CONSTRUCCION SISTEMA DE RIEGO Y PRESA SENKATA ALTA (CALAMARCA)

PROYECTO:
LA PAZ - BOLIVIA

COMUNIDAD: SENKATA ALTA


MUNICIPIO: CALAMARCA
PROVINCIA: AROMA
DEPARTAMENTO: LA PAZ

CALCULOS DE SEDIMENTOS

S= 4.00% (%) pendiente hidráulica del rio


Qmax= 4.64 (m3/s)
B= 25 (m)
q= 0.1856 (m3/sm) caudal unitario
ɤs= 1300.00 (kg/m3) peso específico del sedimetno
ɤw= 1000 (kg/m3) peso específico del agua
Δ= 44 densidad relativa de las partículas sumergidas
Pmuestra= 530.61 (gr)
No TAMIZ PESO RETENIDO PESO RETENIDO % RETENIDO PORCENTAJE
PULGADAS c/TAMIZ ACUMULADO ACUMULADO QUE PASA
2 1/2" 0.00 0.00 0.00 100.00 0.000
2" 0.00 0.00 0.00 100.00 0.000
1 1/2" 0.00 0.00 0.00 100.00 0.000
1" 26.00 26.00 4.90 95.10 4.900
3/4" 76.00 102.00 19.30 80.70 14.323
3/8" 113.00 215.00 40.80 59.20 21.296
4 98.00 313.00 59.30 40.70 18.469
10 81.00 394.00 74.70 25.30 15.265
40 53.30 53.30 53.90 11.70 10.045
200 71.20 71.20 72.00 7.10 13.419
Base 0.00 0.00 0.00 100.00 0.000
No TAMIZ PORCENTAJE
DIÁMETRO (mm) Pi (mm) Di (mm) Pi*Di
PULGADAS QUE PASA (%)
2 1/2" 63.50
2" 50.80 100.00 0.000 56.9 0.00
1 1/2" 38.10 100.00 0.000 44.45 0.00
1" 25.40 100.00 0.000 31.75 0.00
3/4" 19.00 95.10 4.900 22.225 108.90
3/8" 9.50 80.70 14.323 9.5 136.07
4 4.75 59.20 21.296 5.525 117.66
10 2.00 40.70 18.469 2.19 40.45
40 0.43 25.30 15.265 0.5125 7.82
200 0.07 7.10 13.419 0.11 1.48
TOTAL 87.67 412.38
Dm= 4.70 (mm)
D16= 2.00 (mm)
D35= 5.00 (mm)
D40= 5.40 (mm)
D50= 13.00 (mm)
D84= 33.00 (mm)
D90= 36.00 (mm)
Dmax= 45.00 (mm)
PROYECTO: CONSTRUCCION SISTEMA DE RIEGO Y PRESA SENKATA ALTA
(CALAMARCA) – LA PAZ - BOLIVIA
COMUNIDAD: SENKATA ALTA
MUNICIPIO: CALAMARCA
PROVINCIA: AROMA
DEPARTAMENTO: LA PAZ

CÁLCULO DE LA PRODUCCIÓN ANUAL DE SEDIMENTOS EN EL EMBALSE


MÉTODO DE SCHOKLITSCH
Schoklitsch propuso un modelo para el estudio del arrastre de fondo de las partículas sedimentadas pero que lo fue
perfeccionandp a través de diferentes ensayos y en el año de 1950 conocimos el modelo final de su ecuación.
Método de Schoklitsch
Caudal unitario (2)

Caudal crítico ds
q c  1.94  105 4 (3)
S3 3
Considerar que: q > qc → Se produce transporte
q < qc → No existe transporte

Transporte unitario (4)

Transporte crítico (5)

Transporte total (6)

Donde: Qi .- Caudal mensual de aporte de la cuenca


Br .- Ancho promedio de la sección transversal del cauce principal [m]
ds .- Diámetro de las partículas de sedimento [mm]
S3 .- Pendiente media del cauce principal
q .- Caudal unitario
qc .- Caudal crítico
gsi .- Transporte unitario de sedimento para un diámetro i
gs .- Transporte crítico
Gs .- Transporte total de sedimento
a, b,…, n .- Valor numérico del porcentaje del peso retenido
correspondiente al diámetro de sedimento
DATOS DE LA CUENCA
S= 0.0004 (m/m) Pendiente media del río
ɤs= 45000 (kg/m3) Peso específico del material de arrastre
q= 0.18560 Caudal unitario
Δ= 44
D= 0.0054 (m) Diámetro representativo de la muestra
Cuando el tamaño de las partículas no es uniforme, Schoklitsch recomienda que se utilice como diámetro
representativo de la mezcla el D40.

