REHABILITACION DEL LOCAL ESCOLAR 86821- HUASCARAN CON CODIGO LOCAL 041449, DISTRITO DE
QUILLO - YUNGAY - ANCASH
CLIENTE: MUNICIPALIDAD DISTRITAL DE QUILLO
LUGAR: ANCASH -YUNGAY - QUILLO
ESTRUCTURAS: RESUMEN
01 OBRAS PRELIMINARES
01.01 TRABAJOS PROVISIONALES
01.01.01 CASETA, GUARDIANIA Y ALMACEN glb 1.00
01.01.02 CARTEL DE IDENTIFICACION DE OBRA 5.40x3.60m und 1.00
01.01.03 ENERGIA ELECTRICA PARA LA CONSTRUCCION glb 1.00
01.01.04 CERCO PROVISIONAL C./MALLA RASCHEL m 303.30
01.02 TRABAJOS PRELIMINARES
01.02.01 LIMPIEZA MANUAL DE TERRENO m2 1,850.00
01.02.02 TRAZO DURANTE LA EJECUCION DE LA OBRA m2 1,850.00
01.02.03 MOVILIZACION DE MAQUINARIAS HERRAMIENTAS PARA LA OBRA glb 1.00
01.02.04 DEMOLICION DE CERCO PERIMETRICO EXISTENTE m 34.20
01.02.05 DESMONTAJE DE CANALONES Y VIGAS m2 375.24
01.02.06 DEMOLICION Y ELIMINACION DE CONSTRUCCIONES EXISTENTES m2 375.24
01.02.07 DEMOLICION Y ELIMINACION DE LOSAS Y VEREDAS EXISTENTES m2 1,103.19
01.02.08 LIMPIEZA FINAL DE OBRA glb 1.00
01.03 SEGURIDAD Y SALUD EN EL TRABAJO
01.03.01 EQUIPOS DE PROTECCION INDIVIDUAL glb 1.00
01.03.02 EQUIPOS DE PROTECCION COLECTIVA glb 1.00
01.03.03 SEÑ ALIZACION TEMPORAL DE SEGURIDAD glb 1.00
01.03.04 ELABORACIÓ N, IMPLEMENTACIÓ N Y ADMINISTRACIÓ N DEL PLAN DE SEGURIDAD Y SALUD EN EL TRABAJO glb 1.00
01.03.05 CAPACITACION EN SEGURIDAD Y SALUD glb 1.00
01.03.06 EMERGENCIAS EN SEGURIDAD Y SALUD glb 1.00
01.04 ADECUACION E IMPLEMENTACION DEL PLAN COVID-19
01.04.01 ADECUACION DE AMBIENTES DE TRABAJO
01.04.01.01 ADECUACION DE LOS AMBIENTES DE TRABAJO glb 1.00
01.04.02 ACTIVIDADES DE PREVENCION DEL PLAN COVID-19
01.04.02.01 LIMPIEZA Y DESINFECCION DE LOS CENTROS DE TRABAJO mes 4.00
01.04.02.02 LAVADO Y DESINFECCION DE MANOS (OBLIGATORIO) mes 4.00
01.04.02.03 IDENTIFICACION DE SINTOMATOLOGIA COVID-19 AL INGRESO A LA OBRA glb 1.00
01.04.03 EQUIPAMIENTO Y PERSONAL DE SEGURIDAD Y SALUD
01.04.03.01 EQUIPAMIENTO PARA LA VIGILANCIA DE LA SALUD glb 1.00
01.04.03.02 PROFESIONAL DE SEGURIDAD Y SALUD mes 4.00
01.05 CORTE, RELLENO, Y ELIMINACION PRELIMINAR DE TIERRAS
