PÁGINA :2
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
1X10 X 3.20 M. PINO CEPILLADO SECO. 6.60 c/u 5,790 38,214
SUBTOTAL 96,081
B. MANO DE OBRA
CARPINTERO + 1 AYUD 0.67 dia 47,190 31,617
SUBTOTAL 41,208
TOTAL 137,289
PÁGINA :3
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
PINO CUARTON 3X3 3.2MT 6.60 uni 2,765 18,249
SUBTOTAL 103,496
B. MANO DE OBRA
ALBAÑIL + 1 AYUD 0.10 dia 52,817 5,282
SUBTOTAL 97,387
TOTAL 200,883
PÁGINA :4
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
SEÑALETICA 1.00 uni 155,000 155,000
SUBTOTAL 155,000
TOTAL 155,000
PÁGINA :5
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
TOTAL 0
PÁGINA :6
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
DERECHO A BOTADERO 1.30 m3 500 650
SUBTOTAL 650
B. MANO DE OBRA
JORNALERO 45 HORAS SEMANALES 0.01 dia 16,335 162
SUBTOTAL 237
C. EQUIPOS Y MAQUINARIAS
EXCAVADORA 20 TON. 0.05 hor 33,990 1,700
SUBTOTAL 2,180
TOTAL 3,067
PÁGINA :7
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
1X10 X 3.20 M. PINO CEPILLADO SECO. 0.32 c/u 5,790 1,853
SUBTOTAL 2,719
B. MANO DE OBRA
MAESTRO ESTAQUERO 0.12 dia 27,225 3,267
SUBTOTAL 4,741
TOTAL 7,460
PÁGINA :8
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
B. MANO DE OBRA
SUBCONTRATO EXTRACCION DE ESCOMBROS 1.00 m3 6,000 6,000
SUBTOTAL 6,000
TOTAL 6,000
PÁGINA :9
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
RIPIO (flete 15km) 0.05 m3 15,000 795
SUBTOTAL 12,799
B. MANO DE OBRA
MAESTRO DE PRIMERA 0.12 dia 32,670 3,920
SUBTOTAL 8,470
C. EQUIPOS Y MAQUINARIAS
BETONERA 11p 7,5hp MES=208h 0.03 dia 12,975 415
SUBTOTAL 415
TOTAL 21,684
PÁGINA : 10
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
3X8 X 4M VIGA PINO OREGON 0.25 c/u 26,042 6,511
SUBTOTAL 7,204
B. MANO DE OBRA
CARPINTERO TERMINACION+AYUD 0.07 dia 49,005 3,430
SUBTOTAL 4,425
TOTAL 11,629
PÁGINA : 11
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
2X5" X 3.2M PINO DIMENSIONADO SECO 1.33 c/u 5,118 6,807
SUBTOTAL 6,915
B. MANO DE OBRA
CARPINTERO TERMINACION+AYUD 0.09 dia 49,005 4,410
SUBTOTAL 5,689
TOTAL 12,604
PÁGINA : 12
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
2X4" X 3.2M PINO DIMENSIONADO SECO 1.00 c/u 2,723 2,723
SUBTOTAL 7,462
B. MANO DE OBRA
CARPINTERO + 1 AYUD 0.06 dia 47,190 2,831
SUBTOTAL 3,652
TOTAL 11,114
PÁGINA : 13
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
LP OSB ST APA 9.5X1220X2440MM 0.34 pla 7,261 2,469
TORNILLO P/MADERA 10X1 1/2 T-2 144UNI 0.05 uni 4,109 185
SUBTOTAL 2,654
B. MANO DE OBRA
CARPINTERO + 1 AYUD 0.03 dia 47,190 1,557
SUBTOTAL 2,009
TOTAL 4,663
PÁGINA : 14