GRANULOMETRÍA DEL MATERIAL DE ARRASTRE


TAMIZ
% RET. ACUM. % RET.
Nominal (mm)
2 1/2" 63.50 0.00 0.00
2" 50.80 0.00 0.00
1 1/2" 38.10 0.00 0.00
1" 25.40 4.90 4.90
3/4" 19.00 19.30 14.32
3/8" 9.50 40.80 21.30
4 4.75 59.30 18.47
10 2.00 74.70 15.27
40 0.43 53.90 10.05
200 0.07 72.00 13.42
Fuente: Ensayos de Laboratorio presentados por la Consultora

Peso específico del sedimento


ɤs= 45000 (kg/m3)
Pendiente del cauce principal
S= 0.04 (m/m)
Ancho promedio del cauce principal:
B= 25 (m)

Caudales mensuales de aporte de la cuenca:

Qpromedio
MES
(l/s) (m3/s)
ENE 51.83 0.05183
FEB 38.42 0.03842
MAR 29.74 0.02974
ABR 11.47 0.01147
MAY 2.73 0.00273
JUN 2.47 0.00247
JUL 2.48 0.00248
AGO 5.41 0.00541
SEP 10.57 0.01057
OCT 13.25 0.01325
NOV 19.93 0.01993
DIC 33.97 0.03397
Fuente: Aforos de la Consultora

CAUDALES PROMEDIO MENSUALES


0.06

0.05

0.04

0.03

0.02

0.01

0
Jun Jul Ago Sep Oct Nov Dic Ene Feb Mar Abr May
TRANSPORTE MENSUAL DE SEDIMENTOS
Mes= ENERO
Qmes= 0.052 (m3/s)
TAMIZ Se Produce gsi
% RET. a, b, n q (m3/sm) qc (m3/sm) gs (kg/sm)
Nominal (mm) Transporte? (kg/sm)
3/8" 9.5 21.30 0.213 0.00207 0.013472412 NO
4 4.75 18.47 0.185 0.00207 0.006736206 NO
10 2 15.27 0.153 0.00207 0.002836297 NO
40 0.425 10.05 0.100 0.00207 0.000602713 SI 0.126 0.013
200 0.07 13.42 0.134 0.00207 0.000099270 SI 0.418 0.056
Ʃ= 0.069

Mes= FEBRERO
Qmes= 0.038 (m3/s)
TAMIZ Se Produce gsi
% RET. a, b, n q (m3/sm) qc (m3/sm) gs (kg/sm)
Nominal (mm) Transporte? (kg/sm)
3/8" 9.5 21.30 0.213 0.00154 0.013472412 NO
4 4.75 18.47 0.185 0.00154 0.006736206 NO
10 2 15.27 0.153 0.00154 0.002836297 NO
40 0.425 10.05 0.100 0.00154 0.000602713 SI 0.080 0.008
200 0.07 13.42 0.134 0.00154 0.000099270 SI 0.304 0.041
Ʃ= 0.049

Mes= MARZO
Qmes= 0.030 (m3/s)
TAMIZ Se Produce gsi
% RET. a, b, n q (m3/sm) qc (m3/sm) gs (kg/sm)
Nominal (mm) Transporte? (kg/sm)
3/8" 9.5 21.30 0.213 0.00119 0.013472412 NO
4 4.75 18.47 0.185 0.00119 0.006736206 NO
10 2 15.27 0.153 0.00119 0.002836297 NO
40 0.425 10.05 0.100 0.00119 0.000602713 SI 0.050 0.005
200 0.07 13.42 0.134 0.00119 0.000099270 SI 0.231 0.031
Ʃ= 0.036

