CRONOGRAMA VALORIZADO MENSUAL DE ADQUISICIÓN DE MANO DE OBRA, MATERIALES Y EQUIPOS

"MEJORAMIENTO CON SECTORIZACION DEL SISTEMA DE DISTRIBUCION DE AGUA POTABLE DEL DISTRITO DE TUPAC AMARU, PROVINCIA DE PISCO,
DEPARTAMENTO DE ICA"
FECHA: jun-22
MES 01 MES 02
ITEM UND CANT. PRECIO TOTAL
CANT. COSTO S/. CANT. COSTO S/.

1.00 MANO DE OBRA


0101010002 CAPATAZ hh 66.6932 26.60 1,774.04 50.00% 887.02 50.0% 887.02
0101010003 OPERARIO hh 488.6657 24.18 11,815.94 50.00% 5,907.97 50.0% 5,907.97
0101010004 OFICIAL hh 152.2472 19.09 2,906.40 50.00% 1,453.20 50.0% 1,453.20
0101010005 PEON hh 706.9276 17.26 12,201.57 50.00% 6,100.79 50.0% 6,100.79
01010100060002 OPERADOR DE EQUIPO LIVIANO hh 6.7906 23.44 159.17 50.00% 79.59 50.0% 79.59
2.00 MATERIALES
0201030001 GASOLINA gal 0.3132 20.50 6.42 50.00% 3.21 50.0% 3.21
0203020002 FLETE TERRESTRE glb 3.0000 800.00 2,400.00 100.00% 1,200.00 0.0% 1,200.00
02040100010001 ALAMBRE NEGRO RECOCIDO N° 8 kg 19.5520 6.00 117.31 50.00% 58.66 50.0% 58.66
02040100010002 ALAMBRE NEGRO RECOCIDO N° 16 kg 58.7417 6.00 352.45 50.00% 176.23 50.0% 176.23
02040100020001 ALAMBRE NEGRO N° 16 kg 64.0000 6.00 384.00 50.00% 192.00 50.0% 192.00
0204020009 ANGULO 1 1/2"x1 1/2x3/16"x6m var 4.0000 48.70 194.80 0.00% 97.40 100.0% 97.40
0204030001 ACERO CORRUGADO fy = 4200 kg/cm2 GRADO 60 kg 1,332.5550 4.98 6,636.12 50.00% 3,318.06 50.0% 3,318.06
02041200010001 CLAVOS PARA MADERA CON CABEZA DE 1" kg 32.0000 6.00 192.00 50.00% 96.00 50.0% 96.00
02041200010002 CLAVOS PARA MADERA CON CABEZA 1 1/2" kg 1.7800 6.00 10.68 50.00% 5.34 50.0% 5.34
02041200010003 CLAVOS PARA MADERA CON CABEZA DE 2" kg 36.0000 6.00 216.00 50.00% 108.00 50.0% 108.00
02041200010004 CLAVOS PARA MADERA CON CABEZA DE 3" kg 5.8558 6.00 35.13 50.00% 17.57 50.0% 17.57
02041200010005 CLAVOS PARA MADERA CON CABEZA DE 3" kg 15.6083 6.00 93.65 50.00% 46.83 50.0% 46.83
02041200010007 CLAVOS PARA MADERA CON CABEZA DE 4" kg 1.6260 4.15 6.75 50.00% 3.38 50.0% 3.38
0204210005 TEE DE ACERO DE 1 1/2"X1 1/2"X3/16" und 3.0000 65.50 196.50 0.00% 98.25 100.0% 98.25
0204240030 ABRAZADERA F° G° und 12.0000 18.00 216.00 0.00% 108.00 100.0% 108.00
02050100010001 TUBERIA PVC-SAP ELECTRICA DE 1/2" X 3 m (15 mm) m 17.5064 4.66 81.58 0.00% 40.79 100.0% 40.79
02050200010001 CURVAS PVC-SAP ELECTRICAS 1/2" und 9.3752 1.06 9.94 0.00% 4.97 100.0% 4.97
02050400010001 CONEXIONES PVC-SAP 1/2" ELECTRICAS und 3.7226 0.42 1.56 0.00% 0.78 100.0% 0.78
02070100010002 PIEDRA CHANCADA 1/2" m3 7.2788 45.00 327.55 50.00% 163.78 50.0% 163.78
0207010005 PIEDRA CHANCADA DE 1/2" m3 9.8306 55.01 540.78 50.00% 270.39 50.0% 270.39
02070200010001 ARENA FINA m3 42.5068 38.14 1,621.21 50.00% 810.61 50.0% 810.61
02070200010002 ARENA GRUESA m3 11.6010 50.85 589.91 50.00% 294.96 50.0% 294.96
0207030001 HORMIGON m3 0.8026 35.00 28.09 50.00% 14.05 50.0% 14.05
0207040002 AFIRMADO m3 14.5800 35.00 510.30 50.00% 255.15 50.0% 255.15
0207070001 AGUA PUESTA EN OBRA m3 12.2884 11.20 137.63 50.00% 68.82 50.0% 68.82
CRONOGRAMA VALORIZADO MENSUAL DE ADQUISICIÓN DE MANO DE OBRA, MATERIALES Y EQUIPOS
"MEJORAMIENTO CON SECTORIZACION DEL SISTEMA DE DISTRIBUCION DE AGUA POTABLE DEL DISTRITO DE TUPAC AMARU, PROVINCIA DE PISCO,
DEPARTAMENTO DE ICA"
FECHA: jun-22
MES 01 MES 02
ITEM UND CANT. PRECIO TOTAL
CANT. COSTO S/. CANT. COSTO S/.

