Está en la página 1de 4

CALENDARIO DE AVANCE VALORIZADO DE OBRA

PROYECTO
"MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD DE LAS CALLES Y AVENIDAS COLINDANTES A LA PLAZA CÍVICA DE SAN MARTÍN DE PANGOA DEL DISTRITO DE PANGOA - PROVINCIA DE SATIPO - DEPARTAMENTO DE JUNIN” C.U.I.N°2466249

ENTIDAD GOBIERNO REGIONAL DE JUNIN

ITEM DESCRIPCION UND METRADO COSTO TOTAL MES 01 MES 02 MES 03 MES 04 MES 05 MES 06 MES 07 MES 08 MES 09 MES 10 MES 11 MES 12 MES 13 MES 14 MES 15 MES 16 MES 17 MES 18
01 PAVIMENTO RÍGIDO
01.01 OBRAS PROVISIONALES
01.01.01 ALMACEN DE OBRA mes 18.00 500.00 9,000.00 500.00 500.00 500.00 500.00 500.00 500.00 500.00 500.00 500.00 500.00 500.00 500.00 500.00 500.00 500.00 500.00 500.00 500.00
01.01.02 GUARDIANIA Y/O VIGILANCIA mes 18.00 1,033.04 18,594.72 1,033.04 1,033.04 1,033.04 1,033.04 1,033.04 1,033.04 1,033.04 1,033.04 1,033.04 1,033.04 1,033.04 1,033.04 1,033.04 1,033.04 1,033.04 1,033.04 1,033.04 1,033.04
01.01.03 SERVICIOS HIGIENICOS PORTATIL mes 18.00 600.00 10,800.00 600.00 600.00 600.00 600.00 600.00 600.00 600.00 600.00 600.00 600.00 600.00 600.00 600.00 600.00 600.00 600.00 600.00 600.00
01.01.04 CARTEL DE OBRA (3.60Mx7.20M) und 2.00 3,200.60 6,401.20 6,401.20
01.01.05 CAMPAMENTO Y AREA DE MANIOBRAS (MAQUINARIAS) m2 400.00 42.20 16,880.00 16,880.00
01.01.06 MOVILIZACIÓN Y DESMOVILIZACIÓN DE MAQUINARIA glb 1.00 50,614.05 50,614.05 50,614.05
01.01.07 PLAN DE DESVIO DE TRANSITO Y SEGURIDAD VIAL glb 1.00 20,000.00 20,000.00 20,000.00
01.02 OBRAS PRELIMINARES
01.02.01 LIMPIEZA MANUAL DE TERRENO m2 142,273.14 0.16 22,763.70 22,763.70
01.02.02 TRAZO Y REPLANTEO PRELIMINAR m2 142,273.14 0.47 66,868.38 66,868.38
01.02.03 TRAZO, NIVELES Y REPLANTEO DURANTE EJECUCION m2 142,273.14 1.36 193,491.47 10,749.53 10,749.53 10,749.53 10,749.53 10,749.53 10,749.53 10,749.53 10,749.53 10,749.53 10,749.53 10,749.53 10,749.53 10,749.53 10,749.53 10,749.53 10,749.53 10,749.53 10,749.53
01.02.04 MANTENIMIENTO TEMPORAL DE TRANSITO VIAL DURANTE EJECUCION
glb 1.00 27,949.92 27,949.92 9,316.64 9,316.64 9,316.64
01.02.05 ACCESOS A CANTERAS, DME Y FUENTES DE AGUA glb 1.00 60,000.00 60,000.00 60,000.00
01.02.06 REUBICACION DE POSTES DE ALUMBRADO glb 1.00 160,000.00 160,000.00 160,000.00
01.02.07 IMPLEMENTACION Y REUBICACION DE SEMAFOROS und 15.00 10,500.00 157,500.00 157,500.00
01.03 SEÑALES Y PROTECCION
01.03.01 CINTA PLASTICA SEÑALIZADORA PARA SEGURIDAD DE OBRA glb 1.00 32.90 32.90 32.90
01.03.02 SEÑALIZACIÓN TEMPORAL DE SEGURIDAD DURANTE EJECUCION glb 1.00 10,605.69 10,605.69 10,605.69
01.03.03 CERCO DE MALLA HDPE 1M ALTURA PARA LIMITE DE SEGURIDAD DE
glbOBRA 1.00 9,278.90 9,278.90 9,278.90
01.03.04 PROTECCIÓN DE CONEXIONES DOMICILIARIAS DE AGUA POTABLE glb 1.00 2,380.16 2,380.16 2,380.16
01.03.05 PROTECCIÓN DE CONEXIONES DOMICILIARIAS DE DESAGUE glb 1.00 2,380.16 2,380.16 2,380.16
01.04 SEGURIDAD Y SALUD EN OBRA
01.04.01 ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DEglb
SEGURIDAD Y SALUD
1.00 EN EL5,521.34
TRABAJO 5,521.34 5,521.34
