CEMENTO BL. 18,321.49 42.50 778.66 ALAMBRE, CLAV. ETC KG 5,829.62 1.00 5.83 ACERO CORRUGADO Kg 78,719.19 1.00 78.72 MADERA P2 19,376.95 26.64 516.20 YESO BOL 220.82 28.00 6.18 PINTURA, IMPERM, LACAS, ACEITES , ETC GAL 128.12 4.50 0.58 MATERIALES P/OBRAS PROVISIONALES KG 2,500.00 1.00 2.50 OTROS MATERIALES KG 2,500.00 1.00 2.50 PESO TOTAL 1,391.17 CAPACIDAD DEL CAMION ( TON ) 15.00 COSTO POR VIAJE S/. S/. 1,248.00 NUMERO DE VIAJES 92.744667 COSTO DIRECTO POR FLETE S/. S/. 115,745.34
AGREGADOS
DESCRIPC. UNIDAD VOL. TOTAL PESO.TOTAL (ton)
ARENA FINA M3 25.30 37.95 PIEDRA CHANCADA DE 1/2"-3/4" M3 1,624.43 2,192.98 ARENA GRUESA M3 1,997.14 2,895.85 MATERIAL DE RELLENO M3 200.20 380.38 GRAVA M3 399.34 539.11 HORMIGON M3 103.23 247.75 PESO TOTAL CAPACIDAD DEL CAMION (TON) 15.00 COSTO POR VIAJE S/. S/. 75.00 NUMERO DE VIAJES 419.6013 COSTO DIRECTO POR FLETE S/. S/. 31,470.10
TUBERÍAS
DESCRIPC. UNIDAD CANT N° TUBOS PESO.TOTAL (ton)
TUBERIA PVC 160 MM M 2,523.850 421.00 12.63 TUBERIA PVC 110MM M 7,842.950 1,307.00 19.61 TUBERIA PVC 75 MM M 1,149.640 192.00 1.54 TUBERIA PVC 50 M 1,564.620 261.00 1.31 TUBERIA PVC 200 M 11,257.180 1,876.00 178.22 TUBERIA PVC 250 M 1,497.970 250.00 30.75 PESO TOTAL 244.06 CAPACIDAD DEL CAMION (TON) 40.00 COSTO POR VIAJE S/. S/. 1,536.00 NUMERO DE VIAJES 6.1015 COSTO DIRECTO POR FLETE S/. S/. 9,371.90
ASFALTO
DESCRIPC. UNIDAD VOL. TOTAL VOL. TOTAL (M3) PESO.TOTAL (ton)
ASFALTO CALIENTE M3 749.10 749.10 1,273.47 ASFALTO LIQUIDO (250 GLN) GLN 3,795.45 14.37 24.43 PESO TOTAL 1,297.90 CAPACIDAD DEL CAMION (TON) 15.00 COSTO POR VIAJE S/. S/. 1,495.00 NUMERO DE VIAJES 86.529559 COSTO DIRECTO POR FLETE S/. S/. 129,361.69 FLETE DE MATERIALES EN CAMION 15 TON CAMION(15TON) 15TON/VIAJE
DISTANCIA (AREQUIPA)= 230 KM 50 KM/H
TIEMPO = HORAS
1 CAMION= VIAJES /DIA
COSTO CAMION/DIA = 1600 SOLES
COSTO POR VIAJE = 7.67/8= 0.96 xS/.1300 1248.00
COSTO POR TON = 1248/15 TN S/. 83.20 /TN FLETE DE AGREGADOS EN CAMION 15 M3 CAMION(15M3) 15000 KG/VIAJE
1M3 = 1,650 KG/24750= 0.07 VIAJES PARA 1 3
DISTANCIA (CANTERA)= 9.12 KM 60 KM/H
TIEMPO = (9.12+9.12)/50 = 0.36 HORAS
1 CAMION= 8/0.36=22.22 VIAJES /DIA
COSTO CAMION/DIA = 1400 SOLES
COSTO POR VIAJE = 0.36/8= 0.05 x1500 75.00
COSTO POR TON = 75/15 TN 5.00
FLETE DE TUBERIA (SEMI-TRAYLER)
SEMI-TRAYLER(40TON) 40000 KG/VIAJE
DISTANCIA (AREQUIPA)= 230 KM 60 KM/H
TIEMPO = (230+230)/60 = 7.67 HORAS
1 SEMI-TRAYLER = 1.04 VIAJES /DIA
COSTO SEMI-TRAYLER/DIA = 1700 SOLES
COSTO POR VIAJE = 0.96 x1600 1536.00
COSTO POR TON = 38.40
FLETE DE ASFALTO EN CAMION 15 M3
CAMION(15M3) 15000 KG/VIAJE
1M3 = 1,800 KG/24750= 0.07 VIAJES PARA 1 M3
DISTANCIA (AREQUIPA)= 230 KM 55KM/H
TIEMPO = (230+230)/50 = 9.20 HORAS
1 CAMION= 0.87 VIAJES /DIA
COSTO CAMION/DIA = 1400 SOLES
COSTO POR VIAJE = 1.15 x1600 1495.00
COSTO POR TON = 99.67 CLIENTE : SERVICIO DE AGUA POTABLE Y ALCANTARILLADO DE AREQUIPA S.A
PROYECTO : AMPLIACION Y MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y ALCANTARILLADO
SANITARIO EN LA LOCALIDAD DE CHUQUIBAMBA
UBICACIÓN : AREQUIPA - CONDESUYOS - CHUQUIBAMBA
Descripción Peso (Ton) Precio Unitario (Costo /Ton) Total
Flete de Materiales 1391.17 S/.83.20 S/.115,745.34 Flete de Agregados 6294.02 S/.5.00 S/.31,470.10 Flete de Tuberías 244.06 S/.38.40 S/.9,371.90 Flete de Asfalto 1297.90 S/.99.67 S/.129,361.69
Japanese Joinery; Guía de carpintería japonesa de nivel intermedio: El secreto para hacer juntas complejas y muebles japoneses con herramientas asequibles