“REHABILITACIÓN DE PUENTES PAQUETES 3- ANCASH (OBRA 3: PUENTE CONCHUCOS Y ACCESOS, PUENTE HUATAULIO Y ACCESOS, PUENTE
MAYAS Y ACCESOS, PUENTE GUAGUANCU Y ACCESOS Y PUENTE ASTERIA Y ACCESOS)”
OBRA
REAJUSTES (R)
FORMULA GENERAL (VALORIZACION MES DE
175,785.49 59,393.22 235,178.71
OCTUBRE 2021)
REINTEGRO DEL REAJUSTE 45,641.70 (675.23) 44,966.47
AMORTIZACIONES (A)
SON: DOSCIENTOS TREINTA Y SIETE MIL OCHOCIENTOS OCHENTA Y OCHO CON 38/100 NUEVOS SOLES
VALORIZACIÓN N°13 DEL 01 AL 30 DE NOVIEMBRE DEL 2021
PUENTE GUAGUANCU
PROCESO LPI N° 007-2019-MTC
OBRA REHABILITACIÓN DE PUENTES PAQUETE 3 – ANCASH (OBRAS3: PUENTE CONCHUCOS Y ACCESOS, PUENTE MAYAS Y ACCESOS, PUENTE HUATAULIO Y ACCESOS, PUENTE GUAGUANCU Y ACCESOS, PUENTE ASTERIA Y ACCESOS)”
CONTRATIST CONSORCIO PUENTES DE ANCASH PLAZO EJECUCION : 180 dias calendarios
JEFE DE SUP ING VÍCTOR CARLOS OCHARAN LARA
RESIDENTE DING. MIGUEL ZAPATA AREVALO
VALOR REFERENCIAL ACUMULADO ANTERIOR AVANCE ACTUAL ACUMULADO ACTUAL SALDO CONTRACTUAL
PARTIDA DESCRIPCION UND.
METRADO PU (S/.) PRESUP. Metrado Monto (S/.) Metrado Monto (S/.) Metrado Monto (S/.) % Metrado Monto (S/.) %
- - - -
04 PUENTE GUAGUANCU (L=19.00m) 2,201,589.45 - - -
04.01 PUENTE - - - -
04.01.01 OBRAS PRELIMINARES - - - -
04.01.01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS OBRA 3 glb 1.00 118,610.68 118,610.68 0.50 59,305.34 - 0.50 59,305.34 50.00% 0.50 59,305.34 50.00%
04.01.01.02 TOPOGRAFIA Y GEOREFERENCIACION m2 2,934.24 3.40 9,976.42 2,673.95 9,091.43 - 2,673.95 9,091.43 91.13% 260.29 884.99 8.87%
04.01.01.03 MANTENIMIENTO DE TRANSITO TEMPORAL Y SEGURIDAD VIAL mes 3.00 11,362.06 34,086.18 1.56 17,724.81 0.31 3,522.24 1.87 21,247.05 62.33% 1.13 12,839.13 37.67%
04.01.01.04 ACCESO A CANTERAS, FUENTES DE AGUA Y DEPOSITO DE MATERI km 18.86 10,787.84 203,458.66 18.86 203,458.66 - 18.86 203,458.66 100.00% - - 0.00%
04.01.01.05 DESBROCE Y LIMPIEZA DE TERRENO ha 0.43 4,164.93 1,790.92 0.43 1,790.92 - 0.43 1,790.92 100.00% - - 0.00%
04.01.01.06 DESVIO TEMPORAL DEL PUENTE GUAGUANCU m 138.76 714.02 99,077.42 138.76 99,077.42 - 138.76 99,077.42 100.00% - - 0.00%
04.01.01.07 DESMONTAJE DE PUENTE ROLLIZOS - GUAGUANCU und 1.00 932.61 932.61 1.00 932.61 - 1.00 932.61 100.00% - - 0.00%
04.01.01.08 TUBERIA TMC Ø 60" m 49.82 558.38 27,818.49 - - - - - 0.00% 49.82 27,818.49 100.00%
04.01.02 OBRAS TEMPORALES 0.00 - - - -
04.01.02.01 ENCAUZAMIENTO EN PUENTES m3 108.00 13.18 1,423.44 108.00 1,423.44 - 108.00 1,423.44 100.00% - - 0.00%
04.01.03 SUB-ESTRUCTURA (ESTRIBOS) - - - -
04.01.03.01 EXCAVACION PARA ESTRUCTURAS EN MATERIAL COMUN EN SECO m3 1,398.59 5.36 7,496.44 1,398.59 7,496.44 - 1,398.59 7,496.44 100.00% - - 0.00%
04.01.03.02 EXCAVACION PARA ESTRUCTURAS EN MATERIAL COMUN BAJO AGU m3 736.63 8.29 6,106.66 736.63 6,106.66 - 736.63 6,106.66 100.00% - - 0.00%
04.01.03.03 RELLENO CON MATERIAL DE PRESTAMO PARA ESTRUCTURAS m3 1,790.23 49.98 89,475.70 280.60 14,024.39 - 280.60 14,024.39 15.67% 1,509.63 75,451.31 84.33%
04.01.03.04 CONCRETO CLASE H1 (f´c = 100 kg/cm2), BAJO AGUA m3 16.46 387.59 6,379.73 16.46 6,379.73 - 16.46 6,379.73 100.00% - - 0.00%
04.01.03.05 CONCRETO CLASE C1 (f'c=280 kg/cm2), BAJO AGUA m3 131.66 630.63 83,028.75 131.66 83,028.75 - 131.66 83,028.75 100.00% - - 0.00%
04.01.03.06 CONCRETO CLASE C1 (f'c=280 kg/cm2) m3 239.56 578.80 138,657.33 195.30 113,039.64 44.26 25,617.69 239.56 138,657.33 100.00% - - 0.00%
04.01.03.07 ENCOFRADO Y DESENCOFRADO BAJO AGUA m2 64.35 119.08 7,662.80 64.35 7,662.80 - 64.35 7,662.80 100.00% - - 0.00%
04.01.03.08 ENCOFRADO Y DESENCOFRADO EN SECO m2 290.30 72.82 21,139.65 290.30 21,139.65 - 290.30 21,139.65 100.00% - - 0.00%
04.01.03.09 ENCOFRADO Y DESENCOFRADO CARA VISTA EN SECO m2 333.46 78.42 26,149.93 333.46 26,149.93 - 333.46 26,149.93 100.00% - - 0.00%
04.01.03.10 ACERO DE REFUERZO f'y=4200 KG/CM2 kg 27,878.90 5.40 150,546.06 27,878.90 150,546.06 - 27,878.90 150,546.06 100.00% - - 0.00%
04.01.03.11 TRANSPORTE DE MATERIAL GRANULAR ENTRE 120 M Y 1000 M m3k 1,575.40 6.50 10,240.10 246.93 1,605.05 - 246.93 1,605.05 15.67% 1,328.47 8,635.05 84.33%
04.01.03.12 TRANSPORTE DE MATERIAL GRANULAR A MAS DE 1000 M m3k 27,480.03 1.45 39,846.04 4,307.21 6,245.45 - 4,307.21 6,245.45 15.67% 23,172.82 33,600.59 84.33%
04.01.03.13 TRANSPORTE DE MATERIALES EXCEDENTES ENTRE 120 M Y 1000 M m3k 1,878.99 9.48 17,812.83 1,878.99 17,812.83 - 1,878.99 17,812.83 100.00% - - 0.00%
04.01.03.14 TRANSPORTE DE MATERIALES EXCEDENTES A MAS DE 1000 M m3k 2,241.98 1.57 3,519.91 2,241.98 3,519.91 - 2,241.98 3,519.91 100.00% - - 0.00%
04.01.04 SUPER-ESTRUCTURA - - - -
04.01.04.01 FALSO PUENTE CURVO - GUAGUANCU m 20.98 3,397.05 71,270.11 10.49 35,635.05 - 10.49 35,635.05 50.00% 10.49 35,635.06 50.00%
04.01.04.02 CONCRETO CLASE C1 (f'c=280 kg/cm2) m3 269.74 578.80 156,125.51 - - 269.74 156,125.51 269.74 156,125.51 100.00% - - 0.00%
04.01.04.03 ENCOFRADO Y DESENCOFRADO CARA VISTA EN SECO m2 329.31 78.42 25,824.49 164.65 12,912.17 - 164.65 12,912.17 50.00% 164.66 12,912.32 50.00%
04.01.04.04 ACERO DE REFUERZO f'y=4200 KG/CM2 kg 33,307.95 5.39 179,529.85 33,307.95 179,529.85 - 33,307.95 179,529.85 100.00% - - 0.00%
04.01.05 LOSA DE APROXIMACION - - - -
04.01.05.01 CONCRETO CLASE H1 (f´c = 100 kg/cm2) m3 10.52 335.73 3,531.88 - - - - - 0.00% 10.52 3,531.88 100.00%
04.01.05.02 CONCRETO CLASE C1 (f'c=280 kg/cm2) m3 33.66 578.74 19,480.39 - - - - - 0.00% 33.66 19,480.39 100.00%
04.01.05.03 ENCOFRADO Y DESENCOFRADO EN SECO m2 41.42 72.81 3,015.79 - - - - - 0.00% 41.42 3,015.79 100.00%
VALORIZACIÓN N°13 DEL 01 AL 30 DE NOVIEMBRE DEL 2021
PUENTE GUAGUANCU
PROCESO LPI N° 007-2019-MTC
OBRA REHABILITACIÓN DE PUENTES PAQUETE 3 – ANCASH (OBRAS3: PUENTE CONCHUCOS Y ACCESOS, PUENTE MAYAS Y ACCESOS, PUENTE HUATAULIO Y ACCESOS, PUENTE GUAGUANCU Y ACCESOS, PUENTE ASTERIA Y ACCESOS)”
CONTRATIST CONSORCIO PUENTES DE ANCASH PLAZO EJECUCION : 180 dias calendarios
JEFE DE SUP ING VÍCTOR CARLOS OCHARAN LARA
RESIDENTE DING. MIGUEL ZAPATA AREVALO
VALOR REFERENCIAL ACUMULADO ANTERIOR AVANCE ACTUAL ACUMULADO ACTUAL SALDO CONTRACTUAL
PARTIDA DESCRIPCION UND.