01.04.02 CAPACITACION EN SEGURIDAD Y SALUD EN EL TRABAJO glb 1.00 6,413.63 6,413.63 356.31 356.31 356.31 356.31 356.31 356.31 356.31 356.31 356.31 356.31 356.31 356.31 356.31 356.31 356.31 356.31 356.31 356.31
01.04.03 RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SEGURIDAD
glb Y SALUD EN EL 1.00
TRABAJO 6,254.15 6,254.15 6,254.15
01.04.04 EQUIPOS DE PROTECCION PERSONAL glb 1.00 4,774.08 4,774.08 4,774.08
01.04.05 EQUIPOS DE PROTECCION COLECTIVA glb 1.00 7,402.00 7,402.00 7,402.00
01.04.06 SEÑALIZACIÓN TEMPORAL DE SEGURIDAD VIAL glb 1.00 4,359.10 4,359.10 4,359.10
01.05 DEMOLICIONES Y ELIMINACION
01.05.01 DEMOLICION DE PAVIMENTO DE CONCRETO E=0.20M m3 476.78 25.86 12,329.53 12,329.53
01.05.02 DEMOLICION DE PAVIMENTO FLEXIBLE E=0.10M m3 114.71 18.00 2,064.78 2,064.78
01.05.03 DEMOLICION DE VEREDAS, RAMPAS Y MARTILLOS CON EQUIPO m3 1,659.33 21.93 36,389.11 36,389.11
01.05.04 DEMOLICION DE CUNETAS, MUROS DE CONCRETO m3 346.13 25.59 8,857.47 8,857.47
01.05.05 ACARREO INTERNO DE MATERIAL EXCEDENTE PARA ELIMINACION m3 3,246.19 7.95 25,807.21 25,807.21
01.05.06 CARGUIO DE MATERIAL (ELIMINACION DE MATERIAL EXCEDENTE) m3 3,246.19 6.02 19,542.06 19,542.06
01.05.07 TRANSPORTE DE MATERIAL (ELIMINACION DE MATERIAL EXCEDENTE)
m3 3,246.19 6.18 20,061.45 20,061.45
01.06 MOVIMIENTO DE TIERRAS
01.06.01 CORTE EN TERRENO P/MEJORAMIENTO DEBAJO DE SUB RASANTE m3
C/MAQUINARIA7,776.00 7.76 60,341.76 30,170.88 30,170.88
01.06.02 CORTE DE TERRENO NORMAL A NIVEL DE SUB RASANTE C/MAQUINARIA
m3 45,504.65 8.04 365,857.39 365,857.39
01.06.03 PERFILADO Y COMPACTADO A NIVEL DE SUB RASANTE C/MAQUINARIA
m2 81,657.13 7.84 640,191.90 320,095.95 320,095.95
01.06.04 EXCAVACION A MANO EN TERRENO COMPACTO P/CUNETAS m3 6,922.97 47.49 328,771.85 328,771.85
01.06.05 ACARREO INTERNO DE MATERIAL EXCEDENTE PARA ELIMINACION m3 75,254.51 7.95 598,273.35 598,273.35
01.06.06 CARGUIO DE MATERIAL (ELIMINACION DE MATERIAL EXCEDENTE) m3 75,254.51 6.02 453,032.15 453,032.15
01.06.07 TRANSPORTE DE MATERIAL (ELIMINACION DE MATERIAL EXCEDENTE)
m3 75,254.71 6.18 465,074.11 465,074.11
01.07 ESTRUCTURA DEL PAVIMENTO
01.07.01 MEJORAMIENTO DEBAJO DE SUB RASANTE P/CAPAS E=0.50
01.07.01.01 EXTRACCIÓN Y ACOPIO DE MATERIAL P/MEJ DEBAJO DE SUB RASANTE
m3 9,720.00 36.33 353,127.60 176,563.80 176,563.80
01.07.01.02 CARGUIO Y TRANSPORTE DEL MATERIAL P/MEJ DEBAJO DE SUB RASANTE
m3 9,720.00 13.65 132,678.00 132,678.00
01.07.01.03 EXTENDIDO, RIEGO Y COMPACTADO P/MEJ. DEBAJO DE SUB RASANTE
m2 5,184.00 5.40 27,993.60 27,993.60
01.07.02 MEJORAMIENTO DE SUB RASANTE E=0.15
01.07.02.01 EXTRACCIÓN Y ACOPIO DE MATERIAL P/MEJ DE SUB RASANTE m3 15,310.71 54.59 835,811.66 417,905.83 417,905.83
01.07.02.02 CARGUIO Y TRANSPORTE DE MATERIAL P/MEJ DE SUB RASANTE m3 15,310.71 13.65 208,991.19 208,991.19
01.07.02.03 EXTENDIDO, RIEGO Y COMPACTADO P/MEJ. SUB RASANTE m2 81,657.13 6.13 500,558.21 500,558.21
01.07.03 SUB BASE GRANULAR E=0.20M
01.07.03.01 EXTRACCIÓN Y ACOPIO DE MATERIAL P/SUB BASE m3 20,414.28 60.84 1,242,004.80 621,002.40 621,002.40
01.07.03.02 CARGUIO Y TRANSPORTE DE MATERIAL P/SUB BASE m3 20,414.28 13.65 278,654.92 278,654.92