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
2X6 X 3.2M VIGA PINO OREGON 1.33 c/u 25,202 33,519
SUBTOTAL 33,813
B. MANO DE OBRA
CARPINTERO TERMINACION+AYUD 0.05 dia 49,005 2,450
SUBTOTAL 3,161
TOTAL 36,974
PÁGINA : 15
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
2X4" X 3.2M PINO DIMENSIONADO SECO 0.69 c/u 2,723 1,879
SUBTOTAL 2,042
B. MANO DE OBRA
CARPINTERO + 1 AYUD 0.07 dia 47,190 3,303
SUBTOTAL 4,261
TOTAL 6,303
PÁGINA : 16
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
2X2' X 3.2 M PINO DIMENSIONADO VERDE 0.33 c/u 1,504 496
SUBTOTAL 1,193
B. MANO DE OBRA
CARPINTERO + 1 AYUD 0.01 dia 47,190 613
SUBTOTAL 791
TOTAL 1,984
PÁGINA : 17
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
LP OSB ST APA 9.5X1220X2440MM 0.34 pla 7,261 2,469
TORNILLO P/MADERA 10X1 1/2 T-2 144UNI 0.10 uni 4,109 411
SUBTOTAL 2,880
B. MANO DE OBRA
CARPINTERO + 1 AYUD 0.03 dia 47,190 1,557
SUBTOTAL 2,009
TOTAL 4,889
PÁGINA : 18
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
PL ZINCALUM P-11 0.35X851X2500MM 0.50 uni 9,824 4,912
CLAVO TECHO HELICOIDAL 2 1/2", BOLSA 100 0.04 c/u 5,034 201
UNIDADES
PL ZINCALUM LISO 0.4X1000X2000MM 0.03 uni 6,462 162
SUBTOTAL 5,275
B. MANO DE OBRA
CARPINTERO + 1 AYUD 0.02 dia 47,190 944
SUBTOTAL 2,904
TOTAL 8,179
PÁGINA : 19
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
TOTAL 0
PÁGINA : 20
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
MEMBRANA HIDROFUGA TYPAR 83.51M2 0.06 uni 77,647 4,659
GRAPA STANLEY GRAPAS 1/4 (8 MM) P/TR 100 T/PES 0.15 uni 2,655 398
1000 UNIDADES
VARIOS 10.00 % 466
SUBTOTAL 5,523
B. MANO DE OBRA
CARPINTERO + 1 AYUD 0.02 dia 47,190 944
SUBTOTAL 1,218
TOTAL 6,741
PÁGINA : 21
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
0,6X10 M. 50MM LANA DE VIDRIO ROLLO LIBRE 1.46 c/u 12,681 18,514
AISLANGLASS
PL SUPERBOARD INTERNIT 6.0X1200X2400MM 0.38 uni 14,866 5,649
GRAPA STANLEY GRAPAS 1/4 (8 MM) P/TR 100 T/PES 0.15 uni 2,655 398
1000 UNIDADES
SUBTOTAL 24,561
B. MANO DE OBRA
JORNALERO 0.01 dia 16,335 163
SUBTOTAL 210
PERDIDAS 3.00 % 0
TOTAL 25,213
PÁGINA : 22
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
1X4 X 3.20 M. PINO CEPILLADO SECO. 0.82 c/u 2,008 1,647
PERDIDAS 5.04 % 83
SUBTOTAL 1,739
B. MANO DE OBRA
CARPINTERO + 1 AYUD 0.06 dia 47,190 2,831
SUBTOTAL 3,652
TOTAL 5,391
PÁGINA : 23
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
15MM 1.20X2.40 M TERCIADO ESTRUCTURAL PINO 0.37 pla 17,639 6,518
ADHESIVO POLVO P/CERAMICA BEKRON 25KG SACO 0.56 uni 2,302 1,295
S/T (Yolito)
FRAGUE WEBER BLANCO 1KG 0.40 uni 965 386
SUBTOTAL 23,494
