DIAGRAMA DE GANTT DEL PROYECTO B

NOMBRE DE LA DURACION EN
ACTIVIDAD FECHA DE INICIO DIAS

INICIO Monday, March 5, 2007 0

ACTIVIDAD A Monday, March 5, 2007 6

ACTIVIDAD B Monday, March 5, 2007 3

ACTIVIDAD C Thursday, March 22, 2007 18

ACTIVIDAD D Sunday, March 11, 2007 11

ACTIVIDAD E Monday, April 9, 2007 11

ACTIVIDAD F Monday, April 9, 2007 5

ACTIVIDAD G Friday, April 20, 2007 5

CIERRE Tuesday, April 24, 2007 0

INICIO DEL PROYECTO 39146.00


FIN DEL PROYECTO 39196.00
DIAGRAMA DE GANTT DEL PROYECTO B

FECHA FINAL DIAGRAMA DE GANTT

Th

W
Monday, March 5, 2007

Su

Sa
M

ur

ed

tu
on

nd
sd

ne

rd
da

ay

ay

sd

ay
,M

,M
y,

ay
Saturday, March 10, 2007

,A
M

,A
ar

ar

pr
ar

ch

ch

pr

il 1
ch

il 4
1

25

4
5,

5,
Wednesday, March 7, 2007

,2
20

20

20

00
07
07

07

7
Sunday, April 8, 2007 INICIO
ACTIVIDAD A
Wednesday, March 21, 2007 ACTIVIDAD B
ACTIVIDAD C
Thursday, April 19, 2007
ACTIVIDAD D
Friday, April 13, 2007 ACTIVIDAD E
ACTIVIDAD F
Tuesday, April 24, 2007 ACTIVIDAD G
CIERRE
Tuesday, April 24, 2007
07
20
4,
il 2
A pr
y,
da
es
Tu
07
20
4,
il 1
pr
,A
ay
rd
tu
Sa
7
00
,2
il 4
A pr
y,

NTT
da
es
dn
ACTIVIDAD
ES DU
EF TF

INICIO A C E
0 6 0 17 18 17 35 11
6 0 6 35 0 35 46 0

B D F
0 3 3 6 11 6 35 5
3 3 6 17 0 17 40 6

RUTA CRITICA

INICIO A D C
ACTIVIDAD
LS
LF

E
35
46 G
46 5 46 FIN
F 51 0 51
41
46

TA CRITICA

C E G FINAL