TEMPLO AREQUIPA

PROGRAMA LOOKAHEAD

Fechas ABRIL MAYO MAYO MAYO


COD
Descripción de la Actividad Cronograma SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4
P6 COMENTARIO / RESTRICCIÓN RESPONS.
Inicio Fin L M M J V S D L M M J V S D L M M J V S D L M M J V S D
24 25 26 27 28 29 30 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21
OBRAS PROVISIONALES
ZAPATA TORRE GRÚA 26-Abr 3-May X X X X X X
MONTAJE DE LA GRÚA 10-May 11-May X X

TEMPLO AREQUIPA
MOVIMIENTO DE TIERRAS MASIVO
EXCAVACIÓN MASIVA EXTERIORES 17-Abr 16-Jun X X X X X X X X X X X X X X X X X X X X X X X
EXCAVACIÓN MASIVA TEMPLO 17-Abr 2-May X X X X X X X
EXCAVACIÓN MASIVA DORMITORIOS 25-Abr 6-May X X X X X X X X X X Se está considerando varios días
EXCAVACIÓN MASIVA CUARTOS TÉCNICOS 22-May 17-Jul

CONSTRUCCIÓN
TEMPLO
MOVIMIENTO DE TIERRAS
CIMIENTO CORRIDO (F1/F2/F3/F4/F5/F6/F7/F8) 27-Abr 20-Oct
Exc Exc. localizada 27-Abr 6-May X X X X X X X X
Api Apisonado 28-Abr 8-May X X X X X X X X
Per Perfilado 28-Abr 8-May X X X X X X X X
Sol Solado H 30-Abr 9-May X X X X X X X
Enc Encofrado solado V 1-May 10-May X X X X X X X X
Sol Solado V 2-May 12-May X X X X X X X X X X
Col Colocación de membrana 13-May 15-May X X
Tra Trazo de cimientos 16-May 17-May X X
Hab Habilitación y colocación de acero 16-May 24-May X X X X X
Con Concreto 17-May 25-May X X X X
ZAPATAS (Z1/Z2) 26-Abr 1-Jun
Exc Exc. localizada 26-Abr 29-Abr X X X X
Api Apisonado 28-Abr 2-May X X X
Per Perfilado 28-Abr 5-May X X X X X X
Sol Solado H 4-May 8-May X X X X
Enc Encofrado solado V 7-May 11-May X X X X
Sol Solado V 9-May 13-May X X X X X
MEM MEMBRANA 14-May 16-May X X
Tra Trazo 17-May 18-May X X
Hab Habilitación y colocación de acero 18-May 20-May X X X
Con Concreto Zapata 20-May 21-May X X
PILA BAUTISMAL (CC/ZB) 8-May 15-Jun
Exc Exc. localizada 8-May 10-May X X X
Api Apisonado 11-May 13-May X X X
Per Perfilado 11-May 15-May X X X X
Sol Soldado H 15-May 16-May X X
Enc Encofrado solado V 17-May 18-May X X
Sol Solado V 19-May 19-May X
MEM MEMBRANA 20-May 21-May X
Tra Trazo 23-May 24-May
Hab Habilitación y colocación de acero 24-May 27-May
Con Concreto Zapata 28-May 31-May
CONCRETO
ESTRUCTURAS
PLACAS Y MUROS PERIMETRAL 26-May 23-Jun
PLACAS Y MUROS 14-May 26-Jun
COLUMNAS CENTRALES + ASC 1-Jun 14-Jun
LOSA DE PISO 23-Jun 20-Oct
LOSAS DE ALUCUBETAS 5-Jul 8-Jul
COLUMNAS, PLACAS Y MUROS 14-Jul 14-Ago
LOSAS DE ALUCUBETAS 27-Jul 31-Ago
COLUMNAS, PLACAS Y MUROS 8-Ago 6-Set
LOSAS DE ALUCUBETAS 29-Ago 22-Set
COLUMNAS, PLACAS Y MUROS 8-Set 27-Set
LOSAS DE ALUCUBETAS 26-Set 17-Set
PARAPETOS 12-Set 18-Oct

Página 1
TEMPLO AREQUIPA

PROGRAMA LOOKAHEAD

Fechas ABRIL MAYO MAYO MAYO


COD
Descripción de la Actividad Cronograma SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4
P6 COMENTARIO / RESTRICCIÓN RESPONS.
Inicio Fin L M M J V S D L M M J V S D L M M J V S D L M M J V S D
24 25 26 27 28 29 30 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21
DORMITORIOS
MOVIMIENTO DE TIERRA
CIMIENTO CORRIDO (F1/F2/F3/F4/F5/F6/F7/F8) 8-May 14-Jun
Exc Exc. localizada 8-May 17-May X X X X X X X X X
Api Apisonado 9-May 19-May X X X X X X X X X X
Per Perfilado 9-May 19-May X X X X X X X X X X
Ins Instalaciones 11-May 20-May X X X X X X X X X
Sol Solado H 12-May 21-May X X X X X X X X
Enc Enc. De solado vertical 13-May 23-May X X X X X X X
Sol Solado V 24-May 26-May
Col Colocación de membrana 27-May 28-May
Tra Trazo de cimientos 27-May 4-Jun
Hab Habilitación y colocación de acero 28-May 5-Jun
Con Concreto
ESTRUCTURAS
PLATEA CISTERNA 21-Jun 11-Jul
PLACAS Y MUROS CISTERNA 28-Jun 12-Jun
TECHO DE CISTERNA 12-Jun 27-Jul
COLUMNAS, PLACAS Y MUROS 5-Jun 6-Jul
LOSA DE PISO 6-Jul 6-Oct
LOSAS MACIZA 17-Jul 10-Ago
COLUMNAS, PLACAS Y MUROS 26-Jul 28-Ago
LOSAS MACIZA 14-Ago 6-Set
COLUMNAS, PLACAS Y MUROS 22-Ago 22-Set
LOSAS MACIZA 11-Set 3-Oct
PARAPETOS 21-Set 5-Oct
BLOQUETAS DE CONCRETO 26-Set 20-Oct
EXTERIORES
INSTRUCCIONES DE OBRA

ELABORADO POR:
NOMBRE: Luis Héctor Muñoz Guevara
CARGO: Ing. Producción
REV: Ing. César Jurado