METRADO PU (S/.) PRESUP. Metrado Monto (S/.) Metrado Monto (S/.) Metrado Monto (S/.) % Metrado Monto (S/.) %
04.01.05.04 ACERO DE REFUERZO f'y=4200 KG/CM2 kg 4,686.53 5.39 25,260.40 - - - - - 0.00% 4,686.53 25,260.40 100.00%
04.01.06 VARIOS - - - -
04.01.06.01 JUNTA ENTRE ESTRIBOS Y LOSA DE APROXIMACION m 25.90 50.00 1,295.00 - - - - - 0.00% 25.90 1,295.00 100.00%
04.01.06.02 TUBO PVC Ø 6" PARA VEREDA m 155.36 57.12 8,874.16 - - 115.36 6,589.36 115.36 6,589.36 74.25% 40.00 2,284.80 25.75%
04.01.06.03 TUBO PVC Ø4" PARA DRENAJE (L=1.40 m) und 5.00 40.77 203.85 - - 3.00 122.31 3.00 122.31 60.00% 2.00 81.54 40.00%
04.01.06.04 BARANDA METALICA TIPO 5 m 62.09 738.38 45,846.01 - - - - - 0.00% 62.09 45,846.01 100.00%
04.01.06.05 BRUÑA ROMPEAGUAS m 18.11 18.64 337.57 - - 18.11 337.57 18.11 337.57 100.00% - - 0.00%
04.01.06.06 ACABADO DE VEREDAS m2 73.27 21.85 1,600.95 - - 73.27 1,600.95 73.27 1,600.95 100.00% - - 0.00%
04.01.06.07 PINTURA BITUMINOSA m2 226.92 31.69 7,191.09 226.92 7,191.09 - 226.92 7,191.09 100.00% - - 0.00%
04.01.06.08 RIEGO DE LIGA m2 294.03 2.35 690.97 - - - - - 0.00% 294.03 690.97 100.00%
04.01.06.09 CARPETA ASFALTICA EN FRIO E=2" m2 294.03 36.08 10,608.60 - - - - - 0.00% 294.03 10,608.60 100.00%
04.01.06.10 PRUEBA DE CARGA PARA PUENTE und 1.00 34,728.21 34,728.21 - - - - - 0.00% 1.00 34,728.21 100.00%
04.01.06.11 GEOCOMPUESTO DE DRENAJE m2 214.20 26.81 5,742.70 - - - - - 0.00% 214.20 5,742.70 100.00%
04.01.06.12 TUBO PVC Ø3" PARA DRENAJE (L=1.00 m) und 24.00 24.13 579.12 24.00 579.12 - 24.00 579.12 100.00% - - 0.00%
04.01.06.13 SUMIDERO PARA DRENAJE und 5.00 126.50 632.50 - - - - - 0.00% 5.00 632.50 100.00%
04.01.06.14 LAVADO DE MATERIAL GRANULAR m3 816.49 27.57 22,510.63 422.49 11,648.05 101.64 2,802.21 524.13 14,450.26 64.19% 292.36 8,060.37 35.81%
04.01.06.15 TUBERIA PERFORADA D=2" m 25.44 18.67 474.96 25.44 474.96 - 25.44 474.96 100.00% - - 0.00%
04.02 ACCESOS - - -
04.02.01 MOVIMIENTO DE TIERRAS - - - -
04.02.01.01 EXCAVACION EN EXPLANACIONES EN MATERIAL SUELTO m3 5,391.58 4.41 23,776.87 3,714.45 16,380.72 - 3,714.45 16,380.72 68.89% 1,677.13 7,396.15 31.11%
04.02.01.02 TERRAPLENES CON MATERIAL PRESTAMO m3 516.92 23.92 12,364.73 - - - - - 0.00% 516.92 12,364.73 100.00%
04.02.01.03 TRANSPORTE DE MATERIAL GRANULAR ENTRE 120 M Y 1000 M m3k 454.89 6.49 2,952.24 - - - - - 0.00% 454.89 2,952.24 100.00%
04.02.01.04 TRANSPORTE DE MATERIAL GRANULAR A MAS DE 1000 M m3k 7,934.67 1.45 11,505.27 - - - - - 0.00% 7,934.67 11,505.27 100.00%
04.02.01.05 TRANSPORTE DE MATERIALES EXCEDENTES ENTRE 120 M Y 1000 M m3k 4,744.59 9.48 44,978.71 3,268.71 30,987.39 - 3,268.71 30,987.39 68.89% 1,475.88 13,991.32 31.11%
04.02.01.06 TRANSPORTE DE MATERIALES EXCEDENTES A MAS DE 1000 M m3k 5,661.15 1.57 8,888.01 1,242.47 1,950.68 - 1,242.47 1,950.68 21.95% 4,418.68 6,937.33 78.05%
04.02.02 OBRAS DE ARTE Y DRENAJE - - - -
04.02.02.01 CUNETA - - - -
04.02.02.01.01 CUNETA TRIANGULAR REVESTIDA (f'c=175 kg/cm2) m 198.71 133.83 26,593.36 - - - - - 0.00% 198.71 26,593.36 100.00%
04.02.02.02 MURO DE CONTENCION - - - -
04.02.02.02.01 EXCAVACIÓN PARA ESTRUCTURAS EN MATERIAL COMÚN EN SECO m3 44.75 5.36 239.86 - - 23.30 124.89 23.30 124.89 52.07% 21.45 114.97 47.93%
04.02.02.02.02 RELLENO CON MATERIAL DE PRÉSTAMO PARA ESTRUCTURAS m3 236.75 49.98 11,832.77 - - - - - 0.00% 236.75 11,832.77 100.00%
04.02.02.02.03 MATERIAL DE FILTRO PARA SUB DRENAJE m3 58.00 30.46 1,766.68 - - - - - 0.00% 58.00 1,766.68 100.00%
04.02.02.02.04 CONCRETO CLASE H1 (f´c = 100 kg/cm2) m3 8.65 335.76 2,904.32 - - 4.50 1,510.92 4.50 1,510.92 52.02% 4.15 1,393.40 47.98%
04.02.02.02.05 CONCRETO CLASE D1 (f'c=210 kg/cm2) m3 121.45 503.34 61,130.64 - - - - - 0.00% 121.45 61,130.64 100.00%
04.02.02.02.06 ENCOFRADO Y DESENCOFRADO EN SECO m2 149.29 72.82 10,871.30 - - - - - 0.00% 149.29 10,871.30 100.00%
04.02.02.02.07 ENCOFRADO Y DESENCOFRADO CARA VISTA EN SECO m2 125.00 78.42 9,802.50 - - - - - 0.00% 125.00 9,802.50 100.00%
04.02.02.02.08 ACERO DE REFUERZO fy=4200 kg/cm2} kg 7,456.47 5.40 40,264.94 - - - - - 0.00% 7,456.47 40,264.94 100.00%
VALORIZACIÓN N°13 DEL 01 AL 30 DE NOVIEMBRE DEL 2021
PUENTE GUAGUANCU
PROCESO LPI N° 007-2019-MTC
OBRA REHABILITACIÓN DE PUENTES PAQUETE 3 – ANCASH (OBRAS3: PUENTE CONCHUCOS Y ACCESOS, PUENTE MAYAS Y ACCESOS, PUENTE HUATAULIO Y ACCESOS, PUENTE GUAGUANCU Y ACCESOS, PUENTE ASTERIA Y ACCESOS)”
CONTRATIST CONSORCIO PUENTES DE ANCASH PLAZO EJECUCION : 180 dias calendarios
JEFE DE SUP ING VÍCTOR CARLOS OCHARAN LARA
RESIDENTE DING. MIGUEL ZAPATA AREVALO
VALOR REFERENCIAL ACUMULADO ANTERIOR AVANCE ACTUAL ACUMULADO ACTUAL SALDO CONTRACTUAL
PARTIDA DESCRIPCION UND.
