Documentos de Académico
Documentos de Profesional
Documentos de Cultura
UF PROGRAMACION FINANCIERA
MESES
ITEM DESCRIPCION UN. CANTIDAD DE PRECIO PRECIO TOTAL d
OBRAS UNITARIO 1 2 3 4 5 6 7 8 9 10 meses valor eepp ($) % avance del mes % avance acumulado
Infraestructura
1 300,560 0.31% 0.31%
156 Relleno Estructural m3 630.00 3,758 2,367,540 3 789,180 789,180 789,180
2 5,479,967 5.64% 5.95%
201 Excavación a máquina m3 680.00 1,326 901,680 3 300,560 300,560 300,560
3 7,877,254 8.10% 14.05%
203 Excavación directa con agotamiento en TCN m3 980.00 9,283 9,097,340 3 3,032,447 3,032,447 3,032,447
4 7,746,987 7.97% 22.02%
251 Moldaje m2 940.00 6,852 6,440,880 3 2,146,960 2,146,960 2,146,960
5 17,089,284 17.58% 39.61%
261 Acero en barras A-63-42H Kg 17100.00 416 7,113,600 4 1,778,400 1,778,400 1,778,400 1,778,400
6 35,189,469 36.21% 75.81%
272 Hormigón Pobre(H5) m3 35.00 35,365 1,237,775 2 618,888 618,888
7 13,816,634 14.22% 90.03%
275 Hormigón H-25 m3 710.00 50,395 35,780,450 3 11,926,817 11,926,817 11,926,817
8 2,630,261 2.71% 92.73%
Superestructura
9 5,217,201 5.37% 98.10%
251 Moldaje m2 300.00 6,852 2,055,600 2 1,027,800 1,027,800
10 1,846,044 1.90% 100.00%
261 Acero en barras A-63-42H Kg 9500.00 416 3,952,000 2 1,976,000 1,976,000
97,193,660
276 Hormigón H-30 m3 70.00 55,700 3,899,000 1 3,899,000
% avance acumulado
281 Hormigón para pavimento m3 13.00 66,309 862,017 1 862,017 120.00%
355 Suministro y colocación de Barandas New Jers ml 72.00 51,279 3,692,088 2 1,846,044 1,846,044 60.00%
Prog. Parcial $ 300,560 5,479,967 7,877,254 7,746,987 17,089,284 35,189,469 13,816,634 2,630,261 5,217,201 1,846,044 0.00%
0 2 4 6 8 10 12
Prog. Acum. $
Prog. Parcial %
Prog. Acum. %
300560 5479966.667 7877254.167 7746986.667 17089284.17 35189468.67 13816633.67 2630261 5217201 1846044
MESES
ITEM DESCRIPCION UN. CANTIDAD DE PRECIO PRECIO TOTAL d
OBRAS UNITARIO 1 2 3 4 5 6 7 8 9 10
Infraestructura
203 Excavación directa con agotamiento en TCN m3 980.00 9,283 9,097,340 3 27% 48% 23%
Superestructura
TOTAL 97,193,660
Real. Parcial $
Real. Acum. $
Real. Parcial %
Real. Acum. %
MESES
ITEM DESCRIPCION UN. CANTIDAD DE PRECIO PRECIO TOTAL d
OBRAS UNITARIO 1 2 3 4 5 6 7 8 9 10
Infraestructura
Superestructura
TOTAL 97,193,660
Real. Parcial $
Real. Acum. $
Real. Parcial %
Real. Acum. %
AVANCE% AVANCE% AVANCE%
AVANCE%
MESES PROGRAMADO PROGRAMADO REAL
REAL PARCIAL
PARCIAL ACUMULADO ACUMULADO
1
2
3
4
5
6
7
8
9
10