𝐻𝑂 = 0.34 𝑚
𝐻1 = 0.45 𝑚
𝐻2 = 3.05 𝑚
𝐻3 = 0.70 𝑚
1. CALCULO DE LA SOBRECARGA (q):
Carga viva de la vereda (RNE E. 020): 0.5 Tn/m2
Carga muertas de la vereda: 0.36 Tn/m2
Carga viva del pavimento : 1.2 Tn/m2
_________________
𝑞 = 2.06 Tn/m2
2. CALCULO DE LOS KA :
40 2
𝐾𝐴 (𝑃𝐴𝑉𝐼𝑀𝐸𝑁𝑇𝑂) = tan(45 − 2
) = 0.172
31.5 2
𝐾𝐴 (𝑆𝑃) = tan(45 − 2
) = 0.245
32 2
𝐾𝐴 (𝑆𝑃−𝑆𝑀) = tan(45 − 2
) = 0.240
3. CALCULAMOS LOS EMPUJES:
𝐸1 = 𝑞 × 𝐻1 × 𝐾𝐴1 = 2.06 × 0.45 × 0.172 = 0.16 𝑇𝑛/𝑚
𝐸2 = 𝑞 × 𝐻2 × 𝐾𝐴2 = 2.06 × 3.05 × 0.245 = 1.54 𝑇𝑛/m
𝐸3 = 𝑞 × 𝐻3 × 𝐾𝐴3 = 2.06 × 0.70 × 0.240 = 0.35 𝑇𝑛/m
1 1
𝐸4 = 2 × 𝛾1 × 𝐻1 2 × 𝐾𝐴1 = 2 × 2.25 × 0.452 × 0.172 = 0.04 𝑇𝑛/m
𝐸5 = 𝛾1 × 𝐻1 × 𝐻2 × 𝐾𝐴2 = 2.25 × 0.45 × 3.05 × 0.245 = 0.76𝑇𝑛/𝑚
𝐸6 = 𝛾1 × 𝐻1 × 𝐻3 × 𝐾𝐴3 = 2.25 × 0.45 × 0.70 × 0.245 = 0.17𝑇𝑛/𝑚
1 1
𝐸7 = 2 × 𝛾2 × 𝐻2 2 × 𝐾𝐴2 = 2 × 1.80 × 3.052 × 0.245 = 2.05𝑇𝑛/m
𝐸8 = 𝛾2 × 𝐻2 × 𝐻3 × 𝐾𝐴3 = 1.80 × 3.05 × 0.70 × 0.24 = 0.92𝑇𝑛/𝑚
1 1
𝐸9 = 2 × 𝛾3 × 𝐻3 2 × 𝐾𝐴3 = 2 × 1.80 × 0.702 × 0.240 = 0.15𝑇𝑛/m
→ 𝐸𝐴 = 𝐸1 + 𝐸2 + 𝐸3 + 𝐸4 + 𝐸5 + 𝐸6 + 𝐸7 + 𝐸8 + 𝐸9
𝐸𝐴 = 6.14 𝑇𝑛/𝑚
0.16 × 3.525 + 1.54 × 2.225 + 0.35 × 0.35 + 0.04 × 3.45 + 0.76 × 2.225 + 0.17 × 0.35 + 2.05 × 1.717 + 0.92 × 0.35 + 0.15 × 0.233
ℎ𝐴 =
6.14
ℎ𝐴 = 1.61𝑚
7. VERIFICAMOS EL VOLCAMIENTO:
∑ 𝑀 𝑓𝑧𝑎𝑠 𝑒𝑠𝑡𝑎𝑏𝑖𝑙𝑖𝑧𝑎𝑛𝑡𝑒𝑠
𝑆𝑉 =
∑ 𝑓𝑧𝑎𝑠 𝑑𝑒𝑠𝑒𝑠𝑡𝑎𝑏𝑖𝑙𝑖𝑧𝑎𝑛𝑡𝑒
𝐵
𝑒 = 0.11 ; = 0.58
6
𝐵
>𝑒
6
Diagrama trapezoidal
∑𝑤 6𝑒
qmax= 𝐵
(1 + 𝐵
)
20.7 6 × 11
qmax = (1 + )
3.48 3.48
𝑞𝑚𝑎𝑥 = 7.08 𝑡𝑛/𝑚2
∑𝑤 6𝑒
qmin = 𝐵
(1 − 𝐵
)
20.7 6 × 11
qmin = (1 − )
3.48 3.48
𝑞𝑚𝑖𝑛 = 4.82 𝑡𝑛/𝑚2