Está en la página 1de 16

PLANILLAS

N° DE DIAS MARZO ABRIL MAYO PRECIO / JORNADA PARCIAL LUNES MARTES MIÉRCOLES JUEVES VIERNES SÁBADO
DIA 3/13/2023 3/14/2023 3/15/2023 3/16/2023 3/17/2023 3/18/2023

PEONES
1 LIMBER DELGADO COPIA 37 12 840 24 1680 1 70 70 2590
2 JOSELITO DELGADO COPIA 13 12 840 1 70 0 0 70 910
3 JUAN CARLOS LOPEZ FRIAS 4 4 280 0 0 0 0 70 280
5 CRISTHIAN CHERO HUIMAN 7 7 490 0 0 0 0 70 490
JHONY PEREZ 14 0 0 13 1040 1 80 80 1120
BRAYAN ZAPATA SOSA 7 0 0 7 616 0 0 88 616
KEVIN ZAPATA SOSA 1 1 70 0 0 70 70
6
OPERARIOS
1 DANIEL SIVA INGA 25 10 1200 15 1800 0 0 120 3000
2 EDUARDO SILUPU HUERTAS 28 9 1080 18.5 2220 0 0 120 3300
3 JOSE ALEJANDRO HUIMAN QUINTANA 4 4 480 0 0 0 0 120 480
JOSE HUERTAS COBEÑAS 4 0 0 4 400 0 0 100 400
4 ADOLFO HUAMURO-GATO 30 18 1800 12 1200 0 0 100 3000 1 1 1 1 1 1
ABEL CINFUEGO ROSALES 7 0 0 6 720 1 120 120 840

APOYO

3 DILMER
NEGRO
MARIANO
FLACO

TOTAL 7010 9816 17096

1 : ASISTIO
DOMINGO LUNES MARTES MIERCOLES JUEVES VIERNES SÁBADO DOMINGO LUNES MARTES MIÉRCOLES JUEVES VIERNES SÁBADO DOMINGO LUNES MARTES
3/19/2023 3/20/2023 3/21/2023 3/22/2023 3/23/2023 3/24/2023 3/25/2023 3/26/2023 3/27/2023 3/28/2023 3/29/2023 3/30/2023 3/31/2023 4/1/2023 4/2/2023 4/3/2023 4/4/2023

1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 0 0
1 1 1 1 0 0 0 0 0 0 0 0 0
1 1 1 1 0 1 0 1 1 0 0 0 0

1 1 1 1 1 1 1 1 1 1 1 0 0
1 1 1 1 0 1 1 1 1 1 1 1 1
1 1 1 1 0 0 0 0 0 0 0 0 0
1
1 1 1 1 1 1 1 1 1 1 1 1 1 0 1

1 1 1 1 1 1 1 1
1 1 1 0
1 1 0 0
1 1
1 1 1
MIÉRCOLES JUEVES VIERNES SABADO DOMINGO LUNES MARTES MIÉRCOLES JUEVES VIERNES SÁBADO
4/5/2023 4/6/2023 4/7/2023 4/8/2023 4/9/2023 4/10/2023 4/11/2023 4/12/2023 4/13/2023 4/14/2023 4/15/2023

1 1 0 1 1 1 1 1 1 1
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
1

1 1 0 1 1 1 1 0 0 0
1 1 0 1 1 1 1 0.5 0 0
0 0 0 0 0 0 0 0 0 0
1 1 0 1 0 0 0 0 0 0
1 1 0 1 1 1 1 1 1 1

1
1
0
1 1 1 1 1
Materiales PRESTADO

FECHA MATERIAL CANTIDAD UNIDAD


3/15/2023 VARILLA DE 1/2" 60 VARILLAS
3/24/2023 Cemento 10 bl
3/29/2023 Piedra chancada de 1/2" 6 m3
3/29/2023 Cemento 60 bl
3/29/2023 Arena Gruesa 20 m3
4/4/2023 Cemento 60 bl
3/31/2023 Piedra chancada de 3/4" 20 m3
4/3/2023 Piedra pilca para base 20 m3
Arena Gruesa 20 m3
Piedra Chancada de 3/4" 20 m3
Hormigon 20 m3
Hormigon 20 m3
Piedra pilca para base 20 m3
MATERIAL COMPRADO

VARILLA DE 3/8" 31 Unidades


VARILLA DE 5/8" 1 tonelada
VARILLA DE 3/4" 2 toneladas

VARILLAS DE 3/4" 32
VARILLAS DE 3/8" 100
CEMENTO 100

4/14/2023 VARILLA DE 3/4" 32 varillas


4/14/2023 VARILLA DE 4/8" 100 varillas
4/14/2023 CEMENTO 100 bolsas
VALORIZACION N° 01

