Documentos de Académico
Documentos de Profesional
Documentos de Cultura
Item ““FORTALECIMIENTO DE CAPACIDADES EN GESTION COMUNAL EN LA COMUNIDAD DE COCAS, DISTRITO DE VILCANCHOS, PROVINCIA DE FAJARDO - AYACUCHO””.
REGION
UBICACIÓN: PROVINCIA AYACUCHO
DISTRITO FAJARDO
VILCANCHOS
MANO DE OBRA
1.00 TOPOGRAFO hh 3.02 9.00 27.15 0.00 46.01 1.39 12.49 40.39 1.22 10.97 13.60 0.41 3.69
2.00 CAPACITADOR AMBIENTALISTA GLB 1.00 350.00 350.00 0.02 46.01 0.46 161.04 40.39 0.40 141.37 13.60 0.14 47.60
3.00 OPERARIO hh 1179.78 8.75 10323.06 0.46 46.01 542.82 4749.64 40.39 476.51 4169.48 13.60 160.45 1403.94
4.00 OFICIAL hh 406.43 6.88 2796.26 0.12 46.01 187.00 1286.56 40.39 164.16 1129.41 13.60 55.27 380.29
5.00 PEON hh 1598.03 5.63 8996.92 0.40 46.01 735.25 4139.48 40.39 645.45 3633.86 13.60 217.33 1223.58
COSTO TOTAL MANO DE OBRA 22,493.39 100.00% 46.01% 10,349.21 40.39% 9,085.08 13.60% 3,059.10
COSTO TOTAL
S/. 22,493.39 100.00% S/. 10,349.21 S/. 9,085.08 S/. 3,059.10
CRONOGRAMA DE REQUERIMIENTO DE MATERIALES
Item ““FORTALECIMIENTO DE CAPACIDADES EN GESTION COMUNAL EN LA COMUNIDAD DE COCAS, DISTRITO DE VILCANCHOS, PROVINCIA DE FAJARDO - AYACUCHO””.
UBICACIÓN: REGION AYACUCHO
PROVINCIA FAJARDO
DISTRITO VILCANCHOS
PROVINCIA FAJARDO
DISTRITO VILCANCHOS
EQUIPOS Y HERRAMIENTAS
1.00 HERRAMIENTAS MANUALES %MO 1.00 658.67 658.67 44.33% 46.01 0.46 303.05 40.39 0.40 266.04 13.60 0.14
2.00 MEZCLADORA DE CONCRETO DE 9 -11P3 hm 5.21 10.00 52.06 3.50% 46.01 2.40 23.95 40.39 2.10 21.03 13.60 0.71
3.00 ANDAMIO día 43.48 5.00 217.41 14.63% 46.01 20.01 100.03 40.39 17.56 87.81 13.60 5.91
4.00 COMPACTADOR VIBR. TIPO PLANCHA 4 HP hm 13.58 8.00 108.61 7.31% 46.01 6.25 49.97 40.39 5.48 43.87 13.60 1.85
5.00 VIBRADOR DE CONCRETO 4 HP 1.50" hm 17.49 8.00 139.92 9.42% 46.01 8.05 64.38 40.39 7.06 56.51 13.60 2.38
6.00 MEZCLADORA CONCRETO TAMBOR 18HP 11P3 hm 18.88 10.00 188.76 12.70% 46.01 8.68 86.85 40.39 7.62 76.24 13.60 2.57
7.00 TEODOLITO hm 15.06 8.00 120.47 8.11% 46.01 6.93 55.43 40.39 6.08 48.66 13.60 2.05
COSTO TOTAL MANO DE OBRA 1,485.90 100.00% 46.01% 683.66 40.39% 600.16 13.60%
89.58
7.08
29.57
14.77
19.03
25.67
16.38
202.08
202.08
MANO DE OBRA
0147000032 TOPOGRAFO hh 3.0171 9.00 27.15
0147000052 CAPACITADOR AMBIENTALISTA GLB 1.0000 350.00 350.00
0147010002 OPERARIO hh 1,179.7779 8.75 10,323.06
0147010003 OFICIAL hh 406.4326 6.88 2,796.26
0147010004 PEON hh 1,598.0325 5.63 8,996.92
22,493.39
MATERIALES
0202010002 CLAVOS PARA MADERA C/C 2 1/2" kg 16.8347 5.00 84.17
0202010005 CLAVOS PARA MADERA C/C 3" kg 15.6725 5.00 78.36
0202010007 CLAVOS PARA MADERA C/C 4" kg 18.8908 5.00 94.45
