Está en la página 1de 8

FORMATO Nº 15

VALORIZACION DE OBRA No. 02


FECHA DE INICIO DE OBRA: 2/11/2023
PERIODO VALORIZADO: 1/12/2023 AL 31/12/2023
PLAZO DE EJECUCIÓN: 120 días calendarios

CONVENIO N°: 1082-0809-2023-193-CUS/VMVU/PNVR

PRESUPUESTO AVANCE ANTERIOR AVANCE ACTUAL ACUMULADO SALDO


PARTIDA DESCRIPCION
UND Metrado P.U. Parcial METRADO VALORIZ % METRADO VALORIZ % METRADO VALORIZ % METRADO VALORIZ %
OBRAS PROVISIONALES, TRABAJOS PRELIMINARES,
01 10,834.07 8,099.29 74.76% 883.75 8.16% 8,983.04 82.91% 1,851.03 17.09%
SEGURIDAD Y SALUD

01.01 TRABAJOS PRELIMINARES 481.37 481.37 100.00% - 0.00% 481.37 100.00% 0.00 0.00%

01.01.01 CARTEL DE OBRA 4.00 X 2.40 und 1.00 481.37 481.37 1.00 481.37 100.00% - 0.00% 1.00 481.37 100.00% 0.00 0.00 0.00%

01.02 TRAZO NIVELES Y REPLANTEO PRELIMINAR 1,574.96 1,435.99 91.18% - 0.00% 1,435.99 91.18% 138.97 8.82%

01.02.01 TRAZO NIVELES Y REPLANTEO PRELIMINAR m2 1,810.30 0.87 1,574.96 1,650.56 1,435.99 91.18% - 0.00% 1,650.56 1,435.99 91.18% 159.74 138.97 8.82%

01.03 SEGURIDAD Y SALUD 8,777.74 6,181.93 70.43% 883.75 10.07% 7,065.68 80.50% 1,712.06 19.50%

01.03.01 EQUIPOS DE SEGURIDAD INDIVIDUAL glb 1.00 4,200.00 4,200.00 1.00 4,200.00 100.00% - 0.00% 1.00 4,200.00 100.00% 0.00 0.00 0.00%

01.03.02 EQUIPOS DE SEGURIDAD COLECTIVA glb 1.00 1,155.00 1,155.00 1.00 1,155.00 100.00% - 0.00% 1.00 1,155.00 100.00% 0.00 0.00 0.00%

01.03.03 SEÑALIZACION TEMPORAL DE SEGURIDAD glb 1.00 532.74 532.74 0.24 128.71 24.16% 0.2582 137.55 25.82% 0.4998 266.26 49.98% 0.50 266.48 50.02%

01.03.04 CAPACITACION EN SALUD Y SEGURIDAD glb 1.00 2,890.00 2,890.00 0.24 698.22 24.16% 0.2582 746.20 25.82% 0.4998 1,444.42 49.98% 0.50 1,445.58 50.02%

02 MOVIMIENTO DE TIERRAS 22,254.27 20,290.84 91.18% - 0.00% 20,290.84 91.18% 1,963.43 8.82%

02.01 EXCAVACIONES 22,254.27 20,290.84 91.18% - 0.00% 20,290.84 91.18% 1,963.43 8.82%

02.01.01 EXCAVACION DE TERRENO MANUAL (APORTE) m3 289.23 26.29 7,603.86 263.71 6,932.94 91.18% - 0.00% 263.71 6,932.94 91.18% 25.52 670.92 8.82%

NIVELACION INTERIOR Y APISONADO MANUAL


02.01.02 m2 1,071.20 4.86 5,206.03 976.69 4,746.71 91.18% - 0.00% 976.69 4,746.71 91.18% 94.51 459.32 8.82%
(APORTE)

02.01.03 SUELO MEJORADO E= 27CM (APORTE) m3 222.85 42.38 9,444.38 203.19 8,611.19 91.18% - 0.00% 203.19 8,611.19 91.18% 19.66 833.19 8.82%

