VALORIZACIÓN

% DE
PARTIDAS P.U UNIDAD CANTIDAD SUB TOTAL EJECUTADO SUB TOTAL
AVANCE
TRABAJOS PRELIMINARES
DEMOLICIÓN DE MURO POSTERIOR DE ADOBE 11M DE LARGO S/550.00 GLB 1.00 550.00 100% 1 S/550.00
ARMADO DE CASETA CON SOLADO PARA LA MISMA S/300.00 GLB 1.00 300.00 100% 1 S/300.00
TRAZO Y REPLANTEO DE TERRENO 330M2 S/800.00 GLB 1.00 800.00 100% 1 S/800.00
SUBTOTAL: S/ 1,650.00 EJECUTADO: S/ 1,650.00
MOVIMIENTO DE TIERRAS
EXCAVACIÓN DE PISCINA MANUAL S/28.00 M3 30.44 852.32 100% 30.44 S/852.32
EXCAVACIÓN DE CIMENTACIONES MANUAL S/26.00 M 27.00 702.00 100% 27.00 S/702.00
EXACAVACIÓN MANUAL DE CISTERNA S/26.00 M3 12.64 328.54 100% 12.64 S/328.54
RELLENO Y COMPACTADO CON MATERIAL PROPIO S/12.00 M2 623.25 7479.00 100% 623.25 S/7,479.00
SUBTOTAL: S/ 9,361.86 EJECUTADO: S/ 9,361.86
CIMENTACIONES
CERCO PERIMÉTRICO CON ALBAÑILERÍA ARMADA S/1,000.00 MILLAR 1.15 1150.00 0% 0.00 S/0.00
COLUMNETAS CONFINADA EN CERCO PERIMETRICO S/200.00 UND - 0% 0.00 S/0.00
VIGA COLLARÍN S/30.00 ML 30.74 922.20 0% 0.00 S/0.00
SOBRECIMIENTO DE CERCO PERIMÉTRICO S/60.00 ML 30.74 1844.40 80% 24.59 S/1,475.52
PISCINA (ARMADO+ENCOFRADO) S/7,000.00 GLB 1.00 7000.00 100% 1.00 S/7,000.00
VACIADO MANUAL DE LA PISCINA S/500.00 GLB 1.00 500.00 100% 1.00 S/500.00
DEMOLICIÓN DE SOLADO DE JACUZZI Y EXCAVACIÓN NUEVA S/500.00 GLB 1.00 500.00 100% 1.00 S/500.00
CISTERNA (MODIFICADA EN OBRA) + TARRAJEO S/2,500.00 GLB 1.00 2500.00 100% 1.00 S/2,500.00
CUARTOS DE MAQUINAS + BOMBAS + CALEFACCIÓN + TARRAJEO S/2,500.00 GLB 1.00 2500.00 100% 1.00 S/2,500.00
FALSA ZAPATAS PARA 15 ZAPATAS S/120.00 UND 15.00 1800.00 100% 15.00 S/1,800.00
ZAPATAS (VACIADAS CON MIXER) + COLUMNAS DE 1ER PISO S/750.00 UND 14.00 10500.00 100% 14.00 S/10,500.00
ZAPATA (VACIADA CON MIXER) + PLACA M1 DE 1ER PISO S/1,900.00 UND 1.00 1900.00 100% 1.00 S/1,900.00
CIMIENTO CORRIDO S/55.00 ML 37.48 2061.40 100% 37.48 S/2,061.40
SOBRECIMIENTO S/60.00 ML 47.46 2847.60 100% 47.46 S/2,847.60
VIGA DE CIMENTACIÓN (ARMADO + ZANJA + VACIADO CON MIXER ) S/90.00 ML 63.10 5679.00 100% 63.10 S/5,679.00
SUBTOTAL: S/ 41,704.60 EJECUTADO: S/ 39,263.52
1ER PISO
ASENTADO DE LADRILLO KK MUROS PERIMETRALES 1ER PISO S/320.00 MILLAR 1.16 369.60 100% 1.16 S/369.60
ASENTADO DE LADRILLO KK MUROS INTERIORES 1ER PISO S/320.00 MILLAR 4.60 1471.68 100% 4.60 S/1,471.68
COLUMNETAS 1ER PISO S/200.00 UND 12.00 2400.00 100% 12.00 S/2,400.00
