MATERIALES
AGUA LTS 190 50.00 9,500.00
ARENA GRUESA M3 0.56 1 45,000.00 25,452.00
GRAVA TRITURADA 3/4" COLOR AZUL M3 0.84 1 75,000.00 63,630.00
GASOLINA CORRIENTE GLN 0.1 6,800.00 680.00
CEMENTO GRIS PORTLAND SACO DE 50 KILOS KLS 350 5 320.00 117,600.00
ACEITE MOTOR 4 TIEMPOS PREMOLDA GLN 0.006 12,500.00 75.00
SUBTOTAL MATERIALES 216,937.00
MANO DE OBRA
M. O. ALBANILERIA 2 AYUDANTE HC 1.1 8,852.00 9,737.20
SUBTOTAL MANO DE OBRA 9,737.20
EQUIPO
MEZCLADORA DE CONCRETO DIA 0.06 45,000.00 2,700.00
HERRAMIENTA MENOR GLB 2.6996 2,000.00 5,399.26
SUBTOTAL EQUIPO 8,099.26
MANO DE OBRA
M.O. ALBANILERIA 1 AYUDANTE HC 0.35 4679 1,637.65
SUBTOTAL MANO DE OBRA 1,637.65
EQUIPO
VOLQUETA 5 M3 VJE 0.03 40000 1,200.00
HERRAMIENTA MENOR GLB 0.675 2000 1,350.00
SUBTOTAL EQUIPO 2,550.00
MATERIALES
PUNTILLA 2 CC LBS 0.02 1850 37.00
BASTIDOR 2"x2"x3M OTOBO ML 0.33 1500 495.00
PIOLA GRUESA 50 METROS ROL 0.06 2500 150.00
MINERAL ROJO KLS 0.005 3915 19.57
SUBTOTAL MATERIALES 701.57
MANO DE OBRA
M.O. ALBANILERIA 2 AYUDANTE-1 OFI HC 0.06 18338 1,100.28
M.O. TOPOGRAFIA 1 CADENERO-1 TOP HC 0.04 13660 546.40
SUBTOTAL MANO DE OBRA 1,646.68
EQUIPO
HERRAMIENTA MENOR GLB 0.039 2000 78.00
SUBTOTAL EQUIPO 78.00
MANO DE OBRA
M.O. ALBANILERIA 1 AYUDANTE HC 1.5 4679 7,018.50
SUBTOTAL MANO DE OBRA 7,018.50
EQUIPO
HERRAMIENTA MENOR GLB 0.168 2000 336.00
SUBTOTAL EQUIPO 336.00
MATERIALES
MEZCLA CONCRETO 1:2:3 3100 PSI 21 MPA M3 0.08 234,773.46 18,781.87
SUBTOTAL MATERIALES 18,781.87
MANO DE OBRA
M.O. ALBANILERIA 1 AYUDANTE-1 OFI HC 0.4 11784 4,713.60
SUBTOTAL MANO DE OBRA 4,713.60
EQUIPO
VOLQUETA TRANSPORTE MAT.PETREOS 1-10KM M3 0.105 4,500.00 472.50
HERRAMIENTA MENOR GLB 0.03 2000 60.00
SUBTOTAL EQUIPO 532.50
MATERIALES
AGUA LTS 190 50.00 9,500.00
ARENA GRUESA M3 0.56 1 45,000.00 25,452.00
GRAVA TRITURADA 3/4" COLOR AZUL M3 0.84 1 75,000.00 63,630.00
GASOLINA CORRIENTE GLN 0.1 6,800.00 680.00
CEMENTO GRIS PORTLAND SACO DE 50 KILOS KLS 350 5 320.00 117,600.00
ACEITE MOTOR 4 TIEMPOS PREMOLDA GLN 0.006 12,500.00 75.00
SUBTOTAL MATERIALES 216,937.00
MANO DE OBRA
M. O. ALBANILERIA 2 AYUDANTE HC 1.1 8,852.00 9,737.20
SUBTOTAL MANO DE OBRA 9,737.20
EQUIPO
MEZCLADORA DE CONCRETO DIA 0.06 45,000.00 2,700.00
HERRAMIENTA MENOR GLB 2.6996 2,000.00 5,399.26
SUBTOTAL EQUIPO 8,099.26
MATERIALES
ALAMBRE NEGRO # 18 KLS 0.04 2,700.00 108.00
HIERR.DE 60000 PSI 420 MPA KLS 1 10 2,383.30 2,621.63
SUBTOTAL MATERIALES 2,729.63
MANO DE OBRA
M.O. ALBANILERIA 1 AYUDANTE-1 OFI HC 0.056 11,784.00 659.90
SUBTOTA MANO DE OBRA 659.90
EQUIPO
HERRAMIENTA MENOR GLB 0.1 2,000.00 200.00
SUBTOTAL EQUIPO 200.00
MATERIALES
ANTISOL BLANCO KLS 2 5185 10,370.00