METRADO PU (S/.) PRESUP. Metrado Monto (S/.) Metrado Monto (S/.) Metrado Monto (S/.) % Metrado Monto (S/.) %
04.02.02.02.09 GEOTEXTIL NO TEJIDO CLASE 2 m2 242.00 10.32 2,497.44 - - - - - 0.00% 242.00 2,497.44 100.00%
04.02.02.02.10 TUBERIA PVC D=2" m 20.00 21.15 423.00 - - - - - 0.00% 20.00 423.00 100.00%
04.02.02.02.11 TUBERIA PERFORADA D=2" m 26.00 18.67 485.42 - - - - - 0.00% 26.00 485.42 100.00%
04.02.02.02.12 JUNTA DE DILATACIÓN m2 24.29 8.68 210.84 - - - - - 0.00% 24.29 210.84 100.00%
04.02.02.02.13 TRANSPORTE DE MATERIAL GRANULAR ENTRE 120 M Y 1000 M m3k 259.38 6.50 1,685.97 - - - - - 0.00% 259.38 1,685.97 100.00%
04.02.02.02.14 TRANSPORTE DE MATERIAL GRANULAR A MÁS DE 1000 M m3k 4,524.41 1.46 6,605.64 - - - - - 0.00% 4,524.41 6,605.64 100.00%
04.02.02.02.15 TRANSPORTE DE MATERIALES EXCEDENTES ENTRE 120 M Y 1000 M m3k 39.38 9.48 373.32 - - 20.50 194.34 20.50 194.34 52.06% 18.88 178.98 47.94%
04.02.02.02.16 TRANSPORTE DE MATERIALES EXCEDENTES A MAS DE 1000 M m3k 46.99 1.57 73.77 - - 24.47 38.42 24.47 38.42 52.07% 22.52 35.35 47.93%
04.02.02.02.17 GEOCOMPUESTO DE DRENAJE m2 106.00 26.81 2,841.86 - - - - - 0.00% 106.00 2,841.86 100.00%
04.02.03 PAVIMENTOS 0.00 - - - -
04.02.03.01 AFIRMADO m3 432.43 31.89 13,790.19 - - - - - 0.00% 432.43 13,790.19 100.00%
04.02.03.02 IMPRIMACION ASFALTICA m2 1,607.22 4.20 6,750.32 - - - - - 0.00% 1,607.22 6,750.32 100.00%
04.02.03.03 SLURRY SEAL E=12 MM m2 1,607.22 9.31 14,963.22 - - - - - 0.00% 1,607.22 14,963.22 100.00%
04.02.04 SEÑALIZACION 0.00 - - - -
04.02.04.01 SEÑALES PREVENTIVAS (0.60x0.60) und 8.00 450.38 3,603.04 - - - - - 0.00% 8.00 3,603.04 100.00%
04.02.04.02 SEÑALES REGLAMENTARIAS (0.60x0.60) und 4.00 547.76 2,191.04 - - - - - 0.00% 4.00 2,191.04 100.00%
04.02.04.03 POSTES DE SOPORTE DE SEÑALES und 12.00 215.46 2,585.52 - - - - - 0.00% 12.00 2,585.52 100.00%
04.02.04.04 SEÑAL INFORMATIVA m2 7.20 816.97 5,882.18 - - - - - 0.00% 7.20 5,882.18 100.00%
04.02.04.05 ESTRUCTURAS DE SOPORTE DE SEÑALES TIPO E-2 und 2.00 2,163.47 4,326.94 - - - - - 0.00% 2.00 4,326.94 100.00%
04.02.04.06 MARCAS EN EL PAVIMENTO m2 85.00 22.52 1,914.20 - - - - - 0.00% 85.00 1,914.20 100.00%
04.02.04.07 GUARDAVIA METALICA m 70.84 323.97 22,950.03 - - - - - 0.00% 70.84 22,950.03 100.00%
04.02.04.08 TACHA RETROREFLECTIVA und 91.00 12.49 1,136.59 - - - - - 0.00% 91.00 1,136.59 100.00%
04.03 PROTECCION AMBIENTAL 0.00 - - - -
04.03.01 SEÑALIZACION AMBIENTAL - - - -
04.03.01.01 SEÑAL INFORMATIVA m2 4.50 817.05 3,676.73 4.50 3,676.73 - 4.50 3,676.73 100.00% - - 0.00%
04.03.01.02 ESTRUCTURAS DE SOPORTE DE SEÑALES TIPO E-2 und 2.00 2,163.47 4,326.94 2.00 4,326.94 - 2.00 4,326.94 100.00% - - 0.00%
04.03.02 PROGRAMA DE MONITOREO AMBIENTAL 0.00 - - - -
04.03.02.01 MONITOREO DE LA CALIDAD DEL AIRE pto 9.00 224.98 2,024.82 6.00 1,349.88 - 6.00 1,349.88 66.67% 3.00 674.94 33.33%
04.03.02.02 MONITOREO DE LA CALIDAD DEL RUIDO pto 9.00 114.99 1,034.91 6.00 689.94 - 6.00 689.94 66.67% 3.00 344.97 33.33%
04.03.02.03 MONITOREO DE LA CALIDAD DEL AGUA pto 9.00 745.93 6,713.37 6.00 4,475.58 - 6.00 4,475.58 66.67% 3.00 2,237.79 33.33%
04.03.02.04 MONITOREO DE LA CALIDAD DEL SUELO pto 2.00 399.96 799.92 1.00 399.96 - 1.00 399.96 50.00% 1.00 399.96 50.00%
04.03.03 PROGRAMA DE CIERRE DE OBRA 0.00 - - - -
04.03.03.01 CAPA SUPERFICIAL CON SUELO CONSERVADO m2 8,434.00 2.86 24,121.24 - - - - - 0.00% 8,434.00 24,121.24 100.00%
04.03.03.02 RECUPERACION AMBIENTAL DE AREAS AFECTADAS ha 0.13 8,789.96 1,142.69 - - - - - 0.00% 0.13 1,142.69 100.00%
04.03.03.03 CONFORMACION DE DEPOSITO DE MATERIAL EXCEDENTE m3 7,693.73 7.05 54,240.80 - - 5,000.00 35,250.00 5,000.00 35,250.00 64.99% 2,693.73 18,990.80 35.01%
04.03.04 COMPENSACION POR AREAS AUXILIARES 0.00 - - - -
04.03.04.01 PAGO POR EXTRACCIÓN DE MATERIALES DE CANTERAS m3 3,052.68 2.54 7,753.81 336.72 855.27 - 336.72 855.27 11.03% 2,715.96 6,898.54 88.97%
- - -
VALORIZACIÓN N°13 DEL 01 AL 30 DE NOVIEMBRE DEL 2021
PUENTE GUAGUANCU
PROCESO LPI N° 007-2019-MTC
OBRA REHABILITACIÓN DE PUENTES PAQUETE 3 – ANCASH (OBRAS3: PUENTE CONCHUCOS Y ACCESOS, PUENTE MAYAS Y ACCESOS, PUENTE HUATAULIO Y ACCESOS, PUENTE GUAGUANCU Y ACCESOS, PUENTE ASTERIA Y ACCESOS)”
CONTRATIST CONSORCIO PUENTES DE ANCASH PLAZO EJECUCION : 180 dias calendarios
JEFE DE SUP ING VÍCTOR CARLOS OCHARAN LARA
RESIDENTE DING. MIGUEL ZAPATA AREVALO
VALOR REFERENCIAL ACUMULADO ANTERIOR AVANCE ACTUAL ACUMULADO ACTUAL SALDO CONTRACTUAL
PARTIDA DESCRIPCION UND.