0210030003 MALLA RASCHEL m 80.0000 12.00 960.00 50.00% 480.00 50.0% 480.00
0211010001 FO CONSTRUCCION kg 1.0185 3.25 3.31 50.00% 1.66 50.0% 1.66
0213010001 CEMENTO PORTLAND TIPO I (42.5 kg) bol 253.0142 22.54 5,702.94 50.00% 2,851.47 50.0% 2,851.47
0213030001 YESO kg 1.1250 8.40 9.45 50.00% 4.73 50.0% 4.73
02160100010001 LADRILLO KK 18 HUECOS 9X13X24 cm und 1,994.4000 1.40 2,792.16 50.00% 1,396.08 50.0% 1,396.08
02160100040002 LADRILLO PARA TECHO 8H DE 15X30X30 cm und 136.5000 3.50 477.75 50.00% 238.88 50.0% 238.88
0217010002 REGLA DE ALUMINIO 1"X4"X8" und 0.3044 25.00 7.61 50.00% 3.81 50.0% 3.81
0222080012 PEGAMENTO PARA PVC gal 0.0480 150.00 7.20 50.00% 3.60 50.0% 3.60
0222160008 MASILLA PLASTICA gal 1.1160 75.60 84.37 50.00% 42.19 50.0% 42.19
0231010001 MADERA TORNILLO p2 535.4396 5.05 2,703.97 50.00% 1,351.99 50.0% 1,351.99
0231010004 LISTONES MADERA TORNILLO und 40.0000 13.50 540.00 50.00% 270.00 50.0% 270.00
0237000002 PUERTA METALICA und 1.0000 1,200.00 1,200.00 50.00% 600.00 50.0% 600.00
0237000003 MALLA GALVANIZADA ELECTROSOLDADA N° 10 2"x2" m2 37.8000 30.00 1,134.00 0.00% 567.00 100.0% 567.00
0238010002 LIJA PARA FIERRO plg 22.3200 3.50 78.12 50.00% 39.06 50.0% 39.06
0238010005 LIJA PARA PARED und 19.0010 2.20 41.80 50.00% 20.90 50.0% 20.90
0240010001 PINTURA LATEX gal 5.2256 35.50 185.51 0.00% 92.76 100.0% 92.76
0240020014 PINTURA ACRILICA gal 3.7200 75.90 282.35 0.00% 141.18 100.0% 141.18
0240020016 PINTURA AL OLEO MATE gal 8.4040 43.22 363.22 0.00% 181.61 100.0% 181.61
0240020017 PINTURA SINCROMATO gal 3.7200 65.80 244.78 0.00% 122.39 100.0% 122.39
0240070003 PINTURA ANTICORROSIVA EPOX-USO NAVAL gal 0.1320 68.90 9.09 0.00% 4.55 100.0% 4.55
0240080012 THINNER gal 7.4400 30.50 226.92 0.00% 113.46 100.0% 113.46
0240150001 IMPRIMANTE gal 22.7501 28.00 637.00 0.00% 318.50 100.0% 318.50
0241020001 CINTA AISLANTE rll 0.0629 7.00 0.44 50.00% 0.22 50.0% 0.22
02460700010003 PERNOS DE ANCLAJE DE FIERRO GALVANIZADO CON CAPUCHON PLASTICO und 60.0000 3.50 210.00 50.00% 105.00 50.0% 105.00
50.00% 0.00 50.0% 0.00
0246140002 EMPAQUETADURA DE JEBE ENLONADO DN 250mm und 21.0000 18.90 396.90 0.00% 198.45 100.0% 198.45
0246140003 EMPAQUETADURA DE JEBE ENLONADO DN 200mm und 26.0000 15.80 410.80 0.00% 205.40 100.0% 205.40
0253180011 VALVULA COMPUERTA DE 10" (L=0.55m) und 2.0000 1,100.00 2,200.00 0.00% 1,100.00 100.0% 1,100.00
02550800010003 SOLDADURA ELECTRICA CELLOCORD P 1/8" kg 14.8800 15.50 230.64 50.00% 115.32 50.0% 115.32
0255080015 SOLDADURA CELLOCORP AP kg 145.0000 15.50 2,247.50 50.00% 1,123.75 50.0% 1,123.75
02620500040019 INTERRUPTOR SIMPLE und 2.0000 15.30 30.60 50.00% 15.30 50.0% 15.30
CRONOGRAMA VALORIZADO MENSUAL DE ADQUISICIÓN DE MANO DE OBRA, MATERIALES Y EQUIPOS
"MEJORAMIENTO CON SECTORIZACION DEL SISTEMA DE DISTRIBUCION DE AGUA POTABLE DEL DISTRITO DE TUPAC AMARU, PROVINCIA DE PISCO,
DEPARTAMENTO DE ICA"
FECHA: jun-22
MES 01 MES 02
ITEM UND CANT. PRECIO TOTAL
CANT. COSTO S/. CANT. COSTO S/.

