PRESUPUESTO DE MATERIALES PRIMER PISO
PRESUPUESTO DE MATERIALES METRADO UND CANTIDAD COSTO UNIT COSTO PARCIAL

1 SOLADOS 1.00 M3 S/. 1,119.50


agregado Confetillo m3 6.00 60.00 360.00
Cemento bol 31.00 24.50 759.50

2 ZAPATAS 39.50 M3 S/. 14,555.00


agregado confetillo m3 39.50 60.00 2370.00
cemento m3 310.00 24.50 7595.00
parrilla de Fierro de 5/8" var 70.00 63.00 4410.00
Alambre # 16 kg 30.00 6.00 180.00

3 CIMENTACION 35.00 M3 S/. 6,855.00


Piedra mediana m3 15.00 65.00 975.00
agregado confetillo m3 20.00 60.00 1200.00
Cemento bol 195.00 24.00 4680.00

4 SOBRECIMIENTO 7.00 M3 S/. 1,239.00


Piedra mediana m3 3.00 65.00 195.00
Hormigón m3 5.00 60.00 300.00
Cemento bol 31.00 24.00 744.00

5 COLUMNAS 17.00 M3 S/. 11,311.50


Agregado Confetillo m3 5.50 60.00 330.00
Cemento bol 45.00 24.50 1102.50
Fierro de 1/2" var 8.00 41.00 328.00
Fierro de 5/8" var 102.00 63.00 6426.00
Fierro de 3/8" var 110.00 24.70 2717.00
Alambre # 8 kg 30.00 6.00 180.00
Alambre # 16 kg 30.00 6.00 180.00
Clavo de 2" kg 4.00 6.00 24.00
Clavo de 2 1/2" kg 4.00 6.00 24.00

6 ESCALERA 1.00 M3 S/. 1,295.00


Agregado Confetillo m3 2.50 60.00 150.00
Cemento bol 16.00 24.50 392.00
Fierro de 1/2" var 18.00 40.50 729.00
Alambre # 16 kg 4.00 6.00 24.00

7 MUROS Y TABIQUES 275.00 M2 S/. 10,921.50


Arena gruesa m3 10.00 60.00 600.00
Cemento bls 57.00 24.50 1396.50
Ladrillo artesanal mll 10.50 850.00 8925.00

8 FALSO PISO 100.00 M2 S/. 4,081.00


Agregado Confetillo m3 18.00 60.00 1080.00
Cemento bol 98.00 24.50 2401.00
Otros (tuberias) gl 1.00 600.00 600.00

9 TECHO ALIGERADO 105.00 M2 S/. 36,449.00


Agregado Confetillo m3 22.00 60.00 1320.00
Cemento bol 200.00 24.50 4900.00
Fierro de 1/2" var 220.00 40.50 8910.00
Fierro de 5/8" var 135.00 63.00 8505.00
Fierro de 3/8" var 220.00 24.70 5434.00
Alambre de Temperatura var 150.00 11.00 1650.00
Alambre # 16 kg 50.00 6.00 300.00
Clavo de 2" kg 10.00 6.00 60.00
Clavo de 2 1/2" kg 10.00 6.00 60.00
Bloque hueco 15 und 1200.00 3.55 4260.00
Tubería para Inst. Electr. glb 1 350.00 350.00
Tubería para Inst. Sanit. glb 1 700.00 700.00

10 TANQUE CISTERNA DE CONCRETO 1.00 GLB S/. 1,956.50


Agregado Confetillo m2 3.50 60.00 210.00
Cemento und 25.00 24.50 612.50
Fierro de 1/2" var 28.00 40.50 1134.00

TOTAL MATERIALES PRIMER PISO S/. 89,783.00


PRESUPUESTO DE MATERIALES SEGUNDO PISO

PRESUPUESTO DE MATERIALES METRADO UND CANTIDAD COSTO UNIT COSTO PARCIAL

1 COLUMNAS 20.00 UND S/. 4,557.50


Agregado Confetillo m3 5.50 60.00 330.00
Cemento bol 45.00 24.50 1102.50
Fierro de 3/8" var 110.00 24.70 2717.00
Alambre # 8 kg 30.00 6.00 180.00
Alambre # 16 kg 30.00 6.00 180.00
Clavo de 2" kg 4.00 6.00 24.00
Clavo de 2 1/2" kg 4.00 6.00 24.00