METRADO PU (S/.) PRESUP. Metrado Monto (S/.) Metrado Monto (S/.) Metrado Monto (S/.) % Metrado Monto (S/.) %
0.00
COSTO DIRECTO 2,201,589.45 1,170,625.30 53.17% 233,836.41 10.62% 1,404,461.71 63.79% 797,127.74 36.21%
GASTOS GENERALES 16.80286653% 369,930.14 196,698.61 39,291.22 235,989.83 133,940.31
UTILIDAD 5.31% 116,904.40 62,160.20 12,416.71 74,576.91 42,327.49
SUB-TOTAL OBRA 2,688,423.99 1,429,484.11 285,544.34 1,715,028.45 973,395.54
FACTOR RELACIONAL 1.0000 1.0000 1.0000 1.0000 1.0000
TOTAL OBRA x F.R. 2,688,423.99 1,429,484.11 285,544.34 1,715,028.45 973,395.54
I.G.V. (18 %) 18.00% 483,916.32 257,307.15 51,397.98 308,705.13 175,211.19
\
PRESUPUESTO CONTRATADO C/IGV 3,172,340.31 1,686,791.26 336,942.32 2,023,733.58 1,148,606.73
RESUMEN DE METRADOS
Obra : REHABILITACIÓN DE PUENTES PAQUETE 3 – ANCASH (OBRAS3: PUENTE CONCHUCOS Y ACCESOS, PUENTE MAYAS Y ACCESOS, PUENTE HUATAULIO Y ACCESOS, PUENTE
GUAGUANCU Y ACCESOS, PUENTE ASTERIA Y ACCESOS)”
Licitación LPI N° 007-2019-MTC
ContratistaCONSORCIO PUENTES DE ANCASH
PROGRAMADO REAL
No. PERIODO SOLES (S/IGV) PORCENTAJE SOLES (S/IGV) PORCENTAJE
VAL MENSUAL ACUMULADO MENSUAL ACUMULADO MENSUAL ACUMULADO MENSUAL ACUMULADO
0 0.00% 0.00%
1 11/11/2020 al 30/11/2020 0.00 0.00 0.00% 0.00% 0.00 0.00 0.00% 0.00%
2 01/12/2020 al 31/12/2020 9,051.54 9,051.54 0.34% 0.34% 4,868.01 4,868.01 0.18% 0.18%
3 01/01/2021 al 31/01/2021 502,080.40 511,131.94 18.68% 19.02% 386,964.45 391,832.46 14.39% 14.57%
4 01/02/2021 al 28/02/2021 540,376.72 1,051,508.66 20.10% 39.12% 86,631.66 478,464.12 3.22% 17.79%
5 01/03/2021 al 31/03/2021 709,284.10 1,760,792.76 26.38% 65.50% 0.00 478,464.12 0.00% 17.79%
6 01/04/2021 al 30/04/2021 281,033.28 2,041,826.04 10.45% 75.95% 1,444.84 479,908.96 0.06% 17.85%
7 01/05/2021 al 31/05/2021 87,759.65 2,129,585.69 3.26% 79.21% 58,740.74 538,649.70 2.19% 20.04%
8 01/06/2021 al 30/06/2022 29,511.77 2,159,097.46 1.10% 80.31% 222,637.89 761,287.59 8.28% 28.32%
9 01/07/2021 al 31/07/2021 52,090.63 2,211,188.09 1.94% 82.25% 240,847.40 1,002,134.99 8.96% 37.28%
10 01/08/2021 al 31/08/2021 277,068.35 2,488,256.44 10.31% 92.56% 149,852.62 1,151,987.61 5.57% 42.85%
11 01/09/2021 al 15/09/2021 171,081.97 2,659,338.41 6.36% 98.92% 142,451.04 1,294,438.65 5.30% 48.15%
12 01/10/2021 al 31/10/2021 29,085.58 2,688,423.99 1.08% 100.00% 135,045.46 1,429,484.11 5.02% 53.17%
13 01/11/2021 al 30/11/2021 - 2,688,423.99 0.00% 100.00% 285,544.34 1,715,028.45 10.62% 63.79%
TOTALES 2,688,423.99 1,715,028.45
PROGRAMADO REAL
No. PERIODO SOLES (S/IGV) PORCENTAJE SOLES (S/IGV) PORCENTAJE
VAL MENSUAL ACUMULADO MENSUAL ACUMULADO MENSUAL ACUMULADO MENSUAL ACUMULADO
0 0.00% 0.00%
1 11/11/2020 al 30/11/2020 0.00 0.00 0.00% 0.00% 0.00 0.00 0.00% 0.00%
2 01/12/2020 al 31/12/2020 9,051.54 9,051.54 0.34% 0.34% 4,868.01 4,868.01 0.18% 0.18%
3 01/01/2021 al 31/01/2021 502,080.40 511,131.94 18.68% 19.02% 386,964.45 391,832.46 14.39% 14.57%
4 01/02/2021 al 28/02/2021 540,376.72 1,051,508.66 20.10% 39.12% 86,631.66 478,464.12 3.22% 17.79%
5 01/03/2021 al 31/03/2021 709,284.10 1,760,792.76 26.38% 65.50% 0.00 478,464.12 0.00% 17.79%
6 01/04/2021 al 30/04/2021 281,033.28 2,041,826.04 10.45% 75.95% 1,444.84 479,908.96 0.06% 17.85%
7 01/05/2021 al 31/05/2021 87,759.65 2,129,585.69 3.26% 79.21% 58,740.74 538,649.70 2.19% 20.04%
8 01/06/2021 al 30/06/2022 29,511.77 2,159,097.46 1.10% 80.31% 222,637.89 761,287.59 8.28% 28.32%
9 01/07/2021 al 31/07/2021 52,090.63 2,211,188.09 1.94% 82.25% 240,847.40 1,002,134.99 8.96% 37.28%
10 01/08/2021 al 31/08/2021 277,068.35 2,488,256.44 10.31% 92.56% 149,852.62 1,151,987.61 5.57% 42.85%
11 01/09/2021 al 15/09/2021 171,081.97 2,659,338.41 6.36% 98.92% 142,451.04 1,294,438.65 5.30% 48.15%
12 01/10/2021 al 31/10/2021 29,085.58 2,688,423.99 1.08% 100.00% 135,045.46 1,429,484.11 5.02% 53.17%
13 01/11/2021 al 30/11/2021 - 2,688,423.99 0.00% 100.00% 285,544.34 1,715,028.45 10.62% 63.79%
TOTALES 2,688,423.99 1,715,028.45
CURVA S
120.00%
60.00% 63.79%
53.17%
39.12% 48.15%
40.00% 42.85%
37.28%
19.02%
28.32%
20.00%
17.79% 17.79% 17.85% 20.04%
0.34% 14.57%
0.00%
0.00% 0.18%3
0 1 0.00% 2 4 5 6 7 8 9 10 11 12 13 14
1 11/11/2020 al 30/11/2020
60.00% 0.00 0.00 0.00% 0.00% 0.00 0.00 0.00% 0.00%
63.79%
2 01/12/2020 al 31/12/2020 9,051.54 9,051.54 0.34% 0.34% 4,868.01 4,868.01 0.18% 0.18%
3 01/01/2021 al 31/01/2021 502,080.40 511,131.94 18.68% 19.02% 386,964.45 391,832.46
53.17% 14.39% 14.57%
4 01/02/2021 al 28/02/2021 540,376.72
39.12% 1,051,508.66 20.10% 39.12% 86,631.66 48.15%
478,464.12 3.22% 17.79%
5 40.00%
01/03/2021 al 31/03/2021 709,284.10 1,760,792.76 26.38% 65.50% 0.00
42.85% 478,464.12 0.00% 17.79%
6 01/04/2021 al 30/04/2021 281,033.28 2,041,826.04 10.45% 75.95% 37.28% 1,444.84 479,908.96 0.06% 17.85%
7 01/05/2021 al 31/05/2021 19.02%
87,759.65 2,129,585.69 3.26% 79.21% 58,740.74 538,649.70 2.19% 20.04%
28.32%
8 01/06/2021 al 30/06/2022
20.00% 29,511.77 2,159,097.46 1.10% 80.31% 222,637.89 761,287.59 8.28% 28.32%
9 01/07/2021 al 31/07/2021 52,090.63 17.79%