01.07.03.03 EXTENDIDO, RIEGO Y COMPACTADO P/SUB BASE m2 81,657.13 6.13 500,558.21 500,558.21
01.07.04 CALZADA DE CONCRETO E=0.20M
01.07.04.01 ENCOFRADO Y DESENCOFRADO PAVIMENTO RÍGIDO m2 6,001.42 36.49 218,991.82 72,997.27 72,997.27 72,997.27
01.07.04.02 CONCRETO F'C=210 KG/CM2 C/MEZCLADORA m3 14,015.70 486.59 6,819,899.46 1,704,974.87 1,704,974.87 1,704,974.87 1,704,974.87
01.07.04.03 ACERO LISO PARA PAVIMENTO (DOWELS) kg 96,545.82 9.64 930,701.70 232,675.43 232,675.43 232,675.43 232,675.43
01.07.04.04 ACERO DE REFUERZO fy=4,200 kg/cm2 (CANASTILLAS 3/8") kg 71,750.18 7.40 530,951.33 176,983.78 176,983.78 176,983.78
01.07.04.05 ACABADO DE LOSA m2 70,078.49 4.24 297,132.80 297,132.80
01.07.04.06 CURADO Y LIMPIEZA DE LOSA m2 70,078.49 13.04 913,823.51 913,823.51
01.07.04.07 JUNTAS ASFALTICAS m 30,007.10 11.27 338,180.02 67,636.00 67,636.00 67,636.00 67,636.00 67,636.00
01.08 DRENAJE LONGITUDINAL
01.08.01 CUNETAS
01.08.01.01 TRAZO, NIVELES Y REPLANTEO DURANTE EJECUCION m2 9,889.95 1.36 13,450.33 13,450.33
01.08.01.02 PERFILADO Y COMPACTADO A MANO P/CUNETAS m2 9,889.95 7.20 71,207.64 71,207.64
01.08.01.03 ENCOFRADO Y DESENCOFRADO DE CUNETAS m2 50,156.01 25.19 1,263,429.89 421,143.30 421,143.30 421,143.30
01.08.01.04 CONCRETO F'C=210 KG/CM2 C/MEZCLADORA m3 5,478.79 486.59 2,665,924.43 888,641.48 888,641.48 888,641.48
01.08.01.05 ACERO DE REFUERZO fy=4,200 kg/cm2 (TAPAS) kg 91,908.35 6.84 628,653.11 209,551.04 209,551.04 209,551.04
01.08.01.06 ACABADO DE CUNETAS m2 16,954.20 13.95 236,511.09 78,837.03 78,837.03 78,837.03
01.08.01.07 JUNTAS ASFALTICAS m 7,532.80 11.27 84,894.66 21,223.67 21,223.67 21,223.67 21,223.67
01.09 SEÑALIZACIÓN VIAL
01.09.01 SEÑALIZACIÓN HORIZONTAL
01.09.01.01 PINTURA LINEAL CONTINUA BORDE (PAVIMENTO) m 14,388.42 6.77 97,409.60 97,409.60
CALENDARIO DE AVANCE VALORIZADO DE OBRA
PROYECTO
"MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD DE LAS CALLES Y AVENIDAS COLINDANTES A LA PLAZA CÍVICA DE SAN MARTÍN DE PANGOA DEL DISTRITO DE PANGOA - PROVINCIA DE SATIPO - DEPARTAMENTO DE JUNIN” C.U.I.N°2466249

ENTIDAD GOBIERNO REGIONAL DE JUNIN

ITEM DESCRIPCION UND METRADO COSTO TOTAL MES 01 MES 02 MES 03 MES 04 MES 05 MES 06 MES 07 MES 08 MES 09 MES 10 MES 11 MES 12 MES 13 MES 14 MES 15 MES 16 MES 17 MES 18
01.09.01.02 PINTURA LINEAL DISCONTINUA CENTRAL m 2,691.00 7.91 21,285.81 21,285.81
01.09.01.03 PINTURA EN SIMBOLOS Y FLECHAS m2 178.83 30.21 5,402.45 5,402.45
01.09.01.04 PINTURA ZONAL EN CRUCE PEATONAL m2 2,924.20 13.08 38,248.54 38,248.54
01.09.02 SEÑALIZACIÓN VERTICAL
01.09.02.01 SEÑALES INFORMATIVAS und 53.00 184.08 9,756.24 9,756.24
01.09.02.02 SEÑALES REGULADORAS und 67.00 184.08 12,333.36 12,333.36
01.09.02.03 SEÑALES PREVENTIVAS und 64.00 184.08 11,781.12 11,781.12
01.09.03 REDUCTOR DE VELOCIDAD
01.09.03.01 ENCOFRADO Y DESENCOFRADO DE GIBA m2 18.03 28.65 516.56 516.56
01.09.03.02 CONCRETO F'C=210 KG/CM2 C/MEZCLADORA m3 8.89 486.59 4,325.79 4,325.79
01.09.03.03 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 1,833.08 7.40 13,564.79 13,564.79
01.09.03.04 ACABADO DE GIBA m2 111.60 17.85 1,992.06 1,992.06
