Está en la página 1de 7

SERVIU REGIÓN DE LA ARAUCANÍA

ESTADO DE
AVANCE Nº 30

MANDANTE: COMITÉ BICENTENARIO II FECHA E. AVANCE 26-May-23

COMUNA: PADRE DE LAS CASAS AVANCE MEDIDO AL 26-May-23

Avance Actual Total pte. E.P. % Avance


CONCEPTO Cant. P. Unit. Total UF Avance Anterior UF
UF UF E.P.

Pago CNT 159 1,200.83 190,932.39 188,727.40 181,385.353 7,342.05 3.845%

98.845% 95.00% 3.85% 3.845%

TOTAL CONTRATO U.F. 159 1,200.83 190,932.39 3.845%

TOTAL
Pte. Estado de AVANCE 7,342.05

Empresa Constructora BIO BIO

CHRISTIAN SCHULZ GARRIDO VICTOR AGURTO ELIAS


F.T.O. SAT SERVIU
SERVIU REGIÓN DE LA ARAUCANÍA

CUADRO CONTROL DE AVANCES POR PARTIDA M3


OBRA : COMITÉ DE VIVIENDA BICENTENARIO II

COMUNA : PADRE LAS CASAS VERSION 2


CONTRATISTA : BIO BIO

E.P / EGIS : DOBLE V

F.T.O. : CHRISTIAN SCHULZ GARRIDO FECHA 26-May-23


S.A.T SERVIU : VICTOR AGURTO E

5
SALDO A PAGAR EN PRESENTE
EJECUTADO A LA FECHA EJECUTADO AL E.P. ANTERIOR
ITEM DESIGNACION UNIDAD CANTIDAD PRECIO UNITARIO TOTAL E.P.
CANT TOTAL CANT TOTAL CANT TOTAL

A.- OBRAS PRELIMINARES Y COMPLEMENTARIAS


A.1 INSTALACION DE FAENAS Y OBRAS PRELIMINARES
A.1.1 Construcciones provisorias n° 1.00 486.47 486.47 1.00 486.47 1.00 486.47 0.00 0.000
A.1.2 Empalmes y conexiones provisorias n° 1.00 38.78 38.78 1.00 38.78 1.00 38.78 0.00 0.000
A.1.3 Despeje de terreno n° 1.00 37.86 37.86 1.00 37.86 1.00 37.86 0.00 0.000
A.1.4 Cierros provisorios ml 1176.47 0.23 265.43 1,176.47 265.43 1,176.47 265.43 0.00 0.000
A.1.5 Señalización provisoria % 100.00 0.94 93.79 95.00 89.10 88.00 82.53 7.00 6.565
A.1.6 Nivelación y replanteo n° 1.00 326.35 326.35 1.00 326.35 1.00 326.35 0.00 0.000
A.2 OBRAS COMPLEMENTARIAS
A.2.1 Letreros de obra n° 1.00 45.20 45.20 1.00 45.20 1.00 45.20 0.00 0.000
A.2.2 Aseo y entrega % 100.00 4.31 431.22 95.00 409.66 88.00 379.47 7.00 30.185
A.2.3 Retiro de escombros % 100.00 2.79 278.78 95.00 264.84 88.00 245.32 7.00 19.514
A.3 CONTROL CALIDAD OBRAS (ENSAYOS)
A.3.1 Suelos
A.3.1.1 Proctor n° 2.00 1.36 2.71 2.00 2.71 2.00 2.71 0.00 0.000
A.3.1.2 CBR o Densidad relativa n° 2.00 1.36 2.71 2.00 2.71 2.00 2.71 0.00 0.000
A.3.1.4 Densidad máxima compactada seca n° 2.00 2.19 4.38 2.00 4.38 2.00 4.38 0.00 0.000
A.3.2 Madera
A.3.2.1 Impregnación n° 2.00 0.51 1.02 2.00 1.02 2.00 1.02 0.00 0.000
A.3.2.2 Grado estructural n°
A.3.3 Hormigón
A.3.3.1 R Compresión n° 4.00 3.95 15.82 4.00 15.82 4.00 15.82 0.00 0.000
A.3.7 SUB BASE, BASE O MEJORAMIENTO
A.3.7.1 Proctor n° 3.00 0.44 1.32 3.00 1.32 3.00 1.32 0.00 0.000
A.3.7.5 Densidad máxima compactada seca n° 3.00 0.10 0.30 3.00 0.30 3.00 0.30 0.00 0.000
A.3.10 Aceras
A.3.10.1 R. compresión n° 2.00 0.78 1.56 2.00 1.56 0.00 0.00 2.00 1.560
A.3.10.2 Espesor n° 2.00 0.14 0.27 2.00 0.27 0.00 0.00 2.00 0.271
A.3.11 Soleras
A.3.11.1 R Compresión n° 2.00 0.78 1.56 2.00 1.56 2.00 1.56 0.00 0.000
A.3.11.2 Impacto n° 2.00 0.14 0.27 2.00 0.27 2.00 0.27 0.00 0.000
A.3.12 Calzadas hormigón
A.3.12.1 Compresión n° 2.00 0.78 1.56 2.00 1.56 2.00 1.56 0.00 0.000
A.3.12.3 Espesor n° 2.00 0.81 1.63 2.00 1.63 2.00 1.63 0.00 0.000
SUBTOTAL 2,038.98 1998.79 1940.69 58.10

B OBRA GRUESA
B.1 FUNDACIONES
B.1.1 Replanteo, trazado y niveles VIV. 159.00 0.40 63.65 159.00 63.65 159.00 63.65 0.00 0.000
B.1.2 Excavación VIV. 159.00 13.05 2,074.53 159.00 2,074.53 159.00 2,074.53 0.00 0.000
B.1.3 Emplantillado VIV. 159.00 1.49 237.31 159.00 237.31 159.00 237.31 0.00 0.000
B.1.4 Hormigón cimientos VIV. 159.00 12.93 2,055.34 159.00 2,055.34 159.00 2,055.34 0.00 0.000
B.1.5 Hormigón sobrecimientos VIV. 159.00 4.65 739.22 159.00 739.22 159.00 739.22 0.00 0.000
B.1.6 Enfierradura Fundaciones VIV. 159.00 13.22 2,102.56 159.00 2,102.56 159.00 2,102.56 0.00 0.000
B.1.7 Moldajes VIV. 159.00 5.47 870.26 159.00 870.26 159.00 870.26 0.00 0.000
B2 RADIER
B.2.1 Base (Cama de ripio) 8 cms VIV. 159.00 10.24 1,627.81 159.00 1,627.81 159.00 1,627.81 0.00 0.000
B.2.2 Hormigón e= 7 cm VIV. 159.00 23.24 3,695.13 159.00 3,695.13 159.00 3,695.13 0.00 0.000
B3 MUROS 1° PISO
B.3.3 Madera
B.3.3.1 Entramado estructural VIV. 159.00 47.19 7,502.46 159.00 7,502.46 159.00 7,502.46 0.00 0.000
B.3.3.2 Entramado Tabiques VIV. 159.00 6.07 965.12 159.00 965.12 159.00 965.12 0.00 0.000
B.4 ENTREPISO
B.4.4 Entramados
B.4.4.1 Madera VIV. 11.00 5.70 62.71 11.00 62.71 11.00 62.71 0.00 0.000
B.4.4.4 Placa piso VIV. 11.00 4.05 44.59 11.00 44.59 11.00 44.59 0.00 0.000
B5 MUROS 2 piso
B.5.3 Madera
B.5.3.1 Entramado Estructural VIV. 11.00 17.16 188.71 11.00 188.71 11.00 188.71 0.00 0.000
B.5.3.2 Entramado de tabique VIV. 11.00 3.37 37.10 11.00 37.10 11.00 37.10 0.00 0.000
B.6.1 Estructura (inc. Costaneras)
B.6.1.1 Madera (estructura Tech. Incl. Costaneras) VIV. 159.00 5.27 837.44 159.00 837.44 159.00 837.44 0.00 0.000
B.6.2 CUBIERTA (inc. Cumbreras)
B.6.2.1 Acero galvanizado VIV. 159.00 13.84 2,200.43 159.00 2,200.43 159.00 2,200.43 0.00 0.000
B.6.3 Hojalatería
B.6.3.1 Canales y forros
B.6.3.1.A canal adosado VIV. 159.00 1.65 262.32 159.00 262.32 159.00 262.32 0.00 0.000
B.6.3.1.B canal larga VIV. 159.00 0.99 157.39 159.00 157.39 159.00 157.39 0.00 0.000
B.6.3.1.C forro coronacion VIV. 159.00 0.66 104.93 159.00 104.93 159.00 104.93 0.00 0.000
B.6.3.2 Bajadas VIV. 159.00 1.53 242.53 159.00 242.53 159.00 242.53 0.00 0.000
B. EXTRAS PARTIDAS DE O. GRUESA AGREGADAS POR LA EMP.
B.EX.1 Forros 0.00 0.000
B.EX.1.A puertas, ventanas, perfil de inicio y perfil J VIV. 159.00 3.54 563.45 159.00 563.45 159.00 563.45 0.00 0.000
B.EX.1.B esquineros VIV. 159.00 0.39 62.61 159.00 62.61 159.00 62.61 0.00 0.000
B.EX.2 Aislación térmica de sobrecimiento VIV. 159.00 1.17 186.32 159.00 186.32 157.00 183.97 2.00 2.344
SUBTOTAL 26,883.93 26883.93 26881.58 2.34
24,742.73 16475.516