2,211,188.09
17.79% 20.04%
17.85%1.94% 82.25% 240,847.40 1,002,134.99 8.96% 37.28%
10 01/08/2021 al 31/08/2021 0.34% 14.57%
277,068.35 2,488,256.44 10.31% 92.56% 149,852.62 1,151,987.61 5.57% 42.85%
0.00%
11 01/09/2021 al 15/09/2021 171,081.97 2,659,338.41 6.36% 98.92% 142,451.04 1,294,438.65 5.30% 48.15%
0.00% 0.18%
12 01/10/2021 al 31/10/2021
0 1 0.00% 2 29,085.58
3 42,688,423.99
5 6 1.08%7 100.00%
8 9 135,045.46
10 1,429,484.11
11 12 5.02%
13 14 53.17%
13 01/11/2021 al 30/11/2021 - 2,688,423.99 0.00% 100.00% 285,544.34 1,715,028.45 10.62% 63.79%
TOTALES 2,688,423.99 1,715,028.45
VALORIZACIONES PROGRAMADO REAL
CRONOGRAMA ACELERADO VALORIZADO DE EJECUCIÓN DE OBRA
“REHABILITACIÓN DE PUENTES PAQUETES 3- ANCASH (OBRA 3: PUENTE CONCHUCOS Y ACCESOS, PUENTE MAYAS Y ACCESOS, PUENTE MAYAS Y ACCESOS, PUENTE GUAGUANCU Y ACCESOS Y PUENTE ASTERIA Y ACCESOS)”
Item Descripción Und. Metrado Precio S/. Parcial S/. Noviembre 2020 Diciembre 2020 Enero 2021 Febrero 2021 Marzo 2021 Abril 2021 Mayo 2021 JUN JUL AGOS
“REHABILITACIÓN DE PUENTES PAQUETES 3- ANCASH (OBRA 3: PUENTE CONCHUCOS Y ACCESOS, PUENTE MAYAS Y ACCESOS, PUENTE MAYAS Y ACCESOS, PUENTE GUAGUANCU Y ACCESOS Y PUENTE ASTERIA Y ACCESOS)”
Item Descripción Und. Metrado Precio S/. Parcial S/. Noviembre 2020 Diciembre 2020 Enero 2021 Febrero 2021 Marzo 2021 Abril 2021 Mayo 2021 JUN JUL AGOS
“REHABILITACIÓN DE PUENTES PAQUETES 3- ANCASH (OBRA 3: PUENTE CONCHUCOS Y ACCESOS, PUENTE MAYAS Y ACCESOS, PUENTE MAYAS Y ACCESOS, PUENTE GUAGUANCU Y ACCESOS Y PUENTE ASTERIA Y ACCESOS)”
Item Descripción Und. Metrado Precio S/. Parcial S/. Noviembre 2020 Diciembre 2020 Enero 2021 Febrero 2021 Marzo 2021 Abril 2021 Mayo 2021 JUN JUL AGOS
04.01.06.12 TUBO PVC Ø3" PARA DRENAJE (L=1.00 m) und 24.00 24.13 579.12 0.00 579.12 579.12
04.01.06.13 SUMIDERO PARA DRENAJE und 5.00 126.50 632.50 0.00 632.50 632.50
04.01.06.14 LAVADO DE MATERIAL GRANULAR m3 816.49 27.57 22,510.63 0.00 22,510.63 22,510.63
04.01.06.15 TUBERIA PERFORADA D=2" m 25.44 18.67 474.96 0.00 474.96 474.96
04.02 ACCESOS 0.00 0.00
04.02.01 MOVIMIENTO DE TIERRAS 0.00 0.00
04.02.01.01 EXCAVACION EN EXPLANACIONES EN MATERIAL SUELTO m3 5,391.58 4.41 23,776.87 0.00 8,321.90 15,454.97 8,321.90 15,454.97
04.02.01.02 TERRAPLENES CON MATERIAL PRESTAMO m3 516.92 23.92 12,364.73 0.00 12,364.73 12,364.73
04.02.01.03 TRANSPORTE DE MATERIAL GRANULAR ENTRE 120 M Y 1000 M m3k 454.89 6.49 2,952.24 0.00 2,952.24 2,952.24
04.02.01.04 TRANSPORTE DE MATERIAL GRANULAR A MAS DE 1000 M m3k 7,934.67 1.45 11,505.27 0.00 11,505.27 11,505.27
04.02.01.05 TRANSPORTE DE MATERIALES EXCEDENTES ENTRE 120 M Y 1000 M m3k 4,744.59 9.48 44,978.71 0.00 44,978.71 44,978.71
04.02.01.06 TRANSPORTE DE MATERIALES EXCEDENTES A MAS DE 1000 M m3k 5,661.15 1.57 8,888.01 0.00 8,888.01 8,888.01
04.02.02 OBRAS DE ARTE Y DRENAJE 0.00 0.00
04.02.02.01 CUNETA 0.00 0.00
04.02.02.01.01 CUNETA TRIANGULAR REVESTIDA (f'c=175 kg/cm2) m 198.71 133.83 26,593.36 0.00 26,593.36 26,593.36
04.02.02.02 MURO DE CONTENCION 0.00 0.00
04.02.02.02.01 EXCAVACIÓN PARA ESTRUCTURAS EN MATERIAL COMÚN EN SECO m3 44.75 5.36 239.86 0.00 239.86 239.86
04.02.02.02.02 RELLENO CON MATERIAL DE PRÉSTAMO PARA ESTRUCTURAS m3 236.75 49.98 11,832.77 0.00 11,832.77
04.02.02.02.03 MATERIAL DE FILTRO PARA SUB DRENAJE m3 58.00 30.46 1,766.68 0.00 1,766.68
04.02.02.02.04 CONCRETO CLASE H1 (f´c = 100 kg/cm2) m3 8.65 335.76 2,904.32 0.00 2,904.32 2,904.32
04.02.02.02.05 CONCRETO CLASE D1 (f'c=210 kg/cm2) m3 121.45 503.34 61,130.64 0.00 56,428.28 4,702.36 56,428.28
04.02.02.02.06 ENCOFRADO Y DESENCOFRADO EN SECO m2 149.29 72.82 10,871.30 0.00 10,871.30 10,871.30
04.02.02.02.07 ENCOFRADO Y DESENCOFRADO CARA VISTA EN SECO m2 125.00 78.42 9,802.50 0.00 9,802.50 9,802.50
04.02.02.02.08 ACERO DE REFUERZO fy=4200 kg/cm2} kg 7,456.47 5.40 40,264.94 0.00 40,264.94 40,264.94
04.02.02.02.09 GEOTEXTIL NO TEJIDO CLASE 2 m2 242.00 10.32 2,497.44 0.00 2,497.44
04.02.02.02.10 TUBERIA PVC D=2" m 20.00 21.15 423.00 0.00 423.00
04.02.02.02.11 TUBERIA PERFORADA D=2" m 26.00 18.67 485.42 0.00 485.42 485.42
04.02.02.02.12 JUNTA DE DILATACIÓN m2 24.29 8.68 210.84 0.00 210.84
04.02.02.02.13 TRANSPORTE DE MATERIAL GRANULAR ENTRE 120 M Y 1000 M m3k 259.38 6.50 1,685.97 0.00 1,685.97
04.02.02.02.14 TRANSPORTE DE MATERIAL GRANULAR A MÁS DE 1000 M m3k 4,524.41 1.46 6,605.64 0.00 6,605.64
04.02.02.02.15 TRANSPORTE DE MATERIALES EXCEDENTES ENTRE 120 M Y 1000 M m3k 39.38 9.48 373.32 0.00 373.32 373.32
04.02.02.02.16 TRANSPORTE DE MATERIALES EXCEDENTES A MAS DE 1000 M m3k 46.99 1.57 73.77 0.00 73.77 73.77
04.02.02.02.17 GEOCOMPUESTO DE DRENAJE m2 106.00 26.81 2,841.86 0.00 2,841.86 2,841.86
04.02.03 PAVIMENTOS 0.00 0.00
04.02.03.01 AFIRMADO m3 432.43 31.89 13,790.19 0.00 13,790.19
04.02.03.02 IMPRIMACION ASFALTICA m2 1,607.22 4.20 6,750.32 0.00 6,750.32
04.02.03.03 SLURRY SEAL E=12 MM m2 1,607.22 9.31 14,963.22 0.00 14,963.22
04.02.04 SEÑALIZACION 0.00 0.00
CRONOGRAMA ACELERADO VALORIZADO DE EJECUCIÓN DE OBRA
