W= 5.925 Tn
qa= 10 Tn/m2
Pp= 7.5 %
f'c= 210 kg/cm2
fy= 4200 kg/cm2
Secc col= 30 cm
Pt = W + Pp (W)
Pt = 5.925 + 0.075 5.925
Pt = 6.369 Tn
Ac = Pt / qa
Ac = 6.369375 / 10
Ac = 0.637 m2
L = = 0.80 m
L = 1.00 m
Ac real = 1 * 1
Ac real = 1.000 m2
Pu = 1.7 * W
Pu = 1.7 * 5.925
Pu = 10.073 Tn
qe = Pu / Ac real
qe = 10.0725 / 1
qe = 10 Tn/m2
qe = 10.0725 * 1
qe = 10 Tn/m
L - Secc col
x=
2
1 - 0.3
x= = 0.35 m
2
10.0725 * 0.1225
M= = 0.617 Tn-m
2
Mu
d=
φKu * b
61.694
d= = 4.293 cm
0.03348 * 100
d= 15 cm
r= 5 cm
h= 20 cm
Ap = 1 - 0.45 * 0.45
Ap = 0.798 m2
bo = d + Secc Col * 4
bo = 0.15 + 0.3 * 4
Vp = qe * Ap
Vp = 10.0725 * 0.7975
Vp = 8.033 Tn
8.03281875
vp = = 30 Tn/m2
1.8 * 0.15
vp = 2.98 kg/cm2
Vv
vv =
bo * d
200
vv = = 0.07 kg/cm2
180 * 15
Vc = φ * 0.53 f'c
Vc = 0.85 * 0.53 210
Vc = 6.53 kg/cm2
Mu
As =
φAu * d
61.6940625
As = = 1.23 cm2
3.334 * 15
Pmin = 14 / fy
Pmin = 0.0033333333
As min = Pmin * b * d
As min = 0.0033333333 * 100 * 15
As min = 5.00 cm2
* Armado de la Zapata
φ = 12 mm
A varilla = 1.13 cm2
# varillas = As / Av
# varillas = 5 / 1.131
# varillas = 4
1 φ 12 @ 25 cm
= 1.80 m
Vpc > vp
13.057 > 2.975
Si Cumple
- d
- 0.15
Vc > vv
6.528 > 0.074
Si Cumple