C OBRAS DE TERMINACION
C1 REVESTIMIENTOS MUROS Y TABIQUES
C.1.1 Exterior
C.1.1.3 madera placas VIV. 159.00 15.24 2,422.54 159.00 2,422.54 159.00 2,422.54 0.00 0.000
C.1.1.5 Sidding VIV. 159.00 23.07 3,668.42 159.00 3,668.42 159.00 3,668.42 0.00 0.000
C.1.2 Interior zona seca
C.1.2.2 Yeso cartón VIV. 159.00 21.10 3,354.78 159.00 3,354.78 159.00 3,354.78 0.00 0.000
C.1.2.2.1 Yeso cartón adosamiento VIV. 159.00 4.14 657.84 159.00 657.84 159.00 657.84 0.00 0.000
C.1.3 Interior zona húmeda
C.1.3.2 Fibrocemento VIV. 159.00 10.86 1,726.31 159.00 1,726.31 159.00 1,726.31 0.00 0.000
C2 AISLACION TERMICA MUROS (INCLUYE BARREAS DE
C.2.3 HUMEDAD Y VAPOR)
Lana vidrio e= 100 mm VIV. 159.00 3.85 612.76 159.00 612.76 159.00 612.76 0.00 0.000
C3 CIELO
C3.2 Estructura cielo falso
C.3.2.1 Madera VIV. 159.00 6.32 1,004.89 159.00 1,004.89 159.00 1,004.89 0.00 0.000
C.3.3 Revestimiento zona seca
C.3.3.1 Yeso cartón VIV. 159.00 8.38 1,331.99 159.00 1,331.99 159.00 1,331.99 0.00 0.000
C.3.4 Revestimiento zona húmeda
C.3.4.1 Fibrocemento VIV. 159.00 3.22 511.86 159.00 511.86 159.00 511.86 0.00 0.000
C.4 Aislacion térmica cubierta
C.4.3 Lana de vidrio e= 150 mm VIV. 159.00 6.28 998.47 159.00 998.47 159.00 998.47 0.00 0.000
C.5 REVESTIMIENTO PISOS
C.5.1 Cerámica VIV. 159.00 5.16 819.85 159.00 819.85 136.00 701.25 23.00 118.594
C.5.3 Cubrepiso VIV. 159.00 0.21 33.65 159.00 33.65 52.00 11.01 107.00 22.647
C 7 ESCALERA INTERIOR
C.7.1 Escalera(estructura, peldaños, baranda y pasamanos) VIV. 11.00 7.25 79.80 11.00 79.80 0.00 0.00 11.00 79.801
C8 ALEROS Y FRONTONES
C.8.1 Estructura
C.8.1.1 Madera VIV. 159.00 6.14 976.62 159.00 976.62 159.00 976.62 0.00 0.000
C.8.2 Revestimiento
C.8.2.4 Fibrocemento VIV. 159.00 3.25 516.83 159.00 516.83 159.00 516.83 0.00 0.000
C.8.2.5 sidding VIV. 159.00 4.00 635.80 159.00 635.80 159.00 635.80 0.00 0.000
C.8.3 Rejillas de ventilacion VIV. 159.00 0.89 141.93 159.00 141.93 151.00 134.79 8.00 7.141
C.8.3.1 Celosia de ventilación regulable VIV. 159.00 5.57 885.18 159.00 885.18 159.00 885.18 0.00 0.000
C.8.4 Tapacan VIV. 159.00 5.66 900.18 159.00 900.18 159.00 900.18 0.00 0.000
C.9 PUERTAS Y VENTANAS
C.9.1 Marcos
C.9.1.1 Madera VIV. 159.00 3.11 494.55 159.00 494.55 159.00 494.55 0.00 0.000
C.9.2 Puertas interiores
C.9.2.1 Puerta ancho 70 N 463.00 2.83 1,307.98 463.00 1,307.98 463.00 1,307.98 0.00 0.000
C.9.2.3 Puerta ancho 80 N 19.00 3.16 60.12 19.00 60.12 19.00 60.12 0.00 0.000
SALDO A PAGAR EN PRESENTE
EJECUTADO A LA FECHA EJECUTADO AL E.P. ANTERIOR
ITEM DESIGNACION UNIDAD CANTIDAD PRECIO UNITARIO TOTAL E.P.
CANT TOTAL CANT TOTAL CANT TOTAL
C.9.2.4 Puerta ancho 85 N 6.00 3.28 19.66 6.00 19.66 6.00 19.66 0.00 0.000
C.9.3 Puerta exteriores
C.9.3.1 Puerta ancho 80 N 157.00 4.66 731.32 157.00 731.32 157.00 731.32 0.00 0.000
C.9.3.2 Puerta ancho 85 N 161.00 4.77 767.34 161.00 767.34 159.00 757.81 2.00 9.532
C.9.4 Quincallería (incluye chapas, perillas, bisagras y topes)
C.9.4.1 Puerta principal VIV. 159.00 1.34 213.81 159.00 213.81 159.00 213.81 0.00 0.000
C.9.4.2 Baño VIV. 159.00 0.47 75.46 159.00 75.46 140.00 66.44 19.00 9.017
C.9.4.3 Interior VIV. 159.00 0.75 118.97 159.00 118.97 140.00 104.75 19.00 14.216
C.9.4.4 Exterior cocina VIV. 159.00 1.12 177.87 159.00 177.87 159.00 177.87 0.00 0.000
C.9.5 Ventanas (incluye quincallería)
C.9.5.2 PVC INCL VIDRIOS VIV. 159.00 15.80 2,512.88 159.00 2,512.88 159.00 2,512.88 0.00 0.000
C.10 MOLDURAS
C.10.1 Guardapolvos VIV. 159.00 2.51 398.41 159.00 398.41 146.00 365.84 13.00 32.575
C.10.2 Cornizas VIV. 159.00 2.99 475.14 159.00 475.14 146.00 436.29 13.00 38.848
C.11 PINTURAS
C.11.2 Esmalte
C.11.2.A huincha + yeso +latex VIV. 159.00 9.55 1,519.05 159.00 1,519.05 159.00 1,519.05 0.00 0.000
C.11.2.B 2a mano VIV. 159.00 9.55 1,519.05 159.00 1,519.05 159.00 1,519.05 0.00 0.000
C.11.2.C 3a mano VIV. 159.00 9.84 1,565.08 159.00 1,565.08 143.00 1,407.59 16.00 157.493
C.11.7 Preparacion de superficie (Impermeabilizacion baño - terrazas) 0.00 0.000