Mes= ABRIL
Qmes= 0.011 (m3/s)
TAMIZ Se Produce gsi
% RET. a, b, n q (m3/sm) qc (m3/sm) gs (kg/sm)
Nominal (mm) Transporte? (kg/sm)
3/8" 9.5 21.30 0.213 0.00046 0.013472412 NO
4 4.75 18.47 0.185 0.00046 0.006736206 NO
10 2 15.27 0.153 0.00046 0.002836297 NO
40 0.425 10.05 0.100 0.00046 0.000602713 NO
200 0.07 13.42 0.134 0.00046 0.000099270 SI 0.076 0.010
Ʃ= 0.010
Mes= MAYO
Qmes= 0.003 (m3/s)
TAMIZ Se Produce gsi
% RET. a, b, n q (m3/sm) qc (m3/sm) gs (kg/sm)
Nominal (mm) Transporte? (kg/sm)
3/8" 9.5 21.30 0.213 0.00011 0.013472412 NO
4 4.75 18.47 0.185 0.00011 0.006736206 NO
10 2 15.27 0.153 0.00011 0.002836297 NO
40 0.425 10.05 0.100 0.00011 0.000602713 NO
200 0.07 13.42 0.134 0.00011 0.000099270 SI 0.002 0.000
Ʃ= 0.000

Mes= JUNIO
Qmes= 0.002 (m3/s)
TAMIZ Se Produce gsi
% RET. a, b, n q (m3/sm) qc (m3/sm) gs (kg/sm)
Nominal (mm) Transporte? (kg/sm)
3/8" 9.5 21.30 0.213 0.00010 0.013472412 NO
4 4.75 18.47 0.185 0.00010 0.006736206 NO
10 2 15.27 0.153 0.00010 0.002836297 NO
40 0.425 10.05 0.100 0.00010 0.000602713 NO
200 0.07 13.42 0.134 0.00010 0.000099270 NO
Ʃ= 0.000

Mes= JULIO
Qmes= 0.002 (m3/s)
TAMIZ Se Produce gsi
% RET. a, b, n q (m3/sm) qc (m3/sm) gs (kg/sm)
Nominal (mm) Transporte? (kg/sm)
3/8" 9.5 21.30 0.213 0.00010 0.013472412 NO
4 4.75 18.47 0.185 0.00010 0.006736206 NO
10 2 15.27 0.153 0.00010 0.002836297 NO
40 0.425 10.05 0.100 0.00010 0.000602713 NO
200 0.07 13.42 0.134 0.00010 0.000099270 SI 0.000 0.000
Ʃ= 0.000

Mes= AGOSTO
Qmes= 0.005 (m3/s)
TAMIZ Se Produce gsi
% RET. a, b, n q (m3/sm) qc (m3/sm) gs (kg/sm)
Nominal (mm) Transporte? (kg/sm)
3/8" 9.5 21.30 0.213 0.00022 0.013472412 NO
4 4.75 18.47 0.185 0.00022 0.006736206 NO
10 2 15.27 0.153 0.00022 0.002836297 NO
40 0.425 10.05 0.100 0.00022 0.000602713 NO
200 0.07 13.42 0.134 0.00022 0.000099270 SI 0.025 0.003
Ʃ= 0.003
Mes= SEPTIEMBRE
Qmes= 0.011 (m3/s)
TAMIZ Se Produce gsi
% RET. a, b, n q (m3/sm) qc (m3/sm) gs (kg/sm)
Nominal (mm) Transporte? (kg/sm)
3/8" 9.5 21.30 0.213 0.00042 0.013472412 NO
4 4.75 18.47 0.185 0.00042 0.006736206 NO
10 2 15.27 0.153 0.00042 0.002836297 NO
40 0.425 10.05 0.100 0.00042 0.000602713 NO
200 0.07 13.42 0.134 0.00042 0.000099270 SI 0.069 0.009
Ʃ= 0.009

