Está en la página 1de 3

Week

From
18/abr
To
24/abr
Operations Chief
Leandro Ramos 17

PLAN SEMANAL Weekly Plan Estéril

Tronaduras
Sector Labor Pendiente Sección
estimadas
TMS Zn% Pb% Au g/t Ag g/t Fe% Zn eq% Control Sector Labor Tronadas estimadas TES

PRV-3 CA-352 W 1 225


S-3 CA 351 W /CA356 5% 7.0 x 5.0 1 210 10.09 0.01 0.02 2.16 21.59 10.19 Techo : Geo. , Piso : Ing
S-3 CA 352 W /CA356 5% 7.0 x 5.0 2 650 8.78 0.01 0.17 2.16 18.01 9.14 Techo : Geo. , Piso : Ing TOTAL 1 225
Porvenir Superior

S-3 CA-315N/DI-325 14% 7.0 x 5.0 2 820 4.07 0.03 0.27 1.57 3.25 4.61 Techo : Geo. , Piso : Ing
S-3 CA-326N/DI-325 16% 7.0 x 5.0 2 820 4.50 0.03 0.11 1.66 4.07 4.77 Techo : Geo. , Piso : Ing
Sub-Total 7 2,500 5.94 0.02 0.17 1.80 8.90 6.31
S-4 XC-401 /RA-66 2% 5,0 x 5,0 1 280 6.00 0.02 0.02 2.94 5.92 6.14 Techo : Geo. , Piso : Ing
S-4 CA-408 S / XC 400 2% 5,0 x 5,0 1 280 6.75 0.01 0.30 1.79 5.70 7.34 Techo : Geo. , Piso : Ing
Porvenir S-4
S-4 XC-402 / CA-408 2% 5,0 x 5,0 2 655 8.05 0.02 0.31 2.75 8.96 8.69 Techo : Geo. , Piso : Ing

Sub-Total 4 1,215 7.28 0.02 0.24 2.57 7.51 7.79


PI-209 4 1,900 7.20 0.00 0.38 3.73 13.29 7.97 Ingeniería
XC-1755 5,0 x 5,0 2 600 6.00 0.08 0.05 8.23 7.15 6.41 Ingeniería
Rosa
BM-36 3 900 6.00 0.01 0.25 2.48 10.00 6.52 Ingeniería

Sub-Total 9 3,400 6.67 0.02 0.29 4.19 11.34 7.31


Concordia CAS 03 C06-08 4,300 5.92 0.62 0.07 38.52 4.85 7.76 Ingeniería
CAS 04 C01-05 850 8.00 0.55 0.13 73.42 7.00 10.94 Ingeniería

Sub-Total 0 5,150 6.26 0.61 0.08 44.28 5.20 8.28


Profunda Inferior DM215 3% 2 500 2.11 0.02 5.90 6.12 4.48 13.89 Techo : Geo. , Piso : Ing
Sub-Total 2 500 2.11 0.02 5.90 6.12 4.48 12.58
Zn Toqui 1016 tpd 21 7,115 6.52 0.01 0.10 1.07 4.41 6.74
Zn Concordia 736 tpd 0 5,150 6.26 0.61 0.08 44.28 5.20 8.28
Zn Total 1752 tpd 21 12,265 6.41 0.26 0.09 19.22 4.74 7.39
Au 71 tpd 2 500 2.11 0.02 5.90 6.12 4.48 12.58
Total Semanal Mineral 1824 tpd 23 12,765 6.24 0.26 0.40 19.82 7.75 7.76

Total Estéril 32 tpd 1 225


Ag
Pb

FLOTA EQUIPOS (ESTIMACION)

Mt FLOTA
Ton/Disp Nº Disp/semana HEF/Disp TPH Perf/Semana HEF Req/ Semana
EQUIPO TONELAJE TCR / Eq HH / Eq DF UT A REQUERIDA

Jumbo Avance 7,615 336 23 4.5 6,346 102 168 126 76% 65% 62 1.6

Jumbo Fortificacion 7,615 336 23 6.0 136 168 126 77% 80% 78 1.8 0

Scoop 12,765 90 142 168 126 83% 60% 63 2.3

Camion 12,765 45 284 168 126 78% 90% 88 3.2


Desde Hasta Jefe de Operaciones
Plan Semanal 19/mar 25/mar Christian Saavedra 12

PLAN SEMANAL

Tronaduras
Mina Manto Labor Ancho Alto Inc N°Tiros TMS Cut% Cui% Cus% OBSERVACIONES
estimadas