0202040065 PERNO CABEZA CUADRADA DE 1/2" x 5" pza 1.0000 4.00 4.00
0202110104 FIERRO LISO DE 1/2" x 6m var 0.5000 35.00 17.50
0202970002 ACERO DE REFUERZO FY=4200 GRADO 60 kg 3,857.4998 4.00 15,430.00
0204000010 ARENA FINA (PUESTO EN OBRA) m3 12.6045 120.00 1,512.54
0205000003 PIEDRA CHANCADA DE 1/2"-3/4" m3 18.1273 180.00 3,262.91
0205010000 AFIRMADO m3 15.5636 40.00 622.54
0205010036 ARENA ZARANDEADA m3 22.9475 90.00 2,065.28
0205010037 PRUEBA DE CALIDAD DE CONCRETO ROTURA und 3.0000 90.00 270.00
0205020052 PIEDRA MEDIANA DE RIO m3 1.4760 60.00 88.56
0205030071 PIEDRA GRANDE PUESTA EN OBRA m3 6.9360 60.00 416.16
0207010000 CABLE TW # 14 AWG 2.5 MM2 m 91.2560 1.20 109.51
0207010036 CABLE TW # 8 AWG - 10mm2 m 44.8140 2.00 89.63
0207020018 ALAMBRE N° 8 kg 59.5870 5.00 297.94
0207100005 ALAMBRE N° 16 kg 144.2056 5.00 721.03
0210020056 INODORO TANQUE BAJO NORMAL BLANCO C/ACCESORIOS und 1.0000 220.00 220.00
0210040094 LAVATORIO 20"x11" DE 1 LLAVE B C/A. und 1.0000 160.00 160.00
0210120051 DISEÑO DE MEZCLA und 3.0000 90.00 270.00
0210130059 DUCHA INCLUYE GRIFERIA 1 LLAVE und 1.0000 75.00 75.00
0211210033 FLUORESCENTE 40 W und 6.0000 45.00 270.00
0212080000 SOCKET DE BAKELITA und 6.0000 5.00 30.00
0212090004 CAJA RECTANG GALV 4"X2 1/8" und 16.0000 1.80 28.80
0212090049 CAJA OCTOGONAL GALV. 4" X 2 1/8 " und 12.0000 1.20 14.40
0212120025 FOCO AHORRADOR 20 W und 6.0000 20.00 120.00
0212400084 INTERRUPTOR TERMOMAGNETICO DE 2x25Ax220V und 2.0000 35.00 70.00
0217080005 LADRILLO DE ARCILLA K.K. (PUESTO EN OBRA) und 3,390.8000 0.80 2,712.64
0217220005 CAJA DE REGISTRO DE MAMPOSTERIA 12"X12" und 1.0000 15.00 15.00
0217300005 LADRILLO HUECO 15 X 30 X 30 CM und 636.0060 3.50 2,226.02
0221000000 CEMENTO PORTLAND TIPO I (42.5KG) BOL 613.6616 27.00 16,568.86
0224030030 MAYOLICA COLOR 1ra 20x30 CM m2 16.0755 35.00 562.64
0226070010 CERRADURA DE TRES GOLPES und 5.0000 55.00 275.00
0226080015 BISAGRA ALUMINIZ.CAPUCHINA 4"x4" und 15.0000 4.00 60.00
0229030002 YESO EN BOLSAS DE 25 KG. BOL 6.5875 8.00 52.70
0229040001 CINTA AISLANTE rll 9.2850 3.50 32.50
0229070083 CANASTILLA DE SUCCION DE 6" (160 mm.) pza 6.0000 15.00 90.00
0229150099 OCRE kg 8.4720 6.00 50.83
0230010103 PEGAMENTO PARA PVC AGUA FORDUIT gln 1.4811 80.00 118.49
0230130024 PEGAMENTO EN POLVO GRIS (25 KG) BOL 3.0620 18.00 55.12
0230290020 RODOPLAST PARA BORDE DE MAYOLICAS m 7.6550 2.50 19.14
0230480032 CINTA TEFLON pza 0.5000 1.00 0.50
0230510127 FRAGUA (5KG) BOL 3.0620 6.00 18.37
0230530001 MASILLA PARA VIDRIO kg 8.0300 4.00 32.12
0230610004 GABINETE METALICO 8 POLOS C/ CHAPA Y BARRA DE COBRE pza 1.0000 40.00 40.00