C.11.7.A sello + 1a mano VIV. 159.00 0.87 138.09 159.00 138.09 158.00 137.22 1.00 0.869
C.11.7.B 2a mano VIV. 159.00 0.45 71.14 159.00 71.14 147.00 65.77 12.00 5.369
C.12 OBRAS EXTERIORES
C.12.1 Pavimento de Acceso
C.12.1.1 Pastelones VIV. 159.00 1.79 285.03 159.00 285.03 16.00 28.68 143.00 256.352
C.12.1.3 Rampa acceso vivienda (incluye baranda doble altura) VIV. 2.00 19.72 39.44 1.00 19.72 0.00 0.00 1.00 19.722
C.12.2 CIERROS
C.12.2.3 Puerta reja (ancho min. 0,90m) VIV. 159.00 2.32 368.32 159.00 368.32 141.00 326.63 18.00 41.697
C.12.2.4 Cierros entre propiedades h= 1,8 m VIV. 159.00 1.73 275.86 144.00 249.84 88.00 152.68 56.00 97.160
C.EXTRAS PARTIDAS DE OBRAS DE TERMINACION AGREGADAS
C.EX.3 POR LA EMPRESA
Sistemas de ventilación VIV. 159.00 10.28 1,635.00 159.00 1,635.00 158.00 1,624.71 1.00 10.283
C.EX.6 Closet VIV. 2.00 6.27 12.53 2.00 12.53 0.00 0.00 2.00 12.532
C.EX.7 Obras adicionales Discapacidad 20UF VIV. 6.00 22.60 135.60 6.00 135.60 0.00 0.00 6.00 135.600
C.EX.9 Cierros madera VIV. 486.27 1.75 853.35 486.27 853.35 305.60 536.29 180.67 317.056
C.EX.10 Pintura sidding
C.EX.10.A pre pintado VIV. 159.00 5.75 913.65 159.00 913.65 159.00 913.65 0.00 0.000
C.EX.10.B 1a mano VIV. 159.00 5.75 913.65 159.00 913.65 159.00 913.65 0.00 0.000
C.EX.10.C 2a mano VIV. 159.00 5.92 941.34 159.00 941.34 159.00 941.34 0.00 0.000
SUBTOTAL 39,819.40 39,773.66 38,387.16 1,386.50
37,513.60 6689.22
D INSTALACIONES
D.1 ARTEFACTOS SANITARIOS (Incl. Griferia)
D.1.1 WC N 159.00 1.41 224.59 159.00 224.59 131.00 185.04 28.00 39.55
D.1.2 Lavamanos con pedestal N 157.00 1.34 211.12 157.00 211.12 122.00 164.05 35.00 47.07
D.1.3 Lavamanos sin pedestal (viv. Discapacidad) N 2.00 1.34 2.69 2.00 2.69 0.00 0.00 2.00 2.69
D.1.4 Tina N 157.00 3.57 560.62 157.00 560.62 123.00 439.21 34.00 121.41
D.1.5 Base ducha N 2.00 3.22 6.45 2.00 6.45 0.00 0.00 2.00 6.45
D.1.6 Lavadero N 159.00 1.12 177.87 159.00 177.87 2.00 2.24 157.00 175.64
D.1.7 Lavaplatos con mueble N 159.00 1.59 253.33 159.00 253.33 125.00 199.16 34.00 54.17
D.1.9 Barras WC N 2.00 0.88 1.77 2.00 1.77 0.00 0.00 2.00 1.77
D.1.10 Barras ducha N 2.00 1.30 2.60 2.00 2.60 0.00 0.00 2.00 2.60
D2 RED AGUA POTABLE
D.2.1 MAP N 159.00 1.74 276.69 159.00 276.69 152.00 264.51 7.00 12.18
D.2.4 Red interior agua fría VIV 159.00 5.15 819.30 159.00 819.30 159.00 819.30 0.00 0.00
D.2.5 Red interior agua caliente VIV. 159.00 2.44 388.09 159.00 388.09 159.00 388.09 0.00 0.00
D3 RED ALCANTARILLADO
D.3.1 UD N 159.00 1.53 242.55 159.00 242.55 159.00 242.55 0.00 0.00
D.3.2 Red interior VIV. 159.00 3.79 601.89 159.00 601.89 159.00 601.89 0.00 0.00
D.3.4 Cámara de inspeccion N 318.00 1.49 474.33 318.00 474.33 318.00 474.33 0.00 0.00
D4 INSTALACIONES ELECTRICAS
D.4.1 Medidor y Empalmes
D.4.1A Medidor y Empalmes N 159.00 3.24 515.65 159.00 515.65 159.00 515.65 0.00 0.00
D.4.2 Tablero (automaticos, protecciones, etc) VIV. 159.00 3.58 569.55 159.00 569.55 159.00 569.55 0.00 0.00
D.4.4 Puesta a tierra VIV. 159.00 6.22 988.90 159.00 988.90 159.00 988.90 0.00 0.00
D.4.5 Red interior
D.4.5.A Canalizacion (35%) VIV. 159.00 6.28 998.67 159.00 998.67 159.00 998.67 0.00 0.00
D.4.5.B Alambrado (35%) VIV. 159.00 6.28 998.67 159.00 998.67 159.00 998.67 0.00 0.00
D.4.5.C Artefactado (30%) VIV. 159.00 5.38 856.00 159.00 856.00 159.00 856.00 0.00 0.00
D5 INSTALACIONES DE GAS
D.5.3 Red interior VIV. 159.00 8.80 1,399.63 159.00 1,399.63 155.00 1,364.42 4.00 35.21
D.5.4 Calefón VIV. 159.00 5.92 941.11 159.00 941.11 151.00 893.76 8.00 47.35
D.5.5 Nicho para cilindros N 159.00 2.80 445.58 159.00 445.58 15.00 42.04 144.00 403.55
D.5.6 Ductos ventilacion y evacuacion de gases VIV. 159.00 0.81 128.46 159.00 128.46 83.00 67.06 76.00 61.40
D.EXTRAS PARTIDAS DE OBRAS DE INSTALACIONES
D.EX.1 Estufa parafina VIV. 39.00 35.58 1,387.77 39.00 1,387.77 38.00 1,352.18 1.00 35.58
D.EX.2 Estufa pellet VIV. 120.00 35.58 4,270.04 120.00 4,270.04 113.00 4,020.96 7.00 249.09
SUBTOTAL 17,743.93 17,743.93 16,448.23 1,295.70