01.05.01 EXCAVACION MASIVA DE TERRENO CON EQUIPO m3 837.86
RELLENO COMP. CON MATERIAL PROPIO C/ EQUIPO LIVIANO
01.05.02 m3 286.79
01.05.03 RELLENO CON MATERIAL CLASIFICADO E=20cm m3 548.44
01.05.04 ACARREO Y ELIMINACION DE MATERIAL EXCEDENTE m3 688.84
01.06 OBRAS DE CONCRETO SIMPLE
01.06.01 LOSAS - CONCRETO f'c=175 kg/cm2 m2 1,115.66
01.06.02 LOSAS - ENCOFRADO Y DESENCOFRADO m2 173.04
01.06.03 LOSAS - JUNTAS DE DILATACION m 691.80
01.06.04 CUNETAS - CONCRETO f'c=175 kg/cm2 m3 30.54
01.06.05 CUNETAS - ENCOFRADO Y DESENCOFRADO m2 538.76
01.06.06 REJILLA DE FIERROS EN CUNETAS m 271.85
01.06.07 CUNETAS - JUNTAS DE DILATACION m2 192.98
01.06.08 TUBERIA PVC 4" ENTERRADA m 16.40
01.07 OBRAS DE CONCRETO ARMADO
01.07.01 MURO DE CONTENCION - CONCRETO f'c=280 kg/cm2 m3 252.59
01.07.02 MURO DE CONTENCION - ENCOFRADO Y DESENCOFRADO m2 816.86
01.07.03 MURO DE CONTENCION - ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 8,179.63
01.07.04 MURO DE CONTENCION - JUNTAS DE DILATACION m2 74.40
01.07.05 TUBERIA PVC 2" DRENAJE m 49.70
01.07.06 SARDINEL PERALTADO - CONCRETO f'c=175 kg/cm2 m3 13.52
01.07.07 SARDINEL PERALTADO - ENCOFRADO Y DESENCOFRADO m2 113.84
01.07.08 SARDINEL PERALTADO - ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 191.39
RESUMEN DE METRADOS ESTRUCTURAS
REHABILITACION DEL LOCAL ESCOLAR 86821- HUASCARAN CON CODIGO LOCAL 041449, DISTRITO DE
QUILLO - YUNGAY - ANCASH
CLIENTE: MUNICIPALIDAD DISTRITAL DE QUILLO
LUGAR: ANCASH -YUNGAY - QUILLO
ESTRUCTURAS: RESUMEN
01.05.02 RELLENO COMP. CON MATERIAL PROPIO C/EQUIPO LIVIANO m3 Area CAD 435.47
Muro de Contencion Tipo 01 1.00 76.60 4.80 1.00 367.68
Muro de Contencion Tipo 02 1.00 18.82 3.45 1.00 64.93
Muro de Contencion Tipo 03 1.00 19.04 0.15 1.00 2.86
01.07.03 MURO DE CONTENCION - ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg kg/ml 19,671.29
Muro de Contencion Tipo 01
Av - fe 5/8" - Pantalla 383.00 6.45 1.56 2.00 7,707.49
Ah - fe 1/2" - Pantalla 23.00 82.13 1.02 2.00 3,853.64
01.08 VARIOS
01.08.01 FLETE TERRESTRE glb 1.00
Transporte de materiales hacia el C.P. 1.00 1.00 1.00
