00 p$345.895.303 9CC+20 días 0%

13 1.1.2.3.2 Reinforcing steel 58 días mar 7/05/24 7:00mié 31/07/24 5:00$61.449.385 12CC 0%

14 1.1.2.4 Reinforced concrete column systems 58 días mié 15/05/24 7: jue 8/08/24 5:00 $424.015.103 0%

15 1.1.2.4.1 Concrete columns 58 días mié 15/05/24 7:0jue 8/08/24 5:00 p$289.426.607 9CC+25 días 0%

16 1.1.2.4.2 Reinforcing steel 30 días mié 15/05/24 7:0jue 27/06/24 5:00$134.588.496 15CC 0%

17 1.1.3 Depot-Building 108 98 días mié 13/03/24 7: jue 8/08/24 5:00 $3.162.565.412 0%

18 1.1.3.1 Groundworks and earthworks systems 50 días mié 13/03/24 7: mar 28/05/24 5:0$1.122.122.796 0%

19 1.1.3.1.1 Earthworks excavating systems 45 días mié 13/03/24 7:0mar 21/05/24 5:0 $297.603.150 3 0%

20 1.1.3.1.2 Earthworks filling systems 40 días lun 1/04/24 7:00mar 28/05/24 5:0 $824.519.645 19CC+10 días 0%

21 1.1.3.2 Concrete foundation systems 72 días lun 22/04/24 7:0mar 6/08/24 5:00$1.228.048.134 0%

22 1.1.3.2.1 Concrete foundation pads 72 días lun 22/04/24 7:0mar 6/08/24 5:00 $1.223.368.555 20CC+15 días 0%

23 1.1.3.2.2 Reinforcing steel 70 días lun 22/04/24 7:0vie 2/08/24 5:00 p$4.679.580 22CC 0%

24 1.1.3.3 Reinforced concrete beam systems 63 días mar 7/05/24 7:0jue 8/08/24 5:00 $353.347.820 0%

25 1.1.3.3.1 Concrete beams 63 días mar 7/05/24 7:00jue 8/08/24 5:00 p$297.778.515 20CC+25 días 0%

26 1.1.3.3.2 Reinforcing steel 60 días mar 7/05/24 7:00vie 2/08/24 5:00 p$55.569.305 25CC 0%

27 1.1.3.4 Reinforced concrete column systems 53 días mié 22/05/24 7: jue 8/08/24 5:00 $459.046.662 0%

28 1.1.3.4.1 Concrete columns 53 días mié 22/05/24 7:0jue 8/08/24 5:00 p$294.961.235 20CC+35 días 0%

29 1.1.3.4.2 Reinforcing steel 50 días mié 22/05/24 7:0vie 2/08/24 5:00 p$164.085.427 28CC 0%

Tareas críticas Tarea Tarea manual solo duración Hito de línea base Resumen Tareas externas Hito inactivo

División crítica División solo el comienzo Línea base Hito Resumen manual Hito externo Resumen inactivo

Progreso de tarea crítica Progreso de tarea solo fin División de la línea base Progreso del resumen Resumen del proyecto Tarea inactiva Fecha límite
Civil Works Construction for Depot Building 105-108-111-112
Id EDT Nombre de tarea Duración Comienzo Fin Costo Predecesoras Semestre 2, 2024
F M A M J J A S
30 1.1.4 Depot-Building 111 99 días mié 13/03/24 7: vie 9/08/24 5:00 p$159.446.762 0%

31 1.1.4.1 Groundworks and earthworks systems 52 días mié 13/03/24 7: jue 30/05/24 5:00$41.490.267 0%

32 1.1.4.1.1 Earthworks excavating systems 45 días mié 13/03/24 7:0mar 21/05/24 5:0 $31.089.886 3CC 0%

33 1.1.4.1.2 Earthworks filling systems 45 días vie 22/03/24 7:0 jue 30/05/24 5:00$10.400.381 32CC+7 días 0%

34 1.1.4.2 Concrete foundation systems 75 días mié 17/04/24 7: mar 6/08/24 5:00$15.505.965 0%

35 1.1.4.2.1 Concrete foundation pads 75 días mié 17/04/24 7:0mar 6/08/24 5:00 $13.124.182 33CC+15 días 0%

36 1.1.4.2.2 Reinforcing steel 70 días mié 17/04/24 7:0mar 30/07/24 5:0 $2.381.783 35CC 0%

