METRADO DEL MODULO DE UNA VIVIENDA (30.

00 m2)
OE.1. OBRAS PROVISIONALES, TRABAJOS PRELIMINARES, SEGURIDAD Y SALUD.
OE.1.1.1.6. SERVICIOS HIGIÉNICOS:
Cantidad = 1 Und ó 1 Gbl ó 1 Est

OE.1.1.1.7. CERCO DE TRIPLAY Y MADERA (Incl. Portón 3.00x2.40 m):


P = (1.00+15.00+1.50)x2 + (1.50+5.00+1.50)x2 = 51 ml

OE.1.1.3. TRABAJOS PRELIMINARES


OE.1.1.3.1. LIMPIEZA DE TERRENO:
Area = 5.00 x 15.00 = 75 m2
OE.1.1.9. TRAZOS, NIVELES Y REPLANTEO:
Area = 5.00 x 6.00 = 30 m2

OE.2. ESTRUCTURAS.
OE.2.1.2. EXCAVACIONES:
OE.2.1.2.1. EXCAVACIONES SIMPLES

Volexc = Volz + Volcc

Volz = 4Z1 +2Z2 = 4(1x1x1.15) + 2(1x1.5x1.15)


Volz = 8.05 m3

Volcc= Lcc x Bcc x hcc


Lcc 0.60 = (5.00-2x1.00)2 + (6.00-2x1.00-1.50)2
Lcc 0.60 = 11 ml
Lcc 0.40= (5.00-2x1.00) + (1.70+0.15+0.15-0.125)-(0.60+0.20) = 4.075ml
VolCC =11x0.6x1.10 +4.075x0.40x1.10 = 9.053m3
VolEXC = 8.05 + 9.053 = 17.103m3

OE.2.1.4. RELLENOS
OE.2.1.4.1. RELLENO CON
MATERIAL PROPIO
(-) (=)

A1 AMyC AR1

A1 = 4Z1 + 2Z2 + Lcc0.60x0.60 + Lcc0.40x0.40


A1 = 4x1.00x1.00 + 2x1.00x1.50 + 11x0.60 + 4.075x0.40 = 15.23 m2
AMyC = 4C1 + 2C2 + LS/C 0.25 x0.25 + LS/C0.15 x0.15
AMyC = LS/C 0.25 x0.25 + LS/C0.15 x0.15
AMyC = (6.00)2x0.25 + (5.00-2x0.25)3x0.15 + 1.70x0.15 = 5.28 m2

AR1 = 15.23 – 5.28 = 9.95m2


Volumen de Relleno con material propio:

VolR1 = 9.95x0.30 = 2.985 m3


CONSIDERANDO COTAS DE PISO DIFERENTES (No es nuestro caso):

(-) (=)
At
AMyC AR2
At = 5.00x6.00 = 30.00 m 2

AMyC = 5.28 m2
AR2 = 30.00 - 5.28 = 24.72 m2
Volumen de Relleno con material de préstamo:

VolR2 = 24.72x0.10 = 2.472 m3


OE.2.1.6. ELIMINACIÓN DE MATERIAL EXCEDENTE
Esponjamiento

Vol elim=( Volexc −Volrelleno ) x (1+ e % )

Vol elim=(17.103 x 1.25−2.985 x 1.35) m3


% compactación
3
Vol. elim = 17.35 m

OE.2.2. OBRAS DE CONCRETO SIMPLE


OE.2.2.1.CIMIENTOS CORRIDOS

Vol cc=11 x 0.60 x 0.80+ 4.075 x 0.40 x 0.80=6.584 m 3


OE.2.2.3. SOLADOS e = 2”

Area=4 x 1.00 x 1.00+2 x 1.00 x 1.50=7 m2

OE.2.2.6. SOBRECIMIENTOS
OE.2.2.6.1. PARA EL CONCRETO:

L0.25=6.00−3 x 0.25=5.25 x 2=10.50 ml .


L0.15=( 5.00−2 x 0.25 ) +1.70+2.70+(5.00−2 x 0.25−1.00)=12.40 ml .
3
V S / C =10.5 x 0.25 x 0.55+ 12.40 x 0.15 x 0.55+ ( 1.00+2 x 0.90 ) x 0.15 x 0.40=2.63 m

OE.2.2.6.2. PARA EL ENCOFRADO Y DESENCOFRADO

L Encof . Exterior =( 6.00−3 x 0.25 ) x 2+ ( 5.00−2 x 0.25 ) + ( 5.00−2 x 0.25−1.00 ) =18.5 ml


Area Exterior =18.50 x 0.25+1.00 x 0.10=¿ 4.725 m2
L Encof . Interior =5.25 x 2+ ( 4.50−0.15 ) +1.70 x 2+2.70+ ( 2.70−0.15 )+3.50=27 ml
2
Area Interior=27 x 0.55+0.90 x 0.40 x 4 +1.00 x 0.40=16.69m
2
AreaCompuerta =4 x 0.15 x 0.15=0.09 m
AREA=∑ ( A E + A I + A C )=0.09+16.69+4.725=21.505 m
2