B. MANO DE OBRA
CERAMISTA 0.25 dia 30,492 7,623
SUBTOTAL 14,814
TOTAL 38,309
PÁGINA : 24
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
18MM 1.20X2.40 M TERCIADO ESTRUCTURAL PINO 0.34 pla 19,824 6,740
ADHESIVO POLVO P/CERAMICA A-C BEKRON A-C 0.18 uni 12,938 2,329
24,5KG SACO S/T (Yolito)
FRAGUE WEBER GRIS PLATA 5KG 0.40 c/u 4,360 1,744
SUBTOTAL 22,031
B. MANO DE OBRA
CERAMISTA 0.25 dia 30,492 7,623
SUBTOTAL 9,632
TOTAL 31,663
PÁGINA : 25
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
PERFIL CORTA GOTERA BASE 100X2500X0,5MM 0.13 uni 8,395 1,091
SUBTOTAL 17,412
B. MANO DE OBRA
CARPINTERO TERMINACION+AYUD 0.08 dia 49,005 4,067
SUBTOTAL 5,246
TOTAL 22,659
PÁGINA : 26
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
TERCIADO RANURADO COLONIAL 9X1220X2440MM 0.41 pla 24,681 10,023
SUBTOTAL 11,192
B. MANO DE OBRA
MAESTRO DE PRIMERA 0.04 dia 32,670 1,269
SUBTOTAL 2,531
TOTAL 13,723
PÁGINA : 27
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
CERAMICA 20 X 30 CM BLANCO 1.5 M2 KAZTELO 0.43 m2 4,866 2,107
SUBTOTAL 9,871
B. MANO DE OBRA
CERAMISTA 0.25 dia 30,492 7,623
SUBTOTAL 9,834
TOTAL 19,705
PÁGINA : 28
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
PINO MACHIMBRADO 3/4X5 3.2MT 2.67 uni 1,840 4,913
CLAVO CORRIENTE 2 1/2", CAJA 25KGS. INCHALAM 0.01 c/u 34,437 344
SUBTOTAL 6,197
B. MANO DE OBRA
CARPINTERO + 1 AYUD 0.06 dia 47,190 2,831
SUBTOTAL 3,652
TOTAL 9,849
PÁGINA : 29
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
10 MM 120X240 CM YESO-CARTON BORDE 0.35 pla 4,882 1,695
REBAJADO VOLCANITA
18MM 1.20X2.40 M TERCIADO ESTRUCTURAL PINO 0.35 pla 19,824 6,883
TORNILLO YESOCARTON PUNTA FINA 6 X 2 1/4 200 0.04 c/u 5,454 240
UNIDADES
2 X 2 X 3.2 M PINO DIMENSIONADO VOLUMEN 0.33 c/u 1,354 447
SUBTOTAL 9,522
B. MANO DE OBRA
CARPINTERO + 1 AYUD 0.14 dia 47,190 6,607
SUBTOTAL 8,523
TOTAL 18,045
PÁGINA : 30
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
PL LISA GALVANIZADA 0.5X1000X3000 MM 0.23 uni 12,345 2,839
SUBTOTAL 3,731
B. MANO DE OBRA
HOJALATERO + AYUD 0.14 dia 43,560 6,098
SUBTOTAL 7,866
TOTAL 11,598
PÁGINA : 31
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
1X8' X 3.20 M. PINO CEPILLADO SECO 0.34 c/u 4,487 1,526
SUBTOTAL 2,257
B. MANO DE OBRA
CARPINTERO 0.03 dia 30,855 926
SUBTOTAL 1,195
TOTAL 3,451
PÁGINA : 32
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
CANALETA PVC 4 MT, MARRON 0.25 uni 7,134 1,784
SUBTOTAL 2,173
B. MANO DE OBRA
INSTALADOR PV6-R + AYUDANTE 0.02 dia 49,005 980
SUBTOTAL 1,264
TOTAL 3,437
PÁGINA : 33
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