LOSA ALIGERADA 1ER PISO EN 2 DIRECCIONES X M2 S/75.00 M2 25.81 1935.75 100% 25.81 S/1,935.75
LOSA ALIGERADA 1ER PISO EN 1 SENTIDO X M2 S/60.00 M2 106.52 6391.20 100% 106.52 S/6,391.20
VIGAS PERALTADAS 1ER PISO X ML S/50.00 ML 95.55 4777.50 100% 95.55 S/4,777.50
TENDIDO DE AGUA 1ER PISO S/1,500.00 GLB 1.00 1500.00 0% 1.00 S/0.00
TENDIDO DE DESAGUE 1ER PISO S/1,300.00 GLB 1.00 1300.00 100% 1.00 S/1,300.00
MONTANTES S/25.00 UND 14.00 350.00 90% 13.00 S/325.00
CAJAS DE REGISTRO S/150.00 UND 5.00 750.00 80% 4.00 S/600.00
TOMACORRIENTES, INTERRUPTORES, PUNTOS EN MURO S/18.00 UND 24.00 432.00 100% 24.00 S/432.00
PUNTOS DE LUZ EN TECHO S/10.00 UND 46.00 460.00 100% 46.00 S/460.00
TABLEROS S/100.00 UND 1.00 100.00 50% 0.50 S/50.00
PUNTOS DE TELECOMUNICACIONES 1ER PISO S/18.00 UND 8.00 144.00 0% 0.00 S/0.00
CAJAS DE PASO S/18.00 UND 5.00 90.00 0% 0.00 S/0.00
ESCALERA GRECA DE 1ER A 2DO PISO S/2,000.00 GLB 1.00 2000.00 0% 0.00 S/0.00
SUBTOTAL: S/ 24,471.73 EJECUTADO: S/ 20,512.73
2DO PISO
COLUMNAS DE 2DO PISO S/450.00 UND 14.00 6300.00 100% 14.00 S/6,300.00
PLACA M1 DE 2DO PISO S/1,400.00 UND 1.00 1400.00 100% 1.00 S/1,400.00
COLUMNETAS DE 2DO PISO S/200.00 UND 34.00 6800.00 100% 34.00 S/6,800.00
LOSA ALIGERADA 2DO PISO EN 2 DIRECCIONES X M2 S/85.00 M2 13.15 1117.75 100% 13.15 S/1,117.75
LOSA ALIGERADA 2DO PISO EN 1 SENTIDO X M2 S/70.00 M2 122.45 8571.50 100% 122.45 S/8,571.50
VIGAS PERALTADAS 2DO PISO X ML S/60.00 ML 98.55 5913.00 100% 98.55 S/5,913.00
ASENTADO DE LADRILLO KK MUROS 2DO PISO S/360.00 MILLAR 8.47 3049.92 100% 8.47 S/3,049.92
TENDIDO DE AGUA 2DO PISO S/600.00 GLB 1.00 600.00 0% 0.00 S/0.00
TENDIDO DE DESAGUE 2DO PISO S/300.00 GLB 1.00 300.00 100% 1.00 S/300.00
MONTANTES S/25.00 UND 14.00 350.00 90% 12.00 S/300.00
TOMACORRIENTES E INTERRUPTORES S/18.00 UND 43.00 774.00 0% 43.00 S/0.00
PUNTOS DE LUZ EN TECHO S/10.00 UND 46.00 460.00 100% 46.00 S/460.00
TABLEROS S/100.00 UND 1.00 100.00 0% 0.00 S/0.00
PUNTOS DE TELECOMUNICACIONES 2DO PISO S/18.00 UND 10.00 180.00 0% 0.00 S/0.00
CAJAS DE PASO S/18.00 UND 2.00 36.00 0% 0.00 S/0.00
ESCALERA GRECA DE 1ER A 2DO PISO S/2,000.00 GLB 1.00 2000.00 0% 0.00 S/0.00
SUBTOTAL: S/ 39,152.17 EJECUTADO: S/ 35,412.17
3ER PISO
COLUMNAS DE 3ER PISO S/450.00 UND 13.00 5850.00 100% 13.00 S/5,850.00
COLUMNETAS DE 3ER PISO S/200.00 UND 16.00 3200.00 100% 16.00 S/3,200.00
LOSA ALIGERADA 3ER PISO EN 1 SENTIDO X M2 S/80.00 M2 91.18 7294.40 70% 63.83 S/5,106.08
