Está en la página 1de 1

INTERNAL #

METRADO LICITACION
"CONSTRUCCION DE LOSA PARA ALMACEN DE REPUESTOS MAYORES "

Precio unitario
Planta Items Equipo Unidad Cantidad Total S/. SIN IGV
S/. SIN IGV

WAYRA 1 OBRAS PROVISIONALES S/ 52,926.39

FLETE DE TRANSPORTE DE MATERIALES, HERRAMIENTAS Y


WAYRA 1.1 Gbl 1.00 S/ 6,566.50 S/ 6,566.50
MAQUINARIA (LIMA - PARQUE EOLICO)
WAYRA 1.2 TRANSPORTE DE PERSONAL Dia 40.00 S/ 262.66 S/ 10,506.40
WAYRA 1.3 INSTALACIÓN Y DESMOVILIZACIÓN DE FAENA Gbl 1.00 S/ 5,910.25 S/ 5,910.25
WAYRA 1.4 ALQUILER DE CAMIONETA 4X4 Dia 40.00 S/ 420.26 S/ 16,810.24
WAYRA 1.5 CASETA PARA ALMACÉN Gbl 1.00 S/ 3,414.58 S/ 3,414.58
WAYRA 1.6 CASETA PARA OFICINA Gbl 1.00 S/ 3,414.58 S/ 3,414.58
WAYRA 1.7 COMEDOR DE MADERA PROVISIONAL Gbl 1.00 S/ 3,414.58 S/ 3,414.58
WAYRA 1.8 BAÑO PORTÁTIL (01 UND) Dia 40.00 S/ 72.23 S/ 2,889.26
WAYRA 2 TRABAJOS PRELIMINARES S/ 2,581.62
WAYRA 2.1 TRAZO, NIVEL Y REPLANTEO M2 260.00 S/ 9.93 S/ 2,581.62
WAYRA 3 MOVIMIENTO DE TIERRAS S/ 24,517.54
WAYRA 3.1 CORTE HASTA ALCANZAR EL NIVEL DE SUB-RASANTE M3 106.53 S/ 76.09 S/ 8,106.32
WAYRA 3.2 CONFORMACION Y COMPACTACION DE SUB RASANTE C/MAQ. M2 260.00 S/ 11.57 S/ 3,008.18
WAYRA 3.3 BASE DE AFIRMADO P/PISO M2 260.00 S/ 48.25 S/ 12,543.72
WAYRA 3.4 RELLENO CON MATERIAL PROPIO EN PEDESTAL M3 14.75 S/ 58.28 S/ 859.33
WAYRA 4 ELIMINACION DE MATERIAL S/ 11,670.64
WAYRA 4.1 ELIMINACION DE MATERIAL EXCEDENTE M3 114.73 S/ 101.72 S/ 11,670.64
WAYRA 5 CONCRETO SIMPLE S/ 14,067.59
WAYRA 5.1 CONCRETO PARA SOLADOS M2 257.48 S/ 54.64 S/ 14,067.59
WAYRA 6 CONCRETO ARMADO S/ 129,737.48
WAYRA 6.1 ZAPATA Y PEDESTAL S/ 17,986.62
WAYRA 6.1.1 CONCRETO F'C 280 KG/CM2 M3 9.22 S/ 958.25 S/ 8,831.26
WAYRA 6.1.2 ENCOFRADO Y DESENCOFRADO M2 23.04 S/ 89.59 S/ 2,064.06
WAYRA 6.1.3 ACERO CORRUGADO PARA ESTRUCTURAS KG 695.46 S/ 9.83 S/ 6,834.14
WAYRA 6.1.4 CURADO CON ADITIVO QUIMICO M2 48.38 S/ 5.31 S/ 257.16
WAYRA 6.2 LOSA ARMADA S/ 111,750.86
WAYRA 6.2.1 CONCRETO F'C 280 KG/CM2 M3 56.48 S/ 958.25 S/ 54,118.80
WAYRA 6.2.2 ENCOFRADO Y DESENCOFRADO M2 59.40 S/ 89.59 S/ 5,321.40
WAYRA 6.2.3 ACERO CORRUGADO PARA ESTRUCTURAS KG 5136.72 S/ 9.83 S/ 50,477.25
WAYRA 6.2.4 CURADO CON ADITIVO QUIMICO M2 344.95 S/ 5.31 S/ 1,833.42
WAYRA 7 JUNTAS DE DILATACION S/ 1,245.14
WAYRA 7.1 RELLENO DE JUNTAS CON MATERIAL ELASTOMERICO M 54.25 S/ 22.95 S/ 1,245.14
WAYRA 8 ENSAYOS S/ 7,587.96
WAYRA 8.1 PRUEBAS DE CAMPO pto 3.00 S/ 2,529.32 S/ 7,587.96
WAYRA 9 OTROS S/ 27,530.45
WAYRA 9.1 LIMPIEZA FINAL DE OBRA M2 260.00 S/ 6.57 S/ 1,707.29
WAYRA 9.2 SUMINISTRO Y APLICACIÓN DE GROUTS EPOXICO PTO 12.00 S/ 390.39 S/ 4,684.64
WAYRA 9.3 SUMINISTRO E INSTALACION DE ANCLAJE EN PEDESTAL UND 12.00 S/ 761.71 S/ 9,140.57
WAYRA 9.4 GASTOS DE SEGURIDAD (EMO, Curso Seguridad, EPP, etc) GL 1.00 S/ 11,997.95 S/ 11,997.95
PA PERU SAC 10 PARTIDAS COMPLEMENTARIAS S/ 9,002.07
PA PERU SAC 10.2 JUNTAS DE CONTRACCION (Aserradas + Sello Poliuretano) ML 37.40 32.98 S/ 1,233.59
PA PERU SAC 10.3 AGUA PARA OBRA GLB 1.00 1622.92 S/ 1,622.92
PA PERU SAC 10.4 ENERGIA PARA OBRA GLB 1.00 6145.56 S/ 6,145.56

TOTAL (SIN IGV) S/ 280,866.88

Notas:
No se considera costos de gestion de permisos o pago de los mismos en el presupuesto.
Se ha considerado para la resistencia del concreto de los solados una resistencia de f'c=175 kg/cm2, en vista de que 1.4 MPa no es comercial
Se ha considerado curador Antisol de SIKA
Se ha considerado plancha de poliestireno de 1/2" para las Juntas de Dilatacion