OE.1. OBRAS PROVISIONALES, TRABAJOS PRELIMINARES, SEGURIDAD Y SALUD.
OE.1.1.1.6. SERVICIOS HIGIÉNICOS:
Cantidad = 1 Und ó 1 Gbl ó 1 Est
OE.2. ESTRUCTURAS.
OE.2.1.2. EXCAVACIONES:
OE.2.1.2.1. EXCAVACIONES SIMPLES
OE.2.1.4. RELLENOS
OE.2.1.4.1. RELLENO CON
MATERIAL PROPIO
(-) (=)
A1 AMyC AR1
(-) (=)
At
AMyC AR2
At = 5.00x6.00 = 30.00 m 2
AMyC = 5.28 m2
AR2 = 30.00 - 5.28 = 24.72 m2
Volumen de Relleno con material de préstamo:
OE.2.2.6. SOBRECIMIENTOS
OE.2.2.6.1. PARA EL CONCRETO:
OE.2.2.6. FALSOPISOS
2
Area del terreno (AT): AT =5 x 6=30 m
2
Area de Muros y Columnas: (AMyC): A MyC =5.28 m
A F / Piso= A T − A MyC
A F / Piso= A C/ Piso = A PISO=30−5.28=24.72 m2
V C ° =( 4 Z 1+ 2 Z 2 ) hcim
3
V C ° =( 4 x 1.00 x 1.00+2 x 1.00 x 1.50 ) x 0.80=5.60 m
L X =Longitud−2 xRecubrimiento
L X =1.00−2 x 0.075=0.85 m.
L X =LY =0.85 m.
L 0.85
N X = Y +1= +1=7
@ 0.15
Redondeo: 6.33 , 6.78 ≈ 7 barras (Inmediato superior)
Lx 0.85
N y= +1= + 1=7
@ 0.15
Use: 7 barras de 0.85 m. en cada sentido.
L X =1.00−2 x 0.075=0.85 m.
LY =1.50−2 x 0.075=1.35 m
LY
N X = +1
@
1.35
N X= +1=10
0.15
0.85
N y= +1=7
0.15
Use: 10 barras de 0.85m. y 7 barras de 1.35m.
Metrado en peso ( Peso Unitario 1/2:0.994 kg/ml) 83.5m x 0.994 kg/m = 83.00 kg.
OE.2.3.7. COLUMNAS
OE.2.3.7.1. PARA EL CONCRETO
3
V C ° =( 0.25 x 0.25 x 2.85 ) x 6=1.07 m
L A =4.185 m .
S
L 1.55
Cantidad de estribos: N ESTRIBO= C −1= −1=6.75 ≅ 7
@ 0.20
2.40
2.85
N ESTRIBO=6+ 7+6=19
NPT. +0.15
0.25
0.08
0.25 0.45
0.04
0.17
0.25
A SESTRIBO =0.83 x 19 x 6=94.62 ml ∅ 1/4
A STOTAL=117.18 x 0.994 +94.62 x 0.25=140.13 kg
OE.2.3.8. VIGAS
OE.2.3.8.1. PARA EL CONCRETO
3
V 1 ( 0.25 x 0.20 ) →Vol C ° V 1= ( 0.25 x 0.20 x 6 ) x 2=0.60 m
3
V 2=0.15 x 0.20 x 4.50 x 2=0.27 m
3
V 3=0.25 x 0.20 x 4.50=0.225 m
3
V C ° =V 1+V 2+V 3=1.095 m
2
V 1 → AREA=6.00 x 0.20 x 2=2.40 m
2
V 2 → AREA=5.00 x 0.20 x 2+ (1.00+ 2.00+0.75+2.175 ) 0.15=2.889 m
2
V 3 → AREA=4.35 x 0.10+0.90 x 0.15 x 2=0.705 m
2
A Enc . = AV 1+ A V 2 + A V 3=5.994 m
Acero Longitudinal:
V 1 → L A =6.00−2 x 0.04+2 x 0.20=6.32 m
S
2.25
N Estribos =
−1=10.25 ≈ 11
0.20
resto @ 0.20
N Estribos=7+11+7=25
o SegundoTramo de 1.50m .
N Estribos=7+(−1)+ 7=13
N EstriboTotal =( 25 ) + ( 13 ) =38
L Estribo=( 0.25−0.04 x 2 ) x 2+ ( 0.20−0.04 x 2 ) x 2+0.075 x 2=0.73 m
A S=38 x 0.73 x 2=55.48 m ∅ 3/8
o Tramo de 4.50 m.
3.00
N Estribos −1=14 =
0.20
resto @ 0.20
N Estribos=7+14 +7=28
L Estribo=( 0.15−0.04 x 2 ) x 2+ ( 0.20−0.04 x 2 ) x 2+0.075 x 2=0.53 m
A S=28 x 0.53 x 2=29.68 m ∅ 1/4
o Tramo de 4.50 m.
3.00
N Estribos −1=14 =
0.20
resto @ 0.20
N Estribos=7+14 +7=28
L Estribo=( 0.25−0.04 x 2 ) x 2+ ( 0.20−0.04 x 2 ) x 2+0.075 x 2=0.73 m
A S=28 x 0.73=20.44 m ∅ 1/ 4
ÁreaUnitaria :
x
1 m2
y
100 100
x= =2.5 vig ; y= =3.33 lad ;
40 30
N Ladrillos=2.5 x 3.33=8.33 lad /m2
2
Vol C ° en un m .
Vol C °=1 x 1 x 0.20−8.33 x 0.30 x 0.30 x 0.15
3 2
Vol C °=0.0875 m / m
Calculo de Areás:
2
A1=4.50 x 1.60=7.20 m .
2
A2=4.50 x 3.85 m=17.33 m .
3
m ( 2 3
Vol C ° =0.0875 2 x 7.20+17.33 ) m =2.15 m
TOTAL
m
Ladrillo :
1
TABLON 1 ”: PT =¿
2
SOLERA 2”x4”: PS =¿
TORNAPUNTA 2”x3”:
P L=¿
ESTACA: P E=¿
RESUMEN
PTOTAL=5.90+ 2.62+1.31+2.15+1.09=13.07 P2
ANALISIS:
0.60 ml → PTOTAL = 13.07 P2
1.00 ml → X
X = 21.78 P2
Dicho valor será usado para el aporte de madera en el costo unitario de encofrados,
añadiéndole el desperdicio y dividiéndolo entre el número de usos respectivamente.
Metrados en edificaciones:
https://aportealaingcivil.blogspot.com/2017/08/curso-metrados-en-edificaciones-ccip-PERU.html
video 1: https://aportealaingcivil.blogspot.com/2017/08/curso-metrados-en-edificaciones-ccip-
PERU.html