Proyecto :“CREACIÓN DE LOCAL DE USOS MÚLTIPLES EN EL ANEXO TOTORALES DEL DISTRITO DE CURIBAYA- CANDARAVE TACNA” - ETAPA I
Modalidad : EJECUCIÓN PRESUPUESTARIA DIRECTA
Ubicación : Totorales - Curibaya-Candarave -Tacna
01 OBRAS PROVICIONALES
01.01 ALMACEN Y CASETA DE GUARDIANIA m2 10.00 68.68 686.80 10.00 686.80 100.00% - - 0.00% - 0.00%
01.02 SSHH, PROVISIONALES PARA OBREROS GLB 1.00 900.00 900.00 - - 0.00% - - 0.00% - 0.00%
01.03 CERCO DE OBRA CON MALLA ARPILLERA m 50.00 24.13 1,206.50 50.00 1,206.50 100.00% 50.00 1,206.50 100.00% - 0.00%
01.04 CARTEL DE IDENTIFICACION DE LA OBRA 3.60x2.40M m 1.00 490.64 490.64 1.00 490.64 100.00% - - 0.00% - 0.00%
01.05 SEGURIDAD EN OBRA. GLB 0.30 5,162.00 1,548.60 0.30 1,548.60 100.00% 0.30 1,548.60 100.00% - 0.00%
01.06 MITIGACIÓN DEL IMPACTO AMBIENTAL GLB 0.50 2,000.00 1,000.00 - - 0.00% - - 0.00% - 0.00%
02 OBRAS PRELIMINARES
02.01 LIMPIEZA DEL TERRENO MANUAL m2 250.00 1.12 280.00 250.00 280.00 100.00% 250.00 280.00 100.00% - 0.00%
02.02 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y HERRAMIENTAS GLB 0.65 1,250.00 812.50 0.65 812.50 100.00% 0.65 812.50 100.00% - 0.00%
02.03 TRAZO, NIVELES Y REPLANTEO m2 250.00 2.41 602.50 250.00 602.50 100.00% 250.00 602.50 100.00% - 0.00%
03 MOVIMIENTO DE TIERRAS
03.01 CORTE DE TERMINO CON MAQUINARIA m3 96.50 7.81 753.67 96.50 753.67 100.00% 96.50 753.67 100.00% - 0.00%
03.02 EXCAVACION PARA ZAPATAS m3 52.65 40.48 2,131.27 52.65 2,131.27 100.00% 42.18 1,707.45 80.11% - 0.00%
03.03 EXCAVACION MANUAL DE ZANJAS PARA CIMIENTOS m3 20.00 57.82 1,156.40 20.00 1,156.40 100.00% 14.70 849.95 73.50% - 0.00%
03.04 RELLENO COMPACTADO CON MATERIAL PROPIO m3 50.00 37.74 1,887.00 50.00 1,887.00 100.00% 15.77 595.16 31.54% - 0.00%
03.05 ELIMINACION DE MATERIAL EXCEDENTE DE ZANJAS m3 50.00 16.27 813.50 - - 0.00% - - 0.00% - 0.00%
04 CONCRETO SIMPLE
04.01 CIMIENTOS CORRIDO 1:10 CEMENTO-HORMHGON+30%PG m3 17.80 293.67 5,227.33 16.15 4,741.60 90.71% 19.40 5,697.20 108.99% 1.60 469.87 8.99%
04.02 SOLADO DE 4" EN ZAPATAS CON MEZCLA 1:12 CEMENTO-HORMIGON m2 8.00 59.68 477.44 8.00 477.44 100.00% 24.81 1,480.66 310.12% 16.81 1,003.22 210.12%
04.03 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIIEIMTOS m2 25.00 67.60 1,690.00 25.00 1,690.00 100.00% 29.88 2,019.89 119.52% 4.88 329.89 19.52%
04.04 CONCRETO SOBRECIMIENTOS f''c=175 kcm2 + 25% P.M. m3 11.00 387.15 4,258.65 2.63 1,017.65 23.90% 2.25 871.09 20.45%
05 CONCRETO ARMADO
05.01 ZAPATAS
05.01.01 CONCRETO ZAPATAS f''c=210 kcm2 m3 15.00 422.41 6,336.15 15.00 6,336.01 100.00% 14.89 6,289.68 99.27%
05.01.02 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 300.00 4.95 1,485.00 300.00 1,485.00 100.00% 334.62 1,656.37 111.54% 34.62 171.37 11.54%
05.02 COLUMNAS
05.02.01 CONCRETO COLUMNAS f''c=210 kcm2 m3 9.00 559.71 5,037.39 2.64 1,479.03 29.36% 1.89 1,057.85 21.00% - 0.00%
05.02.02 ENCOFRADO Y DESENCOFRADO PARA COLUMNAS m2 75.00 36.83 2,762.25 36.50 1,344.30 48.67% 19.80 729.23 26.40% - 0.00%
05.02.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 1,550.00 4.95 7,672.50 1,550.00 7,672.50 100.00% 1,536.39 7,605.13 99.12% - 0.00%
VALORIZACIÓN TÉCNICA FINAL
Proyecto :“CREACIÓN DE LOCAL DE USOS MÚLTIPLES EN EL ANEXO TOTORALES DEL DISTRITO DE CURIBAYA- CANDARAVE TACNA” - ETAPA I
Modalidad : EJECUCIÓN PRESUPUESTARIA DIRECTA
Ubicación : Totorales - Curibaya-Candarave -Tacna
la presente valorizacion tecnica, fue realizada en base al PLAN DE TRABJO 2018, aprobada con R.A. N°349-2018-MPC
Las sgtes partidas
04.01 CIMIENTOS CORRIDO 1:10 CEMENTO-HORMHGON+30%PG
04.04 CONCRETO SOBRECIMIENTOS f''c=175 kcm2 + 25% P.M.
05.01.01 CONCRETO ZAPATAS f''c=210 kcm2
05.02.01 CONCRETO COLUMNAS f''c=210 kcm2
06.01 MURO DE SOGA LADRIILLO DE ARCILLA HERCULES (JUNTA 1.5 CM), el producto del P.U. y el metrado, no da el monto, según informe mensual.
Ver hoja de metrados