ID Task

Task Name Duration Start Finish Predecessors


Resource Names
Mode
Jul 16, '23 Jul 23, '23 Jul 30, '23 Aug 6, '23 Aug 13, '23 Aug 20, '23
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
1 1 PROYECTO DE ARMADO - DR412i 734223 32.5 daysMon 7/17/23 Fri 8/18/23
2 1.1 INICIO DE PROYECTO 0 days Mon 7/17/23 Mon 7/17/23 7/17
3 1.2 PREARMADO 4 days Mon 7/17/23 Thu 7/20/23
4 1.2.1 Preparación de zona de armado, instalación de geomembrana donde se 4 hrs Mon 7/17/23 Mon 2 SE1 SE2 SFS1000 SLID SE1 SE2 SFS1000 SLID SM1
ubicara el chasis principal 7/17/23 SM1

5 1.2.2 Alistar, aproximar tacos armados de 1.20 Mts y 1:00 Mts. Para descanso de 4 hrs Mon 7/17/23 Mon 4 MONTCGA1(16TON) MONTCGA1(16TON) SE1 SE2 SFS1000 SLID SM1
chasis principal delimitación de todo el area de armado 7/17/23 SE1 SE2 SFS1000 SLID
SM1
6 1.2.3 Recepción, descarga, ubicación de Chasis principal, Mástil, tren de rodamientos
12 hrs Tue 7/18/23 Wed 7/19/23 5 GRUA1(90TON) GRUA2(90TON) SE1 GRUA1(90TON) GRUA2(90TON) SE1 SE2 SFS1000 SLID SM1
SE2 SFS1000 SLID SM1
7 1.2.4 Recepción, descarga, ubicación de accesorios (pasadizos, barandas, escaleras8 hrs Wed 7/19/23 Thu 7/20/23 6 MONTCGA1(16TON)
MONTCGA1(16TON) SE1 SE2 SFS1000 SLID SM1 SE1 SE2 SFS1000 SLID SM1
8 1.2.5 FIN PREARMADO 0 days Thu 7/20/23 Thu 7/20/23 7 7/20
9 1.3 ARMADO 16.5 days Fri 7/21/23 Sun 8/6/23
10 1.3.1 Preparación, montaje ajuste instalación de tren de rodamientos Izquierdo 8 hrs Fri 7/21/23 Fri 7/21/23 8 SE1 SM1 MONTCGA1(16TON) SE1 SM1 MONTCGA1(16TON)
11 1.3.2 Preparación, montaje ajuste instalación de tren de rodamientos Derecho 8 hrs Fri 7/21/23 Fri 7/21/23 8 SE2 SFS1000 SLID SE2 SFS1000 SLID
12 1.3.3 Montaje Ajuste de pasadizo lado derecho de cabina, 4 hrs Sat 7/22/23 Sat 7/22/23 10 SE1 MONTCGA1(16TON) SM1 SE1 MONTCGA1(16TON) SM1
13 1.3.4 Montaje ajuste de pasadizo posterior a Cabina de operador 4 hrs Sat 7/22/23 Sat 7/22/23 11 SE2 SLID SFS1000 SE2 SLID SFS1000
14 1.3.5 Montaje ajuste instalación de Escalera de acceso a Cabina de Operador 2 hrs Sat 7/22/23 Sat 7/22/23 12 SE1 MONTCGA1(16TON) SM1 SE1 MONTCGA1(16TON) SM1
15 1.3.6 Montaje instaalción de barandas posterior Izquierdo 2 hrs Sat 7/22/23 Sat 7/22/23 13 SE2 SLID SFS1000 SE2 SLID SFS1000
16 1.3.7 Montaje ajuste instalación mangueras cables de pasadizos y barandas del 4 hrs Sat 7/22/23 Sun 7/23/23 14 SE1 SE1 MONTCGA1(16TON) SM1
derecho, MONTCGA1(16TON)
SM1
17 1.3.8 Montaje instalación de mangueras cableas pasadizo delantero izquierdo 4 hrs Sat 7/22/23 Sun 7/23/23 15 SE2 SLID SFS1000 SE2 SLID SFS1000
18 1.3.9 Montaje instalación regulación de escalera posterior izquierdo 2 hrs Sun 7/23/23 Sun 7/23/23 16 SE1 MONTCGA1(16TON) SM1 SE1 MONTCGA1(16TON) SM1
19 1.3.10 Montaje instalación regulación de escalera delantero izquierdo 2 hrs Sun 7/23/23 Sun 7/23/23 17 SE2 SLID SE2 SLID
20 1.3.11 Cambio de juego de partes por cambio de diametro columna de 0 hrs Sun 7/23/23 Sun 7/23/23 18 7/23
perforación en mastil