DEPARTAMENTO PIURA
"REHABILITACIÓN DE LA INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA LA UNION CON CODICO LOCAL
PROYECTO:
414811, LA UNION - PIURA - PIURA" PROVINCIA PIURA
DISTRITO LA UNION

CONTRACTUAL AVANCE MARZO AVANCE ABRIL AVANCE ACUMULADO


ITEM DESCRIPCION UND CANT P.U. PARCIAL METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO %

02 ESTRUCTURAS
02.01 OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES
02.01.01.00 LIMPIEZA DE TERRENO, MANUAL M2 879.65 1.40 1,231.51 879.65 1231.510 100.0% 0 0.00 0.00% 879.65 1,231.51 100.00%
02.01.02.00 TRAZO, NIVELES Y REPLANTEO PRELIMINAR M2 879.65 0.44 387.05 879.65 387.046 100.0% 0 0.00 0.00% 879.65 387.05 100.00%
02.02 MOVIMIENTO DE TIERRAS
EXCAVACION DE ZAPATAS, VIGAS DE CIMENTACION, CIMIENTOS CORRIDOS Y VIG. CONEX.
02.02.01 M3 174.66 46.62 8,142.52 60.8832 2838.375 34.9% 113.77 5,304.14 65.14% 174.66 8,142.52 100.00%
02.02.02
ACARREO DE MATERIAL EXCEDENTE DIST. 50 m (A MANO USANDO CARRETILLA) M3 209.59 31.75 6,654.44 104.795 3327.241 50.0% 104.79 3,327.22 50.00% 209.59 6,654.46 100.00%
02.02.03 RELLENO CON MATERIAL PROPIO SELECCIONADO M3 23.66 22.42 530.36

RELLENO Y COMPACTO CON AFIRMADO H=0.20M EN PISO INTERIOR m2 161.00 51.65 8,315.65

02.02.06 ELIMINACION DE MATERIAL EXEDENTE, D = 0.5 KM. M3 209.59 10.21 2,139.90 104.79 1069.9499 50.0% 104.7943125 1,069.95 50.00% 209.59 2,139.90 100.00%
02.03 OBRAS DE CONCRETO SIMPLE
02.03.01 SOLADO - CONCRETO 1:12 (C-H) M2 58.32 25.63 1,494.95 58.32 1,494.95 100.00% 58.32 1,494.95 100.00%
02.03.02 CIMIENTO CORRIDO - CONCRETO 1:10 (C-H) + 30% P.G. M3 44.67 261.24 11,670.42 31.271625 8,169.29 70.00% 31.27 8,169.29 70.00%
02.03.03 SOBRECIMIENTO - CONCRETO 1:8 (C-H) + 25% P.M. M3 5.31 241.89 1,283.23
02.03.04 SOBRECIMIENTO - ENCOFRADO Y DESENCOFRADO NORMAL M2 42.44 40.34 1,712.03
02.04 OBRAS DE CONCRETO ARMADO
02.04.01 ZAPATAS
ENCOFRADO EN ZAPATAS M2 155.52 40.34 6,273.68 95.04 3833.9136 61.1% 60.48 2,439.76 38.89% 155.52 6,273.68 100.00%
02.04.01.01 CONCRETO F'C= 210 KG/CM2. EN ZAPATAS M3 34.99 492.60 17,237.14 21.384 10533.8076 61.1% 13.61 6,703.33 38.89% 34.99 17,237.14 100.00%
02.04.01.02 ACERO ESTRUCTURAL FY = 4200 KG/CM2 KG 767.57 6.42 4,927.47 767.57 4927.4718 100.0% 0 0.00 0.00% 767.57 4,927.47 100.00%

02.01.04.03 VIGAS DE CONEXION

02.04.03.01 CONCRETO F'C= 210 KG/CM2. EN VIGA DE CONEXION M3 18.96 491.60 9,322.25 0 0.00 0.00% 0.00 0.00 0.00%

02.04.03.02 ENCOFRADO Y DESENCOFRADO, EN VIGAS DE CONEXIÓN M2 126.42 40.34 5,099.78 63.21 2,549.89 50.00% 63.21 2,549.89 50.00%

02.04.03.03 ACERO ESTRUCTURAL FY = 4200 KG/CM2 KG 1,908.98 6.42 12,254.90 954.490688 6,127.45 50.00% 954.49 6,127.45 50.00%

02.04.05 COLUMNAS

02.04.05.01 CONCRETO F'C= 210 KG/CM2. EN COLUMNAS M3 35.86 491.35 17,619.70 0.00 0.00 0.00%

02.04.05.02 ENCOFRADO Y DESENCOFRADO NORMAL DE COLUMNAS M2 473.70 40.34 19,109.06 0.00 0.00 0.00%

02.04.05.03 ACERO ESTRUCTURAL FY = 4200 KG/CM2 kg 4,858.99 6.42 31,192.78 2683.9736 17230.0369226 55.2% 1707.9832 10,964.57 35.15% 4,391.96 28,194.61 90.39%