03 OBRAS DE CONCRETO SIMPLE 33,431.09 0.00 0.00% 13,765.84 41.18% 13,765.84 41.18% 19,665.24 58.82%

03.01 CIMIENTOS 33,431.09 0.00 0.00% 13,765.84 41.18% 13,765.84 41.18% 19,665.24 58.82%
FORMATO Nº 15

VALORIZACION DE OBRA No. 02


FECHA DE INICIO DE OBRA: 2/11/2023
PERIODO VALORIZADO: 1/12/2023 AL 31/12/2023
PLAZO DE EJECUCIÓN: 120 días calendarios

CONVENIO N°: 1082-0809-2023-193-CUS/VMVU/PNVR

PRESUPUESTO AVANCE ANTERIOR AVANCE ACTUAL ACUMULADO SALDO


PARTIDA DESCRIPCION
UND Metrado P.U. Parcial METRADO VALORIZ % METRADO VALORIZ % METRADO VALORIZ % METRADO VALORIZ %

03.01.01 ENCOFRADO Y DESENCOFRADO DE CIMIENTOS m2 206.37 54.42 11,230.66 0.00 0.00 0.00% 84.9758 4,624.38 41.18% 84.98 4,624.38 41.18% 121.39 6,606.27 58.82%

CONCRETO EN SOBRECIMIENTO MEZCLA 1:8 + 25% P.M


03.01.02 m3 30.82 251.00 7,735.82 0.00 0.00 0.00% 12.6910 3,185.44 41.18% 12.69 3,185.44 41.18% 18.13 4,550.38 58.82%
VR

03.01.03 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTOS m2 440.30 16.22 7,141.67 0.00 0.00 0.00% 181.3000 2,940.69 41.18% 181.30 2,940.69 41.18% 259.00 4,200.98 58.82%

03.01.04 SOLADO f'c=100 Kg/cm2 m2 351.22 20.85 7,322.94 0.00 0.00 0.00% 144.6200 3,015.33 41.18% 144.62 3,015.33 41.18% 206.60 4,307.61 58.82%

04. OBRAS DE CONCRETO ARMADO 260,203.33 0.00 0.00% 115,159.18 44.26% 115,159.18 44.26% 145,044.14 55.74%

04.01 CONCRETO 104,259.08 0.00 0.00% 44,983.83 43.15% 44,983.83 43.15% 59,275.24 56.85%

CONCRETO f'c=175 Kg/cm2 PARA PLATEA DE


04.01.01 m3 215.49 356.40 76,800.64 0.00 0.00 0.00% 101.4069 36,141.42 47.06% 101.41 36,141.42 47.06% 114.08 40,659.22 52.94%
CIMENTACION

04.01.02 CONCRETO f'c=175 Kg/cm2 PARA COLUMNAS m3 29.70 394.41 11,713.98 0.00 0.00 0.00% 9.6086 3,789.73 32.35% 9.61 3,789.73 32.35% 20.09 7,924.25 67.65%

04.01.03 CONCRETO f´c=175 Kg/cm2 PARA VIGAS m3 30.42 388.56 11,820.00 0.00 0.00 0.00% 9.7357 3,782.90 32.00% 9.74 3,782.90 32.00% 20.68 8,037.09 68.00%

CONCRETO f'c= 175 Kg/cm2 PARA VIGA DE CIERRE


04.01.04 m3 10.10 388.56 3,924.46 0.00 0.00 0.00% 3.2679 1,269.78 32.36% 3.27 1,269.78 32.36% 6.83 2,654.68 67.64%
SUPERIOR

04.02 ENCOFRADO Y DESENCOFRADO 26,845.94 0.00 0.00% 8,685.42 32.35% 8,685.42 32.35% 18,160.51 67.65%

04.02.01 ENCOFRADO Y DESENCOFRADO DE COLUMNAS m2 423.94 23.20 9,835.41 0.00 0.00 0.00% 137.1569 3,182.04 32.35% 137.16 3,182.04 32.35% 286.78 6,653.37 67.65%