EJE 1-1 = EJE 3-3 1.00 9.70 1.00 1.50 2.00 29.10
EJE A-A = EJE B-B 1.00 2.95 1.00 1.50 2.00 8.85
EJE E-E = EJE F-F = EJE G-G 1.00 4.20 1.00 1.50 3.00 18.90
EJE 1-1 = EJE 3-3 1.00 9.70 0.75 1.10 2.00 16.01
EJE A-A = EJE B-B 1.00 2.95 0.75 1.10 2.00 4.87
EJE E-E = EJE F-F = EJE G-G 1.00 4.20 0.75 1.10 3.00 10.40
EJE A-A = EJE B-B 1.00 2.95 1.00 0.50 2.00 2.95
EJE E-E = EJE F-F = EJE G-G 1.00 4.20 1.00 0.50 3.00 6.30
Z2
ᶲ 5/8 10.00 1.15 1.56 2.00 35.88
6.00 1.90 1.56 2.00 35.57
Z3
ᶲ 5/8 10.00 1.40 1.56 2.00 43.68
7.00 2.20 1.56 2.00 48.05
METRADOS PABELLON 01
REHABILITACION DEL LOCAL ESCOLAR 86821- HUASCARAN CON CODIGO LOCAL 041449, DISTRITO DE QUILLO - YUNGAY -
ANCASH
CLIENTE: MUNICIPALIDAD DISTRITAL DE QUILLO
LUGAR: ANCASH -YUNGAY - QUILLO
ESTRUCTURAS: PABELLON 01
MEDIDAS N° DE
ITEM DESCRIPCION UND CANT VECES PARCIAL TOTAL
LONG. ANCHO ALTO
Z4
ᶲ 5/8 6.00 1.40 1.56 2.00 26.21
7.00 1.15 1.56 2.00 25.12
Z5
ᶲ 5/8 6.00 1.45 1.56 1.00 13.57
7.00 1.15 1.56 1.00 12.56
Z6
ᶲ 5/8 6.00 1.15 1.56 5.00 53.82
6.00 1.15 1.56 5.00 53.82
EJE A-A = EJE C-C 1.00 4.95 0.25 0.50 2.00 1.24
EJE B-B = EJE D-D = EJE H-H 1.00 5.45 0.25 0.50 3.00 2.04
EJE E-E = EJE F-F = EJE G-G 1.00 5.20 0.25 0.50 3.00 1.95
EJE B-B = EJE D-D = EJE H-H 2.00 5.45 0.50 3.00 16.35
EJE E-E = EJE F-F = EJE G-G 2.00 5.20 0.50 3.00 15.60
02.03.03 PLACAS
02.03.03.01 PLACAS - CONCRETO f'c=175 kg/cm2 m3 Area CAD 0.59
PL1 1.00 0.16 3.75 1.00 0.59
02.03.04 COLUMNAS
02.03.04.01 COLUMNAS - CONCRETO f'c=210 kg/cm2 m3 AREA CAD 11.72
C1 1.00 0.25 3.75 4.00 3.75
C2 kg/ml
ᶲ 5/8 16.00 5.25 1.56 6.00 786.24
ᶲ 3/8 33.00 1.90 0.58 6.00 218.20
33.00 1.70 0.58 6.00 195.23
C3 kg/ml
ᶲ 5/8 8.00 5.25 1.56 4.00 262.08
ᶲ 3/8 33.00 1.60 0.58 4.00 122.50
C4 kg/ml
ᶲ 5/8 6.00 5.25 1.56 2.00 98.28
ᶲ 3/8 33.00 1.10 0.58 2.00 42.11
C4 kg/ml
ᶲ 5/8 6.00 6.45 1.56 5.00 301.86
ᶲ 3/8 41.00 1.10 0.58 5.00 130.79
Pb kg/ml
ᶲ 3/8 4.00 4.00 0.58 4.00 37.12
ᶲ 1/4 16.00 0.85 0.25 4.00 13.60
Pc kg/ml
ᶲ 3/8 4.00 5.35 0.58 9.00 111.71
ᶲ 1/4 22.00 0.85 0.25 9.00 42.08
Pd kg/ml
ᶲ 3/8 4.00 5.05 0.58 4.00 46.86