SEPAROL DESFORMALETEANTE TARRO 15 KLS KLS 2 8700 17,400.00
SIKAMENT NS SUPERPLASTIFIC TARRO DE 25 K KLS 0.2 6032 1,206.40
CUARTON 2"x4"x3M OTOBO UND 5.67 4519 25,622.73
PUNTILLA 2 CC LBS 8 1850 14,800.00
TABLA 1x10x3M OTOBO UND 5 7500 37,500.00
VARETA 2"x2"x3M OTOBO UND 4.33 4500 19,485.00
MEZCLA CONCRETO 1:2:3 3100 PSI 21 MPA M3 1.05 234,773.46 246,512.13
SUBTOTAL MATERIALES 372,896.26
MANO DE OBRA
M.O. ALBANILERIA 3 AYUDANTE-1 OIF HC 7.8 20635 160,953.00
SUBTOTAL MANO DE OBRA 160,953.00
EQUIPO
VIBRADOR ELECTRICO DIA 0.1 40000 4,000.00
HERRAMIENTA MENOR GLB 0.375 2000 750.00
TACO METALICO EXTENSION DE 2.OM A 3.30MT DIA 24 116 2,784.00
ANDAMIO METALICO TUBULAR U/D 4 350 1,400.00
SUBTOTAL EQUIPO 8,934.00
MATERIALES
CUARTON 2"x4"x3M OTOBO UND 1.5 4519 6,778.50
GUADUA [TACO] 2.50-3M UND 4 1700 6,800.00
PUNTILLA 2 CC LBS 3.8 1850 7,030.00
TABLA 1x10x3M OTOBO UND 3.5 7500 26,250.00
VARETA 2"x2"x3M OTOBO UND 1.5 0.25 4500 6,766.87
MEZCLA CONCRETO 1:2:3 3100 PSI 21 MPA M3 1.03 234,773.46 241,816.66
SUBTOTAL MATERIALES 295,442.03
MANO DE OBRA
M.O. ALBANILERIA 2 AYUDANTE-1 OFI HC 11 18338 201,718.00
SUBTOTAL MANO DE OBRA 201,718.00
EQUIPO
VIBRADOR ELECTRICO DIA 0.3 40000 12,000.00
HERRAMIENTA MENOR GLB 0.33 2000 660.00
ANDAMIO METALICO TUBULAR U/D 4 350 1,400.00
SUBTOTAL EQUIPO 14,060.00
MATERIALES
CUARTON 2"x4"x3M OTOBO UND 1.5 4519 6,778.50
GUADUA [TACO] 2.50-3M UND 4 1700 6,800.00
PUNTILLA 2 CC LBS 3.8 1850 7,030.00
TABLA 1x10x3M OTOBO UND 3.5 7500 26,250.00
VARETA 2"x2"x3M OTOBO UND 1.5 0.25 4500 6,766.87
MEZCLA CONCRETO 1:2:3 3100 PSI 21 MPA M3 1.03 234,773.46 241,816.66
SUBTOTAL MATERIALES 295,442.03
MANO DE OBRA
M.O. ALBANILERIA 2 AYUDANTE-1 OFI HC 11 18338 201,718.00
SUBTOTAL MANO DE OBRA 201,718.00
EQUIPO
VIBRADOR ELECTRICO DIA 0.3 40000 12,000.00
HERRAMIENTA MENOR GLB 0.33 2000 660.00
ANDAMIO METALICO TUBULAR U/D 4 350 1,400.00
SUBTOTAL EQUIPO 14,060.00
MATERIALES
CUARTON 2"x4"x3M OTOBO UND 1.5 4519 6,778.50
GUADUA [TACO] 2.50-3M UND 4 1700 6,800.00
PUNTILLA 2 CC LBS 3.8 1850 7,030.00
TABLA 1x10x3M OTOBO UND 3.5 7500 26,250.00
VARETA 2"x2"x3M OTOBO UND 1.5 0.25 4500 6,766.87
MEZCLA CONCRETO 1:2:3 3100 PSI 21 MPA M3 1.03 234,773.46 241,816.66
SUBTOTAL MATERIALES 295,442.03
MANO DE OBRA
M.O. ALBANILERIA 2 AYUDANTE-1 OFI HC 11 18338 201,718.00
SUBTOTAL MANO DE OBRA 201,718.00
EQUIPO
VIBRADOR ELECTRICO DIA 0.3 40000 12,000.00
HERRAMIENTA MENOR GLB 0.33 2000 660.00
ANDAMIO METALICO TUBULAR U/D 4 350 1,400.00
SUBTOTAL EQUIPO 14,060.00
VIGA CONCRETO AEREA 3000 PSI, TIPO V-D PARA APOYO DE Unidad: M3
ESCALERA ITEM:
DESCRIPCION UND. CANT. DESP.% PRECIO UNIT. VALOR TOTAL
MATERIALES
CUARTON 2"x4"x3M OTOBO UND 1.5 4519 6,778.50