37 1.1.4.3 Reinforced concrete beam systems 66 días jue 2/05/24 7:00jue 8/08/24 5:00 $29.483.526 0%

38 1.1.4.3.1 Concrete beams 66 días jue 2/05/24 7:00jue 8/08/24 5:00 p$4.841.487 33CC+25 días 0%

39 1.1.4.3.2 Reinforcing steel 62 días jue 2/05/24 7:00jue 1/08/24 5:00 p$24.642.039 38CC 0%

40 1.1.4.4 Reinforced concrete column systems 66 días jue 2/05/24 7:00jue 8/08/24 5:00 $14.050.838 0%

41 1.1.4.4.1 Concrete columns 66 días jue 2/05/24 7:00jue 8/08/24 5:00 p$7.064.461 33CC+25 días 0%

42 1.1.4.4.2 Reinforcing steel 62 días jue 2/05/24 7:00jue 1/08/24 5:00 p$6.986.377 41CC 0%

43 1.1.4.5 Reinforced concrete walls 57 días vie 17/05/24 7:0vie 9/08/24 5:00 p$58.916.167 0%

44 1.1.4.5.1 Concrete wall 57 días vie 17/05/24 7:0 vie 9/08/24 5:00 p$34.274.128 33CC+35 días 0%

45 1.1.4.5.2 Reinforcing steel 52 días vie 17/05/24 7:0 jue 1/08/24 5:00 p$24.642.039 44CC 0%

46 1.1.5 Depot-Building 112 97 días mié 13/03/24 7: mar 6/08/24 5:00$769.221.584 0%

47 1.1.5.1 Groundworks and earthworks systems 53 días mié 13/03/24 7: vie 31/05/24 5:00$667.898.182 0%

48 1.1.5.1.1 Earthworks excavating systems 47 días mié 13/03/24 7:0jue 23/05/24 5:00$209.116.949 3CC 0%

49 1.1.5.1.2 Earthworks filling systems 48 días mié 20/03/24 7:0vie 31/05/24 5:00 $458.781.232 48CC+5 días 0%

50 1.1.5.2 Concrete foundation systems 80 días mié 10/04/24 7: mar 6/08/24 5:00$32.936.210 0%

51 1.1.5.2.1 Concrete foundation pads 80 días mié 10/04/24 7:0mar 6/08/24 5:00 $28.877.778 49CC+12 días 0%

52 1.1.5.2.2 Reinforcing steel 75 días mié 10/04/24 7:0mar 30/07/24 5:0 $4.058.432 51CC 0%

53 1.1.5.3 Reinforced concrete beam systems 72 días lun 22/04/24 7:0mar 6/08/24 5:00$44.794.036 0%

54 1.1.5.3.1 Concrete beams 72 días lun 22/04/24 7:0mar 6/08/24 5:00 $34.924.640 49CC+20 días 0%

55 1.1.5.3.2 Reinforcing steel 65 días lun 22/04/24 7:0vie 26/07/24 5:00 $9.869.396 54CC 0%

56 1.1.5.4 Reinforced concrete column systems 65 días lun 29/04/24 7:0vie 2/08/24 5:00 p$23.593.157 0%

57 1.1.5.4.1 Concrete columns 65 días lun 29/04/24 7:0vie 2/08/24 5:00 p$13.311.942 49CC+25 días 0%

58 1.1.5.4.2 Reinforcing steel 60 días lun 29/04/24 7:0vie 26/07/24 5:00 $10.281.215 57CC 0%

Tareas críticas Tarea Tarea manual solo duración Hito de línea base Resumen Tareas externas Hito inactivo

División crítica División solo el comienzo Línea base Hito Resumen manual Hito externo Resumen inactivo

Progreso de tarea crítica Progreso de tarea solo fin División de la línea base Progreso del resumen Resumen del proyecto Tarea inactiva Fecha límite
Civil Works Construction for Depot Building 105-108-111-112
Id EDT Nombre de tarea Duración Comienzo Fin Costo Predecesoras Semestre 2, 2024
F M A M J J A S
59 1.2 fin de obra 0 días vie 9/08/24 5:00 vie 9/08/24 5:00 p$0 4;17;30;46 9/08

Tareas críticas Tarea Tarea manual solo duración Hito de línea base Resumen Tareas externas Hito inactivo

División crítica División solo el comienzo Línea base Hito Resumen manual Hito externo Resumen inactivo

Progreso de tarea crítica Progreso de tarea solo fin División de la línea base Progreso del resumen Resumen del proyecto Tarea inactiva Fecha límite