Está en la página 1de 5

CRONOGRAMA VALORIZADO MENSUAL DE MANO DE OBRA

“CREACION DEL MALECÓN ECOTURÍSTICO SECTOR SUPERIOR DE LA PLAYA REVÉS EN LA CALLE GAVIOTAS ZONA SUR DEL DISTRITO DE PUNTA NEGRA - PROVINCIA DE LIMA -
DEPARTAMENTO DE LIMA”
DIST. : PUNTA NEGRA
PROV. : LIMA FECHA: ABRIL 2022
DPTO. : LIMA
MES 01 MES 02 MES 03 MES 04
ITEM DESCRIPCION UND CANT. PRECIO TOTAL
% COSTO S/. % COSTO S/. % COSTO S/. % COSTO S/.
MANO DE OBRA
0101010003 OPERARIO hh 3,746.8430 24.19 90,636.13 9.75% 8,836.09 29.11% 26,383.67 24.22% 21,955.24 36.92% 33,461.13
0101010004 OFICIAL hh 3,786.3154 19.09 72,280.76 9.75% 7,046.63 29.11% 21,040.52 24.22% 17,508.93 36.92% 26,684.67
0101010005 PEON hh 11,922.6026 17.25 205,664.89 9.75% 20,050.21 29.11% 59,867.90 24.22% 49,819.23 36.92% 75,927.54
0101030000 TOPOGRAFO hh 63.8492 24.19 1,544.51 9.75% 150.57 29.11% 449.60 24.22% 374.13 36.92% 570.20
0101030009 CONSULTOR EXPERTO EN SSOMA (COVID-19) hh 2.4000 2,500.00 6,000.00 9.75% 584.94 29.11% 1,746.57 24.22% 1,453.41 36.92% 2,215.09
TOTAL MANO DE OBRA POR MES 376,126.29 36,668.45 109,488.26 91,110.95 138,858.63
CRONOGRAMA VALORIZADO MENSUAL DE MATERIALES

“CREACION DEL MALECÓN ECOTURÍSTICO SECTOR SUPERIOR DE LA PLAYA REVÉS EN LA CALLE GAVIOTAS ZONA SUR DEL DISTRITO DE PUNTA NEGRA - PROVINCIA DE LIMA - DEPARTAMENTO DE LIMA”
DIST. : PUNTA NEGRA
PROV. : LIMA FECHA: ABRIL 2022
DPTO. : LIMA
MES 01 MES 02 MES 03 MES 04
ITEM DESCRIPCION UND CANT. PRECIO TOTAL
% COSTO S/. % COSTO S/. % COSTO S/. % COSTO S/.
MATERIALES
0201040003 KEROSENE gal 97.9626 13.73 1,345.03 0.00 0.00 100.00% 1,345.03 0.00
02010500010007 ASFALTO MC-30 gal 1,008.2800 14.00 14,115.92 0.00 0.00 100.00% 14,115.92 0.00
0201050005 MEZCLA ASFALTICA m3 189.0076 490.00 92,613.72 0.00 0.00 100.00% 92,613.72 0.00
02040100010001 ALAMBRE NEGRO RECOCIDO N° 8 kg 377.8968 4.69 1,772.34 100.00% 1,772.34 0.00 0.00 0.00
02040100010002 ALAMBRE NEGRO RECOCIDO N° 16 kg 230.3535 4.69 1,080.36 100.00% 1,080.36 0.00 0.00 0.00
0204030001 ACERO CORRUGADO fy = 4200 kg/cm2 GRADO 60 kg 7,908.8035 4.21 33,296.06 50.00% 16,648.03 50.00% 16,648.03 0.00 0.00
02041200010004 CLAVOS PARA MADERA CON CABEZA DE 2 1/2" kg 842.5274 4.94 4,162.09 50.00% 2,081.05 50.00% 2,081.05 0.00 0.00
02041200010005 CLAVOS PARA MADERA CON CABEZA DE 3" kg 283.4235 4.94 1,400.11 50.00% 700.06 50.00% 700.06 0.00 0.00