Mes= OCTUBRE
Qmes= 0.013 (m3/s)
TAMIZ Se Produce gsi
% RET. a, b, n q (m3/sm) qc (m3/sm) gs (kg/sm)
Nominal (mm) Transporte? (kg/sm)
3/8" 9.5 21.30 0.213 0.00053 0.013472412 NO
4 4.75 18.47 0.185 0.00053 0.006736206 NO
10 2 15.27 0.153 0.00053 0.002836297 NO
40 0.425 10.05 0.100 0.00053 0.000602713 NO
200 0.07 13.42 0.134 0.00053 0.000099270 SI 0.091 0.012
Ʃ= 0.012

Mes= NOVIEMBRE
Qmes= 0.020 (m3/s)
TAMIZ Se Produce gsi
% RET. a, b, n q (m3/sm) qc (m3/sm) gs (kg/sm)
Nominal (mm) Transporte? (kg/sm)
3/8" 9.5 21.30 0.213 0.00080 0.013472412 NO
4 4.75 18.47 0.185 0.00080 0.006736206 NO
10 2 15.27 0.153 0.00080 0.002836297 NO
40 0.425 10.05 0.100 0.00080 0.000602713 SI 0.017 0.002
200 0.07 13.42 0.134 0.00080 0.000099270 SI 0.148 0.020
Ʃ= 0.021

Mes= DICIEMBRE
Qmes= 0.034 (m3/s)
TAMIZ Se Produce gsi
% RET. a, b, n q (m3/sm) qc (m3/sm) gs (kg/sm)
Nominal (mm) Transporte? (kg/sm)
3/8" 9.5 21.30 0.213 0.00136 0.013472412 NO
4 4.75 18.47 0.185 0.00136 0.006736206 NO
10 2 15.27 0.153 0.00136 0.002836297 NO
40 0.425 10.05 0.100 0.00136 0.000602713 SI 0.065 0.007
200 0.07 13.42 0.134 0.00136 0.000099270 SI 0.267 0.036
Ʃ= 0.042
TRANSPORTE MENSUAL DE SEDIMENTOS (Sin Corrección)
gsmes
MES MES Q (m3/s) GS (Kg/s) GSmensual (kg/mes) GSmensual (m3/mes)
(kg/sm)
ENE 31 0.0518 0.069 1.71881985 4,603,687.08 102.30
FEB 28 0.0384 0.049 1.22203038 2,956,335.90 65.70
MAR 31 0.0297 0.036 0.90064419 2,412,285.39 53.61
ABR 30 0.0115 0.010 0.25541833 662,044.32 14.71
MAY 31 0.0027 0.000 0.00699883 18,745.68 0.42
JUN 30 0.0025 0.000 Sin Transporte
JUL 31 0.0025 0.000 0.00000752 20.15 0.00
AGO 31 0.0054 0.003 0.08319654 222,833.62 4.95
SEP 30 0.0106 0.009 0.22980709 595,659.97 13.24
OCT 31 0.0132 0.012 0.30582964 819,134.12 18.20
NOV 30 0.0199 0.021 0.53739715 1,392,933.42 30.95
DIC 31 0.0340 0.042 1.05754188 2,832,520.18 62.94
Ʃ= 16,516,199.82 367.03

El transporte de sedimento anual sin ajuste expresado en volumen es:


GS= 367.03 (m3/año)

TRANSPORTE MENSUAL DE SEDIMENTOS (Sin corregir)


2.00

1.80

1.60

1.40

1.20

1.00

0.80

0.60

0.40

0.20

0.00
JUN JUL AGO SEP OCT NOV DIC ENE FEB MAR ABR MAY JUN
CURVA DE SCHOKLITSCH CORREGIDA
2.00

1.80

f(x) = − 4023.07838223845 x³ + 426.772329108316 x² + 22.9543010054678 x − 0.0578144275787946


1.60 R² = 0.999968748627491

1.40
TRANSPORTE DE SEDIMENTOS

1.20

1.00

0.80

0.60

0.40

0.20

0.00
0 0.01 0.02 0.03 0.04 0.05 0.06

CAUDAL DEL RÍO (m3/s)

CÁLCULO DE TRANSPORTE ANUAL DE SEDIMENTOS (Corregido)