04.02.02 ENCOFRADO Y DESENCOFRADO DE VIGAS m2 443.14 28.22 12,505.41 0.00 0.00 0.00% 143.3687 4,045.86 32.35% 143.37 4,045.86 32.35% 299.77 8,459.55 67.65%

ENCOFRADO Y DESENCOFRADO DE VIGA DE CIERRE


04.02.03 m2 135.86 33.16 4,505.12 0.00 0.00 0.00% 43.9543 1,457.52 32.35% 43.95 1,457.52 32.35% 91.91 3,047.59 67.65%
SUPERIOR

04.03 ACERO CORRUGADO 129,098.31 0.00 0.00% 61,489.93 47.63% 61,489.93 47.63% 67,608.39 52.37%

ACERO CORRUGADO fy=4200 kg/cm2 PARA CIMIENTOS


04.03.01 kg 1,860.14 7.06 13,132.59 0.00 0.00 0.00% 984.8347 6,952.93 52.94% 984.83 6,952.93 52.94% 875.31 6,179.66 47.06%
(REFUERZOS)

ACERO CORRUGADO fy=4200 kg/cm2 PARA PLATEA DE


04.03.02 kg 3,843.36 7.06 27,134.12 0.00 0.00 0.00% 2,034.8782 14,366.24 52.95% 2,034.88 14,366.24 52.95% 1,808.48 12,767.88 47.05%
CIMENTACION
FORMATO Nº 15

VALORIZACION DE OBRA No. 02


FECHA DE INICIO DE OBRA: 2/11/2023
PERIODO VALORIZADO: 1/12/2023 AL 31/12/2023
PLAZO DE EJECUCIÓN: 120 días calendarios

CONVENIO N°: 1082-0809-2023-193-CUS/VMVU/PNVR

PRESUPUESTO AVANCE ANTERIOR AVANCE ACTUAL ACUMULADO SALDO


PARTIDA DESCRIPCION
UND Metrado P.U. Parcial METRADO VALORIZ % METRADO VALORIZ % METRADO VALORIZ % METRADO VALORIZ %
ACERO CORRUGADO fy=4200 kg/cm2 PARA VIGA DE
04.03.03 kg 4,381.24 7.06 30,931.55 0.00 0.00 0.00% 2,319.6089 16,376.44 52.94% 2,319.61 16,376.44 52.94% 2,061.63 14,555.12 47.06%
CIMENTACION

04.03.04 ACERO CORRUGADO fy=4200 kg/cm2 EN COLUMNAS kg 4,071.84 7.06 28,747.19 0.00 0.00 0.00% 2,155.7998 15,219.95 52.94% 2,155.80 15,219.95 52.94% 1,916.04 13,527.24 47.06%

04.03.05 ACERO CORRUGADO fy=4200 kg/cm2 EN VIGAS kg 3,685.26 7.06 26,017.94 0.00 0.00 0.00% 1,083.9000 7,652.33 29.41% 1,083.90 7,652.33 29.41% 2,601.36 18,365.60 70.59%

ACERO CORRUGADO fy=4200 kg/cm2 EN VIGAS TIJERAL


04.03.06 kg 444.04 7.06 3,134.92 0.00 0.00 0.00% 130.6000 922.04 29.41% 130.60 922.04 29.41% 313.44 2,212.89 70.59%
(VIGAS INCLINADA)

05 ESTRUCTURA METÁLICA 162,629.39 0.00 0.00% - 0.00% 0.00 0.00% 162,629.39 100.00%

05.01 TIJERAL Y RETICULARES 162,629.39 0.00 0.00% - 0.00% 0.00 0.00 0.00% 162,629.39 100.00%

TIJERAL TIPO DE ACERO LAC 80X40X2.0mm (APOYADO EN


05.01.01 und 68.00 415.95 28,284.60 0.00 0.00 0.00% - 0.00% 0.00 0.00 0.00% 68.00 28,284.60 100.00%
VIGA)

05.01.02 TIJERAL TIPO DE ACERO LAC 80X40X2.0mm (LIBRE) und 34.00 489.27 16,635.18 0.00 0.00 0.00% - 0.00% 0.00 0.00 0.00% 34.00 16,635.18 100.00%