ᶲ 1/4 21.00 0.85 0.25 4.00 17.85
02.03.06 VIGAS
02.03.06.01 VIGAS - CONCRETO f'c=210 kg/cm2 m3 18.62
Eje 1 = Eje 3 (VA-100) - 1P 1.00 22.30 0.100 2.00 4.46
Eje 2 (VS-100) - 2P 1.00 22.30 0.106 1.00 2.36
Eje A hasta Eje H - Techo Inclinado 1.00 0.25 4.51 8.00 9.02
VB-100 - Techo Inclinado 1.00 22.30 0.07 1.00 1.66
VB-101 1.00 22.30 0.25 0.20 1.00 1.12
METRADOS PABELLON 01
REHABILITACION DEL LOCAL ESCOLAR 86821- HUASCARAN CON CODIGO LOCAL 041449, DISTRITO DE QUILLO - YUNGAY -
ANCASH
CLIENTE: MUNICIPALIDAD DISTRITAL DE QUILLO
LUGAR: ANCASH -YUNGAY - QUILLO
ESTRUCTURAS: PABELLON 01
MEDIDAS N° DE
ITEM DESCRIPCION UND CANT VECES PARCIAL TOTAL
LONG. ANCHO ALTO
Eje 2 (VS-100)
ᶲ 5/8 6.00 25.00 1.56 1.00 234.00
ᶲ 5/8 2.00 23.60 1.56 1.00 73.63
ᶲ 3/8 148.00 1.60 0.58 1.00 137.34
VB-100
ᶲ 1/2 4.00 23.60 1.02 2.00 192.58
ᶲ 1/4 148.00 0.75 0.26 2.00 57.72
Eje 3 kg/ml
ᶲ 3/8 4.00 17.18 0.58 1.00 39.85
ᶲ 1/4 68.70 0.65 0.25 1.00 11.16
Voladizo kg/ml
ᶲ 3/8 4.00 23.20 0.58 1.00 53.82
ᶲ 1/4 93.00 0.65 0.25 1.00 15.11
Eje 2 kg/ml
ᶲ 3/8 4.00 6.30 0.58 2.00 29.23
ᶲ 1/4 25.20 0.65 0.25 2.00 8.19
Eje F kg/ml
ᶲ 3/8 4.00 6.05 0.58 2.00 28.07
ᶲ 1/4 24.70 0.65 0.25 2.00 8.03
02.03.08.03 LOSAS ALIGERADAS - ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg kg/ml 917.38
ф1/2 + 1.00 21.80 1.02 19.00 422.48
ф1/2 - 1.00 16.10 1.02 19.00 312.02
02.03.08.04 LOSAS ALIGERADAS - LADRILLO HUECO DE ARCILLA h=15 cm u AREA CAD fc 1,314.58
Pañ os interiores 1.00 157.81 8.33 1.00 1,314.58
EJE 1-1 = EJE 3-3 1.00 7.30 1.00 1.50 2.00 21.90
EJE A-A = EJE G-G 1.00 3.45 1.00 1.50 2.00 10.35
EJE B-B = EJE C-C = EJE D-D = EJE E-E = EJE F-F 1.00 4.20 1.00 1.50 5.00 31.50
EJE 1-1 = EJE 3-3 1.00 7.30 0.75 1.10 2.00 12.05
EJE A-A = EJE G-G 1.00 3.45 0.75 1.10 2.00 5.69
EJE B-B = EJE C-C = EJE D-D = EJE E-E = EJE F-F 1.00 4.20 0.75 1.10 5.00 17.33
EJE A-A = EJE G-G 1.00 3.45 1.00 0.50 2.00 3.45
EJE B-B = EJE C-C = EJE D-D = EJE E-E = EJE F-F 1.00 4.20 1.00 0.50 5.00 10.50
Z2
ᶲ 5/8 10.00 1.15 1.56 4.00 71.76
6.00 1.90 1.56 4.00 71.14
Z3
ᶲ 5/8 6.00 1.15 1.56 2.00 21.53