01.09.03.05 PINTURA EN GIBA m2 111.60 16.89 1,884.92 1,884.92
01.10 INSTALACIONES SANITARIAS
01.10.01 REPOSICIÓN DE INSTALACION DOMICILIARIA DE AGUA glb 1.00 8,563.20 8,563.20 8,563.20
01.10.02 REPOSICIÓN DE INSTALACION DOMICILIARIA DE DESAGUE glb 1.00 8,256.40 8,256.40 8,256.40
01.10.03 REPOSICIÓN DE REDES DE AGUA Y DESAGÜE glb 1.00 6,500.00 6,500.00 6,500.00
01.10.04 REPOSICIÓN DE TECHOS DE BUZON INCL. TAPA Y DEMOLICION glb 1.00 25,732.24 25,732.24 25,732.24
01.10.05 INSTALACION DE HIDRANTES CONTRA INCENDIO INCL. GRIFOS Y VALVULAS
glb 1.00 50,000.00 50,000.00 50,000.00
01.11 PRUEBAS DE CALIDAD
01.11.01 ENSAYO DENSIDAD DE CAMPO und 260.00 32.97 8,572.20 1,714.44 1,714.44 1,714.44 1,714.44 1,714.44
01.11.02 ENSAYO CBR A MATERIAL DE CANTERA und 13.00 324.65 4,220.45 844.09 844.09 844.09 844.09 844.09
01.11.03 DISEÑO DE MEZCLA DEL CONCRETO und 3.00 250.00 750.00 150.00 150.00 150.00 150.00 150.00
01.11.04 PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESIÓN)und 450.00 25.00 11,250.00 2,250.00 2,250.00 2,250.00 2,250.00 2,250.00
01.12 IMPACTO AMBIENTAL
01.12.01 MITIGACION DEL IMPACTO AMBIENTAL glb 1.00 45,000.00 45,000.00 2,500.00 2,500.00 2,500.00 2,500.00 2,500.00 2,500.00 2,500.00 2,500.00 2,500.00 2,500.00 2,500.00 2,500.00 2,500.00 2,500.00 2,500.00 2,500.00 2,500.00 2,500.00
01.13 PLAN DE MONITOREO ARQUEOLOGICO
01.13.01 PLAN DE MONITOREO ARQUEOLOGICO glb 1.00 45,000.00 45,000.00 2,500.00 2,500.00 2,500.00 2,500.00 2,500.00 2,500.00 2,500.00 2,500.00 2,500.00 2,500.00 2,500.00 2,500.00 2,500.00 2,500.00 2,500.00 2,500.00 2,500.00 2,500.00
01.14 VARIOS
01.14.01 SUMINISTRO DE PLACA RECORDATORIO SEGÚN DISEÑO INC. MURETE
glb SEGUN DISEÑO1.00 1,252.35 1,252.35 1,252.35
01.14.02 SUMINISTRO E INSTALACION DE TACHOS ECOLOGICOS und 260.00 125.23 32,559.80 32,559.80
01.14.03 REJILLA METALICA EN CUNETAS m 298.00 196.62 58,592.76 58,592.76
01.14.04 LIMPIEZA FINAL DE OBRA m2 70,078.49 0.16 11,212.56 11,212.56
01.15 FLETE TERRESTRE
01.15.01 FLETE TERRESTRE glb 1.00 286,114.50 286,114.50 286,114.50
02 VEREDAS
02.01 TRABAJOS PRELIMINARES
02.01.01 LIMPIEZA MANUAL DE TERRENO m2 43,548.51 0.16 6,967.76 6,967.76
02.01.02 TRAZO, NIVELES Y REPLANTEO DURANTE EJECUCION m2 43,548.51 1.36 59,225.97 11,845.19 11,845.19 11,845.19 11,845.19 11,845.19
02.02 MOVIMIENTO DE TIERRAS
02.02.01 CORTE A MANO EN TERRENO NORMAL A NIVEL DE SUB RASANTE m3 8,763.63 54.35 476,303.29 476,303.29
02.02.02 EXCAVACION A MANO EN TERRENO NORMAL PARA SARDINEL m3 1,434.29 40.77 58,476.00 58,476.00
02.02.03 REFINE Y NIVELADO A NIVEL DE SUB RASANTE m2 33,458.03 1.81 60,559.03 60,559.03
02.02.04 ACARREO INTERNO DE MATERIAL EXCEDENTE PARA ELIMINACION m3 12,747.40 7.95 101,341.83 101,341.83
02.02.05 CARGUIO DE MATERIAL (ELIMINACION DE MATERIAL EXCEDENTE) m3 12,747.40 6.02 76,739.35 76,739.35
02.02.06 TRANSPORTE DE MATERIAL (ELIMINACION DE MATERIAL EXCEDENTE)
m3 12,747.40 6.18 78,778.93 78,778.93
02.03 CONFORMACION DE BASE
02.03.01 EXTRACCIÓN Y ACOPIO DE MATERIAL P/SUB BASE m3 6,273.38 60.84 381,672.44 381,672.44