05.01.03 CORREAS DE ACERO LAC 40X60X2.0mm m 2,994.72 33.60 100,622.59 0.00 0.00 0.00% - 0.00% 0.00 0.00 0.00% 2,994.72 100,622.59 100.00%

FRISO (ARRIOSTRE DE CORREA FIERRO LAC 40X60mm


05.01.04 m 574.74 29.73 17,087.02 0.00 0.00 0.00% - 0.00% 0.00 0.00 0.00% 574.74 17,087.02 100.00%
e=2.0 mm

06 COBERTURA 87,368.86 0.00 0.00% - 0.00% 0.00 0.00% 87,368.86 100.00%

COBERTURA DE CALAMINA PLANCHA ONDULADA


06.01 m2 2,216.09 35.90 79,557.63 0.00 0.00 0.00% - 0.00% 0.00 0.00 0.00% 2,216.09 79,557.63 100.00%
GALVANIZADA PREPINTADA

CUMBRERA PLANCHA GALVANIZADA O SIMILAR e=


06.02 m 249.56 31.30 7,811.23 0.00 0.00 0.00% - 0.00% 0.00 0.00 0.00% 249.56 7,811.23 100.00%
0.30mm

07 CIELO RASOS 63,580.28 0.00 0.00% - 0.00% 0.00 0.00% 63,580.28 100.00%

07.01 CIELO RASO CON FIBROCEMENTO 4mm 1.2m X 2.40m m2 1,120.16 44.48 49,824.72 0.00 0.00 0.00% - 0.00% 0.00 0.00 0.00% 1,120.16 49,824.72 100.00%

07.02 POLIESTIRENO EXPANDIDO e=1" m2 1,120.16 12.28 13,755.56 0.00 0.00 0.00% - 0.00% 0.00 0.00 0.00% 1,120.16 13,755.56 100.00%

08 MUROS Y TABIQUES DE ALBAÑILERIA 162,524.32 18,018.00 11.09% 105,409.52 64.86% 123,427.52 75.94% 39,096.80 24.06%
FORMATO Nº 15

VALORIZACION DE OBRA No. 02


FECHA DE INICIO DE OBRA: 2/11/2023
PERIODO VALORIZADO: 1/12/2023 AL 31/12/2023
PLAZO DE EJECUCIÓN: 120 días calendarios

CONVENIO N°: 1082-0809-2023-193-CUS/VMVU/PNVR

PRESUPUESTO AVANCE ANTERIOR AVANCE ACTUAL ACUMULADO SALDO


PARTIDA DESCRIPCION
UND Metrado P.U. Parcial METRADO VALORIZ % METRADO VALORIZ % METRADO VALORIZ % METRADO VALORIZ %

08.01 MUROS Y TABIQUES 162,524.32 18,018.00 11.09% 105,409.52 64.86% 0.00 123,427.52 75.94% 39,096.80 24.06%

SUMINISTRO BLOQUETA DE CONCRETO LISO ENTERO


08.01.01 und 18,156.00 4.50 81,702.00 3,204.00 14,418.00 17.65% 14,952.0000 67,284.00 82.35% 18,156.00 81,702.00 100.00% 0.00 0.00 0.00%
.14 X .19 X .39 M

SUMINISTRO BLOQUETA DE CONCRETO LISO MEDIO .14


08.01.02 und 5,100.00 4.00 20,400.00 900.00 3,600.00 17.65% 4,200.0000 16,800.00 82.35% 5,100.00 20,400.00 100.00% 0.00 0.00 0.00%
X .19 X .39 M

08.01.03 MURO CON BLOQUETA DE CONCRETO m2 1,705.40 35.43 60,422.32 0.00 0.00 0.00% 601.9057 21,325.52 35.29% 601.91 21,325.52 35.29% 1,103.49 39,096.80 64.71%