E OBRAS DE URBANIZACIÓN
E.1 PAVIMENTOS
E.1.1 Excavacion m3 3584.05 0.23 810.00 3,584.05 810.00 3,584.05 810.00 0.00 0.00
E.1.3 Aceras e= 7 cm m2 1280.60 0.46 583.17 1,206.75 549.54 932.83 424.80 273.92 124.74
E.1.4 Base estabilizada e= 15 cm m3 1244.83 0.54 675.20 1,244.83 675.20 1,244.83 675.20 0.00 0.00
E.1.6 Calzada de Hormigon 15cms m2 6284.98 0.79 4,985.62 6,284.98 4,985.62 6,284.98 4,985.62 0.00 0.00
E.1.9 Soleras Tipo "A" m 1299.70 0.71 926.73 1,299.70 926.73 1,299.70 926.73 0.00 0.00
E.1.11 Soleras con zarpas m 637.50 0.79 503.54 637.50 503.54 637.50 503.54 0.00 0.00
SUBTOTAL 8,484.25 8,450.62 8,325.88 124.74

E.2 SISTEMA DE EVACUACIÓN DE AGUAS LLUVIA


E.2.1 Red evacuacion de Aguas Lluvias
E.2.1.5 Cama de arena m3 279.60 0.40 110.58 279.60 110.58 279.60 110.58 0.00 0.00
E.2.1.7 Cámaras aguas lluvias
E.2.1.7.A Emplantillado y radier n° 2.00 7.79 15.59 2.00 15.59 2.00 15.59 0.00 0.00
E.2.1.7.B Muros n° 2.00 15.12 30.23 2.00 30.23 2.00 30.23 0.00 0.00
E.2.1.7.C Losa n° 2.00 2.70 5.40 2.00 5.40 2.00 5.40 0.00 0.00
E.2.1.7.D Tapa Hormigon y escalines n° 2.00 9.15 18.30 2.00 18.30 2.00 18.30 0.00 0.00
E.2.2 Sumideros
E.2.2.1 Rejilla fierro fundido n° 68.00 12.30 836.25 68.00 836.25 68.00 836.25 0.00 0.00
E.2.2.3 Hormigón sumidero m3 34.00 3.05 103.85 34.00 103.85 34.00 103.85 0.00 0.00
E.2.2.4 Enfierradura kg 289.85 0.09 25.55 289.85 25.55 289.85 25.55 0.00 0.00
E.2.2.5 Moldaje m2 88.00 0.33 29.04 88.00 29.04 88.00 29.04 0.00 0.00
E.2.2.6 Estuco m2 510.00 0.30 152.14 0.00 0.00 0.00 0.00 0.00 0.00
SUBTOTAL 1,326.92 1,174.78 1,174.78 0.00

E.3 AGUA POTABLE LOTEO


E.3.1 Red de agua ml
E.3.1.A Red de agua ml 1164.00 1.41 1,636.56 1,164.00 1,636.56 1,163.31 1,635.60 0.69 0.96
E.3.1.B Grifo n° 4.00 106.37 425.47 4.00 425.47 4.00 425.47 0.00 0.00
E.3.1.C Camara de Valvula n° 1.00 437.07 437.07 1.00 437.07 1.00 437.07 0.00 0.00
E.3.2 Tuberia PVC C-4 d=200 m 147.00 0.41 59.80 147.00 59.80 147.00 59.80 0.00 0.00
SUBTOTAL 2,558.90 2,558.90 2,557.94 0.96

E.4 ALCANTARILLADO LOTEO


E.4.1 Red de Alcantarillado
E.4.1.1 Tubería PVC C-4 d= 200 m 1123.00 0.41 456.84 1,123.00 456.84 1,123.00 456.84 0.00 0.00
E.4.1.3 Camaras tipo A n°
E.4.1.3.A Excavacion y radier n° 16.00 3.38 54.01 16.00 54.01 16.00 54.01 0.00 0.00
E.4.1.3.B Hormigon Muro n° 16.00 11.76 188.20 16.00 188.20 16.00 188.20 0.00 0.00
E.4.1.3.C Hormigon Losa n° 16.00 2.72 43.52 16.00 43.52 16.00 43.52 0.00 0.00
E.4.1.3.D Tapa clazada n° 16.00 6.25 99.93 16.00 99.93 16.00 99.93 0.00 0.00
E.4.1.7 Cama de arena e = 20 cms m3 112.00 0.40 44.30 112.00 44.30 112.00 44.30 0.00 0.00
SUBTOTAL 886.79 886.79 886.79 0.00
SALDO A PAGAR EN PRESENTE
EJECUTADO A LA FECHA EJECUTADO AL E.P. ANTERIOR
ITEM DESIGNACION UNIDAD CANTIDAD PRECIO UNITARIO TOTAL E.P.
CANT TOTAL CANT TOTAL CANT TOTAL

E.5 ELECTRICIDAD LOTEO


E.5.1 Red eléctrica de distribución y alumbrado público GL 1.00 972.75 972.75
E.5.1.1 Provision e instalacion de Linea de Alumbrado y Postacion ml 1231.00 0.64 781.69 1,231.00 781.69 1,231.00 781.69 0.00 0.00
E.5.1.2 Provision e instalacion de Luminarias 40W un 13.00 1.6257 21.13 13.00 21.13 13.00 21.13 0.00 0.00
E.5.1.3 Provision e instalacion de Luminarias 60W un 34.00 2.1760 73.98 34.00 73.98 34.00 73.98 0.00 0.00
E.5.1.4 Provision e instalacion de Brazos Galvanizados un 47.00 0.45 21.15 47.00 21.15 47.00 21.15 0.00 0.00
E.5.1.5 Provision e instalacion de equipos de proteccion y control un 2.00 26.42 52.85 2.00 52.85 2.00 52.85 0.00 0.00
E.5.1.6 Calculos luminicos e inscripcion SEC TE-2 un 1.00 106.13 106.13 1.00 106.13 1.00 106.13 0.00 0.00
SUBTOTAL 1,056.9302 1,056.93 1,056.93 0.00

E.6 OBRAS ANEXAS


E.6.1 Señalización de calles y pasajes c/u 23.00 5.51 126.83 23.00 126.83 20.00 110.29 3.00 16.54
E.6.2 Arborización de calles y pasajes Nº 114.00 0.40 45.99 84.00 33.89 84.00 33.89 0.00 0.00
SUBTOTAL 172.82 160.72 144.18 16.54

E.EXTRAS PARTIDAS DE OBRAS DE URBANIZACIÓN AGREGADAS POR LA EMPRESA


E.EX.1 Calzada de hormigón 14 cms pasajes m2 1199.35 0.72 867.37 1,199.35 867.37 1,199.35 867.37 0.00 0.00
E.EX.2 Veredas reforzadas e=10cms m2 568.80 0.58 328.44 524.00 302.57 460.14 265.70 63.86 36.88
E.EX.3 HDPE d=400 A.Ll. ml 799.12 2.00 1,598.32 799.12 1,598.32 799.12 1,598.32 0.00 0.00
E.EX.4 HDPE d=500 A.Ll. ml 154.71 2.49 384.61 154.71 384.61 154.71 384.61 0.00 0.00
E.EX.5 Camara decantadora un 1.00 101.30 101.30 1.00 101.30 1.00 101.30 0.00 0.00
E.EX.6 Excavacion y relleno A.S m3 3292.00 0.12 390.60 3,292.00 390.60 3,292.00 390.60 0.00 0.00
E.EX.7 Excavacion y relleno A.LL m3 1049.04 0.12 124.47 1,049.04 124.47 1,049.04 124.47 0.00 0.00
E.EX.8 Cámaras aguas lluvias un
E.EX.8.A Emplantillado y Radier un 11.00 7.68 84.52 11.00 84.52 11.00 84.52 0.00 0.00
E.EX.8.B Muros un 11.00 21.04 231.41 11.00 231.41 11.00 231.41 0.00 0.00
E.EX.8.C Fe losa un 11.00 2.66 29.27 11.00 29.27 11.00 29.27 0.00 0.00
E.EX.8.D Tapa Hormigon un 11.00 9.02 99.27 11.00 99.27 11.00 99.27 0.00 0.00
E.EX.9 demolicion de pavimentos m2 285.50 1.36 387.14 285.50 387.14 285.50 387.14 0.00 0.00
E.EX.10 Reposicion de Pavimentos m2 285.50 0.84 238.74 285.50 238.74 285.50 238.74 0.00 0.00
SUBTOTAL 4,865.45 4,839.59 4,802.71 36.88

