Implementación de Nodo 12
ID Task Name Duration Start Finish Cost Qtr 1, 2020 Qtr 3, 2020 Qtr 1, 2021 Qtr 3, 2021
Sep Nov Jan Mar May Jul Sep Nov Jan Mar May Jul
1 Proyecto: Red Dorsal Nacional Tumbes - Implementación de Nodo 360 days Wed 16/10/19 Tue 2/03/21 S/.9,401,350.00
- Anillo 12
7 H6: Obtencióm de Permisos y Autorización Completas 0 days Tue 31/03/20 Tue 31/03/20 S/.0.00 31/03
54 Prueba General de Nodos 178 days Thu 25/06/20 Mon 1/03/21 S/.40,000.00
Project: PM 2020 Sector Costa Task Milestone Project Summary Rolled Up Task Rolled Up Milestone External Tasks Inactive Task Inactive Summary Duration-only Manual Summary Finish-only Critical Task Critical Split
Date: Sun 13/03/22 Split Summary Group By Summary Rolled Up Critical Task Rolled Up Progress External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start-only Deadline Critical Progress