Gsmensual corregido Gsmensual
MES MES Q (m3/s) GScorr (kg/s)
(kg/mes) corregido(m3/mes)
ENE 31 0.0518 1.72 4,603,775.37 102.31
FEB 28 0.0384 1.11 2,684,161.49 59.65
MAR 31 0.0297 0.76 2,024,186.52 44.98
ABR 30 0.0115 0.14 358,798.62 7.97
MAY 31 0.0027 0.01 18,745.68 0.42
JUN 30 0.0025 Sin Transporte
JUL 31 0.0025 0.00 20.15 0.00
AGO 31 0.0054 0.08 222,833.62 4.95
SEP 30 0.0106 0.11 292,824.15 6.51
OCT 31 0.0132 0.19 508,897.81 11.31
NOV 30 0.0199 0.40 1,039,188.45 23.09
DIC 31 0.0340 0.92 2,475,094.42 55.00
Ʃ= 316.19

El transporte de sedimento ajustado expresado en volumen es:


GS= 316.19 (m3/año)
PROYECTO: CONSTRUCCION SISTEMA DE RIEGO Y PRESA SENKATA ALTA
(CALAMARCA) – LA PAZ - BOLIVIA
COMUNIDAD: SENKATA ALTA
MUNICIPIO: CALAMARCA
PROVINCIA: AROMA
DEPARTAMENTO: LA PAZ

CÁLCULO D E LA PRODUCCIÓN ANUAL DE SEDIMENTOS EN EL EMBALSE


MÉTODO DE DJOROVIC
El modelo Djorovic calcula la degradación específica en función de una serie de parámetros que son repre-
sentativos de los procesos erosivos como: precipitación, clima, suelo, relieve y vegetación, incluye a su vez un
parámetro para estimar el grado de intensjorovicidad que alcanzaron los procesos erosivos en la cuenca y el
tipo de erosión predominante. Este modelo está definido por la siguiente ecuación:

Donde:
W= Caudal sólido (m3/año), como medida de degradación de la cuenca
T= Factor de temperatura, T=((t*0,1)+1)*(1/2)
t= Temperatura media anual en (|C)
F= Área de la zona de riesgo, (km2)
P= Precipitación media anual, (mm)
Z= Factor de riesgo (Coeficiente de erosión que refleja la intensidad y extensión del fenómeno erosivo de
una cuenca y valoriza la influencia d elos factores de suelo, vegetación y relieve).

y= es un coeficiente adimensional de erosionabilidad del suelo


X= es un coeficiente adimensional que cuantifica la vegetación
Ꝋ= es un coeficiente adimensional que cuantifica el estado erosivo
S= es la pendiente media de la cuenca, (m/m)

DATOS DE LA CUENCA:

Cuenca Área de la Cuenca F Precipitación P Pendiente Media S


(km2) (mm) Temperatura t (°C) (m/m)
HUANCAJAHUIRA 6.982 555.29 9.19 0.04
7.02

SUELOS Factor y % Área % Área*y


Suelos sueltos, arenas y gravas 2.00 0.00
Loess y suelos salinos 1.60 0.00
Rocas calizas desintegradas 1.20 0.00
Flisch y areniscas 1.10 0.00
Esquistos 1.00 0.00
Calizas duras y pizarras 0.90 0.05 0.05
Suelos con buena estructura 0.50 0.95 0.48
Ʃ= 1.00 0.52
y= 0.52

COBERTURA VEGETAL Factor x % Área % Área*x


Suelo desnudo 1.00 0.00
Barbecho 0.90 0.00
Viñedos 0.70 0.00
Pastizales de montaña 0.60 0.00
Bosques 0.50 0.00
Praderas 0.40 1.00 0.40
Ʃ= 1.00 0.40
x= 0.40
ESTADO EROSIVO Factor Ꝋ % Área % Área*x
100% con erosiones profundas 1.00 0.00
80% erosiones profundas y cárcavas 0.90 0.00
50 % deslizamientos 0.80 0.00
100% erosión laminar, algunos regueros y cárcavas 0.60 0.00
50 % erosión laminar 0.50 0.00
20 % erosión laminar 0.30 0.00
Sin signos de erosión 0.20 1.00 0.20
Ʃ= 1.00 0.20
Ꝋ= 0.20