09 REVOQUES ENLUCIDOS Y MOLDURAS 45,272.64 0.00 0.00% - 0.00% 0.00 0.00% 45,272.64 100.00%

09.01 TARRAJEO VESTIDURAS Y DERRAMES 45,272.64 0.00 0.00% - 0.00% 0.00 0.00 0.00% 45,272.64 100.00%

09.01.01 DERRAME EN PUERTAS Y VENTANAS m 704.48 14.25 10,038.84 0.00 0.00 0.00% - 0.00% 0.00 0.00 0.00% 704.48 10,038.84 100.00%

09.01.02 CENEFAS EN VENTANAS m 1,285.20 14.25 18,314.10 0.00 0.00 0.00% - 0.00% 0.00 0.00 0.00% 1,285.20 18,314.10 100.00%

09.01.03 TARRAJEO DE VIGAS Y DINTELES INTERNO Y EXTERNO m2 579.00 18.19 10,532.01 0.00 0.00 0.00% - 0.00% 0.00 0.00 0.00% 579.00 10,532.01 100.00%

09.01.04 TARRAJEO DE COLUMNAS m2 377.30 16.93 6,387.69 0.00 0.00 0.00% - 0.00% 0.00 0.00 0.00% 377.30 6,387.69 100.00%

10 PISOS Y PAVIMENTOS 33,003.72 650.26 1.97% 1,788.18 5.42% 2,438.44 7.39% 30,565.29 92.61%

10.01 PISOS 26,210.72 0.00 0.00 0.00% - 0.00% 0.00 0.00 0.00% 26,210.72 100.00%

10.01.01 PISO DE CEMENTO SEMIPULIDO e=2" inc/bruñado m2 910.86 28.16 25,649.82 0.00 0.00 0.00% - 0.00% 0.00 0.00 0.00% 910.86 25,649.82 100.00%

10.01.01 JUNTAS ASFALTICAS DE 1 1/2" X 4" m 91.80 6.11 560.90 0.00 0.00 0.00% - 0.00% 0.00 0.00 0.00% 91.80 560.90 100.00%

10.02 VEREDAS 6,793.00 650.26 9.57% 1,788.18 26.32% 2,438.44 35.90% 4,354.57 64.10%

NIVELACION RELLENO Y APISONADO e=4" C/MAT. PROP-


10.02.01 m2 96.90 7.36 713.18 88.35 650.26 91.18% - 0.00% 88.35 650.26 91.18% 8.55 62.93 8.82%
VEREDA (APORTE)

VEREDA EXTERIOR DE CONCRETO e= 4" ACABADO


10.02.02 m2 111.86 46.18 5,165.69 0.00 0.00 0.00% 32.9000 1,519.32 29.41% 32.90 1,519.32 29.41% 78.96 3,646.37 70.59%
SEMIPULIDO BRUÑA INC/DADO
FORMATO Nº 15

VALORIZACION DE OBRA No. 02


FECHA DE INICIO DE OBRA: 2/11/2023
PERIODO VALORIZADO: 1/12/2023 AL 31/12/2023
PLAZO DE EJECUCIÓN: 120 días calendarios

CONVENIO N°: 1082-0809-2023-193-CUS/VMVU/PNVR

PRESUPUESTO AVANCE ANTERIOR AVANCE ACTUAL ACUMULADO SALDO


PARTIDA DESCRIPCION
UND Metrado P.U. Parcial METRADO VALORIZ % METRADO VALORIZ % METRADO VALORIZ % METRADO VALORIZ %

10.02.03 ENCOFRADO Y DESENCOFRADO DE VEREDAS m2 34.34 26.62 914.13 0.00 0.00 0.00% 10.1000 268.86 29.41% 10.10 268.86 29.41% 24.24 645.27 70.59%