“REHABILITACIÓN DE PUENTES PAQUETES 3- ANCASH (OBRA 3: PUENTE CONCHUCOS Y ACCESOS, PUENTE MAYAS Y ACCESOS, PUENTE MAYAS Y ACCESOS, PUENTE GUAGUANCU Y ACCESOS Y PUENTE ASTERIA Y ACCESOS)”
Item Descripción Und. Metrado Precio S/. Parcial S/. Noviembre 2020 Diciembre 2020 Enero 2021 Febrero 2021 Marzo 2021 Abril 2021 Mayo 2021 JUN JUL AGOS
04.02.04.01 SEÑALES PREVENTIVAS (0.60x0.60) und 8.00 450.38 3,603.04 0.00 3,002.53 600.51
04.02.04.02 SEÑALES REGLAMENTARIAS (0.60x0.60) und 4.00 547.76 2,191.04 0.00 2,191.04
04.02.04.03 POSTES DE SOPORTE DE SEÑALES und 12.00 215.46 2,585.52 0.00 2,585.52
04.02.04.04 SEÑAL INFORMATIVA m2 7.20 816.97 5,882.18 0.00 5,882.18
04.02.04.05 ESTRUCTURAS DE SOPORTE DE SEÑALES TIPO E-2 und 2.00 2,163.47 4,326.94 0.00 4,326.94
04.02.04.06 MARCAS EN EL PAVIMENTO m2 85.00 22.52 1,914.20 0.00 191.42 1,722.78
04.02.04.07 GUARDAVIA METALICA m 70.84 323.97 22,950.03 0.00 2,295.00 20,655.03
04.02.04.08 TACHA RETROREFLECTIVA und 91.00 12.49 1,136.59 0.00 113.66 1,022.93
04.03 PROTECCION AMBIENTAL 0.00 0.00
04.03.01 SEÑALIZACION AMBIENTAL 0.00 0.00
04.03.01.01 SEÑAL INFORMATIVA m2 4.50 817.05 3,676.73 0.00 1,313.12 2,363.61
04.03.01.02 ESTRUCTURAS DE SOPORTE DE SEÑALES TIPO E-2 und 2.00 2,163.47 4,326.94 0.00 1,802.89 2,524.05
04.03.02 PROGRAMA DE MONITOREO AMBIENTAL 0.00 0.00
04.03.02.01 MONITOREO DE LA CALIDAD DEL AIRE pto 9.00 224.98 2,024.82 0.00 343.50 506.21 560.44 542.36 72.31 343.50 506.21 560.44
04.03.02.02 MONITOREO DE LA CALIDAD DEL RUIDO pto 9.00 114.99 1,034.91 0.00 175.57 258.73 286.45 277.21 36.95 175.57 258.73 286.45
04.03.02.03 MONITOREO DE LA CALIDAD DEL AGUA pto 9.00 745.93 6,713.37 0.00 1,138.88 1,678.34 1,858.16 1,798.22 239.77 1,138.88 1,678.34 1,858.16
04.03.02.04 MONITOREO DE LA CALIDAD DEL SUELO pto 2.00 399.96 799.92 0.00 135.70 199.98 221.41 214.26 28.57 135.70 199.98 221.41
04.03.03 PROGRAMA DE CIERRE DE OBRA 0.00 0.00
04.03.03.01 CAPA SUPERFICIAL CON SUELO CONSERVADO m2 8,434.00 2.86 24,121.24 0.00 8,614.73 15,506.51
04.03.03.02 RECUPERACION AMBIENTAL DE AREAS AFECTADAS ha 0.13 8,789.96 1,142.69 0.00 408.10 734.59
04.03.03.03 CONFORMACION DE DEPOSITO DE MATERIAL EXCEDENTE m3 7,693.73 7.05 54,240.80 0.00 19,371.71 34,869.09
04.03.04 COMPENSACION POR AREAS AUXILIARES 0.00 0.00
04.03.04.01 PAGO POR EXTRACCIÓN DE MATERIALES DE CANTERAS m3 3,052.68 2.54 7,753.81 0.00 2,769.22 4,984.59
TOTAL COSTO DIRECTO 2,201,589.45 0.00 7,412.44 411,160.93 442,522.34 580,843.05 230,142.24 71,867.65 24,167.62 42,657.77 226,895.30
GASTOS GENERALES 16.80286653% 369,930.14 0.00 1,245.51 69,086.82 74,356.44 97,598.28 38,670.49 12,075.83 4,060.85 7,167.73 38,124.91
UTILIDAD 5.31% 116,904.40 0.00 393.60 21,832.65 23,497.94 30,842.77 12,220.55 3,816.17 1,283.30 2,265.13 12,048.14
SUBTOTAL 2,688,423.99 0.00 9,051.54 502,080.40 540,376.72 709,284.10 281,033.28 87,759.65 29,511.77 52,090.63 277,068.35
IGV 18.00% 483,916.32 0.00 1,629.28 90,374.47 97,267.81 127,671.14 50,585.99 15,796.74 5,312.12 9,376.31 49,872.30
COSTO TOTAL 3,172,340.31 0.00 10,680.82 592,454.87 637,644.53 836,955.24 331,619.27 103,556.39 34,823.89 61,466.94 326,940.65
% Avance Mensual 0.34% 18.68% 20.10% 26.38% 10.45% 3.26% 1.10% 1.94% 10.31%
% Avance Acumulado 0.34% 19.02% 39.12% 65.50% 75.95% 79.21% 80.31% 82.25% 92.56%
Especialidad: Costos y
Presupuesto
1,423.44
7,496.44
6,106.66
89,475.70
6,379.73
83,028.75
138,657.33
7,662.80
21,139.65
26,149.93
150,546.06
10,240.10
39,846.04
17,812.83
3,519.91
71,270.11
87,430.29 156,125.51
25,824.49
179,529.85
3,531.88 3,531.88
19,480.39 19,480.39
3,015.79 3,015.79
25,260.40 25,260.40
1,295.00 1,295.00
8,874.16
203.85
45,846.01 45,846.01
337.57 337.57
1,600.95 1,600.95
7,191.09
690.97 690.97
3,536.20 7,072.40 10,608.60
34,728.21 34,728.21
5,742.70
Especialidad: Costos y
Presupuesto
579.12
632.50
22,510.63
474.96
23,776.87
12,364.73
2,952.24
11,505.27
44,978.71
8,888.01
26,593.36
239.86
11,832.77 11,832.77
1,766.68 1,766.68
2,904.32
4,702.36 61,130.64
10,871.30
9,802.50
40,264.94
2,497.44 2,497.44
423.00 423.00
485.42
210.84 210.84
1,685.97 1,685.97
6,605.64 6,605.64
373.32
73.77
2,841.86
13,790.19 13,790.19
6,750.32 6,750.32
14,963.22 14,963.22
Especialidad: Costos y
Presupuesto
OBRA REHABILITACIÓN DE PUENTES PAQUETE 3 – ANCASH (OBRAS3: PUENTE CONCHUCOS Y ACCESOS, PUENTE MAYAS Y ACCESOS, PUENTE HUATAULIO
Y ACCESOS, PUENTE GUAGUANCU Y ACCESOS, PUENTE ASTERIA Y ACCESOS)”
AMORTIZACION
DEDUCCION QUE
MES DE VALORIZACION NO CORRESPONDE AMORTIZACION DEL SALDO POR
POR A.D. A.D. (S/IGV) AMORTIZAR (S/IGV)
AMORTIZACION DEL A.D. Y DEDUCCION DE REINTEGRO QUE NO CORRESPONDE POR ADELANTO DIRECTO(DRQNCAD)
OBRA REHABILITACIÓN DE PUENTES PAQUETE 3 – ANCASH (OBRAS3: PUENTE CONCHUCOS Y ACCESOS, PUENTE MAYAS Y ACCESOS, PUENTE HUATAULIO
Y ACCESOS, PUENTE GUAGUANCU Y ACCESOS, PUENTE ASTERIA Y ACCESOS)”
OBRA REHABILITACIÓN DE PUENTES PAQUETE 3 – ANCASH (OBRAS3: PUENTE CONCHUCOS Y ACCESOS, PUENTE MAYAS Y ACCESOS, PUENTE HUATAULIO
Y ACCESOS, PUENTE GUAGUANCU Y ACCESOS, PUENTE ASTERIA Y ACCESOS)”
DRQNC A.D.