F OBRAS DE HABILITACIÓN
F.1 MOVIMIENTO DE TIERRAS
F.1.1 Excavación en corte m3 26582.11 0.33 8,643.64 26,582.11 8,643.64 26,582.11 8,643.64 0.00 0.00
F.1.2 Terraplen m3 15798.21 0.79 12,496.38 15,798.21 12,496.38 15,798.21 12,496.38 0.00 0.00
F.1.4 Escarpes m3 12024.66 0.23 2,759.69 12,024.66 2,759.69 12,024.66 2,759.69 0.00 0.00
F.2 MUROS DE CONTENCIÓN
F.2.1 Hormigón armado
F.2.2.8 Muros hormigón armado h=1,4 0.00 0.00
F.2.2.8.A Zapata ml 35.65 1.36 48.34 35.65 48.34 35.65 48.34 0.00 0.00
F.2.2.8.B Muro ml 35.65 4.49 159.93 35.65 159.93 35.65 159.93 0.00 0.00
F.2.2.8.C Relleno ml 35.65 2.46 87.82 35.65 87.82 35.65 87.82 0.00 0.00
F.2.2.9 Muros hormigón armado h=1,6
F.2.2.9.A Zapata ml 59.00 1.21 71.53 59.00 71.53 59.00 71.53 0.00 0.00
F.2.2.9.B Muro ml 59.00 5.20 306.75 59.00 306.75 59.00 306.75 0.00 0.00
F.2.2.9.C Relleno ml 59.00 2.57 151.74 59.00 151.74 59.00 151.74 0.00 0.00
F. EXTRAS PARTIDAS DE OBRAS DE HABILITACIÓN AGREGADAS POR LA EMPRESA
F.EX.2 Cubo dren m3 1060.00 4.01 4,252.19 1,060.00 4,252.19 1,060.00 4,252.19 0.00 0.00
F.EX.3 Pandereta reforzada ml 230.66 1.70 391.01 230.66 391.01 201.85 342.17 28.81 48.84
F.EX.4 Bloque de Hormigon
F.EX.4.A Enfierradura ml 485.45 0.05 23.59 485.45 23.59 485.45 23.59 0.00 0.00
F.EX.4.B Hormigon ml 485.45 2.12 1,028.00 485.45 1,028.00 485.45 1,028.00 0.00 0.00
F.EX.4.C Bloque de Hormigon ml 485.45 2.92 1,416.93 485.45 1,416.93 485.45 1,416.93 0.00 0.00
F.EX.5 Botadero m3 38606.66 0.18 6,892.83 38,606.66 6,892.83 38,606.66 6,892.83 0.00 0.00
F.EX.6 Relleno gravas cubo dren m3 205.00 0.87 179.02 205.00 179.02 205.00 179.02 0.00 0.00
F.EX.7 Relleno material fino Cubo Dren m3 215.20 0.99 213.99 215.20 213.99 215.00 213.80 0.20 0.20
OBRAS EXTENSION AS-ALL
F.EX.8 Demolición Obra de Arte existente EXTENSION ALL m3 64.00 1.19 76.20 64.00 76.20 64.00 76.20 0.00 0.00
F.EX.9 Traslado a botadero Demolición Obra de Arte existente EXTE m3 64.00 0.14 8.82 64.00 8.82 64.00 8.82 0.00 0.00
F.EX.10 Excavacion Modificacion de Cauce EXTENSION ALL m3 95.02 0.56 53.68 95.02 53.68 95.02 53.68 0.00 0.00
F.EX.11 Enfierradura Modificacion de Cauce EXTENSION ALL kg 380.68 0.06 21.94 380.68 21.94 380.68 21.94 0.00 0.00
F.EX.12 Hormigon modificacion de Cauce EXTENSION ALL m3 11.03 4.15 45.79 11.03 45.79 11.03 45.79 0.00 0.00
F.EX.13 Moldaje Modificacion de Cauce EXTENSION ALL m2 100.00 0.34 33.79 100.00 33.79 100.00 33.79 0.00 0.00
F.EX.14 Muro Boca EXTENSION ALL un 1.00 15.07 15.07 1.00 15.07 1.00 15.07 0.00 0.00
F.EX.15 Tuberia PVC C-4 d=200 EXTENSION AS m 318.00 0.44 138.88 318.00 138.88 318.00 138.88 0.00 0.00
F.EX.16 Camras tipo A EXTENSION AS n° 8.00 24.10 192.83 8.00 192.83 8.00 192.83 0.00 0.00
F.EX.17 Cama de arena EXTENSION AS m3 31.00 0.40 12.26 31.00 12.26 31.00 12.26 0.00 0.00
F.EX.18 Exacavacion y relleno EXTENSION AS m3 780.00 0.12 92.55 780.00 92.55 780.00 92.55 0.00 0.00
F.EX.19 HDPE d=500 A.Ll. EXTENSION ml 156.80 2.18 341.06 156.80 341.06 156.80 341.06 0.00 0.00
F.EX.20 HDPE d=400 A.Ll. EXTENSION ml 25.17 2.00 50.34 25.17 50.34 25.17 50.34 0.00 0.00
F.EX.21 Pvc d=250 all extension ml 11.23 0.62 6.98 11.23 6.98 11.23 6.98 0.00 0.00
F.EX.22 Excavacion y relleno ALL m3 131.94 0.12 15.65 131.94 15.65 131.94 15.65 0.00 0.00
F.EX.23 Demolicion PAVIMENTOS EXTENSION AS m2 189.00 1.13 213.57 189.00 213.57 189.00 213.57 0.00 0.00
F.EX.24 Reposicion Pavimentos EXTENSION AS m3 189.00 0.79 149.93 189.00 149.93 189.00 149.93 0.00 0.00
F.EX.25 Camara Aguas Lluvias Armada un 4.00 40.41 161.63 4.00 161.63 4.00 161.63 0.00 0.00
F.EX.26 Camaras aguas Lluvias de Extensión un 2.00 34.76 69.52 2.00 69.52 2.00 69.52 0.00 0.00
SUBTOTAL 40,823.87 40,823.87 40,774.83 49.04