11 ZOCALOS Y CONTRAZOCALOS 22,759.02 0.00 0.00% - 0.00% 0.00 0.00% 22,759.02 100.00%

11.01 ZOCALOS 22,759.02 0.00 0.00 0.00% - 0.00% 0.00 0.00 0.00% 22,759.02 100.00%

ZOCALO DE CEMENTO SOBRE MURO EXTERIOR H=0.60 CM


11.01.01 m2 439.42 32.48 14,272.36 0.00 0.00 0.00% - 0.00% 0.00 0.00 0.00% 439.42 14,272.36 100.00%
INC/BRUÑAS

CONTRAZOCALO DE CEMENTO PULIDO H=0.265 CM


11.01.01 m2 272.62 31.13 8,486.66 0.00 0.00 0.00% - 0.00% 0.00 0.00 0.00% 272.62 8,486.66 100.00%
INC/BRUÑAS

12 PUERTAS Y VENTANAS 135,574.66 0.00 0.00% - 0.00% 0.00 0.00% 135,574.66 100.00%

12.01 PUERTA 78,916.72 0.00 0.00 0.00% - 0.00% 0.00 0.00 0.00% 78,916.72 100.00%

PUERTA DE MADERA DE TABLERO REBAJADO 2.285x


12.01.01 und 34.00 919.60 31,266.40 0.00 0.00 0.00% - 0.00% 0.00 0.00 0.00% 34.00 31,266.40 100.00%
0.985 PANEL MADERA MACHIHEMBRADA

12.01.02 PUERTA CONTRAPLACADA 2.285 X 0.83 TRIPLAY 4mm und 68.00 700.74 47,650.32 0.00 0.00 0.00% - 0.00% 0.00 0.00 0.00% 68.00 47,650.32 100.00%

12.01 VENTANAS 56,657.94 0.00 0.00% - 0.00% 0.00 0.00 0.00% 56,657.94 100.00%

VENTANA CORREDIZA DE ALUMINIO 1.21 X 1.42 4mm y


12.02.01 und 102.00 355.96 36,307.92 0.00 0.00 0.00% - 0.00% 0.00 0.00 0.00% 102.00 36,307.92 100.00%
sup de 3mm (V1)

VENTANA CORREDIZA DE ALUMINIO 0.95 X 1.42 4mm y


12.02.02 und 34.00 325.49 11,066.66 0.00 0.00 0.00% - 0.00% 0.00 0.00 0.00% 34.00 11,066.66 100.00%
sup de 3mm (V2)

12.02.03 VENTANA DE VENTILACION CON MOSQUITERO (V3) und 136.00 68.26 9,283.36 0.00 0.00 0.00% - 0.00% 0.00 0.00 0.00% 136.00 9,283.36 100.00%

13 PINTURAS 23,589.23 0.00 0.00% - 0.00% 0.00 0.00% 23,589.23 100.00%

13.01.01 PINTURA EN INTERIORES (CIELO RASO) m2 1,120.16 6.31 7,068.21 0.00 0.00 0.00% - 0.00% 0.00 0.00 0.00% 1,120.16 7,068.21 100.00%

13.01.02 PINTURA DE COLUMNAS m2 377.30 10.54 3,976.74 0.00 0.00 0.00% - 0.00% 0.00 0.00 0.00% 377.30 3,976.74 100.00%

13.01.03 PINTURA DE VIGAS Y DINTELES INTERIOR Y EXTERIOR m2 777.97 10.54 8,199.80 0.00 0.00 0.00% - 0.00% 0.00 0.00 0.00% 777.97 8,199.80 100.00%
FORMATO Nº 15

VALORIZACION DE OBRA No. 02


FECHA DE INICIO DE OBRA: 2/11/2023
PERIODO VALORIZADO: 1/12/2023 AL 31/12/2023
PLAZO DE EJECUCIÓN: 120 días calendarios

CONVENIO N°: 1082-0809-2023-193-CUS/VMVU/PNVR

PRESUPUESTO AVANCE ANTERIOR AVANCE ACTUAL ACUMULADO SALDO


PARTIDA DESCRIPCION
UND Metrado P.U. Parcial METRADO VALORIZ % METRADO VALORIZ % METRADO VALORIZ % METRADO VALORIZ %

13.01.03 PINTURA ESMALTE EN ZOCALOS m2 439.28 9.89 4,344.48 0.00 0.00 0.00% - 0.00% 0.00 0.00 0.00% 439.28 4,344.48 100.00%