02.03.02 CARGUIO Y TRANSPORTE DE MATERIAL P/SUB BASE m3 6,273.38 13.65 85,631.64 85,631.64
02.03.03 CONFORMACION Y COMPACTADO C/MAT. AFIRMADO E=0.15M m3 6,273.38 20.41 128,039.69 128,039.69
02.04 CONCRETO SIMPLE
02.04.01 SARDINEL
02.04.01.01 ENCOFRADO Y DESENCOFRADO DE SARDINEL m2 15,537.49 37.39 580,946.75 290,473.38 290,473.38
02.04.01.02 CONCRETO F'C=175 KG/CM2 C/MEZCLADORA m3 1,174.34 449.09 527,384.35 263,692.18 263,692.18
02.04.01.03 ACABADO Y BRUÑADO DE SARDINEL m2 2,195.65 13.95 30,629.32 30,629.32
02.04.01.04 SOLAQUEO DE SARDINEL m2 5,434.59 17.17 93,311.91 93,311.91
02.04.01.05 JUNTAS ASFALTICAS m 1,716.75 11.27 19,347.77 19,347.77
02.04.02 SARDINEL SUMERGIDO
02.04.02.01 ENCOFRADO Y DESENCOFRADO DE SARDINEL m2 3,655.53 37.39 136,680.27 68,340.14 68,340.14
02.04.02.02 CONCRETO F'C=175 KG/CM2 C/MEZCLADORA m3 260.80 449.09 117,122.67 58,561.34 58,561.34
02.04.02.03 ACABADO Y BRUÑADO DE SARDINEL m2 870.92 13.95 12,149.33 12,149.33
02.04.02.04 JUNTAS ASFALTICAS m 289.65 11.27 3,264.36 3,264.36
02.04.03 RAMPAS
02.04.03.01 PERFILADO Y COMPACTADO A MANO P/RAMPA m2 874.23 11.61 10,149.81 5,074.91 5,074.91
02.04.03.02 ENCOFRADO Y DESENCOFRADO DE RAMPA m2 467.97 41.47 19,406.72 9,703.36 9,703.36
02.04.03.03 CONCRETO F'C=175 KG/CM2 C/MEZCLADORA m3 103.84 449.09 46,633.51 23,316.76 23,316.76
02.04.03.04 ACABADO Y BRUÑADO DE RAMPA m2 874.23 20.91 18,280.15 18,280.15
02.04.04 GRADERIA
02.04.04.01 PERFILADO Y COMPACTADO A MANO P/GRADERIA m2 87.94 8.08 710.56 710.56
02.04.04.02 ENCOFRADO Y DESENCOFRADO DE GRADERIA m2 56.08 35.69 2,001.50 2,001.50
02.04.04.03 CONCRETO F'C=175 KG/CM2 C/MEZCLADORA m3 9.74 449.09 4,374.14 4,374.14
02.04.04.04 ACABADO Y BRUÑADO DE GRADERIA m2 87.94 16.80 1,477.39 1,477.39
02.04.05 VEREDAS
02.04.05.01 ENCOFRADO Y DESENCOFRADO DE VEREDAS m2 389.11 36.24 14,101.35 4,700.45 4,700.45 4,700.45
02.04.05.02 CONCRETO F´C=175 KG/CM2 E=4" CON MEZCLADORA m3 2,510.15 449.09 1,127,283.26 375,761.09 375,761.09 375,761.09
02.04.05.03 ACABADO Y BRUÑADO DE VEREDA m2 24,762.31 21.51 532,637.29 177,545.76 177,545.76 177,545.76
02.04.05.04 JUNTAS ASFALTICAS m 3,891.10 11.27 43,852.70 14,617.57 14,617.57 14,617.57
02.05 PISOS Y PAVIMENTOS
02.05.01 PISO CONCRETO PIGMENTADO
CALENDARIO DE AVANCE VALORIZADO DE OBRA
PROYECTO
"MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD DE LAS CALLES Y AVENIDAS COLINDANTES A LA PLAZA CÍVICA DE SAN MARTÍN DE PANGOA DEL DISTRITO DE PANGOA - PROVINCIA DE SATIPO - DEPARTAMENTO DE JUNIN” C.U.I.N°2466249

ENTIDAD GOBIERNO REGIONAL DE JUNIN

ITEM DESCRIPCION UND METRADO COSTO TOTAL MES 01 MES 02 MES 03 MES 04 MES 05 MES 06 MES 07 MES 08 MES 09 MES 10 MES 11 MES 12 MES 13 MES 14 MES 15 MES 16 MES 17 MES 18
02.05.01.01 ENCOFRADO Y DESENCOFRADO DE VEREDAS m2 200.62 36.24 7,270.47 7,270.47
02.05.01.02 CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PIGMENTADO m3 290.79 456.86 132,850.32 132,850.32
02.05.01.03 ACABADO Y BRUÑADO DE PISOS m2 2,907.87 54.95 159,787.46 159,787.46
02.05.01.04 JUNTAS ASFALTICAS m 2,006.22 11.27 22,610.10 22,610.10
02.05.02 PISO DE ADOQUIN
02.05.02.01 ENCOFRADO Y DESENCOFRADO DE VEREDAS m2 108.44 36.24 3,929.87 3,929.87