MES DE K MES DE KA MONTO
MONTO DEL
CONOCIDO AL CONOCIDO A LA MONTO A.D.(S/IGV) CONTRATO (S/IGV) VALORIZADO K KA (𝐀.𝐃.)/𝐂 𝐱𝐕(𝐊/𝐊_𝐀 −𝟏)
VALORIZ. N° MES EJECUTADO MES (S/IGV) REGULARIZACIÓN
MES DE FECHA DEL GIRO
REAJUSTE DEL A.D.
(1) (2) (3) (4) (5) (1x3/2)*(4/5-1)
01 NOVIEMBRE Noviembre Octubre 1,665,946.47 17,509,498.52 - 1.069 1.066 - -
02 DICIEMBRE Diciembre Octubre 1,665,946.47 17,509,498.52 4,868.01 1.075 1.066 3.810 (2.55)
03 ENERO Enero Octubre 1,665,946.47 17,509,498.52 386,964.45 1.093 1.066 924.590 (621.56)
04 FEBRERO Febrero Octubre 1,665,946.47 17,509,498.52 86,631.66 1.109 1.066 330.680 (123.69)
05 MARZO Marzo Octubre 1,665,946.47 17,509,498.52 - 1.123 1.066 - -
06 ABRIL Abril Octubre 1,665,946.47 17,509,498.52 1,444.84 1.123 1.066 7.320 -
07 MAYO Mayo Octubre 1,665,946.47 17,509,498.52 58,740.74 1.137 1.066 370.990 (73.39)
08 JUNIO Junio Octubre 1,665,946.47 17,509,498.52 222,637.89 1.164 1.066 1,942.530 (536.41)
09 JULIO Julio Octubre 1,665,946.47 17,509,498.52 240,847.40 1.173 1.066 2,294.840 (193.43)
10 AGOSTO Agosto Octubre 1,665,946.47 17,509,498.52 149,852.62 1.201 1.066 1,802.250 (374.43)
11 SETIEMBRE Setiembre Octubre 1,665,946.47 17,509,498.52 142,451.04 1.213 1.066 1,869.020 (155.79)
12 OCTUBRE Octubre Octubre 1,665,946.47 17,509,498.52 135,045.46 1.208 1.066 1,711.580 60.27
REGULARIZACIÓN
OBRA REHABILITACIÓN DE PUENTES PAQUETE 3 – ANCASH (OBRAS3: PUENTE CONCHUCOS Y ACCESOS, PUENTE MAYAS Y ACCESOS, PUENTE
HUATAULIO Y ACCESOS, PUENTE GUAGUANCU Y ACCESOS, PUENTE ASTERIA Y ACCESOS)”
Donde:
Au.: Monto del adelanto utilizado en la valorización que se reajusta S : Saldo por amortizar del adelanto para materiales
C i: Coeficiente de incidencia del elemento representativo en la fórmula polinómica A.M.: Adelanto otorgado para elemento (material) representativo
% p: Porcentaje de participación del C i en el monomio del elemento representativo en la FP. D: Deducción de Reajuste que no Corresponde por A.M. (DQNCPAM)
V : Valorización ejecutada del mes, afectada por el factor de relación Imr: Indice de elemento representativo a la fecha de reajuste
A: Amortización del adelanto para materiales a la fecha que se hizo efectivo el adelanto A.M.d: Adelanto para materiales deflactado a la fecha del presupuesto base
Ima: Indice de elemento representativo a la fecha efectiva del adelanto C : Control para que finalice la deducción (paso b del procedimiento del Art. 7° del DS-011-79.Mayc)
Imo: Indice de elemento representativo a la fecha del presupuesto base
OBRA REHABILITACIÓN DE PUENTES PAQUETE 3 – ANCASH (OBRAS3: PUENTE CONCHUCOS Y ACCESOS, PUENTE MAYAS Y ACCESOS, PUENTE
HUATAULIO Y ACCESOS, PUENTE GUAGUANCU Y ACCESOS, PUENTE ASTERIA Y ACCESOS)”
OBRA REHABILITACIÓN DE PUENTES PAQUETE 3 – ANCASH (OBRAS3: PUENTE CONCHUCOS Y ACCESOS, PUENTE MAYAS Y ACCESOS, PUENTE
HUATAULIO Y ACCESOS, PUENTE GUAGUANCU Y ACCESOS, PUENTE ASTERIA Y ACCESOS)”
Valorización Adelanto pagado Coeficiente Indices Adelanto Amortización Saldo por DQNCPAM
Mes Conocido para Indices Regularización
Monto Monto Coef. Incid F. PTO F. PAGO F. MES utilizado Amortizar D=Au x
Nº Mes Fecha A=Au*Ima/Imo de deducción
(Imr-Ima)/Imo
V A.M. Ci % mo ma mr Imo Ima Imr Au=C%V S=A.M.-A
21 CEMENTO PORTALND TIPO I
02 Dec.20 4,868.01 12/4/2020 324,326.18 0.111 100.00% Mar.19 Nov.20 Nov.20 423.68 423.68 423.68 540.35 540.35 323,785.83 - -
03 Jan.21 386,964.45 12/4/2020 324,326.18 0.111 100.00% Mar.19 Nov.20 Dec.20 423.68 423.68 423.68 42,953.05 42,953.05 280,832.78 - -
04 Feb.21 86,631.66 12/4/2020 324,326.18 0.111 100.00% Mar.19 Nov.20 Jan.21 423.68 423.68 423.68 9,616.11 9,616.11 271,216.67 - -
05 Mar.21 - 12/4/2020 324,326.18 0.111 100.00% Mar.19 Nov.20 Feb.21 423.68 423.68 423.68 - - 271,216.67 - -
06 Apr.21 1,444.84 12/4/2020 324,326.18 0.111 100.00% Mar.19 Nov.20 Mar.21 423.68 423.68 423.68 160.38 160.38 271,056.29 - -
07 May.21 58,740.74 12/4/2020 324,326.18 0.111 100.00% Mar.19 Nov.20 Apr.21 423.68 423.68 423.68 6,520.22 6,520.22 264,536.07 - -
08 Jun.21 222,637.89 12/4/2020 324,326.18 0.111 100.00% Mar.19 Nov.20 May.21 423.68 423.68 423.68 24,712.81 24,712.81 239,823.26 - -
09 Jul.21 240,847.40 12/4/2020 324,326.18 0.111 100.00% Mar.19 Nov.20 Jun.21 423.68 423.68 423.68 26,734.06 26,734.06 213,089.20 - -
10 Aug.21 149,852.62 12/4/2020 324,326.18 0.111 100.00% Mar.19 Nov.20 Jul.21 423.68 423.68 423.68 16,633.64 16,633.64 196,455.56 - -
11 Sep.21 142,451.04 12/4/2020 324,326.18 0.111 100.00% Mar.19 Nov.20 Aug.21 423.68 423.68 423.68 15,812.07 15,812.07 180,643.49 - -
12 Oct.21 135,045.46 12/4/2020 324,326.18 0.111 100.00% Mar.19 Nov.20 Sep.21 423.68 423.68 423.68 14,990.05 14,990.05 165,653.44 - 762.81
13 Nov.21 285,544.34 12/4/2020 324,326.18 0.111 100.00% Mar.19 Nov.20 Oct.21 423.68 423.68 445.24 31,695.42 31,695.42 133,958.02 1,612.90
〖∑𝐀〗 _𝐮=
190,368.16 = 324,326.18 〖 =𝑨.𝑴. 〗 _𝒅
Saldo por amortizar fecha base (Sin FR ni IGV)= 133,958.02 C: Continúa Deducción
Valorización Adelanto pagado Coeficiente Indices Adelanto Amortización Saldo por DQNCPAM