14 INSTALACIONES SANITARIAS 40,693.58 0.00 0.00% 4,569.60 11.23% 4,569.60 11.23% 36,123.98 88.77%

14.01 INSTALACIONES SANITARIAS EN MODULO glb 34.00 51.12 1,738.08 0.00 0.00 0.00% 16.0000 817.92 47.06% 16.00 817.92 47.06% 18.00 920.16 52.94%

CANALETA DE PLANCHA GALVANIZADA SEGÚN DISEÑO


14.02 glb 34.00 676.79 23,010.86 0.00 0.00 0.00% 0.0000 - 0.00% 0.00 0.00 0.00% 34.00 23,010.86 100.00%
e=0.30mm

14.03 MONTANTE DE DRENAJE PLUVIAL PVC 3" glb 34.00 468.96 15,944.64 0.00 0.00 0.00% 8.0000 3,751.68 23.53% 8.00 3,751.68 23.53% 26.00 12,192.96 76.47%

15 INSTALACIONES ELECTRICAS 42,830.82 0.00 0.00% 5,038.92 11.76% 5,038.92 11.76% 37,791.90 88.24%

15.01 INSTALACIONES ELECTRICAS EN MODULO glb 34.00 1,259.73 42,830.82 0.00 0.00 0.00% 4.0000 5,038.92 11.76% 4.00 5,038.92 11.76% 30.00 37,791.90 88.24%

16 MITIGACION DE IMPACTO AMBIENTAL 16,650.14 0.00 0.00% 720.88 4.33% 720.88 4.33% 15,929.26 95.67%

16.01 MITIGACION DEL IMPACTO AMBIENTAL (APORTE) glb 34.00 180.22 6,127.48 0.00 0.00 0.00% 4.0000 720.88 11.76% 4.00 720.88 11.76% 30.00 5,406.60 88.24%

16.02 LIMPIEZA FINAL DE OBRA (APORTE) und 34.00 309.49 10,522.66 0.00 0.00 0.00% - 0.00% 0.00 0.00 0.00% 34.00 10,522.66 100.00%

17 FLETE Y TRANSPORTE 186,654.07 32,685.72 17.51% 106,921.59 57.28% 139,607.31 74.79% 47,046.76 25.21%

17.01 FLETE Y TRANSPORTE DE MATERIALES 130,068.08 29,003.25 22.30% 60,312.72 46.37% 0.00 89,315.97 68.67% 40,752.11 31.33%

FLETE TERRESTRE TRANSPORTE DE MATERIAL DEL


17.01.01 glb 1.00 93,558.87 93,558.87 0.31 29,003.25 31.00% 0.4438 41,521.43 44.38% 0.75 70,524.68 75.38% 0.25 23,034.19 24.62%
PROVEEDOR AL ALMACEN (INC. CARGA-DESCARGA)
FLETE TERRESTRE TRANSP. MATERIALES DE
17.01.02 ALMACEN A PUNTA DE CARRETERA (INC. CARGA- glb 1.00 15,486.12 15,486.12 0.00 0.00 0.00% 0.5147 7,970.71 51.47% 0.51 7,970.71 51.47% 0.49 7,515.41 48.53%
DESCARGA)
FLETE RURAL DE ACEMILA PARA TRANSPORTE DE
17.01.03 glb 1.00 13,507.13 13,507.13 0.00 0.00 0.00% 0.5147 6,952.12 51.47% 0.51 6,952.12 51.47% 0.49 6,555.01 48.53%
MATERIALES PUNTA DE CARRETERA A VIVIENDA (APORTE)

ACOMPAÑAMIENTO CARGA Y DESCARGA TRANSP. DE


17.01.04 glb 1.00 7,515.96 7,515.96 0.00 0.00 0.00% 0.5147 3,868.46 51.47% 0.51 3,868.46 51.47% 0.49 3,647.50 48.53%
MATERIALES EN ACEMILA (APORTE)

