% DE AVANCE FISICO

item DESCRIPCION PARCIAL S/. ANTERIOR % ACTUAL % ACUMULADO % SALDO %


CONSTRUCCION DE PISTAS CON PAVIMENTOS DE
4,753,033.43 289,309.55 6.09% 248,600.17 5.23% 537,909.72 11.32% 4,215,123.71 88.68%
1.00 CONCRETO F´C=210KG/CM2 CON ESPESOR DE 20CM
IMPLEMENTACION DE PREVENCION Y CONTROL FRENTE A
40,206.82 6,530.52 16.24% 0.00 0.00% 6,530.52 16.24% 33,676.30 83.76%
2.00 LA PROPAGACION DEL COVID-19
3.00 IMPLEMENTACION DEL PLAN COVID 1,001.70 1,001.70 100.00% 0.00 0.00% 1,001.70 100.00% 0.00 0.00%
TOTAL 4,794,241.95 296,841.77 6.19% 248,600.17 5.19% 545,441.94 11.38% 4,248,800.01 88.62%

% DE AVANCE PROGRAMADO
item DESCRIPCION PARCIAL S/. ANTERIOR % ACTUAL % ACUMULADO % SALDO %
CONSTRUCCION DE PISTAS CON PAVIMENTOS DE
4,753,033.43 289,309.55 6.09% 60,867.98 1.28% 350,177.53 7.37% 4,402,855.90 92.63%
1.00 CONCRETO F´C=210KG/CM2 CON ESPESOR DE 20CM
IMPLEMENTACION DE PREVENCION Y CONTROL FRENTE A
40,206.82 18,075.64 44.96% 0.00 0.00% 18,075.64 44.96% 22,131.18 55.04%
2.00 LA PROPAGACION DEL COVID-19
3.00 IMPLEMENTACION DEL PLAN COVID 1,001.70 1,001.70 100.00% 0.00 0.00% 1,001.70 100.00% 0.00 0.00%
TOTAL 4,794,241.95 308,386.89 6.43% 60,867.98 1.27% 369,254.87 7.70% 4,424,987.08 92.30%