OE.2.2.6. FALSOPISOS

2
Area del terreno (AT): AT =5 x 6=30 m
2
Area de Muros y Columnas: (AMyC): A MyC =5.28 m
A F / Piso= A T − A MyC
A F / Piso= A C/ Piso = A PISO=30−5.28=24.72 m2

OE.2.3. OBRAS DE CONCRETO ARMADO


OE.2.3.2. ZAPATAS
OE.2.3.2.1. PARA EL CONCRETO

V C ° =( 4 Z 1+ 2 Z 2 ) hcim
3
V C ° =( 4 x 1.00 x 1.00+2 x 1.00 x 1.50 ) x 0.80=5.60 m

OE.2.3.2.3. PARA LA ARMADURA DE ACERO.


Analisis : Z 1 ( 1.00 x 1.00 m) :4 und

L X =Longitud−2 xRecubrimiento
L X =1.00−2 x 0.075=0.85 m.
L X =LY =0.85 m.
L 0.85
N X = Y +1= +1=7
@ 0.15
Redondeo: 6.33 , 6.78 ≈ 7 barras (Inmediato superior)
Lx 0.85
N y= +1= + 1=7
@ 0.15
Use: 7 barras de 0.85 m. en cada sentido.

Análisis: Z 2 ( 1.00 x 1.50 m) :2 und

L X =1.00−2 x 0.075=0.85 m.
LY =1.50−2 x 0.075=1.35 m
LY
N X = +1
@
1.35
N X= +1=10
0.15
0.85
N y= +1=7
0.15
Use: 10 barras de 0.85m. y 7 barras de 1.35m.

 A Szap=( 7 x 0.85 x 2 ) x 4 + ( 10 x 0.85+7 x 1.35 ) x 2=83.5 ml Ø 1 /2

Metrado en peso ( Peso Unitario 1/2:0.994 kg/ml) 83.5m x 0.994 kg/m = 83.00 kg.

OE.2.3.7. COLUMNAS
OE.2.3.7.1. PARA EL CONCRETO
3
V C ° =( 0.25 x 0.25 x 2.85 ) x 6=1.07 m

OE.2.3.7.2. PARA EL ENCOFRADO Y DESENCOFRADO


Areá : Pxh=( 0.50 x 2.55+0.10 x 2.85 ) x 4+(0.25 x 2.55+0.25 x 2.85) x 2
Area = 6.24 + 2.70 = 8.94 m2

OE.2.3.7.3. PARA LA ARMADURA DE ACERO.

Acero Principal o Longitudinal:


L A =( 0.20+2.85+ 0.80 )−( 0.04 +0.075 ) + ( 0.20+0.25 )
S

L A =4.185 m .
S

A S=( 4.185 x 4 ) x 4+ ( 4.185 x 6 ) x 2=117.18 ml ∅ 1/2

Acero Transversal o Estribos:


L ESTRIBO=0.17 x 4+ 0.075 x 2=0.83 ml 0.20 0.20

L 1.55
Cantidad de estribos: N ESTRIBO= C −1= −1=6.75 ≅ 7
@ 0.20
2.40

2.85

N ESTRIBO=6+ 7+6=19
NPT. +0.15

0.25

0.08
0.25 0.45

0.04
0.17

0.25
A SESTRIBO =0.83 x 19 x 6=94.62 ml ∅ 1/4
A STOTAL=117.18 x 0.994 +94.62 x 0.25=140.13 kg

OE.2.3.8. VIGAS
OE.2.3.8.1. PARA EL CONCRETO
3
V 1 ( 0.25 x 0.20 ) →Vol C ° V 1= ( 0.25 x 0.20 x 6 ) x 2=0.60 m
3
V 2=0.15 x 0.20 x 4.50 x 2=0.27 m
3
V 3=0.25 x 0.20 x 4.50=0.225 m
3
V C ° =V 1+V 2+V 3=1.095 m

OE.2.3.8.2. PARA EL ENCOFRADO Y DESENCOFRADO

2
V 1 → AREA=6.00 x 0.20 x 2=2.40 m
2
V 2 → AREA=5.00 x 0.20 x 2+ (1.00+ 2.00+0.75+2.175 ) 0.15=2.889 m
2
V 3 → AREA=4.35 x 0.10+0.90 x 0.15 x 2=0.705 m
2
A Enc . = AV 1+ A V 2 + A V 3=5.994 m

OE.2.3.8.3. PARA LA ARMADURA DE ACERO.

