Documentos de Académico
Documentos de Profesional
Documentos de Cultura
Costos Universidad g2
Costos Universidad g2
UNITARIO 0.14
MANO DE OBRA
DESCRIPCION CANTIDAD UNIDAD P UNIT. TOTAL
TOPOGRAFO 1.00 DIA 25.00 25.00
CADENERO 1 DIA 17.00 17.00
CADENERO 1 DIA 17.00 17.00
AUXILIAR 1.00 DIA 12.67 12.67
CALCULISTA 1.00 DIA 17.00 17.00
PRESTACION SI 0.8 0.00 70.94
SUBTOTAL 159.61
UNITARIO 7.06
EQUIPO
DESCRIPCION TIPO CANTIDAD UNIDAD P UNIT. TOTAL
TEODOLITO 1.00 DIA 20.00 20.00
NIVEL 1.00 DIA 10.00 10.00
CINTA 1.00 DIA 1.00 1.00
MIRAS 1.00 DIA 3.00 3.00
SUBTOTAL 34.00
UNITARIO 1.50
DOLARES
COSTO UNITARIO MATERIALES + EQUIPO 1.64
UNITARIO 0.00
MANO DE OBRA
DESCRIPCION CANTIDAD UNIDAD P UNIT. TOTAL
AUXILIAR 2 M3/H/D 2.85 DIA 12.67 36.11
0.00
0.00
0.00
0.00
PRESTACION SI 0.8 0.00 28.89
SUBTOTAL 65.00
UNITARIO 11.40
EQUIPO
DESCRIPCION TIPO CANTIDAD UNIDAD P UNIT. TOTAL
0.00
0.00
0.00
0.00
SUBTOTAL 0.00
UNITARIO 0.00
DOLARES
COSTO UNITARIO MATERIALES + EQUIPO 0.00
MEJORAMIENTO DE SUELO CON S/C CON MATERIAL SELECTO PROPORCIÓN 20:1 (5%) COMPACTADO AL
95% DEL PROCTOR T-134
PROYECTO
SUBPROYECTO FECHA 4/1/2022
PARTIDA: MEJORAMIENTO DE SUELO CON S/C CON MATERIAL SELECTO PROPORCIÓN M3
20:1 (5%) COMPACTADO AL 95% DEL PROCTOR T-134
1.4.1.1.3 1.90
LONGITUD AREA O VOLUMEN A ANALIZAR: 1.90 M3
DESCRIPCION FACTOR CANTIDAD UNIDAD P UNIT. TOTAL
GASOLINA 0.38 GL 4.50 1.71
AGUA 0.04 M3 1.14 0.04
0 0.00 0.00 0.00 0.00
CEMENTO 3.80 BLS. 8.85 33.63
0.00
SUBTOTAL 35.38
UNITARIO 18.62
MANO DE OBRA
DESCRIPCION CANTIDAD UNIDAD P UNIT. TOTAL
AUXILIAR COMPACTANDO 1 0.27 DIA 12.67 3.44
AUXILIAR ACARREANDO 1 0.271428571 DIA 12.67 3.44
0.00
0.00
0.00
PRESTACION SI 0.8 0.00 5.50
SUBTOTAL 12.38
UNITARIO 6.52
EQUIPO
DESCRIPCION TIPO CANTIDAD UNIDAD P UNIT. TOTAL
VIBROCOMPACTADORA A 0.27 DIA 40.00 10.86
MINICARGAD MEZCLANDO A 0.05 DIAS 137.14 7.44
0.00
0.00
SUBTOTAL 18.30
UNITARIO 9.63
DOLARES
COSTO UNITARIO MATERIALES + EQUIPO 28.25
UNITARIO 14.67
MANO DE OBRA
DESCRIPCION CANTIDAD UNIDAD P UNIT. TOTAL
AUXILIAR COMPACTANDO 1 0.33 DIA 12.67 4.18
AUXILIAR ACARREANDO 1 0.33 DIA 12.67 4.18
0.00
0.00
0.00
PRESTACION SI 0.8 0.00 6.69
SUBTOTAL 15.05
UNITARIO 6.52
EQUIPO
DESCRIPCION TIPO CANTIDAD UNIDAD P UNIT. TOTAL
VIBROCOMPACTADORA P 1 0.33 DIA 20.00 6.60
0.00
0.00
0.00
SUBTOTAL 6.60
UNITARIO 2.86
DOLARES
COSTO UNITARIO MATERIALES + EQUIPO 17.53
UNITARIO 0.00
MANO DE OBRA
DESCRIPCION CANTIDAD UNIDAD P UNIT. TOTAL
AUXILIAR 0.0033 DIA/M2 1 2.00 DIA 12.67 25.34
0.00
0.00
0.00
0.00
PRESTACION SI 0.8 0.00 20.27
SUBTOTAL 45.61
UNITARIO 6.16
EQUIPO
DESCRIPCION TIPO CANTIDAD UNIDAD P UNIT. TOTAL
