PSTO N° 2023 - 056

PROYECTO : CASCO PRIMER NIVEL


CLIENTE : VARIOS
UBICACIÓN : PIURA
CONSTRUCTOR : CALIXTO SILVA
CELULAR :
RUC:
Item Descripción Unidad Cantidad Precio Sub Total
1.00 MANO DE OBRA S/ 10,095.00
01.01 CIMENTACION ML 31.00 S/ 80.00 S/ 2,480.00
01.02 ZAPATAS UND 11.00 S/ 200.00 S/ 2,200.00
01.03 SOBRECIMIENTO ML 21.00 S/ 40.00 S/ 840.00
01.04 COLUMNAS DE PRIMER PISO UND 11.00 S/ 200.00 S/ 2,200.00
01.05 MUROS KK 18 H MILL 2.50 S/ 750.00 S/ 1,875.00
01.06 III.SS.1DO PISO MONTANTES GBL 1.00 S/ 250.00 S/ 250.00
01.07 III.EE.1DO PISO MONTANTES GBL 1.00 S/ 250.00 S/ 250.00
TOTAL MANO DE OBRA S/ 10,095.00

2.00 MATERIALES GLOBAL S/ 13,020.00


02.01 CEMENTO AZUL BLS 95.00 S/ 32.00 S/ 3,040.00
02.02 CEMENTO ROJO BLS 25.00 S/ 30.00 S/ 750.00
02.03 HORMIGON M3 20.00 S/ 70.00 S/ 1,400.00
02.03 PIEDRA PILCA M3 10.00 S/ 70.00 S/ 700.00
02.03 ARENA GRUESA M3 9.00 S/ 60.00 S/ 540.00
02.04 PIEDRA CONFITILLO 1/2" M3 4.00 S/ 70.00 S/ 280.00
02.05 LADRILLO KK UND 2500.00 S/ 0.75 S/ 1,875.00
02.07 FIERRO DE 1/2" VAR 50.00 S/ 41.00 S/ 2,050.00
02.08 FIERRO DE 3/8" VAR 26.00 S/ 25.00 S/ 650.00
02.09 FIERRO DE 1/4" VAR 20.00 S/ 10.00 S/ 200.00
02.10 CLAVOS DE 2 " KG 5.00 S/ 7.00 S/ 35.00
02.11 CLAVOS DE 2 1/2" KG 10.00 S/ 7.00 S/ 70.00
02.12 CLAVOS DE 3" KG 5.00 S/ 7.00 S/ 35.00
02.13 ALAMBRE 16 KG 30.00 S/ 7.00 S/ 210.00
02.14 ALAMBRE 8 KG 20.00 S/ 7.00 S/ 140.00
02.15 DISCO DE CORTE DE FIERRO 7 " UND 5.00 S/ 9.00 S/ 45.00
02.16 IIEE GBL 1.00 S/ 500.00 S/ 500.00
02.17 IISS GBL 1.00 S/ 500.00 S/ 500.00
TOTAL MATERIALES S/ 13,020.00

TOTAL MANO DE OBRA S/ 10,095.00


TOTAL MATERIALES S/ 13,020.00
TOTAL GASTOS ( SIN IGV ) S/ 23,115.00