02621300010004 TOMACORRIENTE UNIVERSAL DOBLE + L.T. und 4.0000 10.93 43.72 0.00% 21.86 100.0% 21.86
0265010002 TUBO E. RECT, 4"x4" und 4.0000 210.00 840.00 0.00% 420.00 100.0% 420.00
0265010003 ALUZINC BLANCO TR4 1x6.50x0.40 pln 5.0000 195.80 979.00 0.00% 489.50 100.0% 489.50
0265010004 AUTOPERFORANTE 10x3/4 100 und. pqt 10.0000 10.00 100.00 0.00% 50.00 100.0% 50.00
0265010005 ARENADO LABOR PINTADO TUB FIERRO DN 200mm m 3.0300 6.50 19.70 50.00% 9.85 50.0% 9.85
0265010006 TUB SCHELUDE 40 DE 200mm (8") m 1.0100 60.50 61.11 50.00% 30.56 50.0% 30.56
0265010007 VALVULA COMPUERTA DE 8" und 3.0000 1,160.05 3,480.15 0.00% 1,740.08 100.0% 1,740.08
0265010008 UNION TIPO DRESER DE 8" und 3.0000 169.50 508.50 0.00% 254.25 100.0% 254.25
0265010009 TEE DE 10" und 1.0000 521.30 521.30 0.00% 260.65 100.0% 260.65
0265010010 CODO DE 90° DE 8" und 2.0000 475.00 950.00 0.00% 475.00 100.0% 475.00
0265010011 REDUCCION DE 8" a 6" und 1.0000 450.00 450.00 0.00% 225.00 100.0% 225.00
0265010012 TUBO 10" SH 40 m 2.0200 282.50 570.65 0.00% 285.33 100.0% 285.33
0265010013 VALVULA COMPUERTA DE 8" (L=0.35m) und 1.0000 1,160.05 1,160.05 0.00% 580.03 100.0% 580.03
0265010014 UNION TIPO DRESSER DE 10" und 3.0000 254.24 762.72 0.00% 381.36 100.0% 381.36
0265010015 TEE DE 10" und 2.0000 521.30 1,042.60 0.00% 521.30 100.0% 521.30
0265010016 CODO DE 45° DE 10" und 4.0000 540.00 2,160.00 0.00% 1,080.00 100.0% 1,080.00
0265010017 UNION AUTOPORTANTE DE 10" und 1.0000 385.00 385.00 0.00% 192.50 100.0% 192.50
0265010018 MEDIDOR DE CAUDAL DE 10" und 1.0000 4,000.00 4,000.00 0.00% 2,000.00 100.0% 2,000.00
0265010019 NIPLE BRIDADO DE 10" und 2.0000 165.80 331.60 0.00% 165.80 100.0% 165.80
0265010020 TEE DE 8" und 1.0000 498.67 498.67 0.00% 249.34 100.0% 249.34
0265010021 NIPLE BRIDADO DE 8" und 1.0000 88.50 88.50 0.00% 44.25 100.0% 44.25
0265010022 REDUCCION DE 10" a 8" und 1.0000 530.00 530.00 0.00% 265.00 100.0% 265.00
0265020002 TUBO E. CUADRADO 80x40mm und 4.0000 165.00 660.00 0.00% 330.00 100.0% 330.00
02650600010008 TUBO CIRCULAR 1 1/2" x 2.5 mm pza 33.4800 135.45 4,534.87 50.00% 2,267.44 50.0% 2,267.44
0265060002 LIJA DE FIERRO-TELA ESMERIL 100-9"x11" ASA und 8.0000 3.50 28.00 50.00% 14.00 50.0% 14.00
0265070002 GLN. ESMALTE ANTICORROSIVO NEGRO gal 3.0000 55.50 166.50 0.00% 83.25 100.0% 83.25
0265080002 KGR. SOLDADURA 1/8" kg 20.0000 13.50 270.00 50.00% 135.00 50.0% 135.00
02680900010005 CAJA RECTANGULAR FIERRO GALVANIZADO DE 100 x 50 x 40 mm (6" X 2" X 1½") und 3.2662 2.97 9.70 0.00% 4.85 100.0% 4.85