DEMOLEDOR INDUSTRIAL A 1 9.22 DIA 7.00 64.54
RENDIMIENTO 0.2 M2/HORA 0.00
0.00
0.00
SUBTOTAL 64.54
UNITARIO 8.71
DOLARES
COSTO UNITARIO MATERIALES + EQUIPO 8.71
UNITARIO 204.28
MANO DE OBRA
DESCRIPCION CANTIDAD UNIDAD P UNIT. TOTAL
ARMADO 5 1 0.61 QQ 8.82 5.36
ARMADO 5 1 0.943 QQ 8.82 8.32
ARMADO 0 1 0 QQ 0.00 0.00
ARMADO 0 1 0 QQ 0.00 0.00
CONCRETEADO 1 1.135782 M3 10.30 11.70
AUXILIAR CURADO 1 0.23 DIA 12.67 2.88
MOLDE LATE 50 % RECARG 1 2.81 M2 2.97 8.34
PRESTACION SI 0.8 0.00 29.28
SUBTOTAL 65.88
UNITARIO 57.79
EQUIPO
DESCRIPCION TIPO CANTIDAD UNIDAD P UNIT. TOTAL
BOMBA DE CONCRETO
VIBRADOR 1.00 C/U 0.65 0.65
SUBTOTAL 0.65
UNITARIO 0.57
DOLARES
COSTO UNITARIO MATERIALES + EQUIPO 204.85
UNITARIO 373.28
MANO DE OBRA
DESCRIPCION CANTIDAD UNIDAD P UNIT. TOTAL
ARMADO 8 1 1.00 QQ 7.30 7.30
ARMADO 0 1 0.00 QQ 0.00 0.00
ARMADO 4 1 0.35 QQ 9.68 3.39
ARMADO 0 1 0.00 QQ 0.00 0.00
CONCRETEADO 1 0.64 M3 10.30 6.59
AUXILIAR CURADO 1 0.13 DIA 12.67 1.62
MOLDE 30 % RECARG 1 3.20 M2 2.89 9.24
0 50 % RECARG 1 0.00 0.00 0.00 0.00
ALAMBRE DE AMARRE 0.10 LBS 0.78 0.08
PRESTACION SI 0.8 0.00 22.58
SUBTOTAL 50.80
UNITARIO 89.12
EQUIPO
DESCRIPCION TIPO CANTIDAD UNIDAD P UNIT. TOTAL
BOMBA DE CONCRETO NO 0.64 M3 0
VIBRADOR 1 1 C/U 0.3648 0.36
0.00
SUBTOTAL 0.36
UNITARIO 0.63
DOLARES
COSTO UNITARIO MATERIALES + EQUIPO 373.91
UNITARIO 10.06
MANO DE OBRA
DESCRIPCION CANTIDAD UNIDAD P UNIT. TOTAL
PREPARACION Y MONTAJE 1 9.00 LB 15.00 135.00
CORTE 1 3.6 ML 4.57 16.45
SOLDADURA 1 3.6 ML 2.46 8.86
0.00
0.00
PRESTACION SI 0.8 0.00 128.25
SUBTOTAL 288.56
UNITARIO 32.06
EQUIPO
DESCRIPCION TIPO CANTIDAD UNIDAD P UNIT. TOTAL
0.00
0.00
0.00
0.00
SUBTOTAL 0.00
UNITARIO 0.00
DOLARES
COSTO UNITARIO MATERIALES + EQUIPO 10.06
UNITARIO 16.51
MANO DE OBRA
DESCRIPCION CANTIDAD UNIDAD P UNIT. TOTAL
HECHURA Y MONTAJE 1 24.30 ML 8.90 216.27
0.00
0.00
0.00
0.00
PRESTACION SI 0.8 0.00 173.02
SUBTOTAL 389.29
UNITARIO 16.02
EQUIPO
DESCRIPCION TIPO CANTIDAD UNIDAD P UNIT. TOTAL
0.00
0.00
0.00
0.00
SUBTOTAL 0.00
UNITARIO 0.00
DOLARES
COSTO UNITARIO MATERIALES + EQUIPO 16.51
UNITARIO 15.66
MANO DE OBRA
DESCRIPCION CANTIDAD UNIDAD P UNIT. TOTAL
PREPARACION Y MONTAJE 1 85.10 ML 8.00 680.80
CORTE 1 91.1668 ML 4.57 416.63
SOLDADURA 1 85.7 ML 2.46 210.82
0.00
0.00
PRESTACION SI 0.8 0.00 1,046.60
SUBTOTAL 2,354.85
UNITARIO 27.67
EQUIPO
DESCRIPCION TIPO CANTIDAD UNIDAD P UNIT. TOTAL
0.00
0.00
0.00
0.00
SUBTOTAL 0.00
UNITARIO 0.00
DOLARES
COSTO UNITARIO MATERIALES + EQUIPO 15.66
UNITARIO 15.34
MANO DE OBRA
DESCRIPCION CANTIDAD UNIDAD P UNIT. TOTAL
PREPARACION Y MONTAJE 1 117.60 ML 8.00 940.80