P1 10SA 3.0 3.0 -12% 11 25.0 371 Drenaje constante


P1 9N 3.0 3.0 63% 11 25.0 371 Limpieza y drenaje
P1 15N 3.0 3.0 12% 5 25.0 169 Limpieza
Penosa P1 P1 16N 3.0 3.0 12% 7 20.0 189 Limpieza
P1 16N L13 5.0 2.5 63% 3 20.0 81 Arreo
P1 10NB L17 4.0 2.2 63% 11 20.0 297
P1 16N L15 5.0 2.5 63% 3 20.0 81 Arreo
Sub-Total 51 1,559 0.00% 0.00% 0.00%
P2 18N 5.0 2.5 12% 11 25.0 371 OK

P2 18N L21 5.0 2.5 63% 7 20.0 189 OK

P2 18N L21A 5.0 2.5 63% 7 20.0 189 OK

P2 18N L22 5.0 2.5 63% 3 20.0 81 OK

P2 17N 3.0 3.0 5% 11 25.0 371 OK

P2 10N 3.0 3.0 -15% 18 25.0 608 Limpieza y drenaje


OXIDO

P2 12NC 3.0 3.0 12% 7 25.0 236 OK


Penosa P2
P2 12NC L24 5.0 2.5 63% 4 20.0 108 OK

P2 12NC L25 5.0 2.5 63% 3 20.0 81 OK

P2 12ND 3.0 3.0 0% 10 25.0 338 OK

P2 15N L16 5.0 2.5 63% 10 20.0 270 OK

P2 15S L7 5.0 2.5 63% 5 20.0 135 Trabajo con manitu

P2 15S L9 5.0 2.5 63% 2 20.0 54 OK

P2 15S L10 5.0 2.5 63% 5 20.0 135 OK


Sub-Total 103 3,166 0.00% 0.00% 0.00%
P4 18N 3.0 3.0 12% 20 25.0 675 OK
Penosa P4
P4 18S CHIMENEA 5.0 3.0 63% 20 25.0 675 OK
Sub-Total 40 1,350 0.00% 0.00% 0.00%
C3 25S L12 4.0 2.5 63% 7 20.0 189 OK
C3 25S L13 4.0 2.5 63% 7 20.0 189 OK
C3 23SA 3.0 3.0 -12% 7 25.0 236 OK
Cajon C3
C3 23NA 3.0 3.0 -12% 7 25.0 236 OK
C3 25S L8 4.0 2.5 63% 7 20.0 189 OK
C3 26S 3.0 3.0 12% 7 25.0 236 OK
Sub-Total 42 1,276 0.00% 0.00% 0.00%
Total Penosa 1470 tpd 236 7,351 0.00% 0.00% 0.00%
Total Sem Min 7,351 1470 tpd 236 7,351 0.00% 0.00% 0.00%
17

P7 17SA L11 3 3 12% 7 20 135 2.00% 1.90% 0.10% OK


Penosa P1, P7
P1 10N 3 3 7 20 135 OK
Total 14 270 1.00% 0.95% 0.05%

FORTIFICACION DRENAJE
Descripcion MINA MANTO SECTOR OBJETIVO
Obs
MINA SECTOR Malla M2 Perno SS Perno PH Prioridad P2 10N Mantener frentes operativas oxido
P4 16N shotcrete PENOSA P1 10SA Mantener frentes operativas oxido
DRIFT 11 shotcrete P2 12N D2 Mantener frentes operativas sulfuro
PENOSA
P4 15S PILAR shotcrete
DRIFT 2 shotcrete

SS Splitset ACUÑADURA
PH Perno Helicoidal MINA SECTOR OBJETIVO
Ev Evaluacion de Fort P1 Acuñadura prev
P2 Acuñadura prev
DESARROLLO P4 Acuñadura prev
PENOSA
MINA DESARROLLO DISPAROS (1.3 MTS/DISP) METROS C3 Acuñadura prev
DRIFT 560 7 9 Drift 485 Acuñadura prev
PENOSA DRIFT 515 7 9 Drift 540 Acuñadura prev
DRIFT 28 7 9
OBJETIVO SEMANA 23 14
PUNTOS ALTERNATIVOS
MINA SECTOR OBS
N° Compresor Caudal CFM Estado P1 10S BAJA LEY SULFURO
Compresor 17 502 Operativo
Compresor 18 502 Operativo
PENOSA
Compresor Doosan 850 Operativo
Compresor 2 375 Operativo
Total 2229
Descripcion de actividad - En todas las labores controlar perforacion y tronadura de contorno, tiros paralelos a caja de techo.

Mina Manto Labor Descripcion

P1

P-1

P2 11NA HABILITAR FRENTES PARA RECUPERACIÓN DE GALERÍAS DE ÓXIDO Y EXPLOTACIÓN


DE SECTOR NORESTE DE MINA PENOSA

P2

Penosa

P4 16NA D1 ARREO DE MARINA EN LEVANTES 8 Y 9; OBJETIVO: HABILITAR PIQUES DE TRASPASO


Y DEPOSITACIÓN DE ESTÉRILES DE RAMPA 520

P4

P6
Cajón C3
P7
Penosa
P4