G OBRAS DE CONSTRUCCION SALA MULTIUSO


F.1 OBRA GRUESA
B.1.1 Replanteo, trazado y niveles Uni. 1.00 6.03 6.03 1.00 6.03 1.00 6.03 0.00 0.00
B.1.2 Excavación m3 26.12 0.44 11.60 26.12 11.60 26.12 11.60 0.00 0.00
B.1.3 Emplantillado m3 0.93 1.87 1.74 0.93 1.74 0.93 1.74 0.00 0.00
B.1.4 Hormigón cimientos m3 2.32 2.76 6.40 2.32 6.40 2.32 6.40 0.00 0.00
B.1.5 Hormigón sobrecimientos m3 1.68 2.77 4.65 1.68 4.65 1.68 4.65 0.00 0.00
B.1.6 Enfierradura Fundaciones kg 469.03 0.04 20.14 469.03 20.14 469.03 20.14 0.00 0.00
B.1.7 Moldajes m2 40.09 0.22 9.02 40.09 9.02 40.09 9.02 0.00 0.00
B2 RADIER
B.2.1 Base (Cama de ripio) 8 cms m2 93.06 0.23 21.03 93.06 21.03 93.06 21.03 0.00 0.00
B.2.2 Hormigón e= 8 cm m2 8.51 2.76 23.47 8.51 23.47 8.51 23.47 0.00 0.00
B3 MUROS 1° PISO
B.3.3 Madera
B.3.3.1 Entramado estructural m2 93.12 0.47 43.77 93.12 43.77 93.12 43.77 0.00 0.00
B.3.3.2 Entramado Tabiques m2 15.80 0.39 6.16 15.80 6.16 15.80 6.16 0.00 0.00
B.3.3.3 Pilares ml 22.35 0.65 14.55 22.35 14.55 22.35 14.55 0.00 0.00
B.3.3.4 Vigas ml 23.28 0.54 12.52 23.28 12.52 23.28 12.52 0.00 0.00
B.4 ENTREPISO
B6 CUBIERTA (inc. Cumbreras)
B.6.1 Estructura (inc. Costaneras)
B.6.1.1 Madera (estructura Tech. Incl. Costaneras) Uni. 1.00 5.27 5.27 1.00 5.27 1.00 5.27 0.00 0.00
B.6.2 CUBIERTA (inc. Cumbreras)
B.6.2.1 Acero galvanizado m2 180.73 0.19 34.31 180.73 34.31 180.73 34.31 0.00 0.00
B.6.3 Hojalatería
B.6.3.1 Canales y forros m 13.27 0.18 2.37 13.27 2.37 0.00 0.00 13.27 2.37
B.6.3.2 Bajadas m 5.57 0.14 0.79 5.57 0.79 0.00 0.00 5.57 0.79
C.- OBRAS DE TERMINACION
C1 REVESTIMIENTOS MUROS Y TABIQUES
C.1.1 Exterior
C.1.1.3 Madera placas m2 151.53 0.24 35.96 151.53 35.96 151.53 35.96 0.00 0.00
C.1.2 Interior zona seca
C.1.2.2 Yeso cartón m2 91.22 0.13 12.27 91.22 12.27 0.00 0.00 91.22 12.27
C.1.3 Interior zona húmeda
C.1.3.2 Fibrocemento m2 60.31 0.34 20.38 60.31 20.38 0.00 0.00 60.31 20.38
C2 AISLACION TERMICA MUROS (INCLUYE BARREAS DE HUMEDAD Y VAPOR)
SALDO A PAGAR EN PRESENTE
EJECUTADO A LA FECHA EJECUTADO AL E.P. ANTERIOR
ITEM DESIGNACION UNIDAD CANTIDAD PRECIO UNITARIO TOTAL E.P.
CANT TOTAL CANT TOTAL CANT TOTAL
C.2.3 Lana vidrio e= 50 mm m2 121.53 0.06 7.28 121.53 7.28 0.00 0.00 121.53 7.28
C3 CIELO
C3.2 Estructura cielo falso
C 3.2.1 Madera m2 99.85 0.14 13.54 99.85 13.54 99.85 13.54 0.00 0.00
C.3.3 Revestimiento zona seca
C.3.3.1 Yeso cartón m2 99.85 0.13 13.43 99.85 13.43 0.00 0.00 99.85 13.43
C.3.4 Revestimiento zona húmeda
C.3.4.2 Yeso cartón RH m2 20.97 0.33 6.82 20.97 6.82 0.00 0.00 20.97 6.82
C.4 Aislacion térmica cubierta
C.4.3 Lana vidrio e= 120 mm m2 70.10 0.09 6.18 70.10 6.18 0.00 0.00 70.10 6.18
C.5 REVESTIMIENTO PISOS
C.5.1 Cerámica m2 18.16 0.51 9.28 18.16 9.28 0.00 0.00 18.16 9.28
C8 ALEROS Y FRONTONES
C.8.1 Estructura
C.8.1.1 Madera m2 32.98 0.64 21.06 32.98 21.06 32.98 21.06 0.00 0.00
C.8.2 Revestimiento
C.8.2.4 Fibrocemento m2 32.98 0.34 11.14 32.98 11.14 0.00 0.00 32.98 11.14
C.8.3 Rejillas de ventilacion n° 2.00 0.13 0.26 2.00 0.26 0.00 0.00 2.00 0.26
C.8.4 Tapacan m 47.23 0.14 6.46 47.23 6.46 0.00 0.00 47.23 6.46
C.9 PUERTAS Y VENTANAS
C.9.1 Marcos
C.9.1.1 Madera n° 4.00 0.61 2.45 4.00 2.45 0.00 0.00 4.00 2.45
C.9.2 Puertas interiores
C.9.2.1 Puerta ancho 70 n° 1.00 2.83 2.83 1.00 2.83 0.00 0.00 1.00 2.83
C.9.2.4 Puerta ancho 85 n° 1.00 3.28 3.28 1.00 3.28 0.00 0.00 1.00 3.28
C.9.3 Puerta exteriores
C.9.3.1 Puerta ancho 70 n° 2.00 2.83 5.65 2.00 5.65 0.00 0.00 2.00 5.65
C.9.4 Quincallería (incluye chapas, perillas, bisagras y topes)
C.9.4.1 Puerta principal n° 2.00 1.34 2.69 2.00 2.69 0.00 0.00 2.00 2.69
C.9.4.2 Baño n° 2.00 0.47 0.95 2.00 0.95 0.00 0.00 2.00 0.95
C.9.5 Ventanas (incluye quincallería)
C.9.5.2 PVC INCL VIDRIOS m2 17.09 2.33 39.74 17.09 39.74 17.09 39.74 0.00 0.00
C.10 MOLDURAS
C.10.1 Guardapolvos m 60.50 0.04 2.46 60.50 2.46 0.00 0.00 60.50 2.46
C.10.2 Cornizas m 71.50 0.04 2.91 71.50 2.91 0.00 0.00 71.50 2.91
C.11 PINTURAS
C.11.2 Esmalte m2 385.60 0.12 47.93 385.60 47.93 0.00 0.00 385.60 47.93
C.11.4 Barniz m2 55.80 0.11 6.31 55.80 6.31 0.00 0.00 55.80 6.31
C.11.7 Preparacion de superficie (Impermeabilizacion baño - terrazas) m2 192.80 0.01 2.18 192.80 2.18 0.00 0.00 192.80 2.18
C.12 OBRAS EXTERIORES
C.12.1 Pavimento de Acceso
C.12.1.1 Pastelones m2 2.50 0.64 1.60 2.50 1.60 0.00 0.00 2.50 1.60
C.12.1.3 Rampa acceso vivienda (incluye baranda doble altura) un 1.00 19.72 19.72 1.00 19.72 0.00 0.00 1.00 19.72
C.12.2 CIERROS
C.12.2.3 Cierro de madera m 60.00 1.75 105.29 60.00 105.29 0.00 0.00 60.00 105.29
C.EXTRAS PARTIDAS DE OBRAS DE TERMINACION AGREGADAS POR LA EMPRESA
C.EX.3 Sistemas de ventilación un 3.00 5.14 15.42 3.00 15.42 0.00 0.00 3.00 15.43
C.EX.7 Endurecedor Superficial n° 95.45 0.11 10.68 95.45 10.68 95.45 10.68 0.00 0.00
C.EX.8 Pintura sidding m2 257.00 0.14 34.85 257.00 34.85 0.00 0.00 257.00 34.85
D INSTALACIONES
D1 ARTEFACTOS SANITARIOS (Incl. grifería)
D.1.1 WC n° 2.00 1.41 2.83 1.00 1.41 0.00 0.00 1.00 1.41
D.1.2 Lavamanos con pedestal n° 1.00 1.34 1.34 1.00 1.34 0.00 0.00 1.00 1.35
D.1.3 Lavamanos sin pedestal (viv. Discapacidad) n° 1.00 1.34 1.34 1.00 1.34 0.00 0.00 1.00 1.35
D.1.7 Lavaplatos con mueble n° 1.00 1.59 1.59 1.00 1.59 0.00 0.00 1.00 1.59
D.1.9 Barras WC n° 1.00 0.88 0.88 1.00 0.88 0.00 0.00 1.00 0.88
D2 RED AGUA POTABLE
D.2.1 MAP n° 1.00 1.74 1.74 1.00 1.74 0.00 0.00 1.00 1.74
D.2.4 Red interior agua fría viv 1.00 3.21 3.21 1.00 3.21 1.00 3.21 0.00 0.00
D.2.5 Red interior agua caliente viv 1.00 2.46 2.46 1.00 2.46 1.00 2.46 0.00 0.00
D3 RED ALCANTARILLADO
D.3.1 UD n° 1.00 1.52 1.52 1.00 1.52 1.00 1.52 0.00 0.00
D.3.2 Red interior viv 1.00 2.95 2.95 1.00 2.95 1.00 2.95 0.00 0.00
D.3.4 Cámara de inspeccion n° 3.00 4.18 12.54 3.00 12.54 3.00 12.54 0.00 0.00
D4 INSTALACIONES ELECTRICAS
D.4.1 Medidor y Empalmes
D.4.1A Medidor y Empalmes n° 1.00 3.24 3.24 1.00 3.24 0.00 0.00 1.00 3.24
D.4.2 Tablero (automaticos, protecciones, etc) viv 1.00 3.58 3.58 1.00 3.58 0.00 0.00 1.00 3.58
D.4.4 Puesta a tierra viv 1.00 1.86 1.86 1.00 1.86 0.00 0.00 1.00 1.87
D.4.5 Red interior viv 1.00 4.89 4.89 1.00 4.89 0.00 0.00 1.00 4.89
D5 INSTALACIONES DE GAS
D.5.3 Red interior viv 1.00 3.51 3.51 1.00 3.51 0.00 0.00 1.00 3.51
D.5.4 Calefón viv 1.00 5.92 5.92 1.00 5.92 0.00 0.00 1.00 5.92
D.5.5 Nicho para cilindros n° 1.00 2.80 2.80 1.00 2.80 0.00 0.00 1.00 2.80
D.5.6 Ductos ventilacion y evacuacion de gases viv 1.00 0.81 0.81 1.00 0.81 0.00 0.00 1.00 0.81
D.5.7 Caseta protección calefon viv 1.00 1.10 1.10 1.00 1.10 0.00 0.00 1.00 1.10
SUBTOTAL 754.92 753.50 364.31 389.20