GUADUA [TACO] 2.50-3M UND 4 1700 6,800.00
PUNTILLA 2 CC LBS 3.8 1850 7,030.00
TABLA 1x10x3M OTOBO UND 3.5 7500 26,250.00
VARETA 2"x2"x3M OTOBO UND 1.5 0.25 4500 6,766.87
MEZCLA CONCRETO 1:2:3 3100 PSI 21 MPA M3 1.03 234,773.46 241,816.66
SUBTOTAL MATERIALES 295,442.03
MANO DE OBRA
M.O. ALBANILERIA 2 AYUDANTE-1 OFI HC 11 18338 201,718.00
SUBTOTAL MANO DE OBRA 201,718.00
EQUIPO
VIBRADOR ELECTRICO DIA 0.3 40000 12,000.00
HERRAMIENTA MENOR GLB 0.33 2000 660.00
ANDAMIO METALICO TUBULAR U/D 4 350 1,400.00
SUBTOTAL EQUIPO 14,060.00
MATERIALES
CUARTON 2"x4"x3M OTOBO UND 1.5 4519 6,778.50
GUADUA [TACO] 2.50-3M UND 4 1700 6,800.00
PUNTILLA 2 CC LBS 3.8 1850 7,030.00
TABLA 1x10x3M OTOBO UND 3.5 7500 26,250.00
VARETA 2"x2"x3M OTOBO UND 1.5 0.25 4500 6,766.87
MEZCLA CONCRETO 1:2:3 3100 PSI 21 MPA M3 1.03 234,773.46 241,816.66
SUBTOTAL MATERIALES 295,442.03
MANO DE OBRA
M.O. ALBANILERIA 2 AYUDANTE-1 OFI HC 11 18338 201,718.00
SUBTOTAL MANO DE OBRA 201,718.00
EQUIPO
VIBRADOR ELECTRICO DIA 0.3 40000 12,000.00
HERRAMIENTA MENOR GLB 0.33 2000 660.00
ANDAMIO METALICO TUBULAR U/D 4 350 1,400.00
SUBTOTAL EQUIPO 14,060.00
MATERIALES
ALAMBRE NEGRO # 18 KLS 0.04 2,700.00 108.00
HIERR.DE 60000 PSI 420 MPA KLS 1 10 2,383.30 2,621.63
SUBTOTAL MATERIALES 2,729.63
MANO DE OBRA
M.O. ALBANILERIA 1 AYUDANTE-1 OFI HC 0.056 11,784.00 659.90
SUBTOTA MANO DE OBRA 659.90
EQUIPO
HERRAMIENTA MENOR GLB 0.1 2,000.00 200.00
SUBTOTAL EQUIPO 200.00
MATERIALES
CUARTON 2"x4"x3M OTOBO UND 3.7 4519 16,720.30
GUADUA [TACO] 2.50-3M UND 2.85 1700 4,845.00
GUADUA 6 MT. UND 3 2500 7,500.00
PUNTILLA 2 CC LBS 1.6 1850 2,960.00
TABLA 1x10x3M OTOBO UND 5.1 7500 38,250.00
CINTA PVC JUNT. DILATACION UND 1.42 26181 37,177.02
PLASTOCRETE D.M. (20 KGS) KLS 1.8 4683 8,429.40
MEZCLA CONCRETO 1:2:3 3100 PSI 21 MPA M3 1.05 234,773.46 246,512.13
SUBTOTAL MATERIALES 362,393.85
MANO DE OBRA
M.O. ALBANILERIA 3 AYUDANTE-1 OIF HC 9.9 20635 204,286.50
SUBTOTAL MANO DE OBRA 204,286.50
EQUIPO
VIBRADOR ELECTRICO DIA 0.22 40000 8,800.00
HERRAMIENTA MENOR GLB 0.61 2000 1,220.00
ANDAMIO METALICO TUBULAR U/D 2 350 700.00
SUBTOTAL EQUIPO 10,720.00
MATERIALES
CUARTON 2"x4"x3M OTOBO UND 3.7 4519 16,720.30
GUADUA [TACO] 2.50-3M UND 2.85 1700 4,845.00
GUADUA 6 MT. UND 3 2500 7,500.00
PUNTILLA 2 CC LBS 1.6 1850 2,960.00
TABLA 1x10x3M OTOBO UND 5.1 7500 38,250.00
CINTA PVC JUNT. DILATACION UND 1.42 26181 37,177.02
PLASTOCRETE D.M. (20 KGS) KLS 1.8 4683 8,429.40
MEZCLA CONCRETO 1:2:3 3100 PSI 21 MPA M3 1.05 234,773.46 246,512.13
SUBTOTAL MATERIALES 362,393.85
MANO DE OBRA
M.O. ALBANILERIA 3 AYUDANTE-1 OIF HC 9.9 20635 204,286.50
SUBTOTAL MANO DE OBRA 204,286.50