CORTE 1 68 ML 4.57 310.76
SOLDADURA 1 67 ML 2.46 164.82
0.00
0.00
PRESTACION SI 0.8 0.00 1,133.10
SUBTOTAL 2,549.48
UNITARIO 21.68
EQUIPO
DESCRIPCION TIPO CANTIDAD UNIDAD P UNIT. TOTAL
0.00
0.00
0.00
0.00
SUBTOTAL 0.00
UNITARIO 0.00
DOLARES
COSTO UNITARIO MATERIALES + EQUIPO 15.34
UNITARIO 5.37
MANO DE OBRA
DESCRIPCION CANTIDAD UNIDAD P UNIT. TOTAL
HECHURA Y MONTAJE 1 31.00 ML 2.50 77.50
0.00
0.00
0.00
0.00
PRESTACION SI 0.8 0.00 62.00
SUBTOTAL 139.50
UNITARIO 4.50
EQUIPO
DESCRIPCION TIPO CANTIDAD UNIDAD P UNIT. TOTAL
0.00
0.00
0.00
0.00
SUBTOTAL 0.00
UNITARIO 0.00
DOLARES
COSTO UNITARIO MATERIALES + EQUIPO 5.37
UNITARIO 37.75
MANO DE OBRA
DESCRIPCION CANTIDAD UNIDAD P UNIT. TOTAL
COLOCACION 1 85.55 M2 12.00 1,026.60
0.00
0.00
0.00
0.00
PRESTACION SI 0.8 0.00 821.28
SUBTOTAL 1,847.88
UNITARIO 21.60
EQUIPO
DESCRIPCION TIPO CANTIDAD UNIDAD P UNIT. TOTAL
TRANSPORTE DE LAMINA A LA OBRA 1 85.55 M2 1.25 106.94
0.00
0.00
0.00
SUBTOTAL 106.94
UNITARIO 1.25
DOLARES
COSTO UNITARIO MATERIALES + EQUIPO 39.00
UNITARIO 9.61
MANO DE OBRA
DESCRIPCION CANTIDAD UNIDAD P UNIT. TOTAL
M DE O 100 % RECARG 1 29.50 ML 3.64 107.38
0.00
SOPORTES 1 0.34 QQ 11.00 3.74
0.00
0.00
PRESTACION SI 0.8 0.00 88.90
SUBTOTAL 200.02
UNITARIO 6.78
EQUIPO
DESCRIPCION TIPO CANTIDAD UNIDAD P UNIT. TOTAL
0.00
0.00
0.00
0.00
SUBTOTAL 0.00
UNITARIO 0.00
DOLARES
COSTO UNITARIO MATERIALES + EQUIPO 9.61
UNITARIO 10.28
MANO DE OBRA
DESCRIPCION CANTIDAD UNIDAD P UNIT. TOTAL
M DE O 100 % RECARG 1 5.48 ML 3.64 19.96
BOCATUBO 60 % RECARG 1 1 C/U 6.99 6.99
SOPORTES 1 1 QQ 11.00 11.00
0.00
0.00
PRESTACION SI 0.8 0.00 30.36
SUBTOTAL 68.31
UNITARIO 5.06
EQUIPO
DESCRIPCION TIPO CANTIDAD UNIDAD P UNIT. TOTAL
0.00
0.00
0.00
0.00
SUBTOTAL 0.00
UNITARIO 0.00
DOLARES
COSTO UNITARIO MATERIALES + EQUIPO 10.28
UNITARIO 23.40
MANO DE OBRA
DESCRIPCION CANTIDAD UNIDAD P UNIT. TOTAL
HECHURA 1 23.60 ML 2.25 53.10
COLOCACION 1 23.6 ML 1.50 35.40
PLACA METALICA e=1/4" 1 36 C/U 2.45 88.20
PEDESTAL PASA MANO 1 36.00 C/U 1.67 60.12
0.00
PRESTACION SI 0.8 0.00 189.46
SUBTOTAL 426.28
UNITARIO 18.06
EQUIPO
DESCRIPCION TIPO CANTIDAD UNIDAD P UNIT. TOTAL
0.00
0.00
0.00
0.00
SUBTOTAL 0.00
UNITARIO 0.00
DOLARES
COSTO UNITARIO MATERIALES + EQUIPO 23.40
UNITARIO 6.90
MANO DE OBRA
DESCRIPCION CANTIDAD UNIDAD P UNIT. TOTAL
M DE O 100 % RECARG 1 29.50 ML 3.85 113.58
0.00
0.00
0.00
0.00
PRESTACION SI 0.8 0.00 90.86
SUBTOTAL 204.44
UNITARIO 6.93
EQUIPO
DESCRIPCION TIPO CANTIDAD UNIDAD P UNIT. TOTAL
0.00
0.00
0.00
0.00
SUBTOTAL 0.00
UNITARIO 0.00
DOLARES
COSTO UNITARIO MATERIALES + EQUIPO 6.90