02683000010001 TAPA 1 GANG und 0.1279 2.97 0.38 0.00% 0.19 100.0% 0.19
0270010014 ALAMBRE TW 2.5 mm2 m 58.3238 1.25 72.90 0.00% 36.45 100.0% 36.45
CRONOGRAMA VALORIZADO MENSUAL DE ADQUISICIÓN DE MANO DE OBRA, MATERIALES Y EQUIPOS
"MEJORAMIENTO CON SECTORIZACION DEL SISTEMA DE DISTRIBUCION DE AGUA POTABLE DEL DISTRITO DE TUPAC AMARU, PROVINCIA DE PISCO,
DEPARTAMENTO DE ICA"
FECHA: jun-22
MES 01 MES 02
ITEM UND CANT. PRECIO TOTAL
CANT. COSTO S/. CANT. COSTO S/.

0270010015 ALAMBRE TW 4 mm2 m 21.4626 0.90 19.32 0.00% 9.66 100.0% 9.66
0270110169 LUMINARIA AHR-240 C/ EQUIPO Y LAMP. FLUORESC. 2X36 W und 4.0000 95.00 380.00 0.00% 190.00 100.0% 190.00
0290130022 AGUA m3 1.5360 12.00 18.43 50.00% 9.22 50.0% 9.22
02902300040003 ESPUMA PLASTICA 1" m 23.6250 5.50 129.94 50.00% 64.97 50.0% 64.97
0292010001 CORDEL m 2.2500 0.10 0.23 100.00% 0.12 0.0% 0.12
0293010002 GUANTES DE CUERO par 8.0000 9.24 73.92 100.00% 36.96 0.0% 36.96
0293010003 LENTES DE PROTECCION und 8.0000 2.54 20.32 100.00% 10.16 0.0% 10.16
0293010004 CASCOS DE PROTECCION und 8.0000 14.32 114.56 100.00% 57.28 0.0% 57.28
0293010005 ZAPATOS DE SEGURIDAD par 8.0000 42.29 338.32 100.00% 169.16 0.0% 169.16
0293010006 CAMISA DRILL und 8.0000 33.81 270.48 100.00% 135.24 0.0% 135.24
0293010007 PANTALON DRILL und 8.0000 38.05 304.40 100.00% 152.20 0.0% 152.20
0293010008 MASCARILLAS QUIRURGICA und 960.0000 1.21 1,161.60 50.00% 580.80 50.0% 580.80
0293010009 PRUEBA RAPIDA DE DETECCION COVID-19 und 8.0000 130.00 1,040.00 100.00% 520.00 0.0% 520.00
0293010010 ALCOHOL AL 70% und 8.0000 8.05 64.40 50.00% 32.20 50.0% 32.20
0293010011 CONO DE SEÑALIZACION NARANJA DE 28" DE ALTURA und 10.0000 35.60 356.00 100.00% 178.00 0.0% 178.00
0293010012 CINTA PLASTICA SEÑALIZADORA DE LIMITE DE SEGURIDAD rll 4.0000 60.50 242.00 50.00% 121.00 50.0% 121.00
0293010013 BOTIQUIN BASICO und 1.0000 230.00 230.00 100.00% 115.00 0.0% 115.00
0293010014 TRASLADO PRIVADO DE PERSONAL CON SINTOMAS glb 6.0000 500.00 3,000.00 50.00% 1,500.00 50.0% 1,500.00
0293010015 TERMOMETRO INFRARROJO pza 1.0000 150.00 150.00 100.00% 75.00 0.0% 75.00
0293010016 PULSIOXIMETRO DIGITAL pza 1.0000 112.80 112.80 100.00% 56.40 0.0% 56.40
0293010017 PULVERIZADOR (MOCHILA FUMIGADORA MANUAL 20 LT.) und 1.0000 250.00 250.00 100.00% 125.00 0.0% 125.00
0293010018 PEDILUVIO DESINFECTANTE und 2.0000 45.00 90.00 100.00% 45.00 0.0% 45.00
0293010019 LIMPIADOR DESINFECTANTE (1 KG. RINDE 90 LTS. DE SOLUCION) und 10.0000 2.40 24.00 50.00% 12.00 50.0% 12.00