17.02 FLETE Y TRANSPORTE DE AGREGADO Y PIEDRA 56,585.99 3,682.47 6.51% 46,608.87 82.37% 50,291.34 88.88% 6,294.65 11.12%
FORMATO Nº 15

VALORIZACION DE OBRA No. 02


FECHA DE INICIO DE OBRA: 2/11/2023
PERIODO VALORIZADO: 1/12/2023 AL 31/12/2023
PLAZO DE EJECUCIÓN: 120 días calendarios

CONVENIO N°: 1082-0809-2023-193-CUS/VMVU/PNVR

PRESUPUESTO AVANCE ANTERIOR AVANCE ACTUAL ACUMULADO SALDO


PARTIDA DESCRIPCION
UND Metrado P.U. Parcial METRADO VALORIZ % METRADO VALORIZ % METRADO VALORIZ % METRADO VALORIZ %
FLETE TERRESTRE TRANSPORTE DE AGREGADOS DEL
17.02.01 PROVEDOR A PUNTA DE CARRETERA (INC. CARGA Y glb 1.00 31,491.94 31,491.94 0.11 3,464.11 11.00% 0.8900 28,027.83 89.00% 1.00 31,491.94 100.00% 0.00 0.00 0.00%
DESC.)
FLETE TERRESTRE TRANS. PIEDRA DE CANTERA A
17.02.02 glb 1.00 2,426.24 2,426.24 0.09 218.36 9.00% 0.6597 1,600.59 65.97% 0.75 1,818.95 74.97% 0.25 607.29 25.03%
PUNTA DE CARRETERA (INC. CARGA-DESCARGA)
FLETE RURAL DE ACEMILA TRANS. DE AGREGADO Y
17.02.03 PIEDRA PUNTA DE CARRETERA O CANTERA A VIVIENDA glb 1.00 14,563.84 14,563.84 0.00 0.00 0.00% 0.7491 10,909.77 74.91% 0.75 10,909.77 74.91% 0.25 3,654.07 25.09%
(APORTE)

ACOMPAÑAMIENTO CARGA Y DESCARGA TRANSP. DE


17.02.04 glb 1.00 8,103.97 8,103.97 0.00 0.00 0.00% 0.7491 6,070.68 74.91% 0.75 6,070.68 74.91% 0.25 2,033.29 25.09%
AGREGADO Y PIEDRA EN ACEMILA (APORTE)

COSTO DIRECTO 1,349,853.49 79,744.11 5.91% 354,257.46 26.24% 434,001.57 32.15% 915,851.91 67.85%

PRESIDENTE DEL N.E. RESIDENTE SUPERVISOR


NOMBRES Y APELLIDOS NOMBRES Y APELLIDOS NOMBRES Y APELLIDOS
DNI: DNI: DNI:
CURVA "S" : CONTROL DE AVANCE DE OBRA Y EJECUCION DE OBRA

“MEJORAMIENTO DE VIVIENDA RURAL EN LOS CENTROS POBLADOS CHAPO ALTO, QUINCORINI Y YANAN
HUARI - DISTRITO DE QUELLOUNO - PROVINCIA DE LA CONVENCION - DEPARTAMENTO DE CUSCO"

Control de Obra (Curva "S")


110

100 Programado
90 Ejecutado
% de Avances Acumulados

80

70

60

50

40

30

20

10
Meses Valorizados
0
del 02/11/2023 al del 01/12/2023 al del 01/01/2024 al del 01/02/2024 al
INICIO
30/11/2023 31/12/2023 31/01/2024 29/02/2024
Programado 0 5.91 39.82 81.77 100.00
Ejecutado 0 5.91 32.15

MES NOVIEMBRE DICIEMBRE ENERO FEBRERO


del 02/11/2023 al del 01/12/2023 al del 01/01/2024 al del 01/02/2024 al
DIA INICIO 30/11/2023 31/12/2023 31/01/2024 29/02/2024

Programado 0 5.91 39.82 81.77 100.00


Ejecutado 0 5.91 32.15
AVANCE 100% 81% 0% 0%

También podría gustarte