Mes Conocido para Indices Regularización
Monto Monto Coef. Incid F. PTO F. PAGO F. MES utilizado Amortizar D=Au x
Nº Mes Fecha A=Au*Ima/Imo de deducción
V A.M. Ci % mo ma mr Imo Ima Imr Au=C%V (Imr-Ima)/Imo
S=A.M.-A
43 MADERA NACIONAL PARA ENCOF. Y CARPINT.
02 Dec.20 4,868.01 12/4/2020 4,471.86 0.005 100.00% Mar.19 Nov.20 Nov.20 691.93 753.68 753.68 24.34 26.51 4,445.35 - 0.41
03 Jan.21 386,964.45 12/4/2020 4,471.86 0.005 100.00% Mar.19 Nov.20 Dec.20 691.93 753.68 765.25 1,934.82 2,107.49 2,337.86 32.35 59.31
04 Feb.21 86,631.66 12/4/2020 4,471.86 0.005 100.00% Mar.19 Nov.20 Jan.21 691.93 753.68 786.46 433.16 471.82 1,866.04 20.52 12.97
AMORTIZACION DEL ADELANTO DE MATERIALES Y DEDUCCION DE REINTEGRO QUE NO CORRESPONDE
OBRA REHABILITACIÓN DE PUENTES PAQUETE 3 – ANCASH (OBRAS3: PUENTE CONCHUCOS Y ACCESOS, PUENTE MAYAS Y ACCESOS, PUENTE
HUATAULIO Y ACCESOS, PUENTE GUAGUANCU Y ACCESOS, PUENTE ASTERIA Y ACCESOS)”
OBRA REHABILITACIÓN DE PUENTES PAQUETE 3 – ANCASH (OBRAS3: PUENTE CONCHUCOS Y ACCESOS, PUENTE MAYAS Y ACCESOS, PUENTE
HUATAULIO Y ACCESOS, PUENTE GUAGUANCU Y ACCESOS, PUENTE ASTERIA Y ACCESOS)”
- -
- -
- -
- -
- -
OBRA “REHABILITACIÓN DE PUENTES PAQUETES 3- ANCASH (OBRA 3: PUENTE CONCHUCOS Y ACCESOS, PUENTE HUATAULIO Y ACCESOS, PUENTE MAYAS Y ACCESOS, PUENTE GUAGUANCU Y
ACCESOS Y PUENTE ASTERIA Y ACCESOS)”
FORMULA N° 01
Val. Avance Mensual Factor de Reajuste Reajuste = V (K-1) Reajuste
No. Programada Real mes K Programada Real Mes Reconocido
Perido Regularización
reajuste
Parcial Acumulado Parcial Acumulado val Parcial Acumulado Parcial Acumulado acumulado
Reconocido
1 Nov-20 0.00 0.00 0.00 0.00 Oct-20 1.066 0.01 0.01 0.01 0.01 0.01 0.01 0.01
2 Dec-20 9,051.54 9,051.54 4,868.01 4,868.01 Nov-20 1.069 625.76 625.77 336.54 336.55 336.54 336.55 28.56
3 Jan-21 502,080.40 511,131.94 386,964.45 391,832.46 Dec-20 1.075 37,656.03 38,281.80 29,022.33 29,358.88 29,022.33 29,358.88 6,965.36
4 Feb-21 540,376.72 1,051,508.66 86,631.66 478,464.12 Jan-21 1.093 50,255.03 88,536.84 8,056.74 37,415.63 8,056.74 37,415.63 1,386.11
5 Mar-21 709,284.10 1,760,792.76 0.00 478,464.12 Feb-21 1.109 77,311.97 165,848.80 0.00 37,415.63 0.00 37,415.63 0.00
6 Apr-21 281,033.28 2,041,826.04 1,444.84 479,908.96 Mar-21 1.123 34,567.09 200,415.90 177.72 37,593.34 177.72 37,593.34 0.00
7 May-21 87,759.65 2,129,585.69 58,740.74 538,649.70 Apr-21 1.123 10,794.44 211,210.33 7,225.11 44,818.46 10,794.44 48,387.78 2,746.96
8 Jun-21 29,511.77 2,159,097.46 222,637.89 761,287.59 May-21 1.137 4,043.11 215,253.45 30,501.39 75,319.85 30,501.39 78,889.17 6,011.22
9 Jul-21 52,090.63 2,211,188.09 240,847.40 1,002,134.99 Jun-21 1.164 8,542.86 223,796.31 39,498.97 114,818.82 39,498.97 118,388.15 2,167.63
10 Aug-21 277,068.35 2,488,256.44 149,852.62 1,151,987.61 Jul-21 1.173 47,932.82 271,729.13 25,924.50 140,743.32 0.00 118,388.15 30,120.38
11 Sep-21 171,081.97 2,659,338.41 142,451.04 1,294,438.65 Aug-21 1.201 34,387.48 306,116.61 28,632.66 169,375.98 28,632.66 147,020.81 1,709.41
11 Sep-21 29,085.58 2,688,423.99 135,045.46 1,429,484.11 Sep-21 1.213 6,195.23 312,311.84 28,764.68 198,140.67 28,764.68 175,785.49 675.23
12 Oct-21 0.00 2,688,423.99 285,544.34 1,715,028.45 Oct-21 1.208 0.00 312,311.84 59,393.22 257,533.89 59,393.22 235,178.71
O B R A
REHABILITACIÓN DE PUENTES PAQUETE 3 – ANCASH (OBRAS3: PUENTE CONCHUCOS Y ACCESOS, PUENTE MAYAS Y ACCESOS, PUENTE HUATAULIO Y ACCESOS,
PUENTE GUAGUANCU Y ACCESOS, PUENTE ASTERIA Y ACCESOS)”
Coef.
Base Nov-20 Dec-20 Jan-21 Feb-21 Mar-21
Incidencia
Monomio IUP Concepto % Factor
(Ci) MARZ. 2019 Ir K Ir K Ir K Ir K Ir K
3 ACERO DE CONSTRUCCIÓN CORRUGADO 45.794 0.214 0.098 530.00 578.97 0.107 611.38 0.113 679.83 0.126 748.10 0.138 765.25 0.141
21 CEMENTO PORTLAND TIPO I 51.870 0.214 0.111 423.68 423.68 0.111 423.68 0.111 423.68 0.111 423.68 0.111 423.68 0.111
1
MADERA NACIONAL PARA ENCONFRADO Y
43 2.336 0.214 0.005 691.93 753.68 0.005 765.25 0.006 786.46 0.006 807.18 0.006 820.27 0.006
CARPINTERIA
49 MAQUINARIA Y EQUIPO IMPORTADO 90.582 0.361 0.327 308.64 342.31 0.363 342.31 0.363 344.54 0.365 347.73 0.368 354.37 0.375
2
32 FLETE TERRESTRE 9.418 0.361 0.034 471.42 486.20 0.035 490.89 0.035 490.89 0.035 490.89 0.035 495.98 0.036
3 30 DÓLAR MAS INFLACIÓN DEL MERCADO USA 100.000 0.065 0.065 486.86 547.78 0.073 546.69 0.073 550.38 0.073 555.92 0.074 568.46 0.076
4 47 MANO DE OBRA 100.000 0.171 0.171 600.40 632.89 0.180 632.89 0.180 633.53 0.180 633.53 0.180 633.53 0.180