02.05.02.02 CONCRETO f'c=140 kg/cm2 CON MEZCLADORA m3 76.56 401.13 30,710.51 30,710.51
02.05.02.03 PISO DE ADOQUIN RECTANGULAR COLOR 20X10X8 CM m2 1,531.20 71.44 109,388.93 109,388.93
02.06 EQUIPAMIENTO URBANO
02.06.01 DISEÑO Y ESTRUCTURA DE CONCRETO
02.06.01.01 EXCAVACION A MANO EN TERRENO NORMAL m3 72.26 40.77 2,946.04 2,946.04
02.06.01.02 ENCOFRADO Y DESENCOFRADO DE EQUIPAMIENTO m2 659.37 35.13 23,163.67 23,163.67
02.06.01.03 CONCRETO F'C=210 KG/CM2 C/MEZCLADORA m3 117.48 486.59 57,164.59 57,164.59
02.06.01.04 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 5,823.54 7.40 43,094.20 43,094.20
02.06.01.05 REVESTIMIENTO CON GRANITO LAVADO m2 659.37 470.50 310,233.59 310,233.59
02.06.01.06 SUMINISTRO E INSTALACION ELECTRICA INCL. ACCESORIOS glb 1.00 6,500.00 6,500.00 6,500.00
02.06.02 JARDINERAS ORNAMENTALES SEGUN DISEÑO
02.06.02.01 EXCAVACION A MANO EN TERRENO NORMAL m3 196.02 40.77 7,991.74 7,991.74
02.06.02.02 ENCOFRADO Y DESENCOFRADO DE EQUIPAMIENTO m2 2,425.72 35.13 85,215.54 85,215.54
02.06.02.03 CONCRETO F'C=175 KG/CM2 C/MEZCLADORA m3 357.55 449.09 160,572.13 160,572.13
02.06.02.04 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 5,721.27 7.40 42,337.40 42,337.40
02.06.02.05 REVESTIMIENTO CON GRANITO LAVADO m2 1,416.63 470.50 666,524.42 666,524.42
02.06.03 BANCAS ORNAMENTALES SEGUN DISEÑO
02.06.03.01 EXCAVACION A MANO EN TERRENO NORMAL m3 9.50 40.77 387.32 387.32
02.06.03.02 ENCOFRADO Y DESENCOFRADO DE BANCAS m2 363.17 35.13 12,758.16 12,758.16
02.06.03.03 CONCRETO F'C=175 KG/CM2 C/MEZCLADORA m3 41.40 449.09 18,592.33 18,592.33
02.06.03.04 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 2,871.86 7.40 21,251.76 21,251.76
02.06.03.05 REVESTIMIENTO CON GRANITO PULIDO m2 363.17 493.51 179,228.03 179,228.03
02.06.03.06 PALIZA EN BANCAS Y ESTRUCTURAS m2 112.56 35.30 3,973.37 3,973.37
02.06.04 VARIOS
02.06.04.01 PALIZA DE PERGOLA RECTANGULAR und 42.00 2,153.64 90,452.88 90,452.88
02.06.04.02 PALIZA DE PERGOLA SEMI CIRCULAR und 10.00 3,552.37 35,523.70 35,523.70
02.06.04.03 SUMINISTRO E INSTALACION DE FAROLA ESFERICA und 82.00 554.37 45,458.34 45,458.34
02.06.04.04 SUMINISTRO E INSTALACION DE TACHOS DECORATIVOS und 30.00 185.67 5,570.10 5,570.10
02.07 SEÑALIZACION
02.07.01 PINTURA LINEAL CONTINUA EN SARDINEL m 14,511.19 11.08 160,783.99 160,783.99
02.08 AREA VERDE
02.08.01 REFINE Y NIVELACION A MANO EN TERRENO NORMAL m2 12,891.97 5.44 70,132.32 70,132.32
02.08.02 TIERRA NEGRA DE CHACRA m3 2,578.39 21.82 56,260.47 56,260.47
02.08.03 SEMBRADO DE GRASS m2 12,891.97 11.24 144,905.74 144,905.74
02.08.04 SUMINISTRO Y SEMBRADO DE PLANTAS ORNAMENTALES und 1,200.00 38.87 46,644.00 46,644.00
02.09 PRUEBAS DE CALIDAD
02.09.01 ENSAYO DENSIDAD DE CAMPO und 340.00 32.97 11,209.80 5,604.90 5,604.90
02.09.02 PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESIÓN)und 420.00 25.00 10,500.00 5,250.00 5,250.00
02.10 VARIOS
02.10.01 INSTALACION DE ARTEFACTOS DE ILUMINACION glb 1.00 6,342.53 6,342.53 6,342.53
02.10.02 LIMPIEZA FINAL DE OBRA m2 43,548.51 0.16 6,967.76 6,967.76