0204150003 MALLA DE SEGURIDAD DE PVC rll 5.0000 55.41 277.05 100.00% 277.05 0.00 0.00 0.00
02070100010002 PIEDRA CHANCADA 1/2" m3 302.6335 55.00 16,644.84 50.00% 8,322.42 50.00% 8,322.42 0.00 0.00
0207010005 PIEDRA MEDIANA m3 253.7410 55.00 13,955.76 50.00% 6,977.88 50.00% 6,977.88 0.00 0.00
02070200010001 ARENA FINA m3 3.6382 35.00 127.34 50.00% 63.67 50.00% 63.67 0.00 0.00
02070200010002 ARENA GRUESA m3 256.0747 35.00 8,962.61 50.00% 4,481.31 50.00% 4,481.31 0.00 0.00
0207020003 AFIRMADO m3 1,247.4552 35.00 43,660.93 0.00 0.00 100.00% 43,660.93 0.00
0207030001 HORMIGON m3 432.4197 31.00 13,405.01 50.00% 6,702.51 50.00% 6,702.51 0.00 0.00
02070500010002 TIERRA DE CHACRA m3 1,214.5534 32.00 38,865.71 0.00 0.00 0.00 100.00% 38,865.71
0207070001 AGUA PUESTA EN OBRA m3 1,284.5875 17.00 21,837.99 25.00% 5,459.50 25.00% 5,459.50 25.00% 5,459.50 25.00% 5,459.50
0210030003 LONA NEGRA m2 894.7100 2.50 2,236.78 100.00% 2,236.78 0.00 0.00 0.00
0213010003 CEMENTO PORTLAND TIPO V bol 5,998.4240 28.50 170,955.08 50.00% 85,477.54 50.00% 85,477.54 0.00 0.00
0213030001 YESO kg 192.2743 1.06 203.81 100.00% 203.81 0.00 0.00 0.00
0216020011 GRASS NATURAL m2 4,774.7710 15.45 73,770.21 0.00 0.00 0.00 100.00% 73,770.21
0222140006 LACA DESMOLDEADORA gal 56.9230 119.85 6,822.22 50.00% 3,411.11 50.00% 3,411.11 0.00 0.00
0231010001 MADERA TORNILLO p2 7,521.8046 7.85 59,046.17 50.00% 29,523.09 50.00% 29,523.09 0.00 0.00
02310500010004 TRIPLAY LUPUNA 4 x 8 x 19 mm pln 136.6152 115.20 15,738.07 100.00% 15,738.07 0.00 0.00 0.00
0231220002 PANELES DE INFORMACION und 2.0000 45.00 90.00 100.00% 90.00 0.00 0.00 0.00
0231220003 PANELES DE PREVENCION und 2.0000 45.00 90.00 100.00% 90.00 0.00 0.00 0.00
0240060009 MICROESFERAS DE VIDRIO kg 138.6000 10.50 1,455.30 0.00 0.00 0.00 100.00% 1,455.30
0240060011 PINTURA PARA TRAFICO AMARILLA gal 19.7297 55.00 1,085.13 0.00 0.00 0.00 100.00% 1,085.13
0240060012 PINTURA PARA TRAFICO BLANCA gal 19.2408 55.00 1,058.24 0.00 0.00 0.00 100.00% 1,058.24
0240060013 PINTURA PARA TRAFICO ROJA gal 155.1075 65.00 10,081.99 0.00 0.00 0.00 100.00% 10,081.99
0240080015 SOLVENTE DE PINTURA DE TRAFICO gal 127.1891 35.00 4,451.62 0.00 0.00 0.00 100.00% 4,451.62
0246160003 GIGANTOGRAFIA m2 30.6000 9.92 303.55 100.00% 303.55 0.00 0.00 0.00
02461800010006 PULSOXIMETRO U OXIMETRO DE DEDO und 1.0000 151.41 151.41 100.00% 151.41 0.00 0.00 0.00