02.04.06.02 VIGAS DE AMARRE

02.04.06.02.01 CONCRETO F'C= 210 KG/CM2. EN VIGAS DE AMARRE M3 1.59 491.60 782.38 0.00 0.00 0.00%

02.04.06.02.02 ENCOFRADO Y DESENCOFRADO, EN VIGAS DE AMARRE M2 15.92 40.34 642.01 0.00 0.00 0.00%

02.04.06.02.03 ACERO ESTRUCTURAL FY = 4200 KG/CM2 KG 81.06 6.42 520.40 0.00 0.00 0.00%

MUROS Y TABIQUES DE ALBAÑILERIA

MURO DE CABEZA DE LADRILLO KING KONG DE ARCILLA, MEZCLA 1:4 M² 138.64


03.01.02 123.87 17,173.56 0.00 0.00 0.00%

ACERO ESTRUCTURAL FY = 4200 KG/CM2 Kg 54.05


03.01.05 6.42 347.01 0.00 0.00 0.00%

REVOQUES, ENLUCIDOS Y MOLDADURAS


3.0200
TARRAJEO EN SUPERFICIE DE MUROS EXTERIORES e interiores M² 327.35
03.02.02 32.47 10,630.42 0.00 0.00 0.00%

TARRAJEO EN SUPERFICIE DE COLUMNAS M² 324.90


03.02.04 46.47 15,099.39 0.00 0.00 0.00%

PISOS Y PAVIMENTOS

LOSA DEPORTIVA - ENCOFRADO M2 67.80


49.62 3,364.24 0.00 0.00 0.00%

LOSA PARA PATIOS-CONCRETO M3 123.03


432.89 53,258.46 0.00 0.00 0.00%

CURADO DE CONCRETO CON ADITIVO M2 771.56


0.71 547.80 0.00 0.00 0.00%

PINTURAS

PINTURA LATEX EN MUROS EXTERIORES M² 327.35


03.12.01 9.66 3,162.22 0.00 0.00 0.00%

PINTURA LATEX EN VIGAS Y COLUMNAS M² 324.90


03.12.03 10.57 3,434.19 0.00 0.00 0.00%

PINTURA Y DEMARCACION EN LOSA DE USOS MULTIPLES M² 525.85


03.12.07 7.03 3,696.73 0.00 0.00 0.00%

3.13 VARIOS

03.13.02 JUNTA ASFALTICA, E=1" ML 468.36


6.28 2,941.30 0.00 0.00 0.00%

unid 1.00
SUMINISTRO E INSTALACION DE ARCOS DE FULBITO Y VOLEY 6,500.00 6,500.00 0.00 0.00 0.00%

COSTO DIRECTO …........................................ 288,698.91 45,379.35 15.72% 48,150.56 16.68% 93,529.91 32.40%
UTILIDAD 4% …........................................... 11,547.96 1,815.17 1,926.02 3,741.20

SUBTOTAL…................. 300,246.87 47,194.53 50,076.58 97,271.11


IGV 18%............................................ 54,044.44 8,495.01 9,013.79 17,508.80
TOTAL 354,291.31 55,689.54 59,090.37 114,779.91
1 2
FECHA H. ENTRADA H. SALIDA H. ENTRADA H. SALIDA