Factor Z: Z= 0.08

Factor de Temperatura: T= 1.30

W= 381.34 (m3/año)
PROYECTO: CONSTRUCCION SISTEMA DE RIEGO Y PRESA SENKATA ALTA
(CALAMARCA) – LA PAZ - BOLIVIA
COMUNIDAD: SENKATA ALTA
MUNICIPIO: CALAMARCA
PROVINCIA: AROMA
DEPARTAMENTO: LA PAZ

DETERMINACIÓN DEL NIVEL DE AGUAS MUERTAS NAmu


Transporte de sediemntos Método Schoklistch:
GS= 316.19 (m3/año)
Transporte de sedimentos Método Djorovic:
GS= 381.34 (m3/año)
Se elegirá el valor mayor de los dos métodos utilizados.
Valor de Transporte de sedimentos a utilizar:
GS= 381.34 (m3/año)
El valor anterior corresponde a la cantidad de producción de sedimentos en un tiempo de 1 año.
Para la determinación de la altura de las aguas muertas en el embalse de Huancajahuirase utilizará
un volumen de sedimentos producidos en un tiempo de 1 años, que equivale a:
GS= 381.34 (m3)

Éste volumen corresponde a una elevación de:

DATOS TOPOGRÁFICOS DEL VASO


VOLUMEN
No COTA AREA (m2) OBS
ACUM (m3)
1 4015.50 0.00 0.00 Lecho del río
2 4016.00 89.47 357.89
3 4016.47 381.34 1,188.81 Nivel Muerto
4 4016.50 399.86 1,241.55
5 4017.00 973.14 2,650.99
6 4017.50 1,825.12 4,649.49
7 4018.00 2,971.63 7,237.05
8 4018.50 4,420.14 10,443.49
9 4019.00 6,178.08 14,268.83
10 4019.40 7,806.44 18,585.30
11 4019.50 8,262.65 23,392.91
12 4019.60 8,755.69 28,446.09
13 4019.70 9,273.28 33,744.84
14 4019.80 9,815.44 39,289.16
15 4019.90 10,382.15 45,079.05
El volumen de aguas muertas:
Vol NAmu= 381.34 (m3) Para 1 años
La elevación del Nivel de Aguas Muertas:

Elev (msnm) Vol (m3)

4016.00 --------------- 89.47


Elev NAmu --------------- 381.34
4016.50 --------------- 399.86

ElevNAmu= 4016.470 (msnm)

El área del Nivel de aguas Muertas:

A(m2) Elev (msnm)

357.89 --------------- 4,016.00


Area NAmu --------------- 4,016.47
1,241.55 --------------- 4,016.50

Área NAmu= 1188.81 (m2)


ELEVACIÓN Vs. VOLUMEN
4020.0

4019.5

4019.0

4018.5
ELEVACION (msnm)

4018.0

4017.5

4017.0

4016.5

4016.0

4015.5
0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 5 5.5 6 6.5 7 7.5 8 8.5 9 9.5 10 10.5 11

VOLUMEN (1000*m3)

ELEVACIÓN Vs. ÁREA


4020

4019.5

4019

4018.5
ELEVACIÓN (msnm)

4018

4017.5

4017

4016.5

4016

4015.5
0.00 5.00 10.00 15.00 20.00 25.00 30.00 35.00 40.00 45.00 50.00

ÁREA DE EMBALSE (1000*m2)


AREA VOLUMEN
COTA AREA ACUMULADA ACUMULADO
(M2) (M3)
1 4015.50 0.00 0.00 0.00
2 4016.00 357.89 357.89 89.47
3 4016.50 883.66 1241.55 399.86
4 4017.00 1409.44 2650.99 973.14
5 4017.50 1998.50 4649.49 1825.12
6 4018.00 2587.56 7237.05 2971.63
7 4018.50 3206.45 10443.49 4420.14
8 4019.00 3825.34 14268.83 6178.08
9 4019.40 4316.47 18585.30 7806.44
10 4019.50 4807.61 23392.91 8262.65
11 4019.60 5053.18 28446.09 8755.69
12 4019.70 5298.75 33744.84 9273.28
13 4019.80 5544.32 39289.16 9815.44
14 4019.90 5789.89 45079.05 10382.15