Acero Longitudinal:
V 1 → L A =6.00−2 x 0.04+2 x 0.20=6.32 m
S

A S=5 x 6.32 x 2=63.2 ml ∅ 5 /8


V 2 → L A =5.00−2 x 0.04+2 x 0.20=5.32 m
S

A S=4 x 5.32 x 2=42.56 ml ∅ 1/2


V 3 → L A =5.00−2 x 0.04+2 x 0.20=5.32 m
S

A S=5 x 5.32=26.60 ml ∅ 1/2


LOGÍSTICA: N°VAR = (63.20/9)1.10 = 7.72 ≈ 8Ø5/8”
N°VAR = (69.16/9)1.10 = 8.45 ≈ 9Ø1/2”
Acero Trasversal:

Para la viga V1 la dividimos en 2 tramos:

o Primer tramo de 3.75 m.

2.25
N Estribos =
−1=10.25 ≈ 11
0.20
resto @ 0.20

N Estribos=7+11+7=25

o SegundoTramo de 1.50m .
N Estribos=7+(−1)+ 7=13

N EstriboTotal =( 25 ) + ( 13 ) =38
L Estribo=( 0.25−0.04 x 2 ) x 2+ ( 0.20−0.04 x 2 ) x 2+0.075 x 2=0.73 m
A S=38 x 0.73 x 2=55.48 m ∅ 3/8

Para la viga V2:

o Tramo de 4.50 m.

3.00
N Estribos −1=14 =
0.20
resto @ 0.20

N Estribos=7+14 +7=28
L Estribo=( 0.15−0.04 x 2 ) x 2+ ( 0.20−0.04 x 2 ) x 2+0.075 x 2=0.53 m
A S=28 x 0.53 x 2=29.68 m ∅ 1/4

Para la viga V3:

o Tramo de 4.50 m.

3.00
N Estribos −1=14 =
0.20
resto @ 0.20

N Estribos=7+14 +7=28
L Estribo=( 0.25−0.04 x 2 ) x 2+ ( 0.20−0.04 x 2 ) x 2+0.075 x 2=0.73 m
A S=28 x 0.73=20.44 m ∅ 1/ 4

As TOTAL=63.2ml ∅ 5/8 x1.552kg/ml+69.16ml∅1/2 x 0.994 kg /ml+55.48 m ∅ 3 /8 x 0.56 kg /ml+50.12 ml ∅1/4

OE.2.3.9. LOSA ALIGERADA


OE.2.3.9.1. PARA EL CONCRETO

ÁreaUnitaria :

x
1 m2
y

100 100
x= =2.5 vig ; y= =3.33 lad ;
40 30
N Ladrillos=2.5 x 3.33=8.33 lad /m2
2
Vol C ° en un m .
Vol C °=1 x 1 x 0.20−8.33 x 0.30 x 0.30 x 0.15
3 2
Vol C °=0.0875 m / m
Calculo de Areás:
2
A1=4.50 x 1.60=7.20 m .
2
A2=4.50 x 3.85 m=17.33 m .
3
m ( 2 3
Vol C ° =0.0875 2 x 7.20+17.33 ) m =2.15 m
TOTAL
m

OE.2.3.9.2. PARA EL ENCOFRADO

Area: A1 + A2 =7.20+ 17.33=24.53 m2

OE.2.3.9.3. PARA EL ACERO

L As 3/8 }} = left (1.05+0.25-0.025+0.10 right ) x2=2.75 ¿ ¿


L As 1/2}} =5.00-2x0.025=4.95 ¿ ¿
L As 1/2}} =4.50-2x0.60=3.30 ¿ ¿
L As 1/2}} =8.25 ¿ ¿
L As 1/4 }} =6.00-2x0.025=5.95 ¿ ¿ N °=4.50/0.25=18

N° VIGUETAS = (3.85/0.40 -1) + (1.60/0.40 -1) ≈ 9 + 3 = 12


AS TOTAL
=2.75 x 12 x 0.56+8.25 x 12 x 0.994+5.95 x 18 x 0.248 kg
AsTOTAL = 143.45 kg.

Ladrillo :

N ° Ladrillos =8.33 x ( 7.2+17.33 )


N ° Ladrillos =204.33 ≈ 205und .

METRADO DE MADERA PARA ENCOFRADO

1
TABLON 1 ”: PT =¿
2

SOLERA 2”x4”: PS =¿

BARROTES 2”x 3”: PB =¿

TORNAPUNTA 2”x3”:
P L=¿
ESTACA: P E=¿
RESUMEN
PTOTAL=5.90+ 2.62+1.31+2.15+1.09=13.07 P2

ANALISIS:
0.60 ml → PTOTAL = 13.07 P2
1.00 ml → X

X = 21.78 P2
Dicho valor será usado para el aporte de madera en el costo unitario de encofrados,
añadiéndole el desperdicio y dividiéndolo entre el número de usos respectivamente.
Metrados en edificaciones:
https://aportealaingcivil.blogspot.com/2017/08/curso-metrados-en-edificaciones-ccip-PERU.html

video 1: https://aportealaingcivil.blogspot.com/2017/08/curso-metrados-en-edificaciones-ccip-
PERU.html

También podría gustarte