CRONOGRAMA VALORIZADO DEL PRESUPUESTO

PROYECTO : "CONSTRUCCION DE CERCO PERIMETRICO, SSHH DE ESPECTADORES Y AMBIENTE ADMINISTRATIVO; EN EL(LA) LOCAL COMUNAL EN LA LOCALIDAD SANTA ROSA, DISTRITO DE AUCALLAMA, PROVINCIA HUARAL, DEPARTAMENTO LIMA", CUI 2499271

PRESUPUESTO 1.0 : LOCAL COMUNAL SANTA ROSA


PROPIETARIO : MUNICIPALIDAD DISTRITAL DE AUCALLAMA
UBICACION : DPTO: LIMA PROV: HUARAL DIST: AUCALLAMA LOC: C.P. SANTA ROSA
FECHA PROYECTO : 23/07/2021
SEMANA 01 SEMANA 02 SEMANA 03 SEMANA 04 SEMANA 05 SEMANA 06
Item Descripción Unid. Metrado Precio Parcial Total
PARCIAL (S/.) %AVANCE PARCIAL (S/.) %AVANCE PARCIAL (S/.) %AVANCE PARCIAL (S/.) %AVANCE PARCIAL (S/.) %AVANCE PARCIAL (S/.) %AVANCE
1
### VIVIENDA DE ALBAÑILERIA CONFINADA
1.1 TRABAJOS PRELIMINARES
1.1.1 LIMPIEZA DEL TERRENO MANUAL m² 35.04 S/ 3.61 S/ 126.49 S/ 126.49 100.00% S/ 126.49
1.1.2 TRAZO, NIVEL Y REPLANTE PRELIMINAR m² 35.04 S/ 3.16 S/ 110.73 S/ 110.73 100.00% S/ 110.73
1.2 EXCAVACIONES S/ 0.00
1.2.1 EXCAVACIÓN DE ZANJAS P/CIMIENTOS m³ 14.66 S/ 47.25 S/ 692.69 S/ 692.69 100.00% S/ 692.69
1.2.2 ACARREO DE MATERIA EXCEDENTE Dp = 30 M m³ 17.59 S/ 1.45 S/ 25.51 S/ 25.51 100.00% S/ 25.51
1.2.3 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ m³ 17.59 S/ 11.14 S/ 195.95 S/ 195.95 100.00% S/ 195.95
1.3 125HP/VOLQ
RELLENOS 15m3 D=5Km S/ 0.00
1.3.1 REFINE Y COMPACTACIÓN DE FONDO DE CIMENTACIÓN m² 14.66 S/ 12.21 S/ 179.00 S/ 179.00 100.00% S/ 179.00
1.4 OBRAS DE CONCRETO SIMPLE S/ 0.00
1.4.1 CIMIENTOS CORRIDOS CONCRETO 1:10 + 30% P.G. m³ 14.66 S/ 186.39 S/ 2,732.48 S/ 2,732.48 100.00% S/ 2,732.48
1.4.2 SOLADO CONCRETO C:H 1:12, E = 0.10 M m² 14.66 S/ 36.82 S/ 539.78 S/ 539.78 100.00% S/ 539.78
1.4.3 SOBRECIMIENTOS SIMPLES S/ 0.00
1.4.3.1 CONCRETO 1:8+25% PM, PARA SOBRECIMIENTOS m³ 1.15 S/ 285.92 S/ 328.81 S/ 328.81 100.00% S/ 328.81
1.4.3.2 SOBRECIMIENTO REFORZADOS, ENCOFRADO Y m² 15.29 S/ 46.17 S/ 705.94 S/ 352.97 50.00% S/ 352.97 50.00% S/ 705.94
1.5 DESENCOFRADO
OBRAS DE CONCRETO ARMADO S/ 0.00
1.5.1 COLUMNAS S/ 0.00
1.5.1.1 COLUMNAS, CONCRETO F'C = 210 KG/CM2 m³ 1.72 S/ 585.68 S/ 1,007.37 S/ 1,007.37 100.00% S/ 1,007.37
1.5.1.2 COLUMNAS, ENCOFRADO Y DESENCOFRADO m² 26.19 S/ 56.28 S/ 1,473.97 S/ 1,473.97 100.00% S/ 1,473.97