02461800010007 PEDILUVIO DE ACERO INOXIDABLE und 1.0000 121.75 121.75 100.00% 121.75 0.00 0.00 0.00
0246180002 TERMÓMETRO DIGITAL INFRARROJO und 1.0000 190.68 190.68 100.00% 190.68 0.00 0.00 0.00
0246180003 CONTENEDOR DE DESECHOS BIOCONTAMINADOS 120L und 1.0000 135.00 135.00 100.00% 135.00 0.00 0.00 0.00
02670100010009 CASCO CON PROTECTOR FACIAL und 20.0000 69.21 1,384.20 100.00% 1,384.20 0.00 0.00 0.00
0267020001 LENTES DE POLICARBONA LUNA CLARA und 20.0000 10.88 217.60 100.00% 217.60 0.00 0.00 0.00
0267030003 TAPONES DE ESPUMA CON CUERDA und 60.0000 7.60 456.00 100.00% 456.00 0.00 0.00 0.00
0267030009 MASCARILLA QUIRÚRGICA - MINSA und 200.0000 3.25 650.00 100.00% 650.00 0.00 0.00 0.00
0267050001 GUANTES DE CUERO par 120.0000 6.48 777.60 100.00% 777.60 0.00 0.00 0.00
02670600060004 PANTALON DRILL NARANJA und 20.0000 45.50 910.00 100.00% 910.00 0.00 0.00 0.00
0267060012 POLOS und 40.0000 14.50 580.00 100.00% 580.00 0.00 0.00 0.00
0267060017 CORTAVIENTO PARA CASCO und 40.0000 16.45 658.00 100.00% 658.00 0.00 0.00 0.00
0267060018 CHALECO REFLECTIVO und 20.0000 13.84 276.80 100.00% 276.80 0.00 0.00 0.00
0267070001 BOTINES DE CUERO CON PUNTA DE ACERO par 20.0000 43.79 875.80 100.00% 875.80 0.00 0.00 0.00
CRONOGRAMA VALORIZADO MENSUAL DE MATERIALES

“CREACION DEL MALECÓN ECOTURÍSTICO SECTOR SUPERIOR DE LA PLAYA REVÉS EN LA CALLE GAVIOTAS ZONA SUR DEL DISTRITO DE PUNTA NEGRA - PROVINCIA DE LIMA - DEPARTAMENTO DE LIMA”
DIST. : PUNTA NEGRA
PROV. : LIMA FECHA: ABRIL 2022
DPTO. : LIMA
MES 01 MES 02 MES 03 MES 04
ITEM DESCRIPCION UND CANT. PRECIO TOTAL
% COSTO S/. % COSTO S/. % COSTO S/. % COSTO S/.
0267100004 CAMILLA RIGIDA DE MADERA und 1.0000 300.85 300.85 100.00% 300.85 0.00 0.00 0.00
0267100005 BOTIQUIN (equipado segun lista de materiales) und 0.0000 78.95 0.00 100.00% 0.00 0.00 0.00 0.00
0267110013 CONOS REFLECTANTES und 10.0000 27.88 278.80 100.00% 278.80 0.00 0.00 0.00
0267110023 CINTA DE SEGURIDAD rll 4.0000 35.50 142.00 100.00% 142.00 0.00 0.00 0.00
0267110024 SEÑALIZACION INFORMATIVA und 1.0000 455.00 455.00 100.00% 455.00 0.00 0.00 0.00
0271050139 PERNO HEXAGONAL DE 3/4" X 6" INC. TUERCA und 11.0000 2.32 25.52 100.00% 25.52 0.00 0.00 0.00
0271050140 PLANTA DE FICUS und 29.0000 30.00 870.00 0.00 0.00 0.00 100.00% 870.00
0271050146 PLANTA DE MEIJO und 39.0000 25.00 975.00 0.00 0.00 0.00 100.00% 975.00