6.00 1.15 1.56 2.00 21.53
EJE A-A = EJE G-G 1.00 5.45 0.25 0.50 2.00 1.36
EJE B-B = EJE C-C = EJE D-D = EJE E-E = EJE F-F 1.00 4.20 0.25 0.50 5.00 2.63
EJE B-B = EJE C-C = EJE D-D = EJE E-E = EJE F-F 2.00 4.20 0.50 5.00 21.00
02.03.04 COLUMNAS
02.03.04.01 COLUMNAS - CONCRETO f'c=210 kg/cm2 m3 AREA CAD 13.13
C1 1.00 0.25 3.75 4.00 3.75
C2 kg/ml
ᶲ 5/8 16.00 5.25 1.56 10.00 1310.40
ᶲ 3/8 33.00 1.90 0.58 10.00 363.66
33.00 1.70 0.58 10.00 325.38
C3 kg/ml
ᶲ 5/8 6.00 6.45 1.56 5.00 301.86
ᶲ 3/8 41.00 1.10 0.58 5.00 130.79
Pb kg/ml
ᶲ 3/8 4.00 4.00 0.58 6.00 55.68
ᶲ 1/4 16.00 0.85 0.25 6.00 20.40
Pc kg/ml
ᶲ 3/8 4.00 5.35 0.58 7.00 86.88
ᶲ 1/4 22.00 0.85 0.25 7.00 32.73
Pd kg/ml
ᶲ 3/8 4.00 5.35 0.58 8.00 99.30
ᶲ 1/4 22.00 0.85 0.25 8.00 37.40
02.03.06 VIGAS
02.03.06.01 VIGAS - CONCRETO f'c=210 kg/cm2 m3 18.29
Eje 1 = Eje 3 (VA-100) - 1P 1.00 21.55 0.100 2.00 4.31
Eje 2 (VS-100) - 2P 1.00 21.55 0.106 1.00 2.28
Eje A hasta Eje H - Techo Inclinado 1.00 0.25 4.51 8.00 9.02
VB-100 - Techo Inclinado 1.00 21.55 0.07 1.00 1.61
VB-101 1.00 21.55 0.25 0.20 1.00 1.08
Eje 2 (VS-100)
ᶲ 5/8 6.00 24.95 1.56 1.00 233.53
ᶲ 5/8 2.00 22.85 1.56 1.00 71.29
ᶲ 3/8 216.00 1.60 0.58 1.00 200.45
VB-100
ᶲ 1/2 4.00 22.85 1.02 2.00 186.46
ᶲ 1/4 216.00 0.75 0.26 2.00 84.24
Eje 3 kg/ml
ᶲ 3/8 4.00 14.60 0.58 1.00 33.87
ᶲ 1/4 58.40 0.65 0.25 1.00 9.49
Voladizo kg/ml
ᶲ 3/8 4.00 22.45 0.58 1.00 52.08
ᶲ 1/4 90.00 0.65 0.25 1.00 14.63
Eje 2 kg/ml
ᶲ 3/8 4.00 5.20 0.58 2.00 24.13
ᶲ 1/4 20.80 0.65 0.25 2.00 6.76
METRADOS PABELLON 02
REHABILITACION DEL LOCAL ESCOLAR 86821- HUASCARAN CON CODIGO LOCAL 041449, DISTRITO DE QUILLO - YUNGAY -
ANCASH
CLIENTE: MUNICIPALIDAD DISTRITAL DE QUILLO
LUGAR: ANCASH -YUNGAY - QUILLO
ESTRUCTURAS: PABELLON 02
MEDIDAS N° DE
ITEM DESCRIPCION UND CANT VECES PARCIAL TOTAL
LONG. ANCHO ALTO
Interno entre Eje A y Eje B kg/ml
ᶲ 3/8 4.00 5.48 0.58 2.00 25.40
ᶲ 1/4 22.10 0.65 0.25 2.00 7.18
02.03.08.03 LOSAS ALIGERADAS - ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg kg/ml 909.04
ф1/2 + 1.00 21.30 1.02 19.00 412.79