03 MUROS DE CONTENCION
03.01 TRABAJOS PRELIMINARES
03.01.01 LIMPIEZA MANUAL DE TERRENO m2 8,229.40 0.16 1,316.70 1,316.70
03.01.02 TRAZO, NIVELES Y REPLANTEO DURANTE EJECUCION m2 8,229.40 1.36 11,191.98 2,798.00 2,798.00 2,798.00 2,798.00
03.02 MOVIMIENTO DE TIERRAS
03.02.01 CORTE A MANO EN TERRENO NORMAL PARA MUROS m3 93.73 40.77 3,821.37 3,821.37
03.02.02 EXCAVACION A MANO EN TERRENO NORMAL PARA SARDINEL m3 345.40 40.77 14,081.96 14,081.96
03.02.03 PERFILADO Y COMPACTADO A MANO P/MUROS m2 733.69 7.93 5,818.16 5,818.16
CALENDARIO DE AVANCE VALORIZADO DE OBRA
PROYECTO
"MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD DE LAS CALLES Y AVENIDAS COLINDANTES A LA PLAZA CÍVICA DE SAN MARTÍN DE PANGOA DEL DISTRITO DE PANGOA - PROVINCIA DE SATIPO - DEPARTAMENTO DE JUNIN” C.U.I.N°2466249

ENTIDAD GOBIERNO REGIONAL DE JUNIN

ITEM DESCRIPCION UND METRADO COSTO TOTAL MES 01 MES 02 MES 03 MES 04 MES 05 MES 06 MES 07 MES 08 MES 09 MES 10 MES 11 MES 12 MES 13 MES 14 MES 15 MES 16 MES 17 MES 18
03.02.04 RELLENO Y COMPACTACION CON MAT. DE PRESTAMO m3 301.62 43.11 13,002.84 13,002.84
03.02.05 ACARREO INTERNO DE MATERIAL EXCEDENTE PARA ELIMINACION m3 525.48 7.95 4,177.57 4,177.57
03.02.06 CARGUIO DE MATERIAL (ELIMINACION DE MATERIAL EXCEDENTE) m3 525.48 6.02 3,163.39 3,163.39
03.02.07 TRANSPORTE DE MATERIAL (ELIMINACION DE MATERIAL EXCEDENTE)
m3 525.48 6.18 3,247.47 3,247.47
03.03 CONCRETO ARMADO
03.03.01 MUROS DE CONTENCION
03.03.01.01 ENCOFRADO Y DESENCOFRADO DE MUROS m2 3,976.26 35.13 139,686.01 139,686.01
03.03.01.02 CONCRETO F'C=210 KG/CM2 C/MEZCLADORA m3 590.61 486.59 287,384.92 287,384.92
03.03.01.03 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 20,248.20 7.40 149,836.68 149,836.68
03.03.01.04 JUNTAS DE DILATACION m 898.40 3.65 3,279.16 3,279.16
03.03.02 MUROS DE MANPOSTERIA
03.03.02.01 ENCOFRADO Y DESENCOFRADO DE MURETES m2 125.64 50.90 6,395.08 6,395.08
03.03.02.02 CONCRETO CICLOPEO f'c=175 kg/cm2 + 70% P.M. m3 45.26 197.53 8,940.21 8,940.21
03.03.02.03 JUNTAS DE DILATACION m 63.48 3.65 231.70 231.70
03.03.03 SARDINEL ARMADO
03.03.03.01 ENCOFRADO Y DESENCOFRADO DE SARDINEL ARMADO m2 245.63 35.13 8,628.98 8,628.98
03.03.03.02 CONCRETO F'C=175 KG/CM2 C/MEZCLADORA m3 253.64 449.09 113,907.19 113,907.19
03.03.03.03 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 16,263.48 7.40 120,349.75 120,349.75
03.03.03.04 ACABADO Y BRUÑADO DE SARDINEL m2 624.51 13.95 8,711.91 8,711.91
03.03.03.05 JUNTAS ASFALTICAS m 654.25 9.50 6,215.38 6,215.38
03.04 VARIOS
03.04.01 SUMINISTRO Y COLOCACION DE BARANDAS METALICAS DE F°G° m 274.26 73.74 20,223.93 20,223.93
03.04.02 LIMPIEZA FINAL DE OBRA m2 8,229.40 0.16 1,316.70 1,316.70
04 DRENAJE PLUVIAL
04.01 TRABAJOS PRELIMINARES
04.01.01 LIMPIEZA MANUAL DE TERRENO m2 1,556.85 0.16 249.10 249.10
04.01.02 TRAZO, NIVELES Y REPLANTEO DURANTE EJECUCION m2 1,556.85 1.36 2,117.32 529.33 529.33 529.33 529.33
04.02 MOVIMIENTO DE TIERRAS
04.02.01 EXCAVACION DE ZANJA C/MAQUINARIA m3 1,810.50 14.03 25,401.32 25,401.32
04.02.02 REFINE, NIVELACION Y COMPACTACION DE ZANJA m2 1,556.85 16.85 26,232.92 26,232.92