VIGAS PERALTADAS 3ER PISO X ML S/60.00 ML 48.70 2922.00 70% 34.09 S/2,045.40
ASENTADO DE LADRILLO KK MUROS 3ER PISO S/420.00 MILLAR 5.74 2408.70 100% 5.74 S/2,408.70
TENDIDO DE AGUA 3ER PISO S/600.00 GLB 1.00 600.00 0% 0.00 S/0.00
TENDIDO DE DESAGUE 3ER PISO S/300.00 GLB 1.00 300.00 100% 1.00 S/300.00
MONTANTES S/25.00 UND 9.00 225.00 100% 7.00 S/175.00
TOMACORRIENTES E INTERRUPTORES S/18.00 UND 35.00 630.00 0% 0.00 S/0.00
PUNTOS DE LUZ EN TECHO S/10.00 UND 31.00 310.00 0% 0.00 S/0.00
TABLEROS S/100.00 UND 1.00 100.00 0% 0.00 S/0.00
PUNTOS DE TELECOMUNICACIONES 3ER PISO S/18.00 UND 8.00 144.00 0% 0.00 S/0.00
CAJAS DE PASO S/18.00 UND 3.00 54.00 0% 0.00 S/0.00
SUBTOTAL: S/ 24,038.10 EJECUTADO: S/ 19,085.18
TECHO
TENDIDO DE SUMIDEROS Y VENTILACIONES S/150.00 UND 1.00 150.00 0% 0.00 S/0.00
ASENTADO DE LADRILLO PANDERETA 2 HILADAS S/430.00 MILLAR 0.27 117.82 0% 0.00 S/0.00
PULIDO DE TECHO S/10.00 M2 98.14 981.40 0% 0.00 S/0.00
CONTRAPISO S/15.00 M2 98.14 1472.10 0% 0.00 S/0.00
SUBTOTAL: S/ 2,721.32 EJECUTADO: S/ 0.00
ARQUITECTURA
TARRAJEOS DE MUROS 1ER PISO S/16.00 M2 214.32 3429.09 50.93 S/814.88
TARRAJEO DE CERCO PERIMÉTRICO S/16.00 M2 89.15 1426.34 0% 0.00 S/0.00
TARRAJEO DE MUROS 2DO PISO S/16.00 M2 421.28 6740.45 0% 0.00 S/0.00
TARRAJEO DE MUROS 3ER PISO S/16.00 M2 114.55 1832.80 0% 0.00 S/0.00
TARRAJEOS DE PARAPETOS TECHO S/16.00 M2 16.61 265.76 0% 0.00 S/0.00
TARRAJEOS DE CIELORASO 1ER PISO S/16.00 M2 134.11 2145.76 100% 134.11 S/2,145.76
TARRAJEO DE CIELORASO 2DO PISO S/16.00 M2 137.00 2192.00 100% 137.00 S/2,192.00
TARRAJEO DE CIELORASO 3ER PISO S/16.00 M2 120.46 1927.36 0% 0.00 S/0.00
CONTRAPISOS 1ER PISO S/15.00 M2 175.24 2628.60 0% 0.00 S/0.00
CONTRAPISOS 2DO PISO S/15.00 M2 425.35 6380.25 0% 0.00 S/0.00
CONTRAPISOS 3ER PISO S/15.00 M2 116.20 1743.00 0% 0.00 S/0.00
CONTRAPISOS TECHO S/15.00 M2 98.10 1471.50 0% 0.00 S/0.00
LOSA REBAJADA S/100.00 UND 4.00 400.00 0% 0.00 S/0.00
PARASOLES S/200.00 UND 13.00 2600.00 100% 13.00 S/2,600.00
CHAFLÁN GRANDE S/5,000.00 UND 1.00 5000.00 100% 1.00 S/5,000.00
CHAFLAN CHICO S/3,000.00 UND 1.00 3000.00 100% 1.00 S/3,000.00
PARASOLES TARRAJEO S/20.00 ML 0.00 100% 0.00 S/0.00
CHAFLÁN GRANDE TARRAJEO S/20.00 M2 0.00 100% 0.00 S/0.00
CHAFLAN CHICO TARRAJEO S/20.00 M2 0.00 100% 0.00 S/0.00
LIMPIEZA DE VIVIENDA S/700.00 UND 1.00 700.00 100% 1.00 S/700.00
SUBTOTAL: S/ 11,300.00 EJECUTADO: S/ 16,452.64

TOTAL EJECUTADO S/141,738.10