EQUIPO
VIBRADOR ELECTRICO DIA 0.22 40000 8,800.00
HERRAMIENTA MENOR GLB 0.61 2000 1,220.00
ANDAMIO METALICO TUBULAR U/D 2 350 700.00
SUBTOTAL EQUIPO 10,720.00
MATERIALES
CUARTON 2"x4"x3M OTOBO UND 3.7 4519 16,720.30
GUADUA [TACO] 2.50-3M UND 2.85 1700 4,845.00
GUADUA 6 MT. UND 3 2500 7,500.00
PUNTILLA 2 CC LBS 1.6 1850 2,960.00
TABLA 1x10x3M OTOBO UND 5.1 7500 38,250.00
CINTA PVC JUNT. DILATACION UND 1.42 26181 37,177.02
PLASTOCRETE D.M. (20 KGS) KLS 1.8 4683 8,429.40
MEZCLA CONCRETO 1:2:3 3100 PSI 21 MPA M3 1.05 234,773.46 246,512.13
SUBTOTAL MATERIALES 362,393.85
MANO DE OBRA
M.O. ALBANILERIA 3 AYUDANTE-1 OIF HC 9.9 20635 204,286.50
SUBTOTAL MANO DE OBRA 204,286.50
EQUIPO
VIBRADOR ELECTRICO DIA 0.22 40000 8,800.00
HERRAMIENTA MENOR GLB 0.61 2000 1,220.00
ANDAMIO METALICO TUBULAR U/D 2 350 700.00
SUBTOTAL EQUIPO 10,720.00
MATERIALES
ALAMBRE NEGRO # 18 KLS 0.04 2,700.00 108.00
HIERR.DE 60000 PSI 420 MPA KLS 1 10 3,500.00 3,850.00
SUBTOTAL MATERIALES 3,958.00
MANO DE OBRA
M.O. ALBANILERIA 1 AYUDANTE-1 OFI HC 0.056 11,784.00 659.90
SUBTOTA MANO DE OBRA 659.90
EQUIPO
HERRAMIENTA MENOR GLB 0.1 2,000.00 200.00
SUBTOTAL EQUIPO 200.00
MATERIALES
WAIPE KLS 0.15 3,870.00 580.50
TORNILLO 3/4" L=8.3CM, CON TUERCA Y ARAN UND 8 2,000.00 16,000.00
NIPLE A.C 6" BXEL L=0.50MTS UND 1 236,466.00 236,466.00
SUBTOTAL MATERIALES 253,046.50
MANO DE OBRA
M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. HC 0.65 17,314.00 11,254.10
SUBTOTAL- MANO DE OBRA 11,254.10
EQUIPO
HERRAMIENTA MENOR GLB 0.2 2,000.00 400.00
SUBTOTAL- EQUIPO 400.00
MATERIALES
CODO A.C 6"X90º BXB UND 1 460,000.00 460,000.00
TORNILLO 3/4" L=8.3CM, CON TUERCA Y ARAN UND 16 2,000.00 32,000.00
WAIPE KLS 0.085 3,870.00 328.95
PIOLA GRUESA 50 METROS ROL 0.025 2,500.00 62.50
SUBTOTAL MATERIALES 492,391.45
MANO DE OBRA
M.O. HIDROSANIT. 1 AYUDANTE-1 OFI HC 0.35 12,520.00 4,382.00
SUBTOTA MANO DE OBRA 4,382.00
EQUIPO
HERRAMIENTA MENOR GLB 0.258 2,000.00 516.00
SUBTOTAL EQUIPO 516.00
MATERIALES
WAIPE KLS 0.15 3870 580.50
PIOLA GRUESA 50 METROS ROL 0.115 2500 287.50
TUB.ACE CARBON D=6" SCHEDULE 40 USO AGU ML 1 204000 204,000.00
SUBTOTAL MATERIALES 204,868.00
MANO DE OBRA
M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. HC 0.65 17314 11,254.10
SUBTOTAL MANO DE OBRA 11,254.10
EQUIPO
HERRAMIENTA MENOR GLB 0.165 2000 330.00
SUBTOTAL EQUIPO 330.00
MATERIALES
TEE AC 6 x 6 ACERO CARBON UND 1 330000 330,000.00
WAIPE KLS 0.15 3870 580.50
PIOLA GRUESA 50 METROS ROL 0.15 2500 375.00
SUBTOTAL MATERIALES 330,955.50
MANO DE OBRA
M.O. HIDROSANIT. 1 AYUDANTE-1 OFI HC 1.2 12520 15,024.00
SUBTOTAL MANO DE OBRA 15,024.00
EQUIPO
HERRAMIENTA MENOR GLB 0.515 2000 1,030.00