TUBO BAJADA PVC 3 M MARRON VINILIT 0.34 c/u 4,630 1,574
PERDIDAS 2.00 % 31
SUBTOTAL 1,960
B. MANO DE OBRA
INSTALADOR PV6-R + AYUDANTE 0.01 dia 49,005 490
SUBTOTAL 632
TOTAL 2,592
PÁGINA : 34
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
PUERTA RUST P.OREGON FLORENCIA 85X200CM 1.00 uni 83,185 83,185
JUEGO MARCO PARA PUERTA PINO OREGÓN 1.00 c/u 21,252 21,252
PREMIUM 40 MM X 90 CM PUERTAS WOODS
TARUGO NYLON M-8 100UNI 0.10 uni 2,008 201
BISAGRA L290 3X3" AC.INOX. SAT C/ROD 3.00 uni 4,193 12,579
SUBTOTAL 117,648
B. MANO DE OBRA
CARPINTERO + 1 AYUD 0.20 dia 47,190 9,438
SUBTOTAL 12,175
TOTAL 129,823
PÁGINA : 35
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
SET MARCO PTA PINO 3 PZAS 40X90X5,4MM 1.00 uni 13,437 13,437
BISAGRA L290 3X3" AC.INOX. SAT C/ROD 3.00 uni 4,193 12,579
SUBTOTAL 45,216
B. MANO DE OBRA
CARPINTERO + 1 AYUD 0.17 dia 47,190 8,022
SUBTOTAL 10,348
TOTAL 55,564
PÁGINA : 36
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
CERRADURA ACCESO 4180 1.00 c/u 55,454 55,454
SUBTOTAL 55,454
B. MANO DE OBRA
CERRAJERO ACERO 0.06 dia 25,410 1,525
SUBTOTAL 1,525
TOTAL 58,892
PÁGINA : 37
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
CERRADURA 4041 PATIO/LOGIA 1.00 dsp 34,445 34,445
SUBTOTAL 34,445
B. MANO DE OBRA
CERRAJERO ACERO 0.06 dia 25,410 1,525
SUBTOTAL 1,525
TOTAL 37,501
PÁGINA : 38
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
TARUGO NYLON M-8 100UNI 8.00 uni 2,008 16,064
SUBTOTAL 18,694
B. MANO DE OBRA
CARPINTERO + 1 AYUD 0.30 dia 47,190 14,157
SUBTOTAL 18,263
TOTAL 36,957
PÁGINA : 39
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
GUARDAPOLVO PINO 1X3" 0.37 uni 2,933 1,085
SUBTOTAL 1,552
B. MANO DE OBRA
CARPINTERO TERMINACION 0.03 dia 32,670 817
SUBTOTAL 1,054
TOTAL 2,606
PÁGINA : 40
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
MDF MEL 1/4 RODON HAYA CR2 20X20X2400M 0.46 uni 1,840 846
SUBTOTAL 1,221
B. MANO DE OBRA
CARPINTERO TERMINACION 0.03 dia 32,670 817
SUBTOTAL 1,054
TOTAL 2,275
PÁGINA : 41
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
PILASTRA 13X43X3000 0.35 uni 1,924 673
SUBTOTAL 893
B. MANO DE OBRA
CARPINTERO TERMINACION 0.02 dia 32,670 653
SUBTOTAL 842
TOTAL 1,735
PÁGINA : 42
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
ACEITE DE LINAZA PROTECTOR DE MADERA 1 GALÓN 0.03 c/u 12,244 367
SUBTOTAL 450
B. MANO DE OBRA
PINTOR 0.05 dia 33,759 1,688
SUBTOTAL 2,178
TOTAL 2,628
PÁGINA : 43
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
PROTECTOR DE MADERA NATURAL 1 GALON 0.07 c/u 20,076 1,405
CERESITA
LIJA MADERA Nº 50 0.15 c/u 160 24