0293010020 CHARLAS DE CAPACITACION SOBRE SALUD EN EL TRABAJO und 2.0000 2,500.00 5,000.00 50.00% 2,500.00 50.0% 2,500.00
3.00 EQUIPOS
0301010006 HERRAMIENTAS MANUALES %mo 863.18 50.00% 431.59 50.0% 431.59

0301100001 COMPACTADORA VIBRATORIA TIPO PLANCHA 7 HP hm 4.3492 12.00 52.19 75.00% 26.10 25.0% 26.10
0301120002 EQUIPO DE PINTURA hm 29.7600 25.00 744.00 0.00% 372.00 100.0% 372.00
03011600010003 CARGADOR SOBRE LLANTAS DE 125-135 HP 3 yd3 hm 2.5164 169.49 426.50 100.00% 213.25 0.0% 213.25
03012200040002 CAMION VOLQUETE DE 10 m3 hm 12.5819 144.07 1,812.67 100.00% 906.34 0.0% 906.34
CRONOGRAMA VALORIZADO MENSUAL DE ADQUISICIÓN DE MANO DE OBRA, MATERIALES Y EQUIPOS
"MEJORAMIENTO CON SECTORIZACION DEL SISTEMA DE DISTRIBUCION DE AGUA POTABLE DEL DISTRITO DE TUPAC AMARU, PROVINCIA DE PISCO,
DEPARTAMENTO DE ICA"
FECHA: jun-22
MES 01 MES 02
ITEM UND CANT. PRECIO TOTAL
CANT. COSTO S/. CANT. COSTO S/.

0301270005 MOTOSOLDADORA DE 250 AMP hm 23.2000 25.00 580.00 50.00% 290.00 50.0% 290.00
03012900010002 VIBRADOR DE CONCRETO 4 HP 1.25" hm 2.9204 8.75 25.55 50.00% 12.78 50.0% 12.78
03012900010005 VIBRADOR DE CONCRETO 4 HP 2.40" hm 6.7906 10.00 67.91
" 50.00% 33.96 50.0% 33.96

0301290003 MEZCLADORA DE CONCRETO hm 0.6264 24.50 15.35 50.00% 7.68 50.0% 7.68
03012900030001 MEZCLADORA DE CONCRETO 11 P3 (23 HP) hm 10.8486 24.50 265.79 50.00% 132.90 50.0% 132.90
0301330008 CIZALLA P/CORTE DE FIERRO hm 83.9832 2.30 193.16 50.00% 96.58 50.0% 96.58
0301340001 ANDAMIO METALICO día 12.1515 20.00 243.03 50.00% 121.52 50.0% 121.52
0301340008 ANDAMIO METALICO hm 14.4593 8.00 115.67 50.00% 57.84 50.0% 57.84
4.00 SUB CONTRATOS
0400010004 SC MITIGACION DE IMPACTO AMBIENTAL glb 1.0000 1,271.19 1,271.19 50.00% 635.60 50.0% 635.60
0400010005 SC. INSTALACION DE COBERTURA METALICA CON ALUZINC glb 1.0000 6,500.00 6,500.00 0.00% 3,250.00 100.0% 3,250.00
0411010001 SC PUERTA METALICA und 1.0000 1,500.00 1,500.00 0.00% 750.00 100.0% 750.00
04110200010002 SC VENTANA METALICA und 1.0000 600.00 600.00 0.00% 300.00 100.0% 300.00
0411100019 SC GIGANTOGRAFIA und 1.0000 450.00 450.00 100.00% 225.00 0.0% 225.00
TOTAL 121,524.44 60,762.22 60,762.22