0230700089 GIGANTOGRAFIA DE LONA DE 3.60 x 2.40 m (Inc. diseño) und 1.0000 220.00 220.00
0232990010 FLETE AYACUCHO - VILCANCHOS (COCAS) GLB 1.0000 4,000.00 4,000.00
0234000001 GASOLINA 95 OCTANOS gln 4.5607 13.50 61.57
0238000004 HORMIGON (PUESTO EN OBRA) m3 41.2881 80.00 3,303.05
0239010047 LIJA PAPEL GRANATE ASA 80 plg 30.7995 2.00 61.60
0239050000 AGUA m3 10.3649 1.00 10.36
0243010003 MADERA TORNILLO p2 1,431.0956 6.00 8,586.57
0243160052 REGLA DE MADERA p2 52.2288 4.00 208.92
0243600043 ROLLIZO DE EUCALIPTO DE 3" X 3 M pza 180.2750 15.00 2,704.13
0250010000 CAJA DE DESAGUE DE 12"X24" und 1.0000 40.00 40.00
0250060010 TAPA C/MARCO FºFº DE DESAGUE 12" X 24" pza 1.0000 30.00 30.00
0250550011 TAPA Y MARCO F°GAL. P/REGISTRO 12" X 12" pza 1.0000 20.00 20.00
0251990008 VENTANA METALICA V4 1.2 X 0.60 und 1.0000 120.00 120.00
0251990009 VENTANA METALICA V2 1.2 X 1.40 und 2.0000 180.00 360.00
0251990094 VENTANA METALICA V1 1.4 X 1.4 und 1.0000 220.00 220.00
0251990095 VENTANA METALICA V3 2.0 X 1.4 und 3.0000 250.00 750.00
0253030027 THINER gln 1.2613 16.00 20.18
0253040002 BREA kg 7.6000 5.50 41.80
0254010015 IMPRIMANTE gln 39.5090 18.00 711.16
0254010051 PINTURA LATEX gln 14.2494 32.00 455.98
0254020042 PINTURA ESMALTE SINTETICO gln 2.8290 40.00 113.16
0254310018 PINTURA ESMALTE OLEO MATE gln 6.6270 42.00 278.33
0256020100 PLANCHA CORRUGADA SUPER TECHALIT 1.80 X 0.60M m2 0.1000 400.00 40.00
0265050011 UNION UNIVERSAL DE Fo. GALV. DE 1/2" und 2.0000 2.50 5.00
0265130064 NIPLE DE Fo Go DE 1/2" x 1 1/2" und 2.0000 2.50 5.00
0265170028 TUB. Fo. NEGRO STAND.ISO-I 3/4" x 6.4m und 0.0415 40.00 1.66
0268040000 SUMIDERO DE BRONCE DE 2" und 2.0000 15.00 30.00
0272000081 TUB. PVC SAP PRESION P/AGUA C-10 R. 1/2" m 6.9300 6.00 41.58
0272000082 TUB. PVC SAP PRESION P/AGUA C-10 R. 3/4" m 5.6175 6.50 36.51
0272100001 UNION PVC SAP P/INST. ELECT. DE 3/4" und 12.0000 1.00 12.00
0272140001 CODO DE 90 PVC SAL DE 2" und 3.0000 8.00 24.00
0272150074 REDUCCION PVC C-10 160-63 mm UF CON ANILLO Y ESPIGA CAMPANA (LADO pza 1.0000 8.00 8.00
0272250002 MENOR DIAMETRO)
CURVA LIVIANO PVC SEL P/INST. ELECT 3/4" und 26.0000 0.80 20.80
0272300089 CODO DE 45° PVC SAL DE 2" und 3.0000 8.00 24.00
0272300090 CODO DE 90º PVC SAL DE 2" und 4.0000 8.00 32.00
0272320002 YEE PVC SAL 2" und 3.0000 8.00 24.00
0273010026 TUBERIA PVC SAL 2" m 10.2710 3.50 35.95
0273010029 TUBERIA PVC SAL 4" m 15.5820 8.00 124.66
0273230001 SOMBRERO DE VENTILACION PVC SAL 2" pza 1.0000 9.00 9.00
0274010002 TUBO PVC SAP (LUZ) (E/C) 3/4" X 3 M. pza 77.6820 3.50 271.89