0272040053 MOVILIZACION Y DESMOVILIZACION DE EQUIPO Y MAQUINARIAS glb 1.0000 17,228.57 17,228.57 100.00% 17,228.57 0.00 0.00 0.00
0279010048 ALCOHOL GEL AL 70% (1 litro rinde 1000 aplicaciones) l 120.0000 8.51 1,021.20 100.00% 1,021.20 0.00 0.00 0.00
02901300080004 JABON LIQUIDO (galòn de 4 litros 2000 aplicaciones) gal 2.0000 23.45 46.90 100.00% 46.90 0.00 0.00 0.00
0290130013 PAPEL TOALLA und 30.0000 6.58 197.40 100.00% 197.40 0.00 0.00 0.00
02901300130008 LIMPIADOR DESINFECTANTE (Lavanda 19 L) und 10.0000 40.03 400.30 100.00% 400.30 0.00 0.00 0.00
02901500260002 CARTEL DE SEGURIDAD und 2.0000 120.00 240.00 100.00% 240.00 0.00 0.00 0.00
02901800040006 MATERIAL CAPACITACION (FOLLETOS) und 50.0000 5.00 250.00 25.00% 62.50 25.00% 62.50 25.00% 62.50 25.00% 62.50
02901800040007 MATERIAL CAPACITACION COVID-1 (FOLLETOS) und 50.0000 5.00 250.00 25.00% 62.50 25.00% 62.50 25.00% 62.50 25.00% 62.50
0291020001 ABONOS NATURALES kg 16,233.1100 2.18 35,388.18 0.00 0.00 0.00 100.00% 35,388.18
TOTAL MATERIALES POR MES 720,365.60 219,486.48 169,973.14 157,320.09 173,585.88
CRONOGRAMA VALORIZADO MENSUAL DE EQUIPOS

“CREACION DEL MALECÓN ECOTURÍSTICO SECTOR SUPERIOR DE LA PLAYA REVÉS EN LA CALLE GAVIOTAS ZONA SUR DEL DISTRITO DE PUNTA NEGRA - PROVINCIA DE LIMA -
DEPARTAMENTO DE LIMA”
DIST. : PUNTA NEGRA
PROV. : LIMA FECHA: ABRIL 2022
DPTO. : LIMA
MES 01 MES 02 MES 03 MES 04
ITEM DESCRIPCION UND CANT. PRECIO TOTAL
% COSTO S/. % COSTO S/. % COSTO S/. % COSTO S/.
EQUPOS Y HERRAMIENTAS
0301000020 ESTACION TOTAL hm 63.8492 20.00 1,276.98 50.00% 638.49 50.00% 638.49 0.00 0.00
0301000021 NIVEL TOPOGRAFICO CON TRIPODE he 63.8492 7.50 478.87 50.00% 239.44 50.00% 239.44 0.00 0.00
0301010006 HERRAMIENTAS MANUALES %mo 8,805.40 100.00% 8,805.40 0.00 0.00 0.00
0301100001 COMPACTADORA VIBRATORIA TIPO PLANCHAhm 200.3874 20.00 4,007.75 0.00 100.00% 4,007.75 0.00 0.00
03011000040003 RODILLO NEUMATICO AUTOP. 127 HP 8-23 TO hm 5.0647 200.00 1,012.94 0.00 0.00 100.00% 1,012.94 0.00
0301100010 RODILLO LISO VIBR AUTOP 101-135HP 10-12T hm 56.2818 180.00 10,130.72 0.00 0.00 100.00% 10,130.72 0.00
0301100011 RODILLO TANDEM ESTATIC AUT 58-70HP 8-10T hm 5.0647 220.00 1,114.23 0.00 0.00 100.00% 1,114.23 0.00
0301100012 COMPACTADORA VIBRATORIA TIPO PLANCHAhm 118.3793 10.00 1,183.79 0.00 0.00 100.00% 1,183.79 0.00