ф1/2 - 1.00 15.90 1.02 19.00 308.14
02.03.08.04 LOSAS ALIGERADAS - LADRILLO HUECO DE ARCILLA h=15 cm u AREA CAD fc 1,282.20
Pañ os interiores 1.00 153.93 8.33 1.00 1,282.20
EJE 1-1 = 2-2 = 3-3 1.00 3.20 1.00 1.50 3.00 14.40
EJE A-A = EJE B-B = EJE C-C 1.00 2.05 1.00 1.50 3.00 9.23
EJE 1-1 = 2-2 = 3-3 1.00 10.95 0.75 1.10 3.00 27.10
EJE A-A = EJE B-B = EJE C-C 1.00 3.28 0.75 1.10 3.00 8.12
EJE A-A = EJE B-B = EJE C-C 1.00 2.05 1.00 0.50 3.00 3.08
EJEA-A = EJE B-B = EJE C-C 1.00 4.05 0.25 0.50 3.00 1.52
EJEA-A = EJE B-B = EJE C-C 2.00 4.05 0.50 3.00 12.15
METRADOS PABELLON 03
REHABILITACION DEL LOCAL ESCOLAR 86821- HUASCARAN CON CODIGO LOCAL 041449, DISTRITO DE QUILLO - YUNGAY -
ANCASH
CLIENTE: MUNICIPALIDAD DISTRITAL DE QUILLO
LUGAR: ANCASH -YUNGAY - QUILLO
ESTRUCTURAS: PABELLON 03
MEDIDAS N° DE
ITEM DESCRIPCION UND CANT VECES PARCIAL TOTAL
LONG. ANCHO ALTO
02.03.02.03 VIGAS DE CIMENTACION - ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 441.60
EJE 1-1 = EJE 2-2 = EJE 3-3 kg/ml
ᶲ 5/8 4.00 6.65 1.56 3.00 124.49
ᶲ 5/8 2.00 5.95 1.56 3.00 55.69
ᶲ 3/8 21.00 1.45 0.58 3.00 52.98
EJE A-A = EJE B-B = EJE C-C 1.00 4.10 0.25 1.05 3.00 3.23
EJE A-A = EJE B-B = EJE C-C 1.00 4.10 1.05 6.00 25.83
02.03.04 COLUMNAS
02.03.04.01 COLUMNAS - CONCRETO f'c=210 kg/cm2 m3 AREA CAD 3.38
C1 - 1P 1.00 0.0625 5.40 6.00 2.03
C1C - 1P 1.00 0.0625 7.23 3.00 1.35
C1C - 1P kg/ml
ᶲ 5/8 6.00 8.73 1.56 3.00 245.00
ᶲ 3/8 40.00 1.00 0.58 3.00 69.60
Pb kg/ml
ᶲ 3/8 4.00 4.85 0.58 4.00 45.01
ᶲ 1/4 12.00 0.75 0.25 4.00 9.00
Pc kg/ml
ᶲ 3/8 4.00 2.65 0.58 4.00 24.59
ᶲ 1/4 17.00 0.75 0.25 4.00 12.75
02.03.06 VIGAS
02.03.06.01 VIGAS - CONCRETO f'c=210 kg/cm2 m3 5.61
Eje 1 = Eje 3 (VA-100) - 1P 1.00 5.20 0.112 2.00 1.16
Eje 2 (VS-100) - 1P 1.00 5.20 0.106 1.00 0.55
Eje A hasta Eje C - Techo Inclinado 1.00 0.25 4.60 3.00 3.45
VB-100 - Techo Inclinado 1.00 5.20 0.04 2.00 0.45
Eje 2 (VS-100)
ᶲ 5/8 6.00 8.00 1.56 1.00 74.88
ᶲ 5/8 2.00 5.90 1.56 1.00 18.41
ᶲ 3/8 46.00 1.60 0.58 1.00 42.69
VB-100
ᶲ 1/2 4.00 8.00 1.02 2.00 65.28
ᶲ 1/4 52.00 0.75 0.26 2.00 20.28
Eje 3 kg/ml