SUBTOTAL 1,488
B. MANO DE OBRA
PINTOR 0.03 dia 33,759 1,013
SUBTOTAL 1,307
TOTAL 2,795
PÁGINA : 44
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
ÓLEO PROFESIONAL BRILLANTE 1 GALÓN BLANCO 0.05 c/u 22,849 1,142
PERDIDAS 5.00 % 57
SUBTOTAL 1,660
B. MANO DE OBRA
PINTOR 0.06 dia 33,759 2,026
SUBTOTAL 2,614
TOTAL 4,273
PÁGINA : 45
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
BARNIZ VITROLUX 60 URETANO 1 GALÓN 0.06 c/u 30,244 1,815
SUBTOTAL 1,935
B. MANO DE OBRA
PINTOR 0.05 dia 33,759 1,688
SUBTOTAL 2,178
TOTAL 4,113
PÁGINA : 46
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
HORMIGON G-25 ESTRUCTURAL (PROVISION) 1.05 m3 61,574 64,653
SUBTOTAL 65,134
B. MANO DE OBRA
CONCRETERO COLOCACION HORMIGON 0.49 dia 23,595 11,562
SUBTOTAL 14,915
TOTAL 80,049
PÁGINA : 47
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
CEMENTO POLPAICO 25 KG 12.43 c/u 3,546 44,066
SUBTOTAL 63,239
B. MANO DE OBRA
CUADRILLA HORMIGONERA 0.05 dia 179,685 8,984
SUBTOTAL 11,589
C. EQUIPOS Y MAQUINARIAS
TROMPO BENCINERO 0.01 mes 40,881 409
SUBTOTAL 409
TOTAL 75,237
PÁGINA : 48
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
CEMENTO POLPAICO 25 KG 10.20 c/u 3,546 36,169
SUBTOTAL 55,077
B. MANO DE OBRA
CUADRILLA HORMIGONERA 0.05 dia 179,685 8,984
SUBTOTAL 11,589
C. EQUIPOS Y MAQUINARIAS
TROMPO BENCINERO 0.01 mes 40,881 409
SUBTOTAL 409
TOTAL 67,075
PÁGINA : 49
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
WC CENTURY C/ASTO REG MAD B/MET BLANCO 2.00 uni 30,160 60,320
SUBTOTAL 100,043
B. MANO DE OBRA
GASFITER PRIMERA 0.40 dia 32,670 13,068
SUBTOTAL 16,858
TOTAL 116,901
PÁGINA : 50
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
LAVAMANO INS (4" Y 8") VALENCIA BLANC 1.00 uni 36,966 36,966
PITON PORTA CADENA 25CMS CADENA CROMADA 1.00 uni 748 748
SUBTOTAL 131,303
B. MANO DE OBRA
GASFITER PRIMERA 0.40 dia 32,670 13,068
SUBTOTAL 16,858
TOTAL 148,161
PÁGINA : 51
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
URINARIO CAMPUS BLANCO 1.00 c/u 48,983 48,983
TORNILLO P/MADERA 12X2 1/2 T-4 144UNI 0.01 uni 7,218 101
SUBTOTAL 101,460
B. MANO DE OBRA
GASFITER PRIMERA 0.40 dia 32,670 13,068
SUBTOTAL 16,858
TOTAL 118,318
PÁGINA : 52
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
BARRA SEGURIDAD INOXIDABLE 60 CM 1.00 c/u 21,168 21,168
SUBTOTAL 188,718
TOTAL 188,718
PÁGINA : 53
FECHA PPTO : 17/09/2022
FECHA : 06/10/2022 01:46 a.m.
INFORME
CÓDIGO : 17822
A. MATERIALES
M/BLOCK LAVAPL VERTICAL BARI 1.00 uni 41,168 41,168
B. MANO DE OBRA
GASFITER PRIMERA 0.04 dia 32,670 1,307
SUBTOTAL 1,686
TOTAL 105,025