2 ESCALERA 1.00 M3 S/. 1,295.00


Agregado Confetillo m3 2.50 60.00 150.00
Cemento bol 16.00 24.50 392.00
Fierro de 1/2" var 18.00 40.50 729.00
Alambre # 16 kg 4.00 6.00 24.00

3 MUROS Y TABIQUES 296 M2 S/. 11,650.00


Arena gruesa m3 11.00 60.00 660.00
Cemento bls 60.00 24.50 1470.00
Ladrillo artesanal mll 11.20 850.00 9520.00

4 TECHO ALIGERADO (CON MIXER) 105.00 M2 S/. 36,449.00


Agregado Confetillo m3 22.00 60.00 1320.00
Cemento bol 200.00 24.50 4900.00
Fierro de 1/2" var 220.00 40.50 8910.00
Fierro de 5/8" var 135.00 63.00 8505.00
Fierro de 3/8" var 220.00 24.70 5434.00
Alambre de Temperatura var 150.00 11.00 1650.00
Alambre # 16 kg 50.00 6.00 300.00
Clavo de 2" kg 10.00 6.00 60.00
Clavo de 2 1/2" kg 10.00 6.00 60.00
Bloque hueco 15 und 1200.00 3.55 4260.00
Tubería para Inst. Electr. glb 1 350.00 350.00
Tubería para Inst. Sanit. glb 1 700.00 700.00

TOTAL MATERIALES SEGUNDO PISO = S/. 53,951.50


PRESUPUESTO DE MANO DE OBRA PRIMER PISO

PRESUPUESTO DE MATERIALES UND METRADO COSTO UNIT COSTO PARCIAL


1 EXCAVACION DE ZAPATAS Gbl 17.00 120.00 S/. 2,040.00
2 EXCAVACION DE ZANJAS Gbl 45.00 20.00 S/. 900.00
3 CIMENTACION ml 80.00 25.00 S/. 2,000.00
4 SOBRECIMIENTO m3 81.00 25.00 S/. 2,025.00
5 SOLADOS Gbl 17.00 50.00 S/. 850.00
6 VACIADO DE ZAPATAS m3 17.00 150.00 S/. 2,550.00
7 COLUMNAS und 17.00 320.00 S/. 5,440.00
8 ESCALERA und 1.00 1000.00 S/. 1,000.00
9 MUROS Y TABIQUES m2 275.00 19.00 S/. 5,225.00
10 FALSO PISO m2 100.00 15.00 S/. 1,500.00
11 TECHO ALIGERADO m2 105.00 75.00 S/. 7,875.00
12 INSTALACIONES SANITARIAS Gbl 1.00 650.00 S/. 650.00
13 INSTALACIONES ELECTRICAS Gbl 1.00 400.00 S/. 400.00
14 TANQUE CISTERNA (ACABADO INTEGRO ) Gbl 1.00 3200.00 S/. 3,200.00

TOTAL MANO DE OBRA PRIMER PISO = S/. 35,655.00

PRESUPUESTO DE MANO DE SEGUNDO PISO

PRESUPUESTO DE MATERIALES UND METRADO COSTO UNIT COSTO PARCIAL


1 COLUMNAS und 17.00 320.00 S/. 5,440.00
2 ESCALERA und 1.00 1000.00 S/. 1,000.00
3 MUROS Y TABIQUES m2 275.00 19.00 S/. 5,225.00
4 TECHO ALIGERADO m2 105.00 75.00 S/. 7,875.00
5 INSTALACIONES SANITARIAS Gbl 1.00 650.00 S/. 650.00
6 INSTALACIONES ELECTICAS Gbl 1.00 400.00 S/. 400.00

TOTAL MANO DE OBRA SEGUNDO PISO = S/. 20,590.00

RESUMEN TOTAL DE PRESUPUESTO


PRESUPUESTO MATERIALES DEL PRIMER PISO S/. 88,783.00
PRESUPUESTO MATERIALES DEL SEGUNDO PISO S/. 53,951.50
PRESUPUESTO MANO DE OBRA DEL PRIMER PISO S/. 41,220.00
PRESUPUESTO MANO DE OBRA DEL SEGUNDO PISO S/. 25,240.00
TOTAL MANO DE PRESUPUESTO = S/. 209,194.50