SUBTOTAL EQUIPO 1,030.00
MATERIALES
SOLDADURA 6011 1/8" VARILLA KLS 0.5 5,970.00 2,985.00
BRIDAS DE 6" PARA SOLDAR UND 1 94,000.00 94,000.00
SUBTOTAL MATERIALES 96,985.00
MANO DE OBRA
M.O. METALISTERIA 1 AYUDANTE-1 OFI HC 1.1 14,141.00 15,555.10
SUBTOTAL- MANO DE OBRA 15,555.10
EQUIPO
HERRAMIENTA MENOR GLB 1 2,000.00 2,000.00
SOLDADOR ELECTRICO DIA 0.125 14,000.00 1,750.00
SUBTOTAL- EQUIPO 3,750.00
MATERIALES
WAIPE KLS 0.15 3,870.00 580.50
PIOLA GRUESA 50 METROS ROL 0.15 2,500.00 375.00
TORNILLO 3/4" L=8.3CM, CON TUERCA Y ARAN UND 16 2,000.00 32,000.00
PASA MURO 6" BXB L=0.5MTS, Z=0.25MTS UND 1 384,000.00 384,000.00
SUBTOTAL MATERIALES 416,955.50
MANO DE OBRA
M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. HC 0.65 17,314.00 11,254.10
SUBTOTAL- MANO DE OBRA 11,254.10
EQUIPO
HERRAMIENTA MENOR GLB 0.2 2,000.00 400.00
SUBTOTAL- EQUIPO 400.00
MATERIALES
WAIPE KLS 0.15 3,870.00 580.50
PIOLA GRUESA 50 METROS ROL 0.15 2,500.00 375.00
TORNILLO 3/4" L=8.9CM, CON TUERCA Y ARAN UND 16 2,000.00 32,000.00
PASAMURO 8" BXE.L L=0.5MTS, Z=0.15MTS UND 1 454,200.00 454,200.00
SUBTOTAL MATERIALES 487,155.50
MANO DE OBRA
M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. HC 0.65 17,314.00 11,254.10
SUBTOTAL- MANO DE OBRA 11,254.10
EQUIPO
HERRAMIENTA MENOR GLB 0.2 2,000.00 400.00
SUBTOTAL- EQUIPO 400.00
MATERIALES
CODO A.C 8"X45º BXB UND 1 548,100.00 548,100.00
TORNILLO 3/4" L=8.9CM, CON TUERCA Y ARAN UND 16 2,000.00 32,000.00
WAIPE KLS 0.085 3,870.00 328.95
PIOLA GRUESA 50 METROS ROL 0.025 2,500.00 62.50
SUBTOTAL MATERIALES 580,491.45
MANO DE OBRA
M.O. HIDROSANIT. 1 AYUDANTE-1 OFI HC 0.35 12,520.00 4,382.00
SUBTOTA MANO DE OBRA 4,382.00
EQUIPO
HERRAMIENTA MENOR GLB 0.25 2,000.00 500.00
SUBTOTAL EQUIPO 500.00
MATERIALES
PIOLA GRUESA 50 METROS ROL 0.15 2,500.00 375.00
WAIPE KLS 0.15 3,870.00 580.50
TUBERIA A.C 8" PARA SOLDAR ML 1 298,000.00 298,000.00
SUBTOTAL MATERIALES 298,955.50
MANO DE OBRA
M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. HC 0.65 17,314.00 11,254.10
SUBTOTAL- MANO DE OBRA 11,254.10
EQUIPO
HERRAMIENTA MENOR GLB 0.2 2,000.00 400.00
SUBTOTAL- EQUIPO 400.00
MATERIALES
SOLDADURA 6011 1/8" VARILLA KLS 0.5 5,970.00 2,985.00
BRIDAS PARA SOLDAR 8" UND 1 140,940.00 140,940.00
SUBTOTAL MATERIALES 143,925.00
MANO DE OBRA
M.O. METALISTERIA 1 AYUDANTE-1 OFI HC 1.1 14,141.00 15,555.10
SUBTOTAL- MANO DE OBRA 15,555.10
EQUIPO
HERRAMIENTA MENOR GLB 1 2,000.00 2,000.00
SOLDADOR ELECTRICO DIA 0.125 14,000.00 1,750.00
SUBTOTAL- EQUIPO 3,750.00
MATERIALES
TEE AC 8"X6"X8" BXBXB UND 1 752000 752,000.00
WAIPE KLS 0.15 3870 580.50
PIOLA GRUESA 50 METROS ROL 0.15 2500 375.00