H AREAS VERDES Y RECREACIONALES


H.1 PREPARACION TERRENO
H.1.3 Solerillas m 1368.98 0.22 307.84 1,343.92 302.21 75.67 17.02 1,268.25 285.19
H.1.6 Pavimento circulacion peatonal, areas de estar, juegos etc.
H.1.6.1 Homrigón m2 505.06 0.47 236.85 336.60 157.85 0.00 0.00 336.60 157.85
H.1.6.2 Polvo de roca e=5cms m2 525.84 0.19 100.42 525.84 100.42 0.00 0.00 525.84 100.42
H.2 INSTALACION ELECTRICA
H.2.1 Empalme y medidor un 1.00 2.78 2.78 1.00 2.78 0.00 0.00 1.00 2.78
H.2.2 RED un 1 90.52 90.52 1.00 90.52 0.00 0.00 1.00 90.52
H.2.3 Luminarias n° 12.00 25.73 308.76 12.00 308.76 0.00 0.00 12.00 308.76
H.3 RIEGO
H.3.1 Medidor un 1.00 13.01 13.01 0.00 0.00 0.00 0.00 0.00 0.00
H.3.2 Red interior (inc. Cámaras) un 1.00 14.11 14.11 1.00 14.11 0.00 0.00 1.00 14.12
H.4 MOBILIARIO URBANO (Bancas, juegos infantiles, maq. De ejercicio)
H.4.1 Bancas n° 10.00 11.30 113.00 10.00 113.00 0.00 0.00 10.00 113.00
H.4.2 Basureros n° 7.00 5.42 37.97 7.00 37.97 0.00 0.00 7.00 37.97
H.4.3 Juegos infantiles (Resbalin - columpio) un 6.00 12.07 72.41 6.00 72.41 0.00 0.00 6.00 72.41
H.5 VEGETACION
H.5.1 Preparacion suelo para plantacion m2 238.00 0.30 71.27 79.33 23.76 0.00 0.00 79.33 23.76
H.5.2 Arboles (incluye taza y tutor) n° 116.00 0.40 46.80 5.00 2.02 0.00 0.00 5.00 2.02
H.5.5 Cesped m2 1813.11 0.61 1,106.36 0.00 0.00 0.00 0.00 0.00 0.00
H.EXTRAS PARTIDAS DE OBRAS DE AREAS VERDES Y RECREACIONALES AGREGADAS POR LA EMPRESA
H.EX.1 Arena m2 1017.90 0.11 115.02 1,017.90 115.02 0.00 0.00 1,017.90 115.02
H.EX.2 Maicillo m2 836.48 0.18 151.24 836.48 151.24 0.00 0.00 836.48 151.24
H.EX.3 Juego modular un 1.00 135.00 135.00 0.00 0.00 0.00 0.00 0.00 0.00
SUBTOTAL 2,923.38 1,492.07 17.02 1,475.06

MODIFICACIÓN PROYECTO PAVIMENTOS Y AGUAS LLUVIAS


AUMENTOS
E.1.3 Aceras e= 7 cm m2 84.00 0.46 38.25 84.00 38.25 31.50 14.34 52.50 23.91
DISMINUCIONES
E.1.1 Excavacion m3 -43.47 0.23 -9.82 -43.47 -9.82 -43.47 -9.82 0.00 0.00
E.1.4 Base Estabilizada e = 15 cms m3 -14.18 0.54 -7.69 -14.18 -7.69 -14.18 -7.69 0.00 0.00
E.1.6 Calzada de Hormigón 15 cms m2 -178.50 0.79 -141.60 -178.50 -141.60 -178.50 -141.60 0.00 0.00
E.1.9 Soleras Tipo "A" ml -3.49 0.71 -2.48 -3.49 -2.48 -3.49 -2.48 0.00 0.00
E.2.2 Sumideros (34 unidades - 6 unidades) 0.00 0.00
E.2.2.1 Rejilla fierro fundido n° -12.00 12.30 -147.57 -12.00 -147.57 -12.00 -147.57 0.00 0.00
E.2.2.3 Hormigón sumidero m3 -6.00 3.05 -18.33 -6.00 -18.33 -6.00 -18.33 0.00 0.00
SALDO A PAGAR EN PRESENTE
EJECUTADO A LA FECHA EJECUTADO AL E.P. ANTERIOR
ITEM DESIGNACION UNIDAD CANTIDAD PRECIO UNITARIO TOTAL E.P.
CANT TOTAL CANT TOTAL CANT TOTAL
E.2.2.4 Enfierradura kg -51.15 0.09 -4.51 -51.15 -4.51 -51.15 -4.51 0.00 0.00
E.2.2.5 Moldaje m2 -15.53 0.33 -5.12 -15.53 -5.12 -15.53 -5.12 0.00 0.00
E.2.2.6 Estuco m2 -90.00 0.30 -26.85 0.00 0.00 0.00 0.00 0.00 0.00
E.EX.3 HDPE d=400 A.Ll. ml -98.47 2.00 -196.95 -98.47 -196.95 -98.47 -196.95 0.00 0.00
E.EX.7 Excavacion y relleno A.LL m3 -129.27 2.49 -321.36 -129.27 -321.36 -129.27 -321.36 0.00 0.00
SUBTOTAL -844.03 -817.18 -841.09 23.91

