Nombre Duracion Inicio Terminado Predece.. Nombres del Re.. VSDL MMJ VSDL MMJ VSDL MMJ VSDL MMJ VSDL MMJ VSDL MMJ VSDL MMJ VSDL MMJ VSDL MMJ VSDL MMJ VSDL MMJ VSDL MMJ VSDL MMJ VS
1 CLARIFICADORES PRIMARIOS 45 days 15/01/18 08:0... 15/03/18 05:00 ...
2 TANQUE 57.1 32 days 15/01/18 08:0... 26/02/18 05:00 ...
3 ACERO LOSA DE FONDO 18 days 15/01/18 08:00 ... 6/02/18 05:00 PM
4 ENCOFRADO LOSA DE FONDO 12 days 2/02/18 08:00 AM 16/02/18 05:00 PM 3FS-4 . .
5 VERTIDO CONCRETO LOSA DE FONDO FASE 1 2 days 19/02/18 08:00 ... 20/02/18 05:00 PM 4
6 DESENCOFRADO LOSA DE FONDO FASE 1 4 days 21/02/18 08:00 ... 26/02/18 05:00 PM 5
7 CONSTRUCCIÒN DIAFRAGMA 39 days 16/01/18 08:0... 8/03/18 05:00 PM
8 ACERO VIGA DIAFRAGMA 5 days 16/01/18 08:00 ... 22/01/18 05:00 PM
9 ENCOFRADO VIGA 2 days 23/01/18 08:00 ... 24/01/18 05:00 PM 8
10 CONCRETO VIGA 1 day 25/01/18 08:00 ... 25/01/18 05:00 PM 9
11 DESENCOFRADO VIGAS 2 days 26/01/18 08:00 ... 29/01/18 05:00 PM 10
12 ACERO PILASTRAS DIAFRAGMA 4 days 30/01/18 08:00 ... 2/02/18 05:00 PM 11
13 ENCOFRADO PILASTRAS 2 days 3/02/18 08:00 AM 5/02/18 05:00 PM 12
14 VERTIDO PILASTRAS 1 day 6/02/18 08:00 AM 6/02/18 05:00 PM 13
15 COLOCACIÒN CODO 2 days 7/02/18 08:00 AM 8/02/18 05:00 PM 14
16 ACERO MURO DIAFRAGMA 4 days 9/02/18 08:00 AM 14/02/18 05:00 PM 15
17 ENCOFRADO MURO DIAFRAGMA-FASE 1 2 days 15/02/18 08:00 ... 16/02/18 05:00 PM 16
18 VERTIDO CONCRETO MURO-FASE 1 1 day 19/02/18 08:00 ... 19/02/18 05:00 PM 17
19 DESENCOFRADO MURO-FASE 1 2 days 20/02/18 08:00 ... 21/02/18 05:00 PM 18
20 ENCOFRADO PERDIDO DIAFRAGMAS FASE 2 3 days 22/02/18 08:00 ... 26/02/18 05:00 PM 19
21 VERTIDO DE CONCRETO DIAFRAGMAS FASE-2 1 day 27/02/18 08:00 ... 27/02/18 05:00 PM 20
22 VERTIDO CONCRETO DE LOSA EN ZONA CODO-FASE 2 2 days 28/02/18 08:00 ... 1/03/18 05:00 PM 21
23 RELLENO ZONA DIAFRAGMA 5 days 2/03/18 08:00 AM 8/03/18 05:00 PM 22
24 Construccion losa fase 2 (zona diafragma) 10 days 2/03/18 08:00... 15/03/18 05:00 ...
25 CONCRETO LIMPIEZA FASE 2 1 day 2/03/18 08:00 AM 2/03/18 05:00 PM 22
26 COLOCACIÒN ACERO FASE 2 4 days 5/03/18 08:00 AM 8/03/18 05:00 PM 25
27 ENCOFRADO LOSA FASE 2 2 days 9/03/18 08:00 AM 12/03/18 05:00 PM 26
28 VERTIDO CONCRETO FASE 2 1 day 13/03/18 08:00 ... 13/03/18 05:00 PM 27
29 DESENCOFRADO FASE 2 2 days 14/03/18 08:00 ... 15/03/18 05:00 PM 28
30 TANQUE 57.2 30 days 15/01/18 08:0... 22/02/18 05:00 ...
31 ACERO LOSA DE FONDO 30 days 15/01/18 08:00 ... 22/02/18 05:00 PM