SUBTOTAL MATERIALES 752,955.50
MANO DE OBRA
M.O. HIDROSANIT. 1 AYUDANTE-1 OFI HC 1.2 12520 15,024.00
SUBTOTAL MANO DE OBRA 15,024.00
EQUIPO
HERRAMIENTA MENOR GLB 0.515 2000 1,030.00
SUBTOTAL EQUIPO 1,030.00
MATERIALES
PIOLA GRUESA 50 METROS ROL 0.15 2,500.00 375.00
WAIPE KLS 0.15 3,870.00 580.50
TORNILLO 3/4" L=8.9CM, CON TUERCA Y ARAN UND 16 2,000.00 32,000.00
NIPLE A.C 8" BXE.L PARA PVC L=0.50MTS UND 1 407,160.00 407,160.00
SUBTOTAL MATERIALES 440,115.50
MANO DE OBRA
M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. HC 0.65 17,314.00 11,254.10
SUBTOTAL- MANO DE OBRA 11,254.10
EQUIPO
HERRAMIENTA MENOR GLB 0.2 2,000.00 400.00
SUBTOTAL- EQUIPO 400.00
MATERIALES
PIOLA GRUESA 50 METROS ROL 0.15 2,500.00 375.00
WAIPE KLS 0.15 3,870.00 580.50
TORNILLO 5/8" L=7.6CM, CON TUERCA Y ARAN UND 16 2,000.00 32,000.00
NIPLE A.C 4" BXB L=0.30MTS UND 1 172,300.00 172,300.00
SUBTOTAL MATERIALES 205,255.50
MANO DE OBRA
M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. HC 0.65 17,314.00 11,254.10
SUBTOTAL- MANO DE OBRA 11,254.10
EQUIPO
HERRAMIENTA MENOR GLB 0.2 2,000.00 400.00
SUBTOTAL- EQUIPO 400.00
MATERIALES
CODO AC 90 X 4" BXB UND 1 187920 187,920.00
TORNILLO 5/8" L=7.6CM, CON TUERCA Y ARAN UND 16 2000 32,000.00
WAIPE KLS 0.1 3870 387.00
PIOLA GRUESA 50 METROS ROL 0.15 2500 375.00
SUBTOTAL MATERIALES 220,682.00
MANO DE OBRA
M.O. HIDROSANIT. 1 AYUDANTE-1 OFI HC 0.5 12520 6,260.00
SUBTOTAL MANO DE OBRA 6,260.00
EQUIPO
HERRAMIENTA MENOR GLB 0.308 2000 616.00
SUBTOTAL EQUIPO 616.00
MATERIALES
PIOLA GRUESA 50 METROS ROL 0.15 2,500.00 375.00
WAIPE KLS 0.15 3,870.00 580.50
TUBERIA A.C 4" PARA SOLDAR ML 1 141,000.00 141,000.00
SUBTOTAL MATERIALES 141,955.50
MANO DE OBRA
M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. HC 0.65 17,314.00 11,254.10
SUBTOTAL- MANO DE OBRA 11,254.10
EQUIPO
HERRAMIENTA MENOR GLB 0.2 2,000.00 400.00
SUBTOTAL- EQUIPO 400.00
MATERIALES
WAIPE KLS 0.15 3,870.00 580.50
PIOLA GRUESA 50 METROS ROL 0.15 2,500.00 375.00
TORNILLO 5/8" L=7.6CM, CON TUERCA Y ARAN UND 16 2,000.00 32,000.00
NIPLE 4" BXE.L PARA PVC L=0.50MTS UND 1 141,000.00 141,000.00
SUBTOTAL MATERIALES 173,955.50
MANO DE OBRA
M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. HC 0.65 17,314.00 11,254.10
SUBTOTAL- MANO DE OBRA 11,254.10
EQUIPO
HERRAMIENTA MENOR GLB 0.2 2,000.00 400.00
SUBTOTAL- EQUIPO 400.00
MATERIALES
SOLDADURA 6011 1/8" VARILLA KLS 0.5 5,970.00 2,985.00
BRIDA PARA SOLDAR 4" UND 1 54,497.00 54,497.00
SUBTOTAL MATERIALES 57,482.00
MANO DE OBRA
M.O. METALISTERIA 1 AYUDANTE-1 OFI HC 1.1 14,141.00 15,555.10
SUBTOTAL- MANO DE OBRA 15,555.10
EQUIPO
HERRAMIENTA MENOR GLB 1 2,000.00 2,000.00
SOLDADOR ELECTRICO DIA 0.125 14,000.00 1,750.00
SUBTOTAL- EQUIPO 3,750.00
MATERIALES
TEE A.C 8"X4"X8" BXBXB UND 1 712530 712,530.00
WAIPE KLS 0.15 3870 580.50
PIOLA GRUESA 50 METROS ROL 0.15 2500 375.00
SUBTOTAL MATERIALES 713,485.50
MANO DE OBRA
M.O. HIDROSANIT. 1 AYUDANTE-1 OFI HC 1.2 12520 15,024.00
SUBTOTAL MANO DE OBRA 15,024.00
EQUIPO
HERRAMIENTA MENOR GLB 0.515 2000 1,030.00
SUBTOTAL EQUIPO 1,030.00
MATERIALES
CODO A.C 8"X90º BXB UND 1 657,720.00 657,720.00
WAIPE KLS 0.085 3,870.00 328.95
PIOLA GRUESA 50 METROS ROL 0.025 2,500.00 62.50
SUBTOTAL MATERIALES 658,111.45
MANO DE OBRA
M.O. HIDROSANIT. 1 AYUDANTE-1 OFI HC 0.35 12,520.00 4,382.00
SUBTOTA MANO DE OBRA 4,382.00
EQUIPO
HERRAMIENTA MENOR GLB 0.258 2,000.00 516.00
SUBTOTAL EQUIPO 516.00
MATERIALES
VALVULA DE COMPUERTA VNA 6" BXB UND 1 1,508,000.00 1,508,000.00
TORNILLO 3/4" L=8.3CM, CON TUERCA Y ARAN UND 16 2,000.00 32,000.00
SUBTOTAL MATERIALES 1,540,000.00
MANO DE OBRA
M.O. HIDROSANIT. 1 AYUDANTE-1 OFI HC 5 12,520.00 62,600.00
SUBTOTA MANO DE OBRA 62,600.00
EQUIPO
HERRAMIENTA MENOR GLB 5 2,000.00 10,000.00
SUBTOTAL EQUIPO 10,000.00
MATERIALES
TORNILLO 3/4" L=8.9CM, CON TUERCA Y ARAN UND 16 2,000.00 32,000.00
VALVULA DE COMPUERTA VNA 8" BXB UND 1 2,010,280.00 2,010,280.00
SUBTOTAL MATERIALES 2,042,280.00
MANO DE OBRA
M.O. HIDROSANIT. 1 AYUDANTE-1 OFI HC 5 12,520.00 62,600.00
SUBTOTA MANO DE OBRA 62,600.00
EQUIPO
HERRAMIENTA MENOR GLB 5 2,000.00 10,000.00
SUBTOTAL EQUIPO 10,000.00
MATERIALES
TORNILLO 5/8" L=7.6CM, CON TUERCA Y ARAN UND 16 2000 32,000.00
VALVULA DE COMPUERTA VNA 4" BXB UND 1 719200 719,200.00
SUBTOTAL MATERIALES 751,200.00
MANO DE OBRA
M.O. HIDROSANIT. 1 AYUDANTE-1 OFI HC 0.4 12520 5,008.00
SUBTOTAL MANO DE OBRA 5,008.00
EQUIPO
HERRAMIENTA MENOR GLB 0.308 2000 616.00
SUBTOTAL EQUIPO 616.00
MATERIALES
LIJA 320 AGUA PLI 2 800.00 1,600.00
WASH PRIMER LTS 0.2 5,740.00 1,148.00
SOLDADURA 6011 1/8" VARILLA KLS 0.5 5,970.00 2,985.00
MASILLA PLASTICA INTERIORES CUム 0.06 52,000.00 3,120.00
TUBO GALV. 1.1/2"*6.0M UND 0.67 75,550.00 50,618.50
SUBTOTAL MATERIALES 59,471.50
MANO DE OBRA
M.O. METALISTERIA 1 AYUDANTE-1 OFI HC 2.6 14,141.00 36,766.60
SUBTOTAL MANO DE OBRA 36,766.60
EQUIPO
SOLDADOR ELECTRICO DIA 0.125 14,000.00 1,750.00
HERRAMIENTA MENOR GLB 10 2,000.00 20,000.00
SUBTOTAL EQUIPO 21,750.00
ESCALERAS CON PASA MANOS DEL NIVEL 0.0 A NIVEL 25.0 EN Unidad: ML
TUBERIA DE H.G 1 1/2" ITEM:
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL
MATERIALES
LIJA 320 AGUA PLI 2 800.00 1,600.00
WASH PRIMER LTS 0.35 5,740.00 2,009.00
SOLDADURA 6011 1/8" VARILLA KLS 1 5,970.00 5,970.00
MASILLA PLASTICA INTERIORES CUム 0.07 52,000.00 3,640.00
TUBO GALV. 1.1/2"*6.0M UND 1.54 0 75,550.00 116,347.00
SUBTOTAL MATERIALES 129,566.00
MANO DE OBRA
M.O. METALISTERIA 1 AYUDANTE-1 OFI HC 3.5 14,141.00 49,493.50
SUBTOTA MANO DE OBRA 49,493.50
EQUIPO
HERRAMIENTA MENOR GLB 1 2,000.00 2,000.00
SOLDADOR ELECTRICO DIA 0.125 14,000.00 1,750.00
SUBTOTAL EQUIPO 3,750.00
ANALISIS DE PRECIOS UNITARIOS
CONSTRUCCIÓN DE TANQUE DE ALMACENAMIENTO ELEVADO DE 500 M3 EN EL MUNICIPIO
DE LOS CÓRDOBAS, DEPARTAMENTO DE CÓRDOBA
COSTO DIRECTO 182,809.50
ANALISIS DE PRECIOS UNITARIOS
CONSTRUCCIÓN DE TANQUE DE ALMACENAMIENTO ELEVADO DE 500 M3 EN EL MUNICIPIO
DE LOS CÓRDOBAS, DEPARTAMENTO DE CÓRDOBA
MATERIALES
LIJA 320 AGUA PLI 2 800.00 1,600.00
WASH PRIMER LTS 0.35 5,740.00 2,009.00
SOLDADURA 6011 1/8" VARILLA KLS 1 5,970.00 5,970.00
MASILLA PLASTICA INTERIORES CUム 0.07 52,000.00 3,640.00
TUBO GALV. 1.1/2"*6.0M UND 0.54 75,550.00 40,797.00
SUBTOTAL MATERIALES 54,016.00
MANO DE OBRA
M.O. METALISTERIA 1 AYUDANTE-1 OFI HC 3.5 14,141.00 49,493.50
SUBTOTA MANO DE OBRA 49,493.50
EQUIPO
HERRAMIENTA MENOR GLB 1 2,000.00 2,000.00
SOLDADOR ELECTRICO DIA 0.125 14,000.00 1,750.00
SUBTOTAL EQUIPO 3,750.00
MATERIALES
LIJA 320 AGUA PLI 2 800.00 1,600.00
WASH PRIMER LTS 0.35 5,740.00 2,009.00
SOLDADURA 6011 1/8" VARILLA KLS 1 5,970.00 5,970.00
MASILLA PLASTICA INTERIORES CUム 0.07 52,000.00 3,640.00
TUBO GALV. 1.1/2"*6.0M UND 0.54 75,550.00 40,797.00
SUBTOTAL MATERIALES 54,016.00
MANO DE OBRA
M.O. METALISTERIA 1 AYUDANTE-1 OFI HC 3.5 14,141.00 49,493.50
SUBTOTA MANO DE OBRA 49,493.50
EQUIPO
HERRAMIENTA MENOR GLB 1 2,000.00 2,000.00
SOLDADOR ELECTRICO DIA 0.125 14,000.00 1,750.00
SUBTOTAL EQUIPO 3,750.00
MANO DE OBRA
M.O. METALISTERIA 1 AYUDANTE-1 OFI HC 0.6 14,141.00 8,484.60
SUBTOTAL MANO DE OBRA 8,484.60
EQUIPO
HERRAMIENTA MENOR GLB 1 2,000.00 2,000.00
SUBTOTAL EQUIPO 2,000.00
MANO DE OBRA
M.O. ALBANILERIA 1 AYUDANTE HC 1.5 4679 7,018.50
SUBTOTAL MANO DE OBRA 7,018.50
EQUIPO
HERRAMIENTA MENOR GLB 0.168 2000 336.00
SUBTOTAL EQUIPO 336.00
MATERIALES
LUBRICANTE TUB PVC/500GR 500GRS UND 0.05 11921 596.05
TUBO PVC UM 8 RDE-41 PRESION ML 1 2 51936 52,974.72
SUBTOTAL MATERIALES 53,570.77
MANO DE OBRA
M.O. CARP.MADERA 1 AYUDANTE-1 OFI HC 0.2 13256 2,651.20
SUBTOTAL MANO DE OBRA 2,651.20
EQUIPO
HERRAMIENTA MENOR GLB 0.04 2000 80.00
SUBTOTAL EQUIPO 80.00
MATERIALES
GASOLINA CORRIENTE GLN 0.05 6800 340.00
ACEITE MOTOR 4 TIEMPOS PREMOLDA GLN 0.015 12500 187.50
SUBTOTAL MATERIALES 527.50
MANO DE OBRA
M.O. ALBANILERIA 2 AYUDANTE HC 0.5 8852 4,426.00
SUBTOTAL MANO DE OBRA 4,426.00
EQUIPO
VIBROCOMPACTADOR TIPO RANA DIA 0.04 45000 1,800.00
HERRAMIENTA MENOR GLB 0.05 2000 100.00
SUBTOTAL EQUIPO 1,900.00