CRONOGRAMA DE ADQUISICIÓN DE EQUIPOS

PROYECTO: "RENOVACION DE PUENTE; EN EL(LA) VIA VECINAL CA 1414, SOBRE EL RIO GUAYOMAYO EN LOCALIDAD EL GUAYO, DISTRITO DE CONTUMAZA, PROVINCIA CONTUMAZA,
DEPARTAMENTO CAJAMARCA"

UBICACIÓN: EL GUAYO CONTUMAZA CONTUMAZA CAJAMARCA

3 MESES

ITEM DESCRIPCIÓN UNIDAD CANTIDAD PRECIO S/. SUB TOTAL S/. VAL N°001 VAL N°002 VAL N°003

% MONTO S/. % MONTO S/. % MONTO S/.

1 HERRAMIENTAS MANUALES %MO S/ 3,735.72 33% S/ 1,245.24 33% S/ 1,245.24 33% S/ 1,245.24 100%

2 MEZCLADORA DE CONCRETO DE 11P3 18 HP hm 164.7178 S/ 9.00 S/ 1,482.46 72% S/ 1,067.37 25% S/ 370.62 3% S/ 44.47 100%

3 MOTOBOMBA 34 HP 8" hm 48.0576 S/ 10.80 S/ 519.02 100% S/ 519.02 0% S/ - 0% S/ - 100%

4 CAMION VOLQUETE DE 15 m3 hm 124.3519 S/ 81.00 S/ 10,072.50 6% S/ 604.35 94% S/ 9,468.15 0% S/ - 100%

5 CAMION CISTERNA (2,500 GLNS) hm 36.3419 S/ 81.00 S/ 2,943.69 40% S/ 1,177.48 60% S/ 1,766.21 0% S/ - 100%

6 COMPRESORA NEUMATICA 240 HP 700-800 hm 8.7680 S/ 22.50 S/ 197.28 100% S/ 197.28 0% S/ - 0% S/ - 100%

7 COMPACTADOR VIBRATORIO TIPO PLANCHA 7 HP hm 36.3488 S/ 10.80 S/ 392.57 40% S/ 157.03 60% S/ 235.54 0% S/ - 100%

8 EXCAVADORA SOBRE ORUGAS 115-165 HP hm 116.7881 S/ 315.00 S/ 36,788.25 78% S/ 28,694.84 11% S/ 4,046.71 11% S/ 4,046.71 100%

9 RETROEXCAVDARA SOBRE LLANTAS 58 HP 1/2 Y3 hm 184.5368 S/ 144.00 S/ 26,573.30 18% S/ 4,719.50 82% S/ 21,853.80 0% S/ - 100%

10 MARTILLO NEUMATICO DE 24 kg hm 8.7680 S/ 13.50 S/ 118.37 100% S/ 118.37 0% S/ - 0% S/ - 100%

11 VIBRADOR DE CONCRETO 4 HP 1.35" hm 244.3481 S/ 9.00 S/ 2,199.13 78% S/ 1,720.38 18% S/ 391.68 4% S/ 87.07 100%

12 MOTOSOLDADORA DE 250 A hm 1.6000 S/ 22.50 S/ 36.00 0% S/ - 0% S/ - 100% S/ 36.00 100%

13 ESTACION TOTAL CON TRIPODE hm 4.0061 S/ 18.00 S/ 72.11 100% S/ 72.11 0% S/ - 0% S/ - 100%

14 NIVEL TOPOGRAFICO hm 2.0000 S/ 10.80 S/ 21.60 100% S/ 21.60 0% S/ - 0% S/ - 100%

COSTO DIRECTO S/ 85,152.00 S/ 40,314.55 S/ 39,377.96 S/ 5,459.49 S/ 85,152.00

GG 10.00% S/ 8,515.20 S/ 4,031.46 S/ 3,937.80 S/ 545.94 S/ 8,515.20


GASTOS GENERALES
UTI 5.00% S/ 4,257.60 S/ 2,015.73 S/ 1,968.90 S/ 272.97 S/ 4,257.60
UTILIDAD
SUB TOTAL ST S/ 97,924.80 S/ 46,361.74 S/ 45,284.66 S/ 6,278.40 S/ 97,924.80

IGV 18.00% S/ 17,626.46 S/ 8,345.11 S/ 8,151.24 S/ 1,130.11 S/ 17,626.46


IMPUESTO
TOTAL PRESUPUESTO P_T S/ 115,551.26 S/ 54,706.85 S/ 53,435.90 S/ 7,408.51 S/ 115,551.26

PORCENTAJE DE AVANCE 100% 47.34% 46.24% 6.41% 100.00%