ᶲ 3/8 4.00 6.65 0.58 1.00 15.43
ᶲ 1/4 16.75 0.65 0.25 1.00 2.72
Voladizo kg/ml
ᶲ 3/8 4.00 12.80 0.58 1.00 29.70
ᶲ 1/4 59.50 0.65 0.25 1.00 9.67
02.03.08.03 LOSAS ALIGERADAS - ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg kg/ml 277.80
ф1/2 + 1.00 5.75 1.02 15.00 87.98
ф1/2 - 1.00 4.40 1.02 15.00 67.32
02.03.08.04 LOSAS ALIGERADAS - LADRILLO HUECO DE ARCILLA h=15 cm u AREA CAD fc 294.12
Pañ os Interiores Inclinados 1.00 35.31 8.33 1.00 294.12
EJE A-A = EJE B-B = EJE C-C = EJE D-D 1.00 2.00 1.00 1.50 4.00 12.00
EJE A-A = EJE B-B = EJE C-C = EJE D-D 1.00 3.28 0.75 1.10 4.00 10.83
EJE A-A = EJE B-B = EJE C-C = EJE D-D 1.00 2.00 1.00 0.50 4.00 4.00
EJEA-A = EJE B-B = EJE C-C = EJE D-D 1.00 3.00 0.25 0.50 4.00 1.50
EJEA-A = EJE B-B = EJE C-C = EJE D-D 2.00 3.00 0.50 4.00 12.00
METRADOS PABELLON 04
REHABILITACION DEL LOCAL ESCOLAR 86821- HUASCARAN CON CODIGO LOCAL 041449, DISTRITO DE QUILLO - YUNGAY -
ANCASH
CLIENTE: MUNICIPALIDAD DISTRITAL DE QUILLO
LUGAR: ANCASH -YUNGAY - QUILLO
ESTRUCTURAS: PABELLON 04
MEDIDAS N° DE
ITEM DESCRIPCION UND CANT VECES PARCIAL TOTAL
LONG. ANCHO ALTO
02.03.02.03 VIGAS DE CIMENTACION - ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 388.31
EJE 1-1 = EJE 3-3 kg/ml
ᶲ 5/8 4.00 6.85 1.56 2.00 85.49
ᶲ 5/8 2.00 6.15 1.56 2.00 38.38
ᶲ 3/8 55.00 1.45 0.58 2.00 92.51
EJE A-A = EJE B-B = EJE C-C = EJE D-D 1.00 2.75 0.15 1.05 4.00 1.73
EJE A-A = EJE B-B = EJE C-C = EJE D-D 1.00 2.75 1.05 8.00 23.10
02.03.03 PLACAS
02.03.03.01 PLACAS - CONCRETO f'c=175 kg/cm2 m3 0.99
PL1 1.00 0.83 0.15 2.55 1.00 0.32
PL2 kg/ml
ᶲ 3/8 8.00 3.50 0.58 2.00 32.48
ᶲ 3/8 22.00 1.75 0.58 2.00 44.66
02.03.04 COLUMNAS
02.03.04.01 COLUMNAS - CONCRETO f'c=210 kg/cm2 m3 AREA CAD 2.70
C1 - 1P 1.00 0.0625 5.40 8.00 2.70
02.03.06 VIGAS
02.03.06.01 VIGAS - CONCRETO f'c=210 kg/cm2 m3 7.16
Eje 1 = Eje 3 (VA-100) - 1P 1.00 6.15 0.112 2.00 1.38
Eje 2 (VS-100) - 1P 1.00 6.15 0.106 1.00 0.65
Eje A hasta Eje D - Techo Inclinado 1.00 0.25 4.60 4.00 4.60
VB-100 - Techo Inclinado 1.00 6.15 0.04 2.00 0.53
Eje 2 (VS-100)
ᶲ 5/8 6.00 8.25 1.56 1.00 77.22