21 1.3.12 Montaje ajuste de cabina en lugar correspondiente, instalación de 8 hrs Sun 7/23/23 Mon 19 SE2 SLID SE2 SLID
mangueras cableado en su totalidad 7/24/23

22 1.3.13 Instaalción de sistema contra incendios (FS1000) 80 hrs Sun 7/23/23 Wed 8/2/23 17 SFS1000 SOLD1 SFS1000 SOLD1
23 1.3.14 Revisión de equipo, arranque, bajar equipo de los tacos haciendo uso de los 4gatos
hrs Mon 7/24/23 Mon 7/24/23 21 SE2 SLID SE2 SLID
24 1.3.15 Pruebas de actuadores, purgado de sistemas hidráulicos 4 hrs Tue 7/25/23 Tue 7/25/23 23 SE2 SLID SE2 SLID
25 1.3.16 Preparación de mástil para su montaje (bancadas, puños para cilindros) 8 hrs Sun 7/23/23 Mon 18 SE1 SM1 SE1 SM1
reajustar perneria, 7/24/23

26 1.3.17 Instaalción de tableros electricos, cableado, luminarias camaras de video, 8 hrs Tue 7/25/23 Wed 24 SE2 SLID SE2 SLID
paradas de emergencia, preparar chasis para recibir al mástil 7/26/23

27 1.3.18 Montaje ajuste de mástil, instalación de mangueras cables electricos, 16 hrs Wed 7/26/23 Fri 7/28/23 26 GRUA1(90TON) GRUA2(90TON) SE1 SE2 SLID SM1 GRUA1(90TON) GRUA2(90TON) SE1 SE2 SLID SM1
28 1.3.19 Prueba de recorrido, descanso de mástil, nivelar, configurar, 8 hrs Fri 7/28/23 Sat 7/29/23 27 SE1 SM1 SE1 SM1

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline

Milestone Inactive Summary Start-only Critical

Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 1
ID Task
Task Name Duration Start Finish Predecessors
Resource Names
Mode
Jul 16, '23 Jul 23, '23 Jul 30, '23 Aug 6, '23 Aug 13, '23 Aug 20, '23
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
29 1.3.20 Montaje instalación de antenas de GPS (03 Un) 8 hrs Fri 7/28/23 Sat 7/29/23 27 SM2 SE2 SM2 SE2
30 1.3.21 Cambio de llave mordaza por llave "U" alojamiento de bocina de mesa 0 hrs Sat 7/29/23 Sat 7/29/23 28 7/29
de perforación, porta postizos de PBO

31 1.3.22 Montaje ajuste de campana de perforación, faldon de campana 8 hrs Sat 7/29/23 Sun 7/30/23 28 SE1 SM1 SE1 SM1
32 1.3.23 Instalación de equipo de sonido en cabina de operador 8 hrs Sat 7/29/23 Sun 7/30/23 29 SM2 SE2 SM2 SE2
33 1.3.24 Instalación de limpiadores de polvo de campana de perforación 4 hrs Sun 7/30/23 Sun 7/30/23 31 SE1 SM1 SE1 SM1
34 1.3.25 Inspección final de armado ajustes reajustes, 8 hrs Sun 7/30/23 Mon 7/31/23 32 SE2 SLID SE2 SLID
35 1.3.26 Cambio de aciete de tanque hidráulico y compresor, revisión rellenado de 8 hrs Mon 7/31/23 Tue 8/1/23 34 SE1 SE2 SM1 LUB1 SE1 SE2 SM1 LUB1
todos los fluidos, incio de pruebas de equipo