0275120002 UNION PVC SEL 3/4" pza 24.0000 0.50 12.00
0275130005 CURVAS PVC SEL 3/4" pza 24.0000 0.80 19.20
0277000002 VALVULA COMPUERTA DE BRONCE DE 1/2" und 1.0000 30.00 30.00
0277030002 VALVULA CHECK DE BRONCE DE 1/2" und 1.0000 22.00 22.00
0279010078 VIDRIO DOBLE p2 168.6300 3.50 590.21
0279560002 PLACA ACRILICA und 1.0000 380.00 380.00
0299010034 MALLA MOSQUITERO m2 0.5000 4.50 2.25
0299010101 CLAVO 5" kg 1.0000 5.00 5.00
73,476.23
EQUIPOS
0337010001 HERRAMIENTAS MANUALES %MO 658.67
0348010011 MEZCLADORA DE CONCRETO DE 9 -11P3 hm 5.2055 10.00 52.06
0348800000 ANDAMIO día 43.4812 5.00 217.41
0349030001 COMPACTADOR VIBR. TIPO PLANCHA 4 HP hm 13.5765 8.00 108.61
0349070003 VIBRADOR DE CONCRETO 4 HP 1.50" hm 17.4895 8.00 139.92
0349100007 MEZCLADORA CONCRETO TAMBOR 18HP 11P3 hm 18.8759 10.00 188.76
0349880003 TEODOLITO hm 15.0590 8.00 120.47
1,485.90
SUBCONTRATOS
0401010031 PUERTA DE MADERA MACHIEMBRADA 1.60X2.45M und 1.0000 1,200.00 1,200.00
0401010032 PUERTA DE MADERA MACHIEMBRADA 1.00X2.45M und 2.0000 950.00 1,900.00
0401010033 PUERTA DE MADERA MACHIEMBRADA 0.80X2.45M und 1.0000 500.00 500.00
0401010034 PUERTA DE MADERA MACHIEMBRADA 0.90X2.45M und 1.0000 600.00 600.00
4,200.00
84.17
78.36
94.45
4.00
17.50
15,430.00
1,512.54
3,262.91
622.54
2,065.28
270.00
88.56
416.16
109.51
89.63
297.94
721.03
220.00
160.00
270.00
75.00
270.00
30.00
28.80
14.40
120.00
70.00
2,712.64
15.00
2,226.02
16,568.86
562.64
275.00
60.00
52.70
32.50
90.00
50.83
118.49
55.12
19.14
0.50
18.37
32.12
40.00
220.00
4,000.00
61.57
3,303.05
61.60
10.36
8,586.57
208.92
2,704.13
40.00
30.00
20.00
120.00
360.00
220.00
750.00
20.18
41.80
711.16
455.98
113.16
278.33
40.00
5.00
5.00
1.66
30.00
41.58
36.51
12.00
24.00
8.00
20.80
24.00
32.00
24.00
35.95
124.66
9.00
271.89
12.00
19.20
30.00
22.00
590.21
380.00
2.25
5.00
73,476.23
658.67
52.06
217.41
108.61
139.92
188.76
120.47
1,485.90
1,200.00
1,900.00
500.00
600.00
4,200.00
101,655.52
CRONOGRAMA VALORIZADO MENSUAL DE OBRA
PROYECTO : "AMPLIACION Y MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LA INSTITUCION EDUCATIVA INICIAL N° 425 Mx-U DE CHANEN, DISTRITO DE VILCASHUAMAN, PROVINCIA DE VILCASHUAMAN, REGION DE AYACUCHO"
FECHA : SETIEMBRE 2013
COSTO DIRECTO DEL PROYECTO S/. 5,263,448.34 PLAZO DE EJECUCION: 5.0 MESES
PROYECTO : "AMPLIACION Y MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LA INSTITUCION EDUCATIVA INICIAL N° 425 Mx-U DE CHANEN, DISTRITO DE VILCASHUAMAN, PROVINCIA DE VILCASHUAMAN, REGION DE AYACUCHO"
FECHA : SETIEMBRE 2013
COSTO DIRECTO DEL PROYECTO S/. 5,263,448.34 PLAZO DE EJECUCION: 5.0 MESES