1.5.1.3 COLUMNAS, ACERO CORRUGADO Fy = 4200 KG/CM2 kg 197.00 S/ 6.00 S/ 1,182.00 S/ 1,182.00 100.00% S/ 1,182.00
1.5.2 VIGAS S/ 0.00
1.5.2.1 VIGAS, CONCRETO F'C = 210 KG/CM2 m³ 1.33 S/ 524.30 S/ 697.32 S/ 697.32 100.00% S/ 697.32
1.5.2.2 VIGAS, ENCOFRADO Y DESENCOFRADO m² 6.63 S/ 79.61 S/ 527.81 S/ 263.91 50.00% S/ 263.91 50.00% S/ 527.82
1.5.2.3 VIGAS, ACERO CORRUGADO Fy = 4200 KG/CM2 kg 209.52 S/ 6.00 S/ 1,257.12 S/ 1,257.12 100.00% S/ 1,257.12
1.5.3 LOSA ALIGERADA S/ 0.00
1.5.3.1 LOSA ALIGERADA, CONCRETO F'C = 210 KG/CM2 m³ 2.48 S/ 442.59 S/ 1,097.62 S/ 1,097.62 100.00% S/ 1,097.62
1.5.3.2 LOSA ALIGERADA, ENCOFRADO Y DESENCOFRADO m² 28.30 S/ 66.99 S/ 1,895.82 S/ 473.96 25.00% S/ 1,421.86 75.00% S/ 1,895.82
1.5.3.3 LOSA ALIGERADA, ACERO CORRUGADO Fy = 4200 KG/CM2 kg 135.03 S/ 6.00 S/ 810.18 S/ 405.09 50.00% S/ 405.09 50.00% S/ 810.18
1.5.3.4 LOSA ALIGERADA, LADRILLO TECHO 8H 15X30X30 CM und 235.74 S/ 23.02 S/ 5,426.73 S/ 5,426.73 100.00% S/ 5,426.73
1.6 MUROS Y TABIQUES DE ALBAÑILERIA S/ 0.00
1.6.1 MURO DE LADRILLO KK DE ARCILLA SOGA M: 1:4 e = 1.5 CM m² 56.17 S/ 70.63 S/ 3,967.29 S/ 2,975.30 75.00% S/ 991.99 25.00% S/ 3,967.29
1.6.2 ACERO DE REFUERZON HORIZONTAL EN MUROS kg 25.27 S/ 5.47 S/ 138.23 S/ 138.23 100.00% S/ 138.23
1
. Costo directo: S/ 25,118.84 S/ 1,330.37 S/ 3,625.23 S/ 4,839.08 S/ 4,349.43 S/ 8,774.71 S/ 2,200.03 S/ 25,118.85
6
. Gastos Generales (12 %) S/ 3,014.26 S/ 159.64 S/ 435.03 S/ 580.69 S/ 521.93 S/ 1,052.97 S/ 264.00 S/ 3,014.26
2 Utilidad (10 %) S/ 2,511.88 S/ 133.04 S/ 362.52 S/ 483.91 S/ 434.94 S/ 877.47 S/ 220.00 S/ 2,511.89
Sub Total S/ 30,644.98 S/ 1,623.05 S/ 4,422.78 S/ 5,903.68 S/ 5,306.30 S/ 10,705.15 S/ 2,684.04 S/ 30,645.00
I.G.V. (18 %) S/ 5,516.10 S/ 292.15 S/ 796.10 S/ 1,062.66 S/ 955.13 S/ 1,926.93 S/ 483.13 S/ 5,516.10
Total de Presupuesto S/ 36,161.08 S/ 1,915.20 S/ 5,218.88 S/ 6,966.34 S/ 6,261.44 S/ 12,632.07 S/ 3,167.16 S/ 36,161.10
Porcentaje de avance por Semana 5.30% sem 1 14.43% sem 2 19.26% sem 3 17.32% sem 4 34.93% sem 5 8.76% sem 6
100.00%
Porcentaje de avance acumulado (CURVA S) 5.30% 19.73% 38.99% 56.31% 91.24% 100.00%

Curva "S"
1 Avance Fisico Programado "PV"
0.9
0.8
0.7
0.6
0.5
0.4
0.3
0.2
0.1
0