0301120005 MAQUINA PARA PINTADO DE LINEAS hm 121.5816 20.00 2,431.63 0.00 0.00 0.00 100.00% 2,431.63
03011400020004 MARTILLO NEUMATICO DE 24 kg hm 0.4749 12.00 5.70 100.00% 5.70 0.00 0.00 0.00
0301140006 COMPRESORA NEUMATICA hm 0.4749 120.00 56.99 100.00% 56.99 0.00 0.00 0.00
03011600010003 CARGADOR SOBRE LLANTAS DE 125-135 HP 3 y hm 88.3653 200.00 17,673.06 0.00 0.00 100.00% 17,673.06 0.00
0301180005 TRACTOR DE ORUGAS DE 140-160 HP hm 11.9208 250.00 2,980.20 0.00 0.00 100.00% 2,980.20 0.00
03012000010005 MOTONIVELADORA DE 125 HP hm 28.0593 210.00 5,892.45 0.00 0.00 100.00% 5,892.45 0.00
03012200040005 CAMION VOLQUETE DE 12 m3 hm 327.6710 120.00 39,320.52 0.00 0.00 100.00% 39,320.52 0.00
03012200080001 CAMION IMPRIMADOR DE 1800 gl hm 11.5955 280.00 3,246.74 0.00 0.00 100.00% 3,246.74 0.00
0301220011 CAMION CISTERNA 4x2 (AGUA) 122 HP 2,000G hm 164.4906 120.00 19,738.87 25.00% 4,934.72 25.00% 4,934.72 25.00% 4,934.72 25.00% 4,934.72
03012900010005 VIBRADOR DE CONCRETO 4 HP 2.40" hm 310.4088 10.00 3,104.09 50.00% 1,552.05 50.00% 1,552.05 0.00 0.00
03012900030001 MEZCLADORA DE CONCRETO 11 P3 (23 HP) hm 676.4823 20.00 13,529.65 50.00% 6,764.83 50.00% 6,764.83 0.00 0.00
0301390001 PAVIMENTADORA SOBRE LLANTAS hm 5.0647 310.00 1,570.06 0.00 0.00 100.00% 1,570.06 0.00
0301390009 BARRENOS hm 0.4749 12.00 5.70 100.00% 5.70 0.00 0.00 0.00
TOTAL EQUIPOS POR MES 137,566.34 23,003.30 18,137.26 89,059.43 7,366.35
CRONOGRAMA VALORIZADO MENSUAL DE SUBCONTRATOS

“CREACION DEL MALECÓN ECOTURÍSTICO SECTOR SUPERIOR DE LA PLAYA REVÉS EN LA CALLE GAVIOTAS ZONA SUR DEL DISTRITO DE PUNTA NEGRA - PROVINCIA DE
LIMA - DEPARTAMENTO DE LIMA”
DIST. : PUNTA NEGRA
PROV. : LIMA FECHA: ABRIL 2022
DPTO. : LIMA
MES 01 MES 02 MES 03 MES 04
ITEM DESCRIPCION UND CANT. PRECIO TOTAL
% COSTO S/. % COSTO S/. % COSTO S/. % COSTO S/.
EQUPOS Y HERRAMIENTAS
04230400010007 SC SERVICIOS HIENICOS PORTATI mes 4.0000 420.90 1,683.60 25.00% 420.90 25.00% 420.90 25.00% 420.90 25.00% 420.90
04230400010008 SC OFICINA Y ALMACENES mes 4.0000 600.00 2,400.00 25.00% 600.00 25.00% 600.00 25.00% 600.00 25.00% 600.00
04230400010009 SC AMBIENTE DE CONTROL DE DE mes 4.0000 450.00 1,800.00 25.00% 450.00 25.00% 450.00 25.00% 450.00 25.00% 450.00
0428010003 ELABORACION, IMPLEMENTACIONglb 1.0000 5,000.00 5,000.00 100.00% 5,000.00 0.00 0.00 0.00
TOTAL EQUIPOS POR MES 10,883.60 6,470.90 1,470.90 1,470.90 1,470.90