MARTES 3/14/2023 02:20:00 AM 05:00:00 AM


MIÉRCOLES 3/15/2023
JUEVES 3/16/2023
VIERNES 3/17/2023
SÁBADO 3/18/2023
DOMINGO 3/19/2023
LUNES 3/20/2023
MARTES 3/21/2023
MIÉRCOLES 3/22/2023 03:10:00 AM 05:00:00 AM
JUEVES 3/23/2023 08:30:00 AM 10:28:00 AM ### 12:00:00 PM
VIERNES 3/24/2023
SÁBADO 3/25/2023
DOMINGO 3/26/2023
LUNES 3/27/2023 09:10:00 AM 09:45:00 AM ### 12:40:00 PM
MARTES 3/28/2023
MIÉRCOLES 3/29/2023 08:45:00 AM 09:00:00 AM
JUEVES 3/30/2023
VIERNES 3/31/2023 09:30:00 AM 10:55:00 AM
SÁBADO 4/1/2023 09:10:00 AM 01:00:00 PM
DOMINGO 4/2/2023
LUNES 4/3/2023
MARTES 4/4/2023
MIÉRCOLES 4/5/2023 ### 04:20:00 AM
JUEVES 4/6/2023
VIERNES 4/7/2023
SÁBADO 4/8/2023
DOMINGO 4/9/2023
LUNES 4/10/2023
MARTES 4/11/2023
MIÉRCOLES 4/12/2023 ### 05:00:00 AM
JUEVES 4/13/2023 ### 04:00:00 AM
VIERNES 4/14/2023 ### 05:00:00 AM
SÁBADO 4/15/2023
DOMINGO 4/16/2023
LUNES 4/17/2023
MARTES 4/18/2023
MIÉRCOLES 4/19/2023
JUEVES 4/20/2023
VIERNES 4/21/2023
SÁBADO 4/22/2023
DOMINGO 4/23/2023
LUNES 4/24/2023 ### 05:00:00 AM
MARTES 4/25/2023 09:00:00 AM 11:30:00 AM
MIÉRCOLES 4/26/2023
JUEVES 4/27/2023
VIERNES 4/28/2023 09:00:00 AM 11:00:00 AM ### 12:53:00 PM
SÁBADO 4/29/2023
DOMINGO 4/30/2023
LUNES 5/1/2023
MARTES 5/2/2023
MIÉRCOLES 5/3/2023
JUEVES 5/4/2023
VIERNES 5/5/2023 10:20:00 AM 11:20:00 AM ### 12:29:00 PM
SÁBADO 5/6/2023
DOMINGO 5/7/2023
3
H. ENTRADA H. SALIDA T. TOTAL
MARZO ABRIL
###
###
### 11:03:00 05:35:00 PM
###
### 1430 2275
###
###
###
###
###
###
###
###
###
###
###
###
### EXCAVACION ZAPATA
### EXCAVACION ZANJA
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
### 02:34:00 AM ###
###
###
###
###
###
###
###
###
###
MAYO

01:34:00 AM

195
METRADOS

EXCAVACION
CIMIENTOS CORRIDOS

EJE A LARGO ANCHO ALTO VOLUMEN


TRAMO 1-2 5.137 0.5 1.2 3.0822
TRAMO 2-3 5.137 0.5 1.2 3.0822
TRAMO 3-4 5.137 0.5 1.2 3.0822
TRAMO 4-5 5.137 0.5 1.2 3.0822
TRAMO 5-6 5.137 0.5 1.2 3.0822

EJE E
TRAMO 1-2 5.137 0.5 1.2 3.0822
TRAMO 2-3 5.137 0.5 1.2 3.0822
TRAMO 3-4 5.137 0.5 1.2 3.0822
TRAMO 4-5 5.137 0.5 1.2 3.0822
TRAMO 5-6 5.137 0.5 1.2 3.0822

EJE 1
TRAMO A-B 3.776 0.5 1.2 2.2656
TRAMO B-C 3.776 0.5 1.2 2.2656
TRAMO C-D 3.776 0.5 1.2 2.2656
TRAMO D-E 3.776 0.5 1.2 2.2656

EJE 6
TRAMO A-B 3.776 0.5 1.2 2.2656
TRAMO B-C 3.776 0.5 1.2 2.2656
TRAMO C-D 3.776 0.5 1.2 2.2656
TRAMO D-E 3.226 0.5 1.2 1.9356

ZAPATAS

NUMERO LARGO ANCHO ALTO VOLUMEN

1 1.8 1.8 1.3 4.212


CONCRETO
CIMIENTOS CORRIDOS

EJE A LARGO ANCHO ALTO VOLUMEN


TRAMO 1-2 5.137 0.5 0.6 1.5411
TRAMO 2-3 5.137 0.5 0.6 1.5411
TRAMO 3-4 5.137 0.5 0.6 1.5411
TRAMO 4-5 5.137 0.5 0.6 1.5411
TRAMO 5-6 5.137 0.5 0.6 1.5411

EJE E
TRAMO 1-2 5.137 0.5 0.6 1.5411
TRAMO 2-3 5.137 0.5 0.6 1.5411
TRAMO 3-4 5.137 0.5 0.6 1.5411
TRAMO 4-5 5.137 0.5 0.6 1.5411
TRAMO 5-6 5.137 0.5 0.6 1.5411

EJE 1
TRAMO A-B 3.776 0.5 0.6 1.1328
TRAMO B-C 3.776 0.5 0.6 1.1328
TRAMO C-D 3.776 0.5 0.6 1.1328
TRAMO D-E 3.776 0.5 0.6 1.1328

EJE 6
TRAMO A-B 3.776 0.5 0.6 1.1328
TRAMO B-C 3.776 0.5 0.6 1.1328
TRAMO C-D 3.776 0.5 0.6 1.1328
TRAMO D-E 3.226 0.5 0.6 0.9678

ZAPATAS

NUMERO LARGO ANCHO ALTO VOLUMEN

1 1.8 1.8 0.6 1.944


15.411

15.411

9.0624

8.7324
7.7055

7.7055

4.5312

4.3662

También podría gustarte