ᶲ 5/8 2.00 6.15 1.56 1.00 19.19
ᶲ 3/8 55.00 1.60 0.58 1.00 51.04
VB-100
ᶲ 1/2 4.00 8.25 1.02 2.00 67.32
ᶲ 1/4 50.00 0.75 0.26 2.00 19.50
Voladizo kg/ml
ᶲ 3/8 4.00 13.20 0.58 1.00 30.62
ᶲ 1/4 61.50 0.65 0.25 1.00 9.99
02.03.08.03 LOSAS ALIGERADAS - ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg kg/ml 286.21
ф1/2 + 1.00 6.05 1.02 15.00 92.57
ф1/2 - 1.00 4.65 1.02 15.00 71.15
02.03.08.04 LOSAS ALIGERADAS - LADRILLO HUECO DE ARCILLA h=15 cm u AREA CAD fc 208.17
Pañ os Interiores Inclinados 1.00 24.99 8.33 1.00 208.17
Z2 kg/ml
ᶲ 1/2 6.00 0.90 1.06 1.00 5.72
6.00 0.90 1.06 1.00 5.72
Z3 kg/ml
ᶲ 1/2 6.00 0.90 1.06 1.00 5.72
6.00 0.90 1.06 1.00 5.72
Z4 kg/ml
ᶲ 1/2 4.00 0.70 1.06 1.00 2.97
4.00 0.70 1.06 1.00 2.97
Z5 kg/ml
ᶲ 1/2 8.00 0.90 1.06 2.00 15.26
6.00 2.15 1.06 2.00 27.35
05.03.03 COLUMNAS
05.03.03.01 COLUMNAS - CONCRETO f'c=210 kg/cm2 m3 AREA CAD 20.47
CP1 1.00 0.25 0.25 4.40 54.00 14.85
PL1 1.00 1.75 0.25 4.40 2.00 3.85
METRADOS DE CERCO PERIMETRICO
REHABILITACION DEL LOCAL ESCOLAR 86821- HUASCARAN CON CODIGO LOCAL 041449, DISTRITO DE QUILLO - YUNGAY -
ANCASH
CLIENTE: MUNICIPALIDAD DISTRITAL DE YAUTAN
LUGAR: ANCASH - CASMA - YAUTAN
ESTRUCTURAS: CERCO PERIMETRICO
MEDIDAS N° DE
ITEM DESCRIPCION UND CANT VECES PARCIAL TOTAL
LONG. ANCHO ALTO
PL2 (sobre Portico de entrada) 1.00 5.75 0.25 1.00 1.00 1.44
Pa 1.00 0.25 0.15 4.40 2.00 0.33
PL1 kg/ml
ᶲ 1/2 18.00 5.35 1.02 2.00 196.45
ᶲ 1/4 62.00 4.25 0.25 2.00 131.75
Pa kg/ml
ᶲ 3/8 4.00 5.35 0.56 2.00 23.97
ᶲ 1/4 31.00 1.25 0.25 2.00 19.38
05.04 VARIOS
08.04.01 JUNTAS DE DILATACION E=1" m 84.00
Entre Muro Tipico 1.00 3.50 24.00 84.00
METRADOS DE BIODIGESTOR - POZO ABSORCIÓN
REHABILITACION DEL LOCAL ESCOLAR 86821- HUASCARAN CON CODIGO LOCAL 041449, DISTRITO DE QUILLO - YUNGAY - ANCASH
CLIENTE: MUNICIPALIDAD DISTRITAL DE QUILLO
LUGAR: ANCASH -YUNGAY - QUILLO
ESTRUCTURAS: BIODIGESTOR - POZO ABSORCION
MEDIDAS
ITEM DESCRIPCION Cantidad Parcial TOTAL UND
Largo Ancho Alto
06.01 BIODIGESTOR
06.01.01 LIMPIEZA DE TERRENO MANUAL 6.13 m2
Biodigestor 2.00 1.75 1.75 6.13