04.02.03 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO m3 2,224.47 41.37 92,026.32 92,026.32
04.02.04 ACARREO INTERNO DE MATERIAL EXCEDENTE PARA ELIMINACION m3 2,263.13 7.95 17,991.88 17,991.88
04.02.05 CARGUIO DE MATERIAL (ELIMINACION DE MATERIAL EXCEDENTE) m3 2,263.13 6.02 13,624.04 13,624.04
04.02.06 TRANSPORTE DE MATERIAL (ELIMINACION DE MATERIAL EXCEDENTE)
m3 2,263.13 6.18 13,986.14 13,986.14
04.03 CONCRETO ARMADO
04.03.01 CANAL PLUVIAL
04.03.01.01 ENCOFRADO Y DESENCOFRADO DE CANAL m2 7,912.49 35.89 283,979.27 141,989.64 141,989.64
04.03.01.02 CONCRETO F'C=210 KG/CM2 C/MEZCLADORA m3 1,166.21 486.59 567,466.12 283,733.06 283,733.06
04.03.01.03 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 43,141.32 7.40 319,245.77 159,622.89 159,622.89
04.03.01.04 SOLAQUEO DE MURO DE CONCRETO m2 3,113.69 34.51 107,453.44 107,453.44
04.03.02 CAJAS DE CONCRETO
04.03.02.01 ENCOFRADO Y DESENCOFRADO DE CAJAS m2 86.40 35.13 3,035.23 3,035.23
04.03.02.02 CONCRETO F'C=210 KG/CM2 C/MEZCLADORA m3 50.04 486.59 24,348.96 24,348.96
04.03.02.03 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 3,754.08 7.40 27,780.19 27,780.19
04.03.02.04 SOLAQUEO DE CAJA DE CONCRETO m2 86.40 34.51 2,981.66 2,981.66
04.03.03 TAPAS DE CONCRETO
04.03.03.01 ENCOFRADO Y DESENCOFRADO DE TAPAS m2 41.40 41.96 1,737.14 1,737.14
04.03.03.02 CONCRETO F'C=210 KG/CM2 C/MEZCLADORA m3 5.40 486.59 2,627.59 2,627.59
04.03.03.03 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 1,263.24 7.40 9,347.98 9,347.98
04.04 PRUEBAS DE CALIDAD
04.04.01 PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESIÓN)und 120.00 25.00 3,000.00 3,000.00
04.05 VARIOS
04.05.01 REJILLA METALICA EN CAJA DE CAPTACION m 19.50 220.96 4,308.72 4,308.72
04.05.02 REJILLA METALICA EN SUMIDEROS m 15.60 203.29 3,171.32 3,171.32
04.05.03 LIMPIEZA FINAL DE OBRA m2 1,556.85 0.16 249.10 249.10
COSTO DIRECTO S/ 33,975,072.54 S/ 1,082,908.32 S/ 967,859.39 S/ 410,739.05 S/ 2,452,191.59 S/ 773,003.79 S/ 504,675.80 S/ 990,310.26 S/ 1,843,148.66 S/ 766,142.75 S/ 1,560,769.57 S/ 1,028,447.22 S/ 3,165,830.03 S/ 4,097,446.12 S/ 4,948,442.36 S/ 4,813,252.73 S/ 2,295,799.65 S/ 1,055,399.93 S/ 1,218,705.32
PORCENTAJE DE AVANCE MENSUAL % 3.19% 2.85% 1.21% 7.22% 2.28% 1.49% 2.91% 5.43% 2.26% 4.59% 3.03% 9.32% 12.06% 14.56% 14.17% 6.76% 3.11% 3.59%
PORCENTAJE DE AVANCE ACUMULADO % 3.19% 6.04% 7.25% 14.46% 16.74% 18.22% 21.14% 26.56% 28.82% 33.41% 36.44% 45.76% 57.82% 72.38% 86.55% 93.31% 96.41% 100.00%
GASTOS GENERALES 7.84% S/ 2,664,196.68 S/ 84,917.57 S/ 75,895.87 S/ 32,208.60 S/ 192,291.59 S/ 60,616.03 S/ 39,574.77 S/ 77,656.38 S/ 144,532.75 S/ 60,078.02 S/ 122,389.65 S/ 80,646.94 S/ 248,252.42 S/ 321,306.23 S/ 388,038.13 S/ 377,437.07 S/ 180,027.92 S/ 82,760.47 S/ 95,566.26
VALOR REFERENCIAL S/ 36,639,269.22 S/ 1,167,825.89 S/ 1,043,755.27 S/ 442,947.66 S/ 2,644,483.18 S/ 833,619.83 S/ 544,250.57 S/ 1,067,966.64 S/ 1,987,681.41 S/ 826,220.77 S/ 1,683,159.21 S/ 1,109,094.16 S/ 3,414,082.45 S/ 4,418,752.34 S/ 5,336,480.49 S/ 5,190,689.80 S/ 2,475,827.57 S/ 1,138,160.40 S/ 1,314,271.58