36 1.3.27 Pruebas de todos los sistemas de la perforadora, sin la columna de 16 hrs Tue 8/1/23 Thu 8/3/23 35 SE1 SE2 SM1 SE1 SE2 SM1
perforación, ajustes, regulaciones, configuración de todos los sistemas

37 1.3.28 Cargar la columna de perforación, asegurar con soldadura, fabricar e 8 hrs Thu 8/3/23 Fri 8/4/23 36 SE1 SE2 SM1 SE1 SE2 SM1
instalar tope inferior mecanico de avance

38 1.3.29 Prueba de todos los sistemas incluyendo perforación ajustes regulaciones 16 hrs Fri 8/4/23 Sun 8/6/23 37 SE1 SE2 SM1 SE1 SE2 SM1
39 1.3.30 FIN ARMADO 0 days Sun 8/6/23 Sun 8/6/23 38 22 25 33 8/6
40 1.4 ARRANQUE INICIAL 7 days Sun 8/6/23 Sun 8/13/23
41 1.4.1 Practicas de perforación ajustes regulaciones seguimiento 8 hrs Sun 8/6/23 Mon 8/7/23 38 SE1 SE1
42 1.4.2 Arranque incial de Motor Diesel Mantenimeinto de las primeras 50 horas del 8 hrs Mon 8/7/23 Tue 8/8/23 41 SE1 MEC1SM SE1 MEC1SM
equipo

43 1.4.3 Entrega de equipo a SMCG para instaalción de MINESENSE Radio de 16 hrs Tue 8/8/23 Thu 8/10/23 42 ELECT1SM SE1 SOLD1 ELECT1SM SE1 SOLD1
comunicación, cintas reflectivas y codificación

44 1.4.4 Traslado de perforadora a zona de trabajo, inicio de operaciones monitoreo 8 hrs Thu 8/10/23 Fri 8/11/23 43 SE1 SE1
seguimiento

45 1.4.5 Seguimiento de equipo en trabajo, 8 hrs Fri 8/11/23 Sat 8/12/23 44 SE1 SE1
46 1.4.6 Seguimiento toma de parametros de trabajo entrega del equipo a 8 hrs Sat 8/12/23 Sun 8/13/23 45 SE1 SE1
operacioens

47 1.4.7 FIN ARRANQUE INICIAL 0 days Sun 8/13/23 Sun 8/13/2346 8/13
48 1.5 ENTRENAMIENTO DE OPERADORES 17 days Tue 8/1/23 Fri 8/18/23
49 1.5.1 Entrenamiento teórico de operación de perforadora DR412i 1er grupo 8 hrs Tue 8/1/23 Wed 8/2/23 35 SLID SLID
50 1.5.2 Entrenamiento práctico de operadores 40 hrs Wed 8/2/23 Mon 8/7/23 49 SLID SLID
51 1.5.3 Entrenamiento teórico de operación de perforadora DR412i 2do grupo 8 hrs Mon 8/7/23 Tue 8/8/23 50 SLID SLID
52 1.5.4 Entrenamiento Práctico de operadores en campo 64 hrs Thu 8/10/23 Fri 8/18/23 51 43 SLID SLID
53 1.5.5 FIN ENTRENAMIENTO DE OPERADORES 0 days Fri 8/18/23 Fri 8/18/23 52 8/18
54 1.6 FIN DE PROYECTO 0 days Fri 8/18/23 Fri 8/18/23 8 39 53 47 8/18

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline

Milestone Inactive Summary Start-only Critical

Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress