PRESUPUESTO
PARTIDAS MAYORES VARIACIÓN (%)
MODIFICADO
NUEVAS METRADOS
0.00 19,433.81 1,151,586.97 -9,025.90 -0.78%
0.00 10,546.76 475,999.15 -8,775.93 -1.81%
0.00 8,887.05 675,587.82 -249.97 -0.04%
0.00 0.00 200,049.04 -21,136.66 -9.56%
0.00 19,433.81 1,351,636.01 -30,162.56 -2.18%
69,300.00 0.00 69,300.00 69,300.00 100.00%
0.00 0.00 101,152.50 0.00 0.00%
0.00 0.00 40,500.00 0.00 0.00%
0.00 0.00 26,782.00 0.00 0.00%
0.00 0.00 15,300.00 -7,500.00 -32.89%
0.00 0.00 0.00 -40,663.34 -100.00%
69,300.00 19,433.81 1,604,670.51 -9,025.90 -0.56%
0.00 0.00 46,830.67 0.00 0.00%
69,300.00 19,433.81
1,651,501.18 -9,025.90 -0.54%
88,733.81
RESUMEN DE PRESUPUESTOS
PRESUPUESTO
PRESUPUESTO
DEDUCTIVO
FINANCIADO AL N.E
VINCULANTE
(A) (D)
MONTO DE INVERSIÓN
DESCRIPCIÓN Expediente Técnico Expediente Técnico
Aprobado (S/.) Modificado (S/.)
MONTO DE INVERSIÓN
DESCRIPCIÓN Expediente Técnico Expediente Técnico
Aprobado (S/.) Modificado (S/.)
MONTO DE INVERSIÓN
DESCRIPCIÓN Expediente Técnico Expediente Técnico
Aprobado (S/.) Modificado (S/.)
MONTO DE INVERSIÓN
DESCRIPCIÓN Expediente Técnico Expediente Técnico
Aprobado (S/.) Modificado (S/.)
EXP. TÉCNICO
ÍTEM COMPONENTE MODIFICACIÓN
APROBADO
1.0 COSTO DIRECTO DE LA INFRAESTRUCTURA 1,160,612.87 -9,025.90
1.1 C.D. SISTEMA DE AGUA POTABLE 484,775.08 -8,775.93
1.2 C.D. DISPOSICIÓN SANITARIA DE EXCERTAS 675,837.79 -249.97
2.0 GASTOS GENERALES 221,185.70 -21,136.66
COSTO TOTAL DE LA OBRA 1,381,798.57 -30,162.56
3.0 GASTOS DE SUPERVISIÓN DE OBRA 0.00 69,300.00
4.0 GASTOS DEL COMPONENTE SOCIAL 101,152.50 0.00
5.0 GASTOS DE SUPERVISIÓN SOCIAL 40,500.00 0.00
6.0 GASTOS DEL NÚCLEO EJECUTOR 26,782.00 0.00
7.0 GASTOS DE MONITOREO ARQUEOLÓGICO 22,800.00 -7,500.00
8.0 EXPEDIENTE TÉCNICO 40,663.34 -40,663.34
SUB TOTAL DE INVERSIÓN DE LA OBRA 1,613,696.41 -9,025.90
9.0 ADICIONAL N° 01: PLAN COVID-19 46,830.67 0.00
COSTO TOTAL DE INVERSIÓN (FINANCIADO) 1,660,527.08 -9,025.90
UPUESTOS
PRESUPUESTOS ADICIONALES
PRESUPUESTO
MAYORES
PARTIDAS NUEVAS REFORMULADO
METRADOS
(B) (C) (E = A+B+C-D)
VARIACIÓN
En Soles En Porcentaje
-28,459.71 -2.45%
VARIACIÓN
En Soles En Porcentaje
0.00 0.00%
VARIACIÓN
En Soles En Porcentaje
19,433.81 1.67%
PARTIDAS MAYORES
MODIFICACIÓN
NUEVAS METRADOS
0.00 10,546.76 -8,775.93
0.00 8,887.05 -249.97
0.00 19,433.81 -9,025.90
VARIACIÓN
En Soles En Porcentaje
-9,025.90 -0.78%
O TOTAL DEL PROYECTO
EXP. TÉCNICO
MODIFICADO
1,151,586.97
475,999.15
675,587.82 NOTAS:
200,049.04 - Presentar Desagregado de GG, ACTUALIZADO
1,351,636.01
69,300.00 - Presentar RD de aprobación del ET
101,152.50
40,500.00
26,782.00
15,300.00 - Presentar Contrato del Arqueólogo (sustento legal)
0.00 - Presentar RD de aprobación del ET
1,604,670.51
46,830.67 - Se tiene disponibilidad presupuestal en GG, con respecto al Especialista A
1,651,501.18
n respecto al Especialista Ambiental, no es necesario utilizar estos recursos.
CUADROS COMPARATIVOS DE LOS PRESUPUESTOS DEL PROYECTO
PROYECTO: "AMPLIACIÓN Y MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE E INSTALACIÓN DEL SANEAMIENTO BÁSICO DE LA LOCALIDAD DE EL CARDÓN, DISTRITO DE JOSÉ SABOGAL - SAN MARCOS - CAJAMARCA"
EJECUTA: N.E. EL CARDÓN - SNIP 300508 LUGAR: EL CARDÓN - JOSÉ SABOGAL - SAN MARCOS - CAJAMARCA FECHA: MAYO, 2022
01.04.01.07.01 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.60 x 0.60 m e=1/8", INCLUYE LLAVE MAESTRA und 1.00 179.00 179.00 1.00 179.00 0.00 0.00
01.04.01.07.02 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.40 x 0.50 m, E=1/8" INCLUYE LLAVE MAESTRA und 1.00 159.00 159.00 1.00 159.00 0.00 0.00
01.04.02.07.01 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.60 X 0.60 m e=1/8', INCLUYE LLAVE MAESTRA und 1.00 179.00 179.00 1.00 179.00 179.00
01.04.02.07.02 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.40 x 0.50m, E=1/8" INCLUYE LLAVE MAESTRA und 1.00 159.00 159.00 1.00 159.00 159.00
01.04.03.07.01 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.60 x0.60m e=1/8",INCLUYE LLAVE MAESTRA und 1.00 179.00 179.00 1.00 179.00 179.00
01.04.03.07.02 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.40 x0.50m, E=1/8" INCLUYE LLAVE MAESTRA und 1.00 159.00 159.00 1.00 159.00 159.00
01.05.02.01.06.01 SUMINISTRO E INSTALACIÓN DE ACCESORIOS DE ENTRADA DE 1 1/2" - (CAPTACIÓN"LA VALERIANA 1") und 1.00 87.29 87.29 1.00 87.29 87.29
01.05.02.01.06.02 SUMINISTRO E INSTALACIÓN DE ACCESORIOS DE ENTRADA DE 1 1/2" - (LA VALERIANA 2) und 1.00 87.29 87.29 1.00 87.29 87.29
01.05.02.01.06.03 SUMINISTRO E INSTALACIÓN DE ACCESORIOS DE SALIDA Ø= 1 1/2" - CÁMARA DE REUNIÓN und 1.00 88.53 88.53 1.00 88.53 88.53
01.05.02.01.06.04 SUMINISTRO E INSTALACIÓN DE ACCESORIOS DE LIMPIA Y REBOSE DE 2 1/2" und 1.00 185.02 185.02 1.00 185.02 185.02
01.05.02.01.06.05 SUMINISTRO E INSTALACIÓN DE ACCESORIOS DE VENTILACIÓN und 1.00 59.08 59.08 1.00 59.08 59.08
01.05.02.01.07 TAPA SANITARIA 179.00 0.00 179.00
01.05.02.01.07.01 SUMINISTRO E INSTALACIÓN DE TAPA METÁLICA, DE 0.60X0.60M E=1/8" INC. LLAVE MAESTRA und 1.00 179.00 179.00 1.00 179.00 179.00
01.05.02.02.06.01 SUMINISTRO E INSTALACIÓN DE ACCESORIOS DE ENTRADA DE 1 1/2" - (CAPTACIÓN"LA VALERIANA") und 1.00 87.29 87.29 1.00 87.29 87.29
01.05.02.02.06.02 SUMINISTRO E INSTALACIÓN DE ACCESORIOS DE ENTRADA DE 1 1/2" - (LA VALERIANA 2) und 1.00 87.29 87.29 1.00 87.29 87.29
01.05.02.02.06.03 SUMINISTRO E INSTALACIÓN DE ACCESORIOS DE SALIDA Ø= 1 1/2" - CÁMARA DE REUNIÓN und 1.00 88.53 88.53 1.00 88.53 88.53
01.05.02.02.06.04 SUMINISTRO E INSTALACIÓN DE ACCESORIOS DE LIMPIA Y REBOSE DE 2 1/2" und 1.00 185.02 185.02 1.00 185.02 185.02
01.05.02.02.06.05 SUMINISTRO E INSTALACIÓN DE ACCESORIOS DE VENTILACIÓN und 1.00 59.08 59.08 1.00 59.08 59.08
01.05.02.02.07 TAPA SANITARIA 179.00 0.00 179.00
01.05.02.02.07.01 SUMINISTRO E INSTALACIÓN DE TAPA METÁLICA, DE 0.60X0.60M E=1/8" INC. LLAVE MAESTRA und 1.00 179.00 179.00 1.00 179.00 179.00
01.06.01.02.04.03 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.60 X 0.60 m e=1/8', INC. LLAVE MAESTRA und 1.00 179.00 179.00 1.00 179.00 179.00
01.06.01.04.05.01 SUMINISTRO E INST. DE ACCESORIOS DE LIMPIEZA Y REBOSE EN SISTEMA DE CLORACION und 1.00 287.56 287.56 1.00 287.56 287.56
01.06.01.06.02.04.01 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.60 X 0,60 m e=1/8*, INCLUYE LLAVE MAESTRA und 1.00 179.00 179.00 1.00 179.00 179.00
01.06.01.07 CERCO PERIMETRICO 1,016.23 0.00 1,016.23
01.06.01.07.01 TRABAJOS PRELIMINARES 19.66 0.00 19.66
01.05.01.07.01.01 TRAZO Y REPLANTEO m2 18.90 1.04 19.66 18.90 1.04 19.66
01.06.01.07.02 MOVIMIENTO DE TIERRAS 26.75 0.00 26.75
01.06.01.07.02.01 EXCAVACION EN TERRENO NORMAL m3 0.64 26.09 16.70 0.64 26.09 16.70
01.06.01.07.02.02 ELIMINACION DE MATERIAL EXCEDENTE DP=30 M m3 0.77 13.05 10.05 0.77 13.05 10.05
01.06.01.07.03 OBRAS DE CONCRETO SIMPLE 240.81 0.00 240.81
01.06.01.07.03.01 CONCRETO fe=140 kg/cm2 + 30%PM, S/MEZCLADORA m3 0.76 316.86 240.81 0.76 316.86 240.81
01.06.01.07.04 VARIOS 729.01 0.00 729.01
01.06.01.07.04.01 SUMINISTRO Y INSTALACION DE POSTES DE MADERA TRATADA und 13.00 12.10 157.30 13.00 12.10 157.30
01.06.01.07.04.02 SUMINISTRO Y INSTALACION DE ALAMBRES DE PUAS m 181.80 0.85 154.53 181.80 0.85 154.53
01.06.01.07.04.03 SUMINISTRO E INSTALACIÓN DE PUERTA und 1.00 417.18 417.18 1.00 417.18 417.18
01.07 REDES DE DISTRIBUCION 281,390.79 8,760.67 10,546.76 0.00 283,176.88
01,07.01 REDES DISTRIBUCION L=8526.4m 197,501.20 0.00 197,501.20
01.07.01.01 TRABAJOS PRELIMINARES 14,750.67 0.00 14,750.67
01.07.01.01.01 LIMPIEZA DE TERRENO MANUAL m 8,526.40 0.78 6,650.59 8,526.40 0.78 6,650.59
01.07.01.01.02 TRAZO, NIVELACION Y REPLANTEO DE ZANJAS m 8,526.40 0.95 8,100.08 8,526.40 0.95 8,100.08
01.07.01.02 MOVIMIENTO DE TIERRAS 118,682.64 0.00 118,682.64
01.07.01.02.01 EXCAVACION EN TERRENO NORMAL DE 0,40x0,60 m P/TUB,AGUA m 6,746.90 7.11 47,970.46 6,746.90 7.11 47,970.46
01.07.01.02.02 EXCAVACION EN TERRENO NORMAL DE 0,50x1,10 m P/TUB,AGUA (Cruce en vía carrozable) m 80.00 14.82 1,185.60 80.00 14.82 1,185.60
01.07.01.02.03 EXCAVACION EN TERRENO SEMIROCOSO DE 0.40 X 0.60M, P/TUB. AGUA m 1,685.50 10.67 17,984.29 1,685.50 10.67 17,984.29
01.07.01.02.04 EXCAVACION EN TERRENO SEMIROCOSO DE 0.50x1.10 m P/TUB.AGUA (Cruce en via carrozable) m 20.00 22.23 444.60 20.00 22.23 444.60
01.07.01.02.05 REPINE Y NIVELACION DE FONDO PARA ZANJA DE 0.40x0.70 m P/TUB. AGUA m 8,526.40 0.43 3,666.35 8,526.40 0.43 3,666.35
01.07.01.02.06 CAMA DE APOYO C/MAT. PROP. ZARANDEADO PARA TUBERIA DE AGUA E=0.10 m m 8,526.40 1.13 9,634.83 8,526.40 1.13 9,634.83
01.07.01.02.07 PRIMER RELLENO COMPACTADO DE ZANJA CON MAT PROPIO ZARANDEADO e=0.30m m 8,526.40 2.23 19,013.87 8,526.40 2.23 19,013.87
01.07.01.02.08 SEGUNDO RELLENO CON MATERIAL PROPIO COMPACTADO e=0.30 m m 8,426.40 1.60 13,482.24 8,426.40 1.60 13,482.24
01.07.01.02.09 SEGUNDO RELLENO CON MATERIAL PROPIO COMPACTADO e=0.70 m m 100.00 1.60 160.00 100.00 1.60 160.00
01.07.01.02.10 ELIMINACION DE MATERIAL EXCEDENTE DP=30 M m3 393.90 13.05 5,140.40 393.90 13.05 5,140.40
01.07.01.03 SUMINISTRO E INSTALACION DE TUBERIAS 60,540.76 0.00 60,540.76
01.07.01.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC NTP IS0 1452 UF DN 75 mm C-10 m 49.20 11.24 553.01 49.20 11.24 553.01
01.07.01.03.02 SUMINISTRO E INSTALACION DE TUBERIA PVC NTP IS0 1452 UF DN 63 mm C-10 m 394.50 8.22 3,242.79 394.50 8.22 3,242.79
01.07.01.03.03 SUMINISTRO E INSTALACION DE TUBERIA PVC NTP ITINTEC 399,002 DN Ø1 1/2" C-10 m 2,060.40 8.77 18,069.71 2,060.40 8.77 18,069.71
01.07.01.03.04 SUMINISTRO E INSTALACION DE TUBERIA PVC NTP ITINTEC 399.002 DN Ø 1" C-10 m 4,166.00 6.04 25,162.64 4,166.00 6.04 25,162.64
01.07.01.03.05 SUMINISTRO E INSTALACION DE TUBERIA PVC NTP ITINTEC 399.002 DN Ø 3/4" C-10 m 1,856.30 4.11 7,629.39 1,856.30 4.11 7,629.39
01.07.01.03.06 PRUEBA HIDRAULICA P/TUB m 8,526.40 0.69 5,883.22 8,526.40 0.69 5,883.22
01.07.01.04 SUMINISTRO E INSTALACION DE ACCESORIOS 3,521.08 0.00 3,521.08
01.07.01.04.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN RED DE DISTRIBUCION PVC glb 1.00 3,521.08 3,521.08 1.00 3,521.08 3,521.08
01.07.01.05 BLOQUE DE ANCLAJE PARA ACCESORIOS 6.05 0.00 6.05
01.07.01.05.01 CONCRETO fc= 100 Kg/cm2, S/MEZCLADORA m3 0.02 302.52 6.05 0.02 302.52 6.05
01.07.02 CAMARA ROMPE PRESION TIPO VII 30,063.56 3,270.98 0.00 26,792.58
01.07.02.01 CAMARA ROMPE PRESION TIPO VII-1A · (3 UND) 7,861.48 0.00 7,861.48
01.07.02.01.01 TRABAJOS PRELIMINARES 8.37 0.00 8.37
01.07.02.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 4.95 0.65 3.22 4.95 0.65 3.22
01.07.02.01.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 4.95 1.04 5.15 4.95 1.04 5.15
01.07.02.01.02 MOVIMIENTO DE TIERRAS 420.51 0.00 420.51
01.07.02.01.02.01 EXCAVACION EN TERRENO NORMAL m3 10.14 26.09 264.55 10.14 26.09 264.55
01.07.02.01.02.02 RELLENO COMPACTADO CON MATERIAL SELECCIONADO m3 5.20 15.11 78.57 5.20 15.11 78.57
01.07.02.01.02.03 ELIMINACION DE MATERIAL EXCEDENTE DP=30 M m3 5.93 13.05 77.39 5.93 13.05 77.39
01.07.02.01.03 OBRAS DE CONCRETO SIMPLE 176.38 0.00 176.38
01.07.02.01.03.01 CONCRETO fc= 100 kg/cm2, e=4", S/MEZCLADORA m2 2.40 29.89 71.74 2.40 29.89 71.74
01.07.02.01.03.02 CONCRETO fc=140 kg/cm2, S/MEZCLADORA m3 0.04 433.66 17.35 0.04 433.66 17.35
01.07.02.01.03.03 ENCOFRADO Y DESENCOFRADO EN DADO DE REBOSE m2 0.72 55.22 39.76 0.72 55.22 39.76
01.07.02.01.03.04 CONCRETO fc=140 kg/cm2 + 30 %PM, S/MEZCLADORA m3 0.15 316.88 47.53 0.15 316.88 47.53
01.07.02.01.04 OBRAS DE CONCRETO ARMADO 3,904.35 0.00 3,904.35
01.07.02.01.04.01 CONCRETO fc= 175 Kg/cm' S/MEZCLADORA m3 3.17 433.66 1,374.70 3.17 433.66 1,374.70
01.07.02.01.04.02 ENCOFRADO Y DESENCOFRADO EN CAMARA ROMPE PRESION m2 33.21 55.22 1,833.86 33.21 55.22 1,833.86
01.07.02.01.04.03 ACERO CORRUGADO fy=4200 kg/cm2, GRADO 60 kg 160.69 4.33 695.79 160.69 4.33 695.79
01.07.02.01.05 REVOQUES, ENLUCIDOS Y MOLADURAS 669.56 0.00 669.56
CUADROS COMPARATIVOS DE LOS PRESUPUESTOS DEL PROYECTO
PROYECTO: "AMPLIACIÓN Y MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE E INSTALACIÓN DEL SANEAMIENTO BÁSICO DE LA LOCALIDAD DE EL CARDÓN, DISTRITO DE JOSÉ SABOGAL - SAN MARCOS - CAJAMARCA"
EJECUTA: N.E. EL CARDÓN - SNIP 300508 LUGAR: EL CARDÓN - JOSÉ SABOGAL - SAN MARCOS - CAJAMARCA FECHA: MAYO, 2022
01.07.02.01.07.01 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.60X 0.60m,e=1/8", INCLUYE LLAVE MAESTRA und 3.00 179.00 537.00 3.00 179.00 537.00
01.07.02.01.07.02 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.40x 0.50m, E=1/8", INCLUYE LLAVE MAESTRA und 3.00 159.00 477.00 3.00 159.00 477.00
01.07.02.02.07.01 SUMINISTRO E INSTALACION TAPA METALICA DE 0.60 X 0.60 m, e=1/8", INCLUYE LLAVE MAESTRA und 7.00 179.00 1,253.00 1.00 179.00 6.00 179.00 1,074.00
01.07.02.02.07.02 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.40 X 0.50 m, E=1/8", INCLUYE LLAVE MAESTRA und 7.00 159.00 1,113.00 1.00 159.00 6.00 159.00 954.00
01.07.03.01.07.01 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.60 x 0.60 m, e=1/8", INCLUYE LLAVE MAESTRA und 10.00 179.00 1,790.00 6.00 1,074.00 16.00 179.00 2,864.00
01.07.03.02.07.01 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.60 x 0.60 m e=1/8", INC LLAVE MAESTRA und 1.00 179.00 179.00 1.00 179.00 179.00
01.07.03.03.07.01 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.60x 0.60 m, e=1/8", INC. LLAVE MAESTRA und 19.00 179.00 3,401.00 8.00 1,432.00 0.00 11.00 179.00 1,969.00
01.07.03.03.08 PINTURA 162.94 0.00 16.29 0.00 179.23
01.07.03.03.08.01 PINTURA C/ESMALTE 02 MANOS (EXTERIORES) m2 12.80 12.73 162.94 0.00 1.28 16.29 14.08 12.73 179.23
01.07.03.03.09 VALVULAS Y ACCESORIOS 1,438.81 295.22 898.65 0.00 2,042.24
01.07.03.03.09.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE PURGA 2" und 1.00 373.42 373.42 0.00 0.00 1.00 373.42 373.42
01.07.03.03.09.02 SUMINISTRO E INST. DE ACCESORIOS EN VALVULA DE PURGA 1" und 1.00 179.73 179.73 0.00 5.00 898.65 6.00 179.73 1,078.38
01.07.03.03.09.03 SUMINISTRO E INST. DE ACCESORIOS EN VALVULA DE PURGA 3/4" und 6.00 147.61 885.66 2.00 295.22 0.00 4.00 147.61 590.44
01.07.04 PASES AEREOS 29,298.67 0.00 29,298.67
01.07.04.01 PASE AEREO L=30m (1UND) 29,298.67 0.00 29,298.67
01.07.02.01.01 OBRAS PRELIMINARES 101.53 0.00 101.53
01.07.02.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 60.08 0.65 39.05 60.08 0.65 39.05
01.07.02.01.01.02 TRAZO Y REPLANTEO m2 60.08 1.04 62.48 60.08 1.04 62.48
01.07.04.01.02 MOVIMIENTO DE TIERRAS 1,562.69 0.00 1,562.69
01.07.04.01.02.01 EXCAVACION EN TERRENO NORMAL m3 18.99 26.09 495.45 18.99 26.09 495.45
01.07.04.01.02.02 EXCAVACION EN TERRENO SEMIROCOSO m3 12.66 39.90 505.13 12.66 39.90 505.13
01.07.04.01.02.03 NIVELACION INTERIOR Y APISONADO m2 15.28 4.69 71.66 15.28 4.69 71.66
01.07.04.01.02.04 RELLENO COMPACTADO CON MATERIAL PROPIO SELECCIONADO m3 9.39 15.11 141.88 9.39 15.11 141.88
01.07.04.01.02.05 ELIMINACION DE MATERIAL EXCEDENTE DP=30 M m3 26.71 13.05 348.57 26.71 13.05 348.57
01.07.04.01.03 OBRAS DE CONCRETO SIMPLE 4,384.10 0.00 4,384.10
01.07.04.01.03.01 CONCRETO fc =100 kg/cm2, e=4", S/MEZCLADORA m2 15.28 29.89 456.72 15.28 29.89 456.72
01.07.04.01.03.02 CONCRETO fc=175 kg/cm2 + 30% PM, S/MEZCLADORA m3 10.32 380.56 3,927.38 10.32 380.56 3,927.38
01.07.04.01.04 OBRAS DE CONCRETO ARMADO 3,672.60 0.00 3,672.60
01.07.04.01.04.01 CONCRETO fc = 210 Kg/cm2 S/MEZCLADORA m3 2.97 489.71 1,454.44 2.97 489.71 1,454.44
01.07.04.01.04.02 ENCOFRADO Y DESENCOFRADO EN PASE AEREO m2 9.60 55.22 530.11 9.60 55.22 530.11
01.07.04.01.04.03 ACERO CORRUGADO fy=4200 kg/cm2, GRADO 60 kg 389.85 4.33 1,688.05 389.85 4.33 1,688.05
01.07.04.01.05 SUMINIST. E INST. DE CLABLE DE ACERO 3/4"SERIE 6x19 TIPO BOA ALMA DE ACERO 15,591.45 0.00 15,591.45
01.07.04.01.05.01 SUMINIST. E INST. DE CLABLE DE ACERO 3/4"SERIE 6x19 TIPO BOA ALMA DE ACERO m 56.00 95.69 5,358.64 56.00 95.69 5,358.64
01.07.04.01.05.02 SUMINIST. E INST. DE CLABLE DE ACERO 1/2"SERIE 6x19 TIPO BOA ALMA DE ACERO m 67.60 88.64 5,992.06 67.60 88.64 5,992.06
01.07.04.01.05.03 PENDOLAS DE ACERO 3/8" SERIE 6x19 TIPO BOA ALMA DE FIBRA gbl 1.00 4,240.75 4,240.75 1.00 4,240.75 4,240.75
01.07.04.01.06 SUMINISTRO E INSTALACION DE ACCESORIOS 3,986.30 0.00 3,986.30
01.07.04.01.06.01 SUMINISTRO E INSTALACION DE ACCESORIOS PARA CRUCE AEREO und 1.00 3,986.30 3,986.30 1.00 3,986.30 3,986.30
01.08 CONEXIONES DOMICILIARIAS 23,364.85 1,537.59 0.00 21,827.26
01.08.01 CONEXIONES DOMICILIARIAS (55 UND) 21,827.26 0.00 21,827.26
01.08.01.01 TRABAJOS PRELIMINARES 1,031.04 0.00 1,031.04
01.08.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 644.40 0.65 418.86 644.40 0.65 418.86
01.08.01.01.02 TRAZO, NIVELACION Y REPLANTEO DE ZANJAS m 644.40 0.95 612.18 644.40 0.95 612.18
01.08.01.02 MOVIMIENTO DE TIERRAS 8,444.19 0.00 8,444.19
01.08.01.02.01 EXCAVACION EN TERRENO NORMAL DE 0.40x0.50 m P/TUB.AGUA m 386.70 5.93 2,293.13 386.70 5.93 2,293.13
01.08.01.02.02 EXCAVACION EN TERRENO SEMIROCOSO DE 0.40x0.50m P/TUB. AGUA m 257.70 8.89 2,290.95 257.70 8.89 2,290.95
01.08.01.02.03 REFINE Y NIVELACION DE FONDO PARA ZANJA DE 0.40 x 0.50m P/TUB. AGUA m 644.40 0.43 277.09 644.40 0.43 277.09
01.08.01.02.04 CAMA DE APOYO PARA TUBERIA DE AGUA E=0.10M (ZANJA DE 0.40 X 0.50m) m 644.40 1.13 728.17 644.40 1.13 728.17
01.08.01.02.05 PRIMER RELLENO COMPACTADO DE ZANJA CON MAT. PROPIO ZARANDEADO e=0.30m m 644.40 2.23 1,437.01 644.40 2.23 1,437.01
01.08.01.02.06 SEGUNDO RELLENO CON MATERIAL PROPIO COMPACTADO e=0.10 M m 644.40 1.60 1,031.04 644.40 1.60 1,031.04
01.08.01.02.07 ELIMINACION DE MATERIAL EXCEDENTE DP=30 M m3 29.64 13.05 386.80 29.64 13.05 386.80
01.08.01.03 SUMINISTRO E INSTALACION DE TUBERIAS 3,112.84 0.00 3,112.84
01.08.01.03.01 SUMINISTRO E INSTALACION DE TUBERIA DE PVC NTP ITINTEC 399.002 DNØ1/2" C-10 m 627.50 4.85 3,043.38 627.50 4.85 3,043.38
01.08.01.03.02 SUMINISTRO E INSTALACION DE TUBERIA DE PVC NTP ITINTEC 399.002 DN Ø3/4" C-10 m 16.90 4.11 69.46 16.90 4.11 69.46
01.08.01.04 SUMINISTRO E INSTALACION DE ACCESORIOS - CONEXIÓN DOMICILIARIA 9,239.19 0.00 9,239.19
01.08.01.04.01 SUMINISTRO E INSTALACION DE ACCESORIOS DOMICILIARIAS (Para 1 1/2") und 7.00 63.07 441.49 7.00 63.07 441.49
01.08.01.04.02 SUMINISTRO E INSTALACION DE ACCESORIOS DOMICILIARIAS (Para 1") und 20.00 57.86 1,157.20 20.00 57.86 1,157.20
SUMINISTRO E INST. DE ACCESORIOS EN CONEXIONES DOMICILIARIAS (Para Ø1")- INSTITUCION
01.08.01.04.03 und 1.00 92.46 92.46 1.00 92.46 92.46
EDUCATIVA
01.08.01.04.04 SUMINISTRO E INSTALACION DE ACCESORIOS DOMICILIARIAS (Para 3/4") und 26.00 55.43 1,441.18 26.00 55.43 1,441.18
01.08.01.04.05 SUMINISTRO E INSTALACION DE CAJA DE CONCRETO 0.50x0.30 M INC ACCESORIOS und 54.00 113.09 6,106.86 54.00 113.09 6,106.86
01.08.02 PILETAS PUBLICAS (1 UND) 1,537.59 1,537.59 0.00 0.00
01.08.02.01 CONEXIÓN PILETA PUBLICA 391.98 391.98 0.00 0.00
01.08.02.01.01 TRABAJOS PRELIMINARES 16.90 16.90 0.00 0.00
01.08.02.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 10.00 0.65 6.50 10.00 6.50 0.00 0.00
01.08.02.01.01.02 TRAZO Y REPLANTEO m2 10.00 1.04 10.40 10.00 10.40 0.00 0.00
01.08.02.01.02 MOVIMIENTO DE TIERRAS 113.10 113.10 0.00 0.00
CUADROS COMPARATIVOS DE LOS PRESUPUESTOS DEL PROYECTO
PROYECTO: "AMPLIACIÓN Y MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE E INSTALACIÓN DEL SANEAMIENTO BÁSICO DE LA LOCALIDAD DE EL CARDÓN, DISTRITO DE JOSÉ SABOGAL - SAN MARCOS - CAJAMARCA"
EJECUTA: N.E. EL CARDÓN - SNIP 300508 LUGAR: EL CARDÓN - JOSÉ SABOGAL - SAN MARCOS - CAJAMARCA FECHA: MAYO, 2022
02.01.01.02.08.03 SUMINISTRO E INSTALACION DE DUCHA TEMPORIZADA A PRESION (INCLUYE ACCESORIOS) und 54.00 76.68 4,140.72 1.00 76.68 55.00 76.68 4,217.40
02.01.01.03 INSTALACIONES SANITARIAS Y ELECTRICAS 55,139.24 1,021.09 0.00 56,160.33
02.01.01.03.01 SISTEMA DE AGUA FRIA 18,418.48 341.08 0.00 18,759.56
02,01.01.03.01.01 SALIDA DE AGUA FRIA CON TUBERIA DE PVC - SAP Ø 1/2' pto 216.00 44.40 9,590.40 4.00 177.60 220.00 44.40 9,768.00
02.01.01.03.01.02 RED DE DISTRIBUCION TUBERIA DE 1/2" PVC SAP m 394.20 6.31 2,487.40 7.30 46.06 401.50 6.31 2,533.46
02.01.01.03.01.03 SUMINISTRO E INSTALACION DE VALVULA Y ACCESORIOS - AGUA und 108.00 58.71 6,340.68 2.00 117.42 110.00 58.71 6,458.10
02.01.01.03.02 SISTEMA DE DESAGÜE 22,931.32 424.65 0.00 23,355.97
02.01.01.03.02.01 SALIDA DE DESAGÜE PVC SAL DE 2' pto 270.00 27.68 7,473.60 5.00 138.40 275.00 27.68 7,612.00
02.01.01.03.02.02 SALIDA DE DESAGÜE PVC SAL DE 4' pto 54.00 36.70 1,981.80 1.00 36.70 55.00 36.70 2,018.50
02.01.01.03.02.03 RED COLECTORA PVC SAL 2" m 345.60 15.85 5,477.76 6.40 101.44 352.00 15.85 5,579.20
02.01.01.03.02,04 RED COLECTORA PVC SAL 4' m 64.80 13.67 885.82 1.20 16.40 66.00 13.67 902.22
02.01.01.03.02.05 SUMIDERO DE BRONCE DE 2" und 162.00 23.20 3,758.40 3.00 69.60 165.00 23.20 3,828.00
02,01,01,03,02,06 SUMINISTRO E INSTALACION DE ACCESORIOS DE PVC SAL DE 2' PARA VIVIENDAS und 54.00 62.11 3,353.94 1.00 62.11 55.00 62.11 3,416.05
02.01.01.03.03 SISTEMA DE VENTILACION 5,847.12 108.28 0.00 5,955.40
02.01.01.03.03.01 SALIDA DE VENTILACION DE PVC SAL Ø2" und 54.00 108.28 5,847.12 1.00 108.28 55.00 108.28 5,955.40
02.01.01.03.04 INSTALACIONES ELECTRICAS 7,942.32 147.08 0.00 8,089.40
02.01.01.03.04.01 SUMINISTRO E INSTALACION DE TUBERIA PVC 1/2' m 324.00 6.22 2,015.28 6.00 37.32 330.00 6.22 2,052.60
02.01.01.03.04.02 INTERRUPTOR SIMPLE pto 54.00 48.78 2,634.12 1.00 48.78 55.00 48.78 2,682.90
02.01.01.03.04.03 SALIDA DE TECHO PARA CENTRO DE LUZ pto 54.00 60.98 3,292.92 1.00 60.98 55.00 60.98 3,353.90
02.01.01.04 TRATAMIENTO DE AGUAS SERVIDAS 235,079.66 3,202.85 0.00 238,282.51
02.01.01.04.01 OBRAS PRELIMINARES 1,460.16 27.04 0.00 1,487.20
02.01.01.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 864.00 0.65 561.60 16.00 10.40 880.00 0.65 572.00
02.01.01.04.01.02 TRAZO, NIVELACION Y REPLANTEO m2 864.00 1.04 898.56 16.00 16.64 880.00 1.04 915.20
02.01.01.04.02 RED DE INTERCONEXION 14,937.27 276.81 0.00 15,214.08
02.01.01.04.02.01 MOVIMIENTO DE TIERRA 6,657.77 123.49 0.00 6,781.26
02.01.01.04.02.01.01 EXCAVACION EN TERRENO NORMAL m3 63.72 26.09 1,662.45 1.18 30.79 64.90 26.09 1,693.24
02.01.01.04.02.01.02 EXCAVACION EN TERRENO SEMIROCOSO m3 38.23 39.90 1,525.38 0.71 28.33 38.94 39.90 1,553.71
02.01.01.04:02.01.03 REPINE Y NIVEUCION DE FONDOS m2 254.88 4.69 1,195.39 4.72 22.14 259.60 4.69 1,217.53
02.01.01.04.02.01.04 CAMA DE APOYO CON MATERIAL PROPIO SELECCIONADO ZARANDEADO PARA TUBERIA E=0.10 m m 637.20 1.13 720.04 11.80 13.33 649.00 1.13 733.37
02.01.01.04.02.01.05 RELLENO COMPACTADO CON MATERIAL PROPIO SELECCIONADO m3 76.46 15.11 1,155.31 1.42 21.46 77.88 15.11 1,176.77
02.01.01.04.02.01.06 ELIMINACION DE MATERIAL EXCEDENTE DP=30 M m3 30.59 13.05 399.20 0.57 7.44 31.16 13.05 406.64
02.01.01.04.02.02 SUMINISTRO E INSTALACION DE TUBERIAS 8,279.50 153.32 0.00 8,432.82
02.01.01.04.02.02.01 SUMINISTRO E INST TUBERIA PVC SAL DE Ø 2" m 513.00 9.10 4,668.30 9.50 86.45 522.50 9.10 4,754.75
02.01.01.04.02.02.02 SUMINISTRO E INST TUBERIA PVC SAL DE Ø 4" m 124.20 13.98 1,736.32 2.30 32.15 126.50 13.98 1,768.47
02.01.01.04.02.02.03 SUMINISTRO E INSTALACION DE ACCESORIOS DE PVC SAL DE 2' PARA VIVIENDAS und 54.00 34.72 1,874.88 1.00 34.72 55.00 34.72 1,909.60
02.01.01.04.03 CAJA DE INSPECCION 2,564.87 47.65 0.00 2,612.52
02.01.01.04.03.01 MOVIMIENTO DE TIERRAS 2,564.87 47.65 0.00 2,612.52
02.01.01.04.03.01.01 EXCAVACION EN TERRENO NORMAL m3 29.11 26.09 759.48 0.54 14.09 29.65 26.09 773.57
02.01.01.04.03.01.02 EXCAVACION EN TERRENO SEMIROCOSO m3 18.83 39.90 751.32 0.35 13.97 19.18 39.90 765.29
02.01.01.04.03.01.03 REPINE Y NIVELACION DE FONDOS m2 64.67 4.69 303.30 1.20 5.63 65.87 4.69 308.93
02.01.01.04.03.01.04 ELIMINACION DE MATERIAL EXCEDENTE DP=30 M m3 57.53 13.05 750.77 1.07 13.96 58.60 13.05 764.73
02.01.01.04.04 CAJA DE REGISTRO 52,781.19 0.00 0.00 52,781.19
02.01.01.04.04.01 CAJA DE REGISTRO DE DESAGÜE 0.25 X0.50 m, INCLUYE MARCO Y TAPA DE CONCRETO und 73.00 138.06 10,078.38 0.00 73.00 138.06 10,078.38
02.01.01.04.04.02 CAJA DE TRAMPA DE NATAS Y SOLIDO 0.30 X 0.60 m INCLUYE MARCO Y TAPA DE CONCRETO und 73.00 201.35 14,698.55 0.00 73.00 201.35 14,698.55
02.01.01.04.04.03 CAJA DE REGISTRO DE LODOS DE 0.60 X 0.60m DE CONCRETO und 73.00 247.93 18,098.89 0.00 73.00 247.93 18,098.89
02.01.01.04.04.04 CAJA DE DISTRIBUCION 0.30x0.60 cm,INCLUYE TAPA DE CONCRETO und 73.00 135.69 9,905.37 0.00 73.00 135.69 9,905.37
02.01.01.04.05 BIODIGESTOR 73,997.75 1,196.60 0.00 75,194.35
02.01.01.04.05.01 MOVIMIENTO DE TIERRAS 5,385.72 99.68 0.00 5,485.40
02.01.01.04.05.01.01 EXCAVACION EN TERRENO NORMAL m3 74.95 26.09 1,955.45 1.39 36.27 76.34 26.09 1,991.72
02.01.01.04.05.01.02 EXCAVACION EN TERRENO SEMIROCOSO m3 52.46 39.90 2,093.15 0.97 38.70 53.43 39.90 2,131.85
02.01.01.04.05.01.03 REPINE Y NIVELACION DE FONDOS m2 37.47 4.69 175.73 0.69 3.24 38.16 4.69 178.97
02.01.01.04.05.01.04 RELLENO COMPACTADO CON MATERIAL PROPIO SELECCIONADO m3 22.40 15.11 338.46 0.41 6.20 22.81 15.11 344.66
02.01.01.04.05.01.05 ELIMINACION DE MATERIAL EXCEDENTE DP=30 M m3 63.06 13.05 822.93 1.17 15.27 64.23 13.05 838.20
02.01.01.04.05.02 OBRAS DE CONCRETO SIMPLE 1,119.98 20.62 0.00 1,140.60
02.01.01.04.05.02.01 CONCRETO fc=100 kg/cm2, e=4', S/MEZCLADORA m2 37.47 29.89 1,119.98 0.69 20.62 38.16 29.89 1,140.60
02.01.01.04.05.03 SUMINISTRO E INSTALACION DE BIODIGESTOR 58,120.20 1,076.30 0.00 59,196.50
02.01.01.04.05.03.01 SUMINISTRO E INST DE BIODIGESTOR Y ACCESORIOS (700 L) und 54.00 1,076.30 58,120.20 1.00 1,076.30 55.00 1,076.30 59,196.50
02.01.01.04.05.04 VARIOS 9,371.85 0.00 0.00 9,371.85
CUADROS COMPARATIVOS DE LOS PRESUPUESTOS DEL PROYECTO
PROYECTO: "AMPLIACIÓN Y MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE E INSTALACIÓN DEL SANEAMIENTO BÁSICO DE LA LOCALIDAD DE EL CARDÓN, DISTRITO DE JOSÉ SABOGAL - SAN MARCOS - CAJAMARCA"
EJECUTA: N.E. EL CARDÓN - SNIP 300508 LUGAR: EL CARDÓN - JOSÉ SABOGAL - SAN MARCOS - CAJAMARCA FECHA: MAYO, 2022
02.01.01.04.06.03.01 SUMINISTRO E INSTALACIÓN DE TUBERIA PVC DE 2" CON AGUJERO CADA 0.15M Y SERAN. 5 mm m 399.60 7.88 3,148.85 7.40 58.31 407.00 7.88 3,207.16
02.01.01.04.06.03.02 SUMINISTRO E INSTALACION DE ACCESORIOS m3 54.00 5.27 284.58 1.00 5.27 55.00 5.27 289.85
02.01,01,04,06,04 VARIOS 66,191.94 1,225.78 0.00 67,417.72
02.01,01,04,06,04.01 SUMINISTRO E INSTALACIÓN DE GEOMEMBRANA e=1" m2 359.64 175.53 63,127.61 6.66 1,169.03 366.30 175.53 64,296.64
02.01,01,04,06,04.02 INSTALACIÓN DE VEGETACION DE LA ZONA m2 979.02 3.13 3,064.33 18.13 56.75 997.15 3.13 3,121.08
02.01.02 UBS ARRASTRE HIDRAULICO - CENTROS EDUCATIVOS (02 UBS) 25,638.79 0.00 25,638.79
02.01.02.01 ESTRUCTURAS 5,558.54 0.00 5,558.54
02.01.02.01.01 TRABAJOS PRELIMINARES 31.95 0.00 31.95
02.01.02.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 18.90 0.65 12.29 18.90 0.65 12.29
02.01.02.01.01.02 TRAZO NIVELACION Y REPLANTEO m2 18.90 1.04 19.66 18.90 1.04 19.66
02.01.02.01.02 MOVIMIENTO DE TIERRAS 404.79 0.00 404.79
02.01.02.01.02.01 EXCAVACION DE TERRENO NORMAL m3 8.79 26.09 229.33 8.79 26.09 229.33
02.01.02.01.02.02 REFINE Y NIVELACION DE FONDOS m2 8.15 4.69 38.22 8.15 4.69 38.22
02.01.02.01.02.03 RELLENO COMPACTADO CON MATERIAL PROPIO SELECCIONADO m3 0.74 15.11 11.18 0.74 15.11 11.18
02.01.02.01.02.04 ELIMININACION DE MATERIAL EXEDENTE DP=30 M m3 9.66 13.05 126.06 9.66 13.05 126.06
02.01.02.01.03 OBRAS DE CONCRETO SIMPLE 2,721.96 0.00 2,721.96
02.01.02.01.03.01 CIMIENTOS 1,146.44 0.00 1,146.44
02.01.02.01.03.01.01 CONCRETO CICLOPEO MEZCLA C:H 1:10 + 30% P.G m3 4.08 280.99 1,146.44 4.08 280.99 1,146.44
02.01.02.01.03.02 SOBRECIMIENTOS 776.65 0.00 776.65
02.01.02.01.03.02.01 CONCRETO SIMPLE MEZCLA 1:8 +25% P.M m3 0.83 300.20 249.17 0.83 300.20 249.17
02.01.02.01.03.02.02 ENCONFRADO Y DESENCOFRADO EN SOBRECIMIENTO m2 13.22 39.90 527.48 13.22 39.90 527.48
02.01.02.01.03.03 VEREDAS 475.75 0.00 475.75
02.01.02.01.03.03.01 CONCRETO fc=100 kg/cm2, e=4', S/MEZCLADORA m2 8.64 41.14 355.45 8.64 41.14 355.45
02.01.02.01.03.03.02 JUNTA DE DILATACION, E=1/2" m 7.20 8.73 62.86 7.20 8.73 62.86
02.01.02.01.03.03.03 BRUÑAS PARA VEREDA e=1cm m 10.90 5.27 57.44 10.90 5.27 57.44
02.01.02.01.03.04 PISOS 323.12 0.00 323.12
02.01.02.01.03.04.01 CONCRETO Fc=140 kg/cm2, ACABADO FROTACHADO, e=10 cm m2 7.44 43.43 323.12 7.44 43.43 323.12
02.01.02.01.04 OBRAS DE CONCRETO ARMADO 2,399.84 0.00 2,399.84
02.01.02.01.04.01 COLUMNETAS 1,396.23 0.00 1,396.23
02.01.02.01.04.01.01 CONCRETO fc=175 kg/cm2, S/MEZCLADORA m3 0.46 407.10 187.27 0.46 407.10 187.27
02.01.02.01.04.01.02 ENCONFRADO Y DESENCOFRADO EN COLUMNETA m2 7.48 60.64 453.59 7.48 60.64 453.59
02.01.02.01.04.01.03 ACERO CORRUGADO F'y=4200 kg/cm2 , GRADO 60 kg 174.45 4.33 755.37 174.45 4.33 755.37
02.01.02.01.04.02 VIGUETAS 1,003.61 0.00 1,003.61
02.01.02.01.04.02.01 CONCRETO fc=175 kg/cm2, S/MEZCLADORA m3 0.39 407.10 158.77 0.39 407.10 158.77
02.01.02.01.04.02.02 ENCONFRADO Y DESENCOFRADO EN VIGUETA m2 6.34 73.36 465.10 6.34 73.36 465.10
02.01.02.01.04.02.03 ACERO CORRUGADO F'y=4200 kg/cm2 , GRADO 60 kg 87.70 4.33 379.74 87.70 4.33 379.74
02.01.02.02 ARQUITECTURA 8,678.52 0.00 8,678.52
02.01.02.02.01 MUROS Y TABIQUES DE ALBAÑILERIA 2,483.89 0.00 2,483.89
MURO DE SOGA CARAVISTA 18 HUECOS MAQUINADO DE 23 x 12.5 x 9 cm, CEMENTO-ARENA 1:5,
02.01.02.02.01.01 m2 36.24 68.54 2,483.89 36.24 68.54 2,483.89
JUNTA 1.5 cm
02.01.02.02.02 REVOQUES Y ENLUCIDOS 910.26 0.00 910.26
02.01.02.02.02.01 TARRAJEO DE MUROS INTERIORES, ACABADO PULIDO IMPERMEABILIZADO C:A=1:4, e=1.5 cm m2 3.60 24.36 87.70 3.60 24.36 87.70
02.01.02.02.02.02 TARRAJEO DE COLUMNETAS, FROTACHADO, C:A=1:4, e=1.5 cm m2 7.48 25.59 191.41 7.48 25.59 191.41
02.01.02.02.02.03 TARRAJEO DE VIGUETAS, CA= 1:4, e=1.5cm m2 6.34 32.51 206.11 6.34 32.51 206.11
02.01.02.02.02.04 VESTIDURAS DE DERRAMES MEZCLA C:A 1:4, e=1.5cm., ANCHO = 0.15m m 27.60 15.40 425.04 27.60 15.40 425.04
02.01.02.02.03 CONTRAZOCALOS 313.92 0.00 313.92
02.01.02.02.03.01 CONTRAZOCALOS DE CEMENTO PULIDO CON MORTERO, C:A 1:4, e=1.5cm m2 12.13 25.88 313.92 12.13 25.88 313.92
CUADROS COMPARATIVOS DE LOS PRESUPUESTOS DEL PROYECTO
PROYECTO: "AMPLIACIÓN Y MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE E INSTALACIÓN DEL SANEAMIENTO BÁSICO DE LA LOCALIDAD DE EL CARDÓN, DISTRITO DE JOSÉ SABOGAL - SAN MARCOS - CAJAMARCA"
EJECUTA: N.E. EL CARDÓN - SNIP 300508 LUGAR: EL CARDÓN - JOSÉ SABOGAL - SAN MARCOS - CAJAMARCA FECHA: MAYO, 2022
02.01.02.02.07.03 SUMINISTRO E INSTALACION DE URINARIO DE LOSA VITRIFICADA - NORMA, (INCLUYE ACCESORIOS) und 2.00 221.95 443.90 2.00 221.95 443.90
02.01.02.04.04.02 CAJA DE TRAMPA DE NATAS Y SOLIDO 0.30 X 0.60 m INCLUYE MARCO Y TAPA DE CONCRETO und 2.00 201.35 402.70 2.00 201.35 402.70
02.01.02.04.04.03 CAJA DE REGISTRO DE LODOS DE 0.60 X 0.60m INCLUYE MARCO Y TAPA DE CONCRETO und 2.00 247.93 495.86 2.00 247.93 495.86
02.01.02.04.04.04 CAJA DE DISTRIBUCION 0.30x0.60 cm,INCLUYE TAPA DE CONCRETO und 2.00 135.69 271.38 2.00 135.69 271.38
02.01.02.04.05 BIODIGESTOR 4,065.92 0.00 4,065.92
02.01.02.04.05.01 MOVIMIENTO DE TIERRAS 279.70 0.00 279.70
02.01.02.04.05.01.01 EXCAVACION EN TERRENO NORMAL m3 6.52 26.09 170.11 6.52 26.09 170.11
02.01.02.04.05.01.02 REFINE Y NIVELACION DE FONDOS m2 1.92 4.69 9.00 1.92 4.69 9.00
02.01.02.04.05.01.03 RELLENO COMPACTADO CON MATERIAL PROPIO SELECCIONADO m3 2.84 15.11 42.91 2.84 15.11 42.91
02.01.02.04.05.01.04 ELIMINACION DE MATERIAL EXCEDENTE DP=30 M m3 4.42 13.05 57.68 4.42 13.05 57.68
02.01.02.04.05.02 OBRAS DE CONCRETO SIMPLE 57.39 0.00 57.39
02.01.02.04.05.02.01 CONCRETO fc= 100 kg/cm2, e=4",S/MEZCLADORA m2 1.92 29.89 57.39 1.92 29.89 57.39
02.01.02.04.05.03 SUMINISTRO E INSTALACION DE BIODIGESTOR 3,294.60 0.00 3,294.60
02.01.02.04.05.03.01 SUMINISTRO E INST. DE BIODIGESTOR Y ACCESORIOS (1600 L) und 2.00 1,647.30 3,294.60 2.00 1,647.30 3,294.60
02.01.02.04.05.04 VARIOS 434.23 0.00 434.23
02.01.02.04.05.04.01 REPELLADO DE C°, E=0.03m, C:A=1:3 CON MALLA EXAGONAL 3/4' m2 21.38 20.31 434.23 21.38 20.31 434.23
02.01.02.04.06 ZANJA DE PERCOLACION 1,884.75 0.00 1,884.75
02.01.02.04.06.01 MOVIMIENTO DE TIERRAS 375.60 0.00 375.60
02.01.02.04.06.01.01 EXCAVACION EN TERRENO NORMAL m3 7.72 26.09 201.41 7.72 26.09 201.41
02.01.02.04.06.01.02 REFINE Y NIVELACION DE FONDOS m2 11.88 4.69 55.72 11.88 4.69 55.72
02.01.02.04.06.01.03 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 4.42 15.11 66.79 4.42 15.11 66.79
02.01.02.04.06.01.04 ELIMINACION DE MATERIAL EXCEDENTE DP=30 M m3 3.96 13.05 51.68 3.96 13.05 51.68
02.01.02.04.06.02 MATERIAL FILTRANTE 277.54 0.00 277.54
02.01.02.04.06.02.01 SUMNISITRO Y COLOCACION DE GRAVA DE 1" A 2" m3 1.78 77.96 138.77 1.78 77.96 138.77
02.01.02.04.06.02.02 SUMNISITRO Y COLOCACION DE GRAVA DE 1 1/2" A 2" m3 1.78 77.96 138.77 1.78 77.96 138.77
02.01.02.04.06.03 SUMINISTRO E INSTALACION DE ACCESORIOS 114.56 0.00 114.56
02.01.02.04.06.03.01 SUMINIST. E INST. DE TUBERIA PVC 2" CON AGUJEROS CADA 0.15 M Y SERAN DE 5 mm m 13.20 7.88 104.02 13.20 7.88 104.02
02.01.02.04.06.03.02 SUMINISTRO E INSTALACION DE ACCESORIOS und 2.00 5.27 10.54 2.00 5.27 10.54
02.01.02.04.06.04 VARIOS 1,117.05 0.00 1,117.05
02.01.02.04.06.04.01 SUMINISTRO Y COLOCACION DE GEOMEMBRANA e=1" m2 5.94 175.53 1,042.65 5.94 175.53 1,042.65
02.01.02.04.06.04.02 INSTALACION DE VEGETACION DE LA ZONA M2 23.77 3.13 74.40 23.77 3.13 74.40
02.02 SISTEMA DE SANEAMIENTO-UNIDAD BASICA DE SANEAMIENTO (UBS- COMPOSTERA SECA)- (1 UBS) 9,137.02 9,137.02 0.00 0.00
02.02.02.01.03 MURO DE LADRILLO KK DE ARCILLA DE SOGA, MEZCLA C:A 1:4 (LAVADERO :DOMICILIARIO) m2 1.08 56.93 61.48 1.08 61.48 0.00 0.00
02.02.02.02.01 TARRAJEO DE MUROS INTERIORES C/IMPERMEABILIZANTE Y PULIDO P/CAMARA (UBS Compostera) m2 5.40 24.04 129.82 5.40 129.82 0.00 0.00
02.02.02.02.02 TARRAJEO PULID01:4 (Lavaderos Domiciliarios) m2 4.21 27.24 114.68 4.21 114.68 0.00 0.00
02.02.02.02.03 TARRAJEO DE VIGAS Y COLUMNAS INCLUYE ARISTAS, C:A= 1:4, e=1.5cm m2 1.29 20.31 26.20 1.29 26.20 0.00 0.00
02.02.02.02.04 TARRAJEO INT. Y EXT. MEZC. 1:4 E=1.5 CM (Lavaderos Domiciliarios) m2 2.31 19.25 44.47 2.31 44.47 0.00 0.00
02.02.02.02.05 VESTIDURAS DE DERRAMES MEZCLA C:A 1:4, e=1.5cm., ANCHO = 0.15m m2 4.60 15.40 70.84 4.60 70.84 0.00 0.00
02.02.02.02.06 VESTIDURAS DE ESCALERA C:A=1.4,e=1.5,ANCHO=0.60m m 2.49 31.90 79.43 2.49 79.43 0.00 0.00
02.02.02.03 PINTURA 53.59 53.59 0.00 0.00
02.02.02.03.01 PINTURA ESMALTE(COLUMNAS Y VIGAS) m2 4.21 12.73 53.59 4.21 53.59 0.00 0.00
02.02.02.04 COBERTURAS 576.04 576.04 0.00 0.00
02.02.02.04.01 COBERTURA DE CALAMINA GALVANIZADA 1.80x0.83x0.22m m2 9.24 23.72 219.17 9.24 219.17 0.00 0.00
02.02.02.04.02 VIGA DE MADERA TORNILLO 2"X3" p2 9.84 14.16 139.33 9.84 139.33 0.00 0.00
02.02.02.04.03 CORREA DE MADERA TORNILLO 2"X2' p2 10.10 12.55 126.76 10.10 126.76 0.00 0.00
02.02.02.04.04 ACCESORIOS DE FIJACION und 6.00 15.13 90.78 6.00 90.78 0.00 0.00
02.02.02.05 CARPINTERIA DE MADERA 230.80 230.80 0.00 0.00
02.02.02.05.01 PUERTA DE CALAMINA UBS INCLUYE CON MARCO DE MADERA DE 2"x1 1/2" und 1.00 230.80 230.80 1.00 230.80 0.00 0.00
02.02.02.06 APARATOS Y ACCESORIOS SANITARIOS 504.90 504.90 0.00 0.00
02.02.02.06.01 SUMINISTRO E INSTALACION DE INODORO BASICO ECOLOGICO SECO(TIPO SEPARATIVA) gbl 2.00 217.11 434.22 2.00 434.22 0.00 0.00
02.02.02.06.02 SUMINISTRO E INS.DE ACCESORIOS-LAVADERO DOMICILIARIO und 1.00 70.68 70.68 1.00 70.68 0.00 0.00
02.02.03 INSTALACIONES SANITARIAS Y ELECTRICAS 478.48 478.48 0.00 0.00
02.02.03.01 SISTEMA DE DESAGUE 162.29 162.29 0.00 0.00
02.02.03.01.01 SALIDA DE DESAGUE PVC SAL Ø2" pto 3.00 27.68 83.04 3.00 83.04 0.00 0.00
02.02.03.01.02 RED COLECTORA PVC SAL 2" m 5.00 15.85 79.25 5.00 79.25 0.00 0.00
02.02.03.02 SISTEMA DE VENTILACION 169.11 169.11 0.00 0.00
02.02.03.02.01 SALIDA DE VENTILACION DE PVC SAL Ø4" und 1.00 169.11 169.11 1.00 169.11 0.00 0.00
02.02.03.03 INSTALACIONES ELECTRICAS 147.08 147.08 0.00 0.00
02.02.03.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC 1/2' m 6.00 6.22 37.32 6.00 37.32 0.00 0.00
02.02.03.03.02 INTERRUPTOR SIMPLE pto 1.00 48.78 48.78 1.00 48.78 0.00 0.00
02.02.03.03.03 SALIDA DE TECHO PARA CENTRO DE LUZ pto 1.00 60.98 60.98 1.00 60.98 0.00 0.00
02.02.04 TRATAMIENTO DE AGUAS SERVIDAS 2,625.59 2,625.59 0.00 0.00
02.02.04.01 OBRAS PRELIMINARES 15.21 15.21 0.00 0.00
02.02.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 9.00 0.65 5.85 9.00 5.85 0.00 0.00
02.02.04.01.02 TRAZO,NIVELACION Y REPLANTEO m2 9.00 1.04 9.36 9.00 9.36 0.00 0.00
02.02.04.02 RED DE INTERCONEXION 57.75 57.75 0.00 0.00
02.02.04.02.01 EXCAVACION EN TERRENO NORMAL m3 0.96 26.09 25.05 0.96 25.05 0.00 0.00
02.02.04.02.02 REFINE Y NIVELACION DE FONDOS m2 2.40 4.69 11.26 2.40 11.26 0.00 0.00
CAMA DE APOYO CON MATERIAL PROPIO SELECCIONADO ZARANDEADO PARA TUBERIA DE AGUA
02.02.04.02.03 m 6.00 1.13 6.78 6.00 6.78 0.00 0.00
e=0.10 m
02.02.04.02.04 RELLENO COMPACTADO CON MATERIAL PROPIO SELECCIONADO m3 0.72 15.11 10.88 0.72 10.88 0.00 0.00
02.02.04.02.05 ELIMINACION DE MATERIAL EXCEDENTE DP=30 M m3 0.29 13.05 3.78 0.29 3.78 0.00 0.00
02.02.04.03 TRAMPA DE GRASA 199.87 199.87 0.00 0.00
02.02.04.03.01 TRAMPA DE GRASA 0.30X0.60 und 1.00 199.87 199.87 1.00 199.87 0.00 0.00
02.02.04.04 ZANJA DE PERCOLACION 2,352.76 2,352.76 0.00 0.00
02.02.04.04.01 MOVIMIENTO DE TIERRAS 148.66 148.66 0.00 0.00
02.02.04.04.01.01 EXCAVACION EN TERRENO NORMAL m3 3.00 26.09 78.27 3.00 78.27 0.00 0.00
CUADROS COMPARATIVOS DE LOS PRESUPUESTOS DEL PROYECTO
PROYECTO: "AMPLIACIÓN Y MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE E INSTALACIÓN DEL SANEAMIENTO BÁSICO DE LA LOCALIDAD DE EL CARDÓN, DISTRITO DE JOSÉ SABOGAL - SAN MARCOS - CAJAMARCA"
EJECUTA: N.E. EL CARDÓN - SNIP 300508 LUGAR: EL CARDÓN - JOSÉ SABOGAL - SAN MARCOS - CAJAMARCA FECHA: MAYO, 2022
02.02.04.04.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC 2" CON AGUJEROS CADA 0.15 m Y SERAN DE 5mm m 11.00 7.88 86.68 11.00 86.68 0.00 0.00
02.02.04.04.03.02 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 5.27 5.27 1.00 5.27 0.00 0.00
02.02.04.04.04 VARIOS 2,004.57 2,004.57 0.00 0.00
02.02.04.04.04.01 SUMINISTRO E INSTALACION DE GEOMEMBRANA e=1" m2 11.22 175.53 1,969.45 11.22 1,969.45 0.00 0.00
02.02.04.04.04.02 INSTALACION DE VEGETACION DE LA ZONA m2 11.22 3.13 35.12 11.22 35.12 0.00 0.00
02.03 FLETE 99,004.33 0.00 99,004.33
02.03.01 FLETE TERRESTRE UBS 76,280.64 0.00 76,280.64
02.03.01.01 FLETE TERRESTRE UBS gbl 1.00 76,280.64 76,280.64 1.00 76,280.64 76,280.64
02.03.02 FLETE RURAL UBS 22,723.69 0.00 22,723.69
02.03.02.01 FLETE RURAL UBS gbl 1.00 22,723.69 22,723.69 1.00 22,723.69 22,723.69
0.00 19,433.81
COSTO DIRECTO 1,160,612.87 28,459.71 1,151,586.97
0.00% 1.67%
19,433.81
INCIDENCIA EN REFERENCIA AL COSTO DIRECTO (%) 100.00% 2.45% 99.22%
1.67%
PRESUPUESTO DE OBRA (FINANCIADO AL N.E.)
PROYECTO: "AMPLIACIÓN Y MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE E INSTALACIÓN DEL SANEAMIENTO BÁSICO DE LA LOCALIDAD DE EL CARDÓN,
DISTRITO DE JOSÉ SABOGAL - SAN MARCOS - CAJAMARCA"
EJECUTA: N.E. EL CARDÓN - SNIP 300508 FECHA: MAYO , 2022
01.04.02.07.01 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.60 X 0.60 m e=1/8', INCLUYE LLAVE MAESTRA und 1.00 179.00 179.00
01.04.02.07.02 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.40 x 0.50m, E=1/8" INCLUYE LLAVE MAESTRA und 1.00 159.00 159.00
01.04.03.07.01 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.60 x0.60m e=1/8",INCLUYE LLAVE MAESTRA und 1.00 179.00 179.00
01.04.03.07.02 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.40 x0.50m, E=1/8" INCLUYE LLAVE MAESTRA und 1.00 159.00 159.00
01.05.02.01.06.01 SUMINISTRO E INSTALACIÓN DE ACCESORIOS DE ENTRADA DE 1 1/2" - (CAPTACIÓN"LA VALERIANA 1") und 1.00 87.29 87.29
PRESUPUESTO DE OBRA (FINANCIADO AL N.E.)
PROYECTO: "AMPLIACIÓN Y MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE E INSTALACIÓN DEL SANEAMIENTO BÁSICO DE LA LOCALIDAD DE EL CARDÓN,
DISTRITO DE JOSÉ SABOGAL - SAN MARCOS - CAJAMARCA"
EJECUTA: N.E. EL CARDÓN - SNIP 300508 FECHA: MAYO , 2022
01.05.02.01.06.03 SUMINISTRO E INSTALACIÓN DE ACCESORIOS DE SALIDA Ø= 1 1/2" - CÁMARA DE REUNIÓN und 1.00 88.53 88.53
01.05.02.01.06.04 SUMINISTRO E INSTALACIÓN DE ACCESORIOS DE LIMPIA Y REBOSE DE 2 1/2" und 1.00 185.02 185.02
01.05.02.01.06.05 SUMINISTRO E INSTALACIÓN DE ACCESORIOS DE VENTILACIÓN und 1.00 59.08 59.08
01.05.02.01.07 TAPA SANITARIA 179.00
01.05.02.01.07.01 SUMINISTRO E INSTALACIÓN DE TAPA METÁLICA, DE 0.60X0.60M E=1/8" INC. LLAVE MAESTRA und 1.00 179.00 179.00
01.05.02.02.06.01 SUMINISTRO E INSTALACIÓN DE ACCESORIOS DE ENTRADA DE 1 1/2" - (CAPTACIÓN"LA VALERIANA") und 1.00 87.29 87.29
01.05.02.02.06.02 SUMINISTRO E INSTALACIÓN DE ACCESORIOS DE ENTRADA DE 1 1/2" - (LA VALERIANA 2) und 1.00 87.29 87.29
01.05.02.02.06.03 SUMINISTRO E INSTALACIÓN DE ACCESORIOS DE SALIDA Ø= 1 1/2" - CÁMARA DE REUNIÓN und 1.00 88.53 88.53
01.05.02.02.06.04 SUMINISTRO E INSTALACIÓN DE ACCESORIOS DE LIMPIA Y REBOSE DE 2 1/2" und 1.00 185.02 185.02
01.05.02.02.06.05 SUMINISTRO E INSTALACIÓN DE ACCESORIOS DE VENTILACIÓN und 1.00 59.08 59.08
01.05.02.02.07 TAPA SANITARIA 179.00
01.05.02.02.07.01 SUMINISTRO E INSTALACIÓN DE TAPA METÁLICA, DE 0.60X0.60M E=1/8" INC. LLAVE MAESTRA und 1.00 179.00 179.00
01.06.01.02.04.03 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.60 X 0.60 m e=1/8', INC. LLAVE MAESTRA und 1.00 179.00 179.00
01.06.01.04.05.01 SUMINISTRO E INST. DE ACCESORIOS DE LIMPIEZA Y REBOSE EN SISTEMA DE CLORACION und 1.00 287.56 287.56
01.06.01.06.02.04.01 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.60 X 0,60 m e=1/8*, INCLUYE LLAVE MAESTRA und 1.00 179.00 179.00
01.07.01.02.04 EXCAVACION EN TERRENO SEMIROCOSO DE 0.50x1.10 m P/TUB.AGUA (Cruce en via carrozable) m 20.00 22.23 444.60
01.07.01.02.05 REPINE Y NIVELACION DE FONDO PARA ZANJA DE 0.40x0.70 m P/TUB. AGUA m 8,526.40 0.43 3,666.35
01.07.01.02.06 CAMA DE APOYO C/MAT. PROP. ZARANDEADO PARA TUBERIA DE AGUA E=0.10 m m 8,526.40 1.13 9,634.83
01.07.01.02.07 PRIMER RELLENO COMPACTADO DE ZANJA CON MAT PROPIO ZARANDEADO e=0.30m m 8,526.40 2.23 19,013.87
01.07.01.02.08 SEGUNDO RELLENO CON MATERIAL PROPIO COMPACTADO e=0.30 m m 8,426.40 1.60 13,482.24
01.07.01.02.09 SEGUNDO RELLENO CON MATERIAL PROPIO COMPACTADO e=0.70 m m 100.00 1.60 160.00
01.07.01.02.10 ELIMINACION DE MATERIAL EXCEDENTE DP=30 M m3 393.90 13.05 5,140.40
01.07.01.03 SUMINISTRO E INSTALACION DE TUBERIAS 60,540.76
01.07.01.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC NTP IS0 1452 UF DN 75 mm C-10 m 49.20 11.24 553.01
01.07.01.03.02 SUMINISTRO E INSTALACION DE TUBERIA PVC NTP IS0 1452 UF DN 63 mm C-10 m 394.50 8.22 3,242.79
01.07.01.03.03 SUMINISTRO E INSTALACION DE TUBERIA PVC NTP ITINTEC 399,002 DN Ø1 1/2" C-10 m 2,060.40 8.77 18,069.71
01.07.01.03.04 SUMINISTRO E INSTALACION DE TUBERIA PVC NTP ITINTEC 399.002 DN Ø 1" C-10 m 4,166.00 6.04 25,162.64
01.07.01.03.05 SUMINISTRO E INSTALACION DE TUBERIA PVC NTP ITINTEC 399.002 DN Ø 3/4" C-10 m 1,856.30 4.11 7,629.39
01.07.01.03.06 PRUEBA HIDRAULICA P/TUB m 8,526.40 0.69 5,883.22
01.07.01.04 SUMINISTRO E INSTALACION DE ACCESORIOS 3,521.08
01.07.01.04.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN RED DE DISTRIBUCION PVC glb 1.00 3,521.08 3,521.08
01.07.01.05 BLOQUE DE ANCLAJE PARA ACCESORIOS 6.05
01.07.01.05.01 CONCRETO fc= 100 Kg/cm2, S/MEZCLADORA m3 0.02 302.52 6.05
01.07.02 CAMARA ROMPE PRESION TIPO VII 30,063.56
01.07.02.01 CAMARA ROMPE PRESION TIPO VII-1A · (3 UND) 7,861.48
01.07.02.01.01 TRABAJOS PRELIMINARES 8.37
01.07.02.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 4.95 0.65 3.22
01.07.02.01.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 4.95 1.04 5.15
01.07.02.01.02 MOVIMIENTO DE TIERRAS 420.51
01.07.02.01.02.01 EXCAVACION EN TERRENO NORMAL m3 10.14 26.09 264.55
01.07.02.01.02.02 RELLENO COMPACTADO CON MATERIAL SELECCIONADO m3 5.20 15.11 78.57
01.07.02.01.02.03 ELIMINACION DE MATERIAL EXCEDENTE DP=30 M m3 5.93 13.05 77.39
01.07.02.01.03 OBRAS DE CONCRETO SIMPLE 176.38
01.07.02.01.03.01 CONCRETO fc= 100 kg/cm2, e=4", S/MEZCLADORA m2 2.40 29.89 71.74
01.07.02.01.03.02 CONCRETO fc=140 kg/cm2, S/MEZCLADORA m3 0.04 433.66 17.35
01.07.02.01.03.03 ENCOFRADO Y DESENCOFRADO EN DADO DE REBOSE m2 0.72 55.22 39.76
01.07.02.01.03.04 CONCRETO fc=140 kg/cm2 + 30 %PM, S/MEZCLADORA m3 0.15 316.88 47.53
01.07.02.01.04 OBRAS DE CONCRETO ARMADO 3,904.35
01.07.02.01.04.01 CONCRETO fc= 175 Kg/cm' S/MEZCLADORA m3 3.17 433.66 1,374.70
01.07.02.01.04.02 ENCOFRADO Y DESENCOFRADO EN CAMARA ROMPE PRESION m2 33.21 55.22 1,833.86
01.07.02.01.04.03 ACERO CORRUGADO fy=4200 kg/cm2, GRADO 60 kg 160.69 4.33 695.79
01.07.02.01.05 REVOQUES, ENLUCIDOS Y MOLADURAS 669.56
01.07.02.01.05.01 TARRAJEO CON IMPERMEABILIZANTE MEZCLA 1:2; E=2.0 CM m2 12.12 17.18 208.22
01.07.02.01.05.02 TARRAJEO INT. Y EXT, MEZC, 1:4 E=1,5 CM m2 23.55 19.59 461.34
01.07.02.01.06 PINTURA 225.70
01.07.02.01.06.01 PINTURA C/ESMALTE 02 MANOS (exterior) m2 17.73 12.73 225.70
01.07.02.01.07 CARPINTERIA METALICA 1,014.00
01.07.02.01.07.01 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.60X 0.60m,e=1/8", INCLUYE LLAVE MAESTRA und 3.00 179.00 537.00
01.07.02.01.07.02 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.40x 0.50m, E=1/8", INCLUYE LLAVE MAESTRA und 3.00 159.00 477.00
01.07.02.02.07.01 SUMINISTRO E INSTALACION TAPA METALICA DE 0.60 X 0.60 m, e=1/8", INCLUYE LLAVE MAESTRA und 7.00 179.00 1,253.00
01.07.02.02.07.02 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.40 X 0.50 m, E=1/8", INCLUYE LLAVE MAESTRA und 7.00 159.00 1,113.00
01.07.03.01.07.01 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.60 x 0.60 m, e=1/8", INCLUYE LLAVE MAESTRA und 10.00 179.00 1,790.00
01.07.03.02.07.01 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.60 x 0.60 m e=1/8", INC LLAVE MAESTRA und 1.00 179.00 179.00
01.07.03.03.07.01 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.60x 0.60 m, e=1/8", INC. LLAVE MAESTRA und 19.00 179.00 3,401.00
02.01.01.02.08.03 SUMINISTRO E INSTALACION DE DUCHA TEMPORIZADA A PRESION (INCLUYE ACCESORIOS) und 54.00 76.68 4,140.72
02.01.01.04.02.01.04 CAMA DE APOYO CON MATERIAL PROPIO SELECCIONADO ZARANDEADO PARA TUBERIA E=0.10 m m 637.20 1.13 720.04
02.01.01.04.02.01.05 RELLENO COMPACTADO CON MATERIAL PROPIO SELECCIONADO m3 76.46 15.11 1,155.31
02.01.01.04.02.01.06 ELIMINACION DE MATERIAL EXCEDENTE DP=30 M m3 30.59 13.05 399.20
02.01.01.04.02.02 SUMINISTRO E INSTALACION DE TUBERIAS 8,279.50
02.01.01.04.02.02.01 SUMINISTRO E INST TUBERIA PVC SAL DE Ø 2" m 513.00 9.10 4,668.30
02.01.01.04.02.02.02 SUMINISTRO E INST TUBERIA PVC SAL DE Ø 4" m 124.20 13.98 1,736.32
02.01.01.04.02.02.03 SUMINISTRO E INSTALACION DE ACCESORIOS DE PVC SAL DE 2' PARA VIVIENDAS und 54.00 34.72 1,874.88
02.01.01.04.03 CAJA DE INSPECCION 2,564.87
02.01.01.04.03.01 MOVIMIENTO DE TIERRAS 2,564.87
02.01.01.04.03.01.01 EXCAVACION EN TERRENO NORMAL m3 29.11 26.09 759.48
02.01.01.04.03.01.02 EXCAVACION EN TERRENO SEMIROCOSO m3 18.83 39.90 751.32
02.01.01.04.03.01.03 REPINE Y NIVELACION DE FONDOS m2 64.67 4.69 303.30
02.01.01.04.03.01.04 ELIMINACION DE MATERIAL EXCEDENTE DP=30 M m3 57.53 13.05 750.77
02.01.01.04.04 CAJA DE REGISTRO 52,781.19
02.01.01.04.04.01 CAJA DE REGISTRO DE DESAGÜE 0.25 X0.50 m, INCLUYE MARCO Y TAPA DE CONCRETO und 73.00 138.06 10,078.38
02.01.01.04.04.02 CAJA DE TRAMPA DE NATAS Y SOLIDO 0.30 X 0.60 m INCLUYE MARCO Y TAPA DE CONCRETO und 73.00 201.35 14,698.55
02.01.01.04.04.03 CAJA DE REGISTRO DE LODOS DE 0.60 X 0.60m DE CONCRETO und 73.00 247.93 18,098.89
02.01.01.04.04.04 CAJA DE DISTRIBUCION 0.30x0.60 cm,INCLUYE TAPA DE CONCRETO und 73.00 135.69 9,905.37
02.01.01.04.05 BIODIGESTOR 73,997.75
02.01.01.04.05.01 MOVIMIENTO DE TIERRAS 5,385.72
02.01.01.04.05.01.01 EXCAVACION EN TERRENO NORMAL m3 74.95 26.09 1,955.45
02.01.01.04.05.01.02 EXCAVACION EN TERRENO SEMIROCOSO m3 52.46 39.90 2,093.15
02.01.01.04.05.01.03 REPINE Y NIVELACION DE FONDOS m2 37.47 4.69 175.73
02.01.01.04.05.01.04 RELLENO COMPACTADO CON MATERIAL PROPIO SELECCIONADO m3 22.40 15.11 338.46
02.01.01.04.05.01.05 ELIMINACION DE MATERIAL EXCEDENTE DP=30 M m3 63.06 13.05 822.93
02.01.01.04.05.02 OBRAS DE CONCRETO SIMPLE 1,119.98
02.01.01.04.05.02.01 CONCRETO fc=100 kg/cm2, e=4', S/MEZCLADORA m2 37.47 29.89 1,119.98
02.01.01.04.05.03 SUMINISTRO E INSTALACION DE BIODIGESTOR 58,120.20
02.01.01.04.05.03.01 SUMINISTRO E INST DE BIODIGESTOR Y ACCESORIOS (700 L) und 54.00 1,076.30 58,120.20
02.01.01.04.05.04 VARIOS 9,371.85
02.01.01.04.05.04.01 REPELLADO DE C°, E=0.03m, C:A=1:3 CON MALLA EXAGONAL 3/4' m2 461.44 20.31 9,371.85
02.01.01.04.06 ZANJA DE PERCOLACION 89,338.42
02.01.01.04.06.01 MOVIMIENTO DE TIERRAS 11,301.17
02.01.01.04.06.01.01 EXCAVACION EN TERRENO NORMAL m3 143.86 26.09 3,753.31
02.01.01.04.06.01.02 EXCAVACION EN TERRENO SEMIROCOSO m3 89.91 39.90 3,587.41
02.01.01.04.06.01.03 REPINE Y NIVELACION DE FONDOS m2 359.64 4.69 1,686.71
02.01.01.04.06.01.04 RELLENO COMPACTADO CON MATERIAL PROPIO SELECCIONADO m3 89.91 15.11 1,358.54
02.01.01.04.06.01.05 ELIMINACION DE MATERIAL EXCEDENTE DP=30 M m3 70.13 13.05 915.20
02.01.01.04.06.02 MATERIAL FILTRANTE 8,411.88
02.01.01.04.06.02.01 SUINISTRO Y COLOCACIÓN DE GRAVA 1" A 2" m3 53.95 77.96 4,205.94
02.01.01.04.06.02.02 SUINISTRO Y COLOCACIÓN DE GRAVA 1 1/2" A 2" m3 53.95 77.96 4,205.94
02.01.01.04.06.03 SUMINISTRO E INSTALACIÓN DE ACCESORIOS 3,433.43
02.01.01.04.06.03.01 SUMINISTRO E INSTALACIÓN DE TUBERIA PVC DE 2" CON AGUJERO CADA 0.15M Y SERAN. 5 mm m 399.60 7.88 3,148.85
02.01.02.02.02.01 TARRAJEO DE MUROS INTERIORES, ACABADO PULIDO IMPERMEABILIZADO C:A=1:4, e=1.5 cm m2 3.60 24.36 87.70
02.01.02.02.07.03 SUMINISTRO E INSTALACION DE URINARIO DE LOSA VITRIFICADA - NORMA, (INCLUYE ACCESORIOS) und 2.00 221.95 443.90
02.01.02.04.04.02 CAJA DE TRAMPA DE NATAS Y SOLIDO 0.30 X 0.60 m INCLUYE MARCO Y TAPA DE CONCRETO und 2.00 201.35 402.70
02.01.02.04.04.03 CAJA DE REGISTRO DE LODOS DE 0.60 X 0.60m INCLUYE MARCO Y TAPA DE CONCRETO und 2.00 247.93 495.86
02.01.02.04.04.04 CAJA DE DISTRIBUCION 0.30x0.60 cm,INCLUYE TAPA DE CONCRETO und 2.00 135.69 271.38
02.01.02.04.05 BIODIGESTOR 4,065.92
02.01.02.04.05.01 MOVIMIENTO DE TIERRAS 279.70
02.01.02.04.05.01.01 EXCAVACION EN TERRENO NORMAL m3 6.52 26.09 170.11
02.01.02.04.05.01.02 REFINE Y NIVELACION DE FONDOS m2 1.92 4.69 9.00
02.01.02.04.05.01.03 RELLENO COMPACTADO CON MATERIAL PROPIO SELECCIONADO m3 2.84 15.11 42.91
02.01.02.04.05.01.04 ELIMINACION DE MATERIAL EXCEDENTE DP=30 M m3 4.42 13.05 57.68
02.01.02.04.05.02 OBRAS DE CONCRETO SIMPLE 57.39
02.01.02.04.05.02.01 CONCRETO fc= 100 kg/cm2, e=4",S/MEZCLADORA m2 1.92 29.89 57.39
02.01.02.04.05.03 SUMINISTRO E INSTALACION DE BIODIGESTOR 3,294.60
02.01.02.04.05.03.01 SUMINISTRO E INST. DE BIODIGESTOR Y ACCESORIOS (1600 L) und 2.00 1,647.30 3,294.60
02.01.02.04.05.04 VARIOS 434.23
02.01.02.04.05.04.01 REPELLADO DE C°, E=0.03m, C:A=1:3 CON MALLA EXAGONAL 3/4' m2 21.38 20.31 434.23
02.01.02.04.06 ZANJA DE PERCOLACION 1,884.75
02.01.02.04.06.01 MOVIMIENTO DE TIERRAS 375.60
02.01.02.04.06.01.01 EXCAVACION EN TERRENO NORMAL m3 7.72 26.09 201.41
02.01.02.04.06.01.02 REFINE Y NIVELACION DE FONDOS m2 11.88 4.69 55.72
02.01.02.04.06.01.03 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 4.42 15.11 66.79
02.01.02.04.06.01.04 ELIMINACION DE MATERIAL EXCEDENTE DP=30 M m3 3.96 13.05 51.68
02.01.02.04.06.02 MATERIAL FILTRANTE 277.54
02.01.02.04.06.02.01 SUMNISITRO Y COLOCACION DE GRAVA DE 1" A 2" m3 1.78 77.96 138.77
02.01.02.04.06.02.02 SUMNISITRO Y COLOCACION DE GRAVA DE 1 1/2" A 2" m3 1.78 77.96 138.77
02.01.02.04.06.03 SUMINISTRO E INSTALACION DE ACCESORIOS 114.56
02.01.02.04.06.03.01 SUMINIST. E INST. DE TUBERIA PVC 2" CON AGUJEROS CADA 0.15 M Y SERAN DE 5 mm m 13.20 7.88 104.02
02.01.02.04.06.03.02 SUMINISTRO E INSTALACION DE ACCESORIOS und 2.00 5.27 10.54
02.01.02.04.06.04 VARIOS 1,117.05
02.01.02.04.06.04.01 SUMINISTRO Y COLOCACION DE GEOMEMBRANA e=1" m2 5.94 175.53 1,042.65
02.01.02.04.06.04.02 INSTALACION DE VEGETACION DE LA ZONA M2 23.77 3.13 74.40
02.02 SISTEMA DE SANEAMIENTO-UNIDAD BASICA DE SANEAMIENTO (UBS- COMPOSTERA SECA)- (1 UBS) 9,137.02
02.02.02.01.03 MURO DE LADRILLO KK DE ARCILLA DE SOGA, MEZCLA C:A 1:4 (LAVADERO :DOMICILIARIO) m2 1.08 56.93 61.48
02.02.02.02.01 TARRAJEO DE MUROS INTERIORES C/IMPERMEABILIZANTE Y PULIDO P/CAMARA (UBS Compostera) m2 5.40 24.04 129.82
02.02.04.04.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC 2" CON AGUJEROS CADA 0.15 m Y SERAN DE 5mm m 11.00 7.88 86.68
01.07.02.02.07.01 SUMINISTRO E INSTALACION TAPA METALICA DE 0.60 X 0.60 m, e=1/8", INCLUYE LLAVE MAESTRA und 1.00 179.00 179.00
01.07.02.02.07.02 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.40 X 0.50 m, E=1/8", INCLUYE LLAVE MAESTRA und 1.00 159.00 159.00
01.07.03.03.07.01 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.60x 0.60 m, e=1/8", INC. LLAVE MAESTRA und 8.00 179.00 1,432.00
02.02 SISTEMA DE SANEAMIENTO-UNIDAD BASICA DE SANEAMIENTO (UBS- COMPOSTERA SECA)- (1 UBS) 9,137.02
02.02.02.01.03 MURO DE LADRILLO KK DE ARCILLA DE SOGA, MEZCLA C:A 1:4 (LAVADERO :DOMICILIARIO) m2 1.08 56.93 61.48
02.02.02.02.01 TARRAJEO DE MUROS INTERIORES C/IMPERMEABILIZANTE Y PULIDO P/CAMARA (UBS Compostera) m2 5.40 24.04 129.82
02.02.04.04.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC 2" CON AGUJEROS CADA 0.15 m Y SERAN DE 5mm m 11.00 7.88 86.68
01.07.03.01.07.01 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.60 x 0.60 m, e=1/8", INCLUYE LLAVE MAESTRA und 6.00 179.00 1,074.00
02.01.01.02.08.03 SUMINISTRO E INSTALACION DE DUCHA TEMPORIZADA A PRESION (INCLUYE ACCESORIOS) und 1.00 76.68 76.68
02.01.01.04.02.01.04 CAMA DE APOYO CON MATERIAL PROPIO SELECCIONADO ZARANDEADO PARA TUBERIA E=0.10 m m 11.80 1.13 13.33
02.01.01.04.02.01.05 RELLENO COMPACTADO CON MATERIAL PROPIO SELECCIONADO m3 1.42 15.11 21.46
02.01.01.04.02.01.06 ELIMINACION DE MATERIAL EXCEDENTE DP=30 M m3 0.57 13.05 7.44
02.01.01.04.02.02 SUMINISTRO E INSTALACION DE TUBERIAS 0.00 153.32
02.01.01.04.02.02.01 SUMINISTRO E INST TUBERIA PVC SAL DE Ø 2" m 9.50 9.10 86.45
02.01.01.04.02.02.02 SUMINISTRO E INST TUBERIA PVC SAL DE Ø 4" m 2.30 13.98 32.15
02.01.01.04.02.02.03 SUMINISTRO E INSTALACION DE ACCESORIOS DE PVC SAL DE 2' PARA VIVIENDAS und 1.00 34.72 34.72
02.01.01.04.03 CAJA DE INSPECCION 0.00 47.65
02.01.01.04.03.01 MOVIMIENTO DE TIERRAS 0.00 47.65
02.01.01.04.03.01.01 EXCAVACION EN TERRENO NORMAL m3 0.54 26.09 14.09
02.01.01.04.03.01.02 EXCAVACION EN TERRENO SEMIROCOSO m3 0.35 39.90 13.97
02.01.01.04.03.01.03 REPINE Y NIVELACION DE FONDOS m2 1.20 4.69 5.63
02.01.01.04.03.01.04 ELIMINACION DE MATERIAL EXCEDENTE DP=30 M m3 1.07 13.05 13.96
02.01.01.04.05 BIODIGESTOR 0.00 1,196.60
"AMPLIACIÓNPRESUPUESTO
Y MEJORAMIENTO ADICIONAL N° 01
DEL SERVICIO DEDE OBRA
AGUA (PARTIDAS
POTABLE NUEVAS +DEL
E INSTALACIÓN MAYORES METRADOS)
SANEAMIENTO BÁSICO DE LA LOCALIDAD DE EL CARDÓN,
PROYECTO: DISTRITO DE JOSÉ SABOGAL - SAN MARCOS - CAJAMARCA"
EJECUTA: N.E. EL CARDÓN - SNIP 300508 FECHA: MAYO , 2022
02.01.01.04.06.03.01 SUMINISTRO E INSTALACIÓN DE TUBERIA PVC DE 2" CON AGUJERO CADA 0.15M Y SERAN. 5 mm m 7.40 7.88 58.31
01.04.02.07.01 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.60 X 0.60 m e=1/8', INCLUYE LLAVE MAESTRA und 1.00 179.00 179.00
01.04.02.07.02 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.40 x 0.50m, E=1/8" INCLUYE LLAVE MAESTRA und 1.00 159.00 159.00
01.04.03.07.01 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.60 x0.60m e=1/8",INCLUYE LLAVE MAESTRA und 1.00 179.00 179.00
01.04.03.07.02 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.40 x0.50m, E=1/8" INCLUYE LLAVE MAESTRA und 1.00 159.00 159.00
01.05.02.01.06.01 SUMINISTRO E INSTALACIÓN DE ACCESORIOS DE ENTRADA DE 1 1/2" - (CAPTACIÓN"LA VALERIANA 1") und 1.00 87.29 87.29
01.05.02.01.06.02 SUMINISTRO E INSTALACIÓN DE ACCESORIOS DE ENTRADA DE 1 1/2" - (LA VALERIANA 2) und 1.00 87.29 87.29
01.05.02.01.06.03 SUMINISTRO E INSTALACIÓN DE ACCESORIOS DE SALIDA Ø= 1 1/2" - CÁMARA DE REUNIÓN und 1.00 88.53 88.53
01.05.02.01.06.04 SUMINISTRO E INSTALACIÓN DE ACCESORIOS DE LIMPIA Y REBOSE DE 2 1/2" und 1.00 185.02 185.02
01.05.02.01.06.05 SUMINISTRO E INSTALACIÓN DE ACCESORIOS DE VENTILACIÓN und 1.00 59.08 59.08
01.05.02.01.07 TAPA SANITARIA 0.00 179.00
01.05.02.01.07.01 SUMINISTRO E INSTALACIÓN DE TAPA METÁLICA, DE 0.60X0.60M E=1/8" INC. LLAVE MAESTRA und 1.00 179.00 179.00
01.05.02.02.06.01 SUMINISTRO E INSTALACIÓN DE ACCESORIOS DE ENTRADA DE 1 1/2" - (CAPTACIÓN"LA VALERIANA") und 1.00 87.29 87.29
01.05.02.02.06.02 SUMINISTRO E INSTALACIÓN DE ACCESORIOS DE ENTRADA DE 1 1/2" - (LA VALERIANA 2) und 1.00 87.29 87.29
01.05.02.02.06.03 SUMINISTRO E INSTALACIÓN DE ACCESORIOS DE SALIDA Ø= 1 1/2" - CÁMARA DE REUNIÓN und 1.00 88.53 88.53
01.05.02.02.06.04 SUMINISTRO E INSTALACIÓN DE ACCESORIOS DE LIMPIA Y REBOSE DE 2 1/2" und 1.00 185.02 185.02
01.05.02.02.06.05 SUMINISTRO E INSTALACIÓN DE ACCESORIOS DE VENTILACIÓN und 1.00 59.08 59.08
01.05.02.02.07 TAPA SANITARIA 0.00 179.00
01.05.02.02.07.01 SUMINISTRO E INSTALACIÓN DE TAPA METÁLICA, DE 0.60X0.60M E=1/8" INC. LLAVE MAESTRA und 1.00 179.00 179.00
01.06.01.02.04.03 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.60 X 0.60 m e=1/8', INC. LLAVE MAESTRA und 1.00 179.00 179.00
01.06.01.04.05.01 SUMINISTRO E INST. DE ACCESORIOS DE LIMPIEZA Y REBOSE EN SISTEMA DE CLORACION und 1.00 287.56 287.56
01.06.01.06.02.04.01 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.60 X 0,60 m e=1/8*, INCLUYE LLAVE MAESTRA und 1.00 179.00 179.00
01.07.01.02.04 EXCAVACION EN TERRENO SEMIROCOSO DE 0.50x1.10 m P/TUB.AGUA (Cruce en via carrozable) m 20.00 22.23 444.60
01.07.01.02.05 REPINE Y NIVELACION DE FONDO PARA ZANJA DE 0.40x0.70 m P/TUB. AGUA m 8,526.40 0.43 3,666.35
01.07.01.02.06 CAMA DE APOYO C/MAT. PROP. ZARANDEADO PARA TUBERIA DE AGUA E=0.10 m m 8,526.40 1.13 9,634.83
01.07.01.02.07 PRIMER RELLENO COMPACTADO DE ZANJA CON MAT PROPIO ZARANDEADO e=0.30m m 8,526.40 2.23 19,013.87
01.07.01.02.08 SEGUNDO RELLENO CON MATERIAL PROPIO COMPACTADO e=0.30 m m 8,426.40 1.60 13,482.24
01.07.01.02.09 SEGUNDO RELLENO CON MATERIAL PROPIO COMPACTADO e=0.70 m m 100.00 1.60 160.00
01.07.01.02.10 ELIMINACION DE MATERIAL EXCEDENTE DP=30 M m3 393.90 13.05 5,140.40
01.07.01.03 SUMINISTRO E INSTALACION DE TUBERIAS 0.00 60,540.76
01.07.01.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC NTP IS0 1452 UF DN 75 mm C-10 m 49.20 11.24 553.01
01.07.01.03.02 SUMINISTRO E INSTALACION DE TUBERIA PVC NTP IS0 1452 UF DN 63 mm C-10 m 394.50 8.22 3,242.79
01.07.01.03.03 SUMINISTRO E INSTALACION DE TUBERIA PVC NTP ITINTEC 399,002 DN Ø1 1/2" C-10 m 2,060.40 8.77 18,069.71
01.07.01.03.04 SUMINISTRO E INSTALACION DE TUBERIA PVC NTP ITINTEC 399.002 DN Ø 1" C-10 m 4,166.00 6.04 25,162.64
01.07.01.03.05 SUMINISTRO E INSTALACION DE TUBERIA PVC NTP ITINTEC 399.002 DN Ø 3/4" C-10 m 1,856.30 4.11 7,629.39
01.07.01.03.06 PRUEBA HIDRAULICA P/TUB m 8,526.40 0.69 5,883.22
01.07.01.04 SUMINISTRO E INSTALACION DE ACCESORIOS 0.00 3,521.08
01.07.01.04.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN RED DE DISTRIBUCION PVC glb 1.00 3,521.08 3,521.08
01.07.01.05 BLOQUE DE ANCLAJE PARA ACCESORIOS 0.00 6.05
01.07.01.05.01 CONCRETO fc= 100 Kg/cm2, S/MEZCLADORA m3 0.02 302.52 6.05
01.07.02 CAMARA ROMPE PRESION TIPO VII 0.00 26,792.58
01.07.02.01 CAMARA ROMPE PRESION TIPO VII-1A · (3 UND) 0.00 7,861.48
01.07.02.01.01 TRABAJOS PRELIMINARES 0.00 8.37
01.07.02.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 4.95 0.65 3.22
01.07.02.01.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 4.95 1.04 5.15
01.07.02.01.02 MOVIMIENTO DE TIERRAS 0.00 420.51
01.07.02.01.02.01 EXCAVACION EN TERRENO NORMAL m3 10.14 26.09 264.55
01.07.02.01.02.02 RELLENO COMPACTADO CON MATERIAL SELECCIONADO m3 5.20 15.11 78.57
01.07.02.01.02.03 ELIMINACION DE MATERIAL EXCEDENTE DP=30 M m3 5.93 13.05 77.39
01.07.02.01.03 OBRAS DE CONCRETO SIMPLE 0.00 176.38
01.07.02.01.03.01 CONCRETO fc= 100 kg/cm2, e=4", S/MEZCLADORA m2 2.40 29.89 71.74
01.07.02.01.03.02 CONCRETO fc=140 kg/cm2, S/MEZCLADORA m3 0.04 433.66 17.35
01.07.02.01.03.03 ENCOFRADO Y DESENCOFRADO EN DADO DE REBOSE m2 0.72 55.22 39.76
01.07.02.01.03.04 CONCRETO fc=140 kg/cm2 + 30 %PM, S/MEZCLADORA m3 0.15 316.88 47.53
01.07.02.01.04 OBRAS DE CONCRETO ARMADO 0.00 3,904.35
01.07.02.01.04.01 CONCRETO fc= 175 Kg/cm' S/MEZCLADORA m3 3.17 433.66 1,374.70
01.07.02.01.04.02 ENCOFRADO Y DESENCOFRADO EN CAMARA ROMPE PRESION m2 33.21 55.22 1,833.86
01.07.02.01.04.03 ACERO CORRUGADO fy=4200 kg/cm2, GRADO 60 kg 160.69 4.33 695.79
01.07.02.01.05 REVOQUES, ENLUCIDOS Y MOLADURAS 0.00 669.56
01.07.02.01.05.01 TARRAJEO CON IMPERMEABILIZANTE MEZCLA 1:2; E=2.0 CM m2 12.12 17.18 208.22
"AMPLIACIÓN Y MEJORAMIENTO PRESUPUESTO REFORMULADO
DEL SERVICIO DE AGUA POTABLE(MODIFICACIÓN AL E.T.)
E INSTALACIÓN DEL SANEAMIENTO BÁSICO DE LA LOCALIDAD DE EL CARDÓN,
PROYECTO: DISTRITO DE JOSÉ SABOGAL - SAN MARCOS - CAJAMARCA"
EJECUTA: N.E. EL CARDÓN - SNIP 300508 FECHA: MAYO , 2022
01.07.02.01.07.01 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.60X 0.60m,e=1/8", INCLUYE LLAVE MAESTRA und 3.00 179.00 537.00
01.07.02.01.07.02 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.40x 0.50m, E=1/8", INCLUYE LLAVE MAESTRA und 3.00 159.00 477.00
01.07.02.02.07.01 SUMINISTRO E INSTALACION TAPA METALICA DE 0.60 X 0.60 m, e=1/8", INCLUYE LLAVE MAESTRA und 6.00 179.00 1,074.00
01.07.02.02.07.02 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.40 X 0.50 m, E=1/8", INCLUYE LLAVE MAESTRA und 6.00 159.00 954.00
01.07.03.01.07.01 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.60 x 0.60 m, e=1/8", INCLUYE LLAVE MAESTRA und 16.00 179.00 2,864.00
01.07.03.02.07.01 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.60 x 0.60 m e=1/8", INC LLAVE MAESTRA und 1.00 179.00 179.00
01.07.03.03.07.01 SUMINISTRO E INSTALACION DE TAPA METALICA DE 0.60x 0.60 m, e=1/8", INC. LLAVE MAESTRA und 11.00 179.00 1,969.00
02.01.01.02.08.03 SUMINISTRO E INSTALACION DE DUCHA TEMPORIZADA A PRESION (INCLUYE ACCESORIOS) und 55.00 76.68 4,217.40
02.01.01.04.02.01.04 CAMA DE APOYO CON MATERIAL PROPIO SELECCIONADO ZARANDEADO PARA TUBERIA E=0.10 m m 649.00 1.13 733.37
02.01.01.04.02.01.05 RELLENO COMPACTADO CON MATERIAL PROPIO SELECCIONADO m3 77.88 15.11 1,176.77
02.01.01.04.02.01.06 ELIMINACION DE MATERIAL EXCEDENTE DP=30 M m3 31.16 13.05 406.64
02.01.01.04.02.02 SUMINISTRO E INSTALACION DE TUBERIAS 0.00 8,432.82
02.01.01.04.02.02.01 SUMINISTRO E INST TUBERIA PVC SAL DE Ø 2" m 522.50 9.10 4,754.75
02.01.01.04.02.02.02 SUMINISTRO E INST TUBERIA PVC SAL DE Ø 4" m 126.50 13.98 1,768.47
"AMPLIACIÓN Y MEJORAMIENTO PRESUPUESTO REFORMULADO
DEL SERVICIO DE AGUA POTABLE(MODIFICACIÓN AL E.T.)
E INSTALACIÓN DEL SANEAMIENTO BÁSICO DE LA LOCALIDAD DE EL CARDÓN,
PROYECTO: DISTRITO DE JOSÉ SABOGAL - SAN MARCOS - CAJAMARCA"
EJECUTA: N.E. EL CARDÓN - SNIP 300508 FECHA: MAYO , 2022
02.01.01.04.04.02 CAJA DE TRAMPA DE NATAS Y SOLIDO 0.30 X 0.60 m INCLUYE MARCO Y TAPA DE CONCRETO und 73.00 201.35 14,698.55
02.01.01.04.04.03 CAJA DE REGISTRO DE LODOS DE 0.60 X 0.60m DE CONCRETO und 73.00 247.93 18,098.89
02.01.01.04.04.04 CAJA DE DISTRIBUCION 0.30x0.60 cm,INCLUYE TAPA DE CONCRETO und 73.00 135.69 9,905.37
02.01.01.04.05 BIODIGESTOR 0.00 75,194.35
02.01.01.04.05.01 MOVIMIENTO DE TIERRAS 0.00 5,485.40
02.01.01.04.05.01.01 EXCAVACION EN TERRENO NORMAL m3 76.34 26.09 1,991.72
02.01.01.04.05.01.02 EXCAVACION EN TERRENO SEMIROCOSO m3 53.43 39.90 2,131.85
02.01.01.04.05.01.03 REPINE Y NIVELACION DE FONDOS m2 38.16 4.69 178.97
02.01.01.04.05.01.04 RELLENO COMPACTADO CON MATERIAL PROPIO SELECCIONADO m3 22.81 15.11 344.66
02.01.01.04.05.01.05 ELIMINACION DE MATERIAL EXCEDENTE DP=30 M m3 64.23 13.05 838.20
02.01.01.04.05.02 OBRAS DE CONCRETO SIMPLE 0.00 1,140.60
02.01.01.04.05.02.01 CONCRETO fc=100 kg/cm2, e=4', S/MEZCLADORA m2 38.16 29.89 1,140.60
02.01.01.04.05.03 SUMINISTRO E INSTALACION DE BIODIGESTOR 0.00 59,196.50
02.01.01.04.05.03.01 SUMINISTRO E INST DE BIODIGESTOR Y ACCESORIOS (700 L) und 55.00 1,076.30 59,196.50
02.01.01.04.05.04 VARIOS 0.00 9,371.85
02.01.01.04.05.04.01 REPELLADO DE C°, E=0.03m, C:A=1:3 CON MALLA EXAGONAL 3/4' m2 461.44 20.31 9,371.85
02.01.01.04.06 ZANJA DE PERCOLACION 0.00 90,993.17
02.01.01.04.06.01 MOVIMIENTO DE TIERRAS 0.00 11,510.64
02.01.01.04.06.01.01 EXCAVACION EN TERRENO NORMAL m3 146.52 26.09 3,822.71
02.01.01.04.06.01.02 EXCAVACION EN TERRENO SEMIROCOSO m3 91.58 39.90 3,654.04
02.01.01.04.06.01.03 REPINE Y NIVELACION DE FONDOS m2 366.30 4.69 1,717.95
02.01.01.04.06.01.04 RELLENO COMPACTADO CON MATERIAL PROPIO SELECCIONADO m3 91.58 15.11 1,383.77
02.01.01.04.06.01.05 ELIMINACION DE MATERIAL EXCEDENTE DP=30 M m3 71.43 13.05 932.17
02.01.01.04.06.02 MATERIAL FILTRANTE 0.00 8,567.80
02.01.01.04.06.02.01 SUINISTRO Y COLOCACIÓN DE GRAVA 1" A 2" m3 54.95 77.96 4,283.90
02.01.01.04.06.02.02 SUINISTRO Y COLOCACIÓN DE GRAVA 1 1/2" A 2" m3 54.95 77.96 4,283.90
02.01.01.04.06.03 SUMINISTRO E INSTALACIÓN DE ACCESORIOS 0.00 3,497.01
02.01.01.04.06.03.01 SUMINISTRO E INSTALACIÓN DE TUBERIA PVC DE 2" CON AGUJERO CADA 0.15M Y SERAN. 5 mm m 407.00 7.88 3,207.16
02.01.02.02.02.01 TARRAJEO DE MUROS INTERIORES, ACABADO PULIDO IMPERMEABILIZADO C:A=1:4, e=1.5 cm m2 3.60 24.36 87.70
02.01.02.02.07.03 SUMINISTRO E INSTALACION DE URINARIO DE LOSA VITRIFICADA - NORMA, (INCLUYE ACCESORIOS) und 2.00 221.95 443.90
02.01.02.04.04.02 CAJA DE TRAMPA DE NATAS Y SOLIDO 0.30 X 0.60 m INCLUYE MARCO Y TAPA DE CONCRETO und 2.00 201.35 402.70
02.01.02.04.04.03 CAJA DE REGISTRO DE LODOS DE 0.60 X 0.60m INCLUYE MARCO Y TAPA DE CONCRETO und 2.00 247.93 495.86
02.01.02.04.04.04 CAJA DE DISTRIBUCION 0.30x0.60 cm,INCLUYE TAPA DE CONCRETO und 2.00 135.69 271.38
02.01.02.04.05 BIODIGESTOR 0.00 4,065.92
02.01.02.04.05.01 MOVIMIENTO DE TIERRAS 0.00 279.70
"AMPLIACIÓN Y MEJORAMIENTO PRESUPUESTO REFORMULADO
DEL SERVICIO DE AGUA POTABLE(MODIFICACIÓN AL E.T.)
E INSTALACIÓN DEL SANEAMIENTO BÁSICO DE LA LOCALIDAD DE EL CARDÓN,
PROYECTO: DISTRITO DE JOSÉ SABOGAL - SAN MARCOS - CAJAMARCA"
EJECUTA: N.E. EL CARDÓN - SNIP 300508 FECHA: MAYO , 2022
1,160,612.87