MODIFICACIÓN PROYECTO PAVIMENTOS Y AGUAS LLUVIAS


DISMINUCIONES
F.EX.8 Demolición Obra de Arte existente EXTENSION ALL m3 -64.00 1.19 -76.20 -64.00 -76.20 -64.00 -76.20 0.00 0.00
F.EX.9 Traslado a botadero Demolición Obra de Arte existente EXTE m3 -64.00 0.14 -8.82 -64.00 -8.82 -64.00 -8.82 0.00 0.00
F.EX.10 Excavacion Modificacion de Cauce EXTENSION ALL m3 -95.02 0.56 -53.68 -95.02 -53.68 -95.02 -53.68 0.00 0.00
F.EX.11 Enfierradura Modificacion de Cauce EXTENSION ALL kg -380.68 0.06 -21.94 -380.68 -21.94 -380.68 -21.94 0.00 0.00
F.EX.12 Hormigon modificacion de Cauce EXTENSION ALL m3 -11.03 4.15 -45.79 -11.03 -45.79 -11.03 -45.79 0.00 0.00
F.EX.13 Moldaje Modificacion de Cauce EXTENSION ALL m2 -100.00 0.34 -33.79 -100.00 -33.79 -100.00 -33.79 0.00 0.00
F.EX.14 Muro Boca EXTENSION ALL un -1.00 15.07 -15.07 -1.00 -15.07 -1.00 -15.07 0.00 0.00
F.EX.15 Tuberia PVC C-4 d=200 EXTENSION AS m -318.00 0.44 -138.88 -318.00 -138.88 -318.00 -138.88 0.00 0.00
F.EX.16 Camras tipo A EXTENSION AS n° -8.00 24.10 -192.83 -8.00 -192.83 -8.00 -192.83 0.00 0.00
F.EX.17 Cama de arena EXTENSION AS m3 -31.00 0.40 -12.26 -31.00 -12.26 -31.00 -12.26 0.00 0.00
F.EX.18 Exacavacion y relleno EXTENSION AS m3 -780.00 0.12 -92.55 -780.00 -92.55 -780.00 -92.55 0.00 0.00
F.EX.19 HDPE d=500 A.Ll. EXTENSION ml -156.80 2.18 -341.06 -156.80 -341.06 -156.80 -341.06 0.00 0.00
F.EX.20 HDPE d=400 A.Ll. EXTENSION ml -25.17 2.00 -50.34 -25.17 -50.34 -25.17 -50.34 0.00 0.00
F.EX.21 Pvc d=250 all extension ml -11.23 0.62 -6.98 -11.23 -6.98 -11.23 -6.98 0.00 0.00
F.EX.22 Excavacion y relleno ALL m3 -131.94 0.12 -15.65 -131.94 -15.65 -131.94 -15.65 0.00 0.00
F.EX.23 Demolicion PAVIMENTOS EXTENSION AS m2 -189.00 1.13 -213.57 -189.00 -213.57 -189.00 -213.57 0.00 0.00
F.EX.24 Reposicion Pavimentos EXTENSION AS m3 -189.00 0.79 -149.93 -189.00 -149.93 -189.00 -149.93 0.00 0.00
F.EX.25 Camara Aguas Lluvias Armada un -4.00 40.41 -161.63 -4.00 -161.63 -4.00 -161.63 0.00 0.00
F.EX.26 Camaras aguas Lluvias de Extensión un -2.00 34.76 -69.52 -2.00 -69.52 -2.00 -69.52 0.00 0.00
SUBTOTAL -1,700.48 -1,700.48 -1,700.48 0.00

MODIFICACIÓN PROYETO ALCANTARILLADO


AUMENTOS
E4.1.3 Camaras tipo A
E.4.1.3.A Excavacion y radier n° 2.00 3.38 6.75 2.00 6.75 2.00 6.75 0.00 0.00
E.4.1.3.B Hormigon Muro n° 2.00 11.76 23.52 2.00 23.52 2.00 23.52 0.00 0.00
E.4.1.3.C Hormigon Losa n° 2.00 2.72 5.44 2.00 5.44 2.00 5.44 0.00 0.00
E.4.1.3.D Tapa clazada n° 2.00 6.25 12.49 2.00 12.49 2.00 12.49 0.00 0.00
SUBTOTAL 48.21 48.21 48.21 0.00

MODIFICACIÓN PROYETO DE HABILITACIÓN


AUMENTOS
F.EX.3 Pandereta reforzada ml 139.87 1.70 237.10 139.87 237.10 71.00 120.36 68.87 116.75
F.EX.3 Pandereta reforzada ml 62.68 1.70 106.25 62.68 106.25 0.00 0.00 0.00 106.25
F.EX.4 Bloque de Hormigon
F.EX.4.A Enfierradura ml 291.00 0.05 14.14 291.00 14.14 291.00 14.14 0.00 0.00
F.EX.4.B Hormigon ml 291.00 2.12 616.23 291.00 616.23 291.00 616.23 0.00 0.00
F.EX.4.C Bloque de Hormigon ml 291.00 2.92 849.37 291.00 849.37 154.69 451.51 136.31 397.86
SUBTOTAL 1,823.08 1,823.09 1,202.23 620.86
ACTUALIZACIÓN PROYECTO ELECTRICO LOTEO
OBRAS EXTRAORDINARIAS
Red eléctrica de distribución y alumbrado público LED un 1.00 136.00 136.00 1.00 136.00 1.00 136.00 0.00 0.00
TRASLADO POSTE PUBLICO ELECTRICO INGRESO un 1.00 184.02
CALLE NVA.3 CON CAMINO SAN VICENTE
Retiro poste Existente un 1.00 46.00 46.00 1.00 46.00 1.00 46.00 0.00 0.00
Instalación poste Nuevo un 2.00 46.00 92.01 2.00 92.01 2.00 92.01 0.00 0.00
Cableado y puesta en marcha un 1.00 46.00 46.00 1.00 46.00 0.00 0.00 1.00 46.00
SUBTOTAL 320.02 320.02 274.01 46.00

ACTUALIZACIÓN DE PROYECTO DE SEÑALETICA


OBRAS EXTRAORDINARIAS
LOMO DE TORO FABRICACION EN ASFALTO CALIENTE un 6.00 40.00 240.00 6.00 240.00 0.00 0.00 6.00 240.00
SEÑALETICAS EXTRAS AGREGADAS POR LA MUNICIPALIDAD
Señalización de calles y pasajes (LOMO DE TORO Y PASO
E.6.1 un 14.00 5.51 77.20 14.00 77.20 14.00 77.20 0.00 0.00
PEATONAL)
un 0.00 0.00 0.00 0.00 0.00 0.00 0.00
SUMINISTRO Y APLICACIÓN PINTURA TERMOPLASTICA
PASO PEATONAL un 2.00 7.66 15.32 2.00 15.32 0.00 0.00 2.00 15.32
FLECHA VIRAGE DOBLE un 4.00 2.89 11.56 0.00 0.00 0.00 0.00 0.00 0.00
FLECHA RECTA Y VIRAGE DOBLE un 3.00 3.04 9.12 0.00 0.00 0.00 0.00 0.00 0.00

SUBTOTAL 353.20 332.52 77.20 255.32

TOTAL DIRECTO SIN


150,340.47 148,604.25 142,823.11 5,781.14
TERRENO

TOTAL % 100.00% 98.85% 95.00% 3.845%

GASTOS GENERALES GL 15.00% 22,551.07 22,290.64 21,423.47 867.17

UTILIDADES GL 12.00% 18,040.86 17,832.51 17,138.77 693.74

SUB TOTAL GL 0.00% 190,932.39 188,727.40 181,385.35 7342.05

TOTAL MONTO DEL SUBISIDO GL 190,932.39 188,727.40 181,385.35 7,342.05

MONTO TOTAL DEL CONTRATO 190,932.39


AVANCE REFERIDO AL TOTAL DEL CONTRATO 98.845%

CONSTRUCTORA CHRISTIAN SCHULZ GARRIDO LUIS OPAZO VICTOR AGURTO


BIO BIO FTO AUTOCONTROL S.A.T. SERVIU
INFORME I.T.O. Nº 30 VIVIENDA/2013
MI GRAN SUEÑO LONQUIMAY

El Inspector Técnico de Obras, certifica que la obra que se indica se encuentra en el


estado de avance que se detalla:

Nombre Comité : Comité de Vivienda MI GRAN SUEÑO


Comuna : Lonquimay
Tipo Subsidio : Fondo Solidario de Vivienda

Monto Terreno : 0 UF
Monto Total del Contrato : Err:509 UF
Monto Ahorro : Err:509 UF

Monto Total Subsidio : 0.00 UF

Monto Estado de Avance


: Err:509 UF
Parcial N° 30 Viviendas

% Estado de avance Referido al Contrato : Err:509


% Estado de avance Referido al Subsidio : Err:509

Monto Estado de avance acumulado : 148,604.25 UF

% Estado de avance acumulado Referido al Contrato : Err:509


% Estado de avance acumulado Referido al Subsidio : #DIV/0!

E. Constructora o Contratista : MONSALVES Y VERGARA LTDA.

El I.T.O. que suscribe ha sido facultado por el SERVIU IX Región para la


Inspección Técnica de Obras para el programa Fondo Solidario de Vivienda año
2012 para el comité individualizado anteriormente y que forma parte de la Zona
Malleco.

VICTOR GALLARDO CÁRCAMO


CONSTRUCTOR CIVIL
ITO

Lonquimay, 26 de mayo de 2023 .-

También podría gustarte