PROYECTO:
LA PAZ - BOLIVIA
CALCULOS DE SEDIMENTOS
Caudal crítico ds
q c 1.94 105 4 (3)
S3 3
Considerar que: q > qc → Se produce transporte
q < qc → No existe transporte
Qpromedio
MES
(l/s) (m3/s)
ENE 51.83 0.05183
FEB 38.42 0.03842
MAR 29.74 0.02974
ABR 11.47 0.01147
MAY 2.73 0.00273
JUN 2.47 0.00247
JUL 2.48 0.00248
AGO 5.41 0.00541
SEP 10.57 0.01057
OCT 13.25 0.01325
NOV 19.93 0.01993
DIC 33.97 0.03397
Fuente: Aforos de la Consultora
0.05
0.04
0.03
0.02
0.01
0
Jun Jul Ago Sep Oct Nov Dic Ene Feb Mar Abr May
TRANSPORTE MENSUAL DE SEDIMENTOS
Mes= ENERO
Qmes= 0.052 (m3/s)
TAMIZ Se Produce gsi
% RET. a, b, n q (m3/sm) qc (m3/sm) gs (kg/sm)
Nominal (mm) Transporte? (kg/sm)
3/8" 9.5 21.30 0.213 0.00207 0.013472412 NO
4 4.75 18.47 0.185 0.00207 0.006736206 NO
10 2 15.27 0.153 0.00207 0.002836297 NO
40 0.425 10.05 0.100 0.00207 0.000602713 SI 0.126 0.013
200 0.07 13.42 0.134 0.00207 0.000099270 SI 0.418 0.056
Ʃ= 0.069
Mes= FEBRERO
Qmes= 0.038 (m3/s)
TAMIZ Se Produce gsi
% RET. a, b, n q (m3/sm) qc (m3/sm) gs (kg/sm)
Nominal (mm) Transporte? (kg/sm)
3/8" 9.5 21.30 0.213 0.00154 0.013472412 NO
4 4.75 18.47 0.185 0.00154 0.006736206 NO
10 2 15.27 0.153 0.00154 0.002836297 NO
40 0.425 10.05 0.100 0.00154 0.000602713 SI 0.080 0.008
200 0.07 13.42 0.134 0.00154 0.000099270 SI 0.304 0.041
Ʃ= 0.049
Mes= MARZO
Qmes= 0.030 (m3/s)
TAMIZ Se Produce gsi
% RET. a, b, n q (m3/sm) qc (m3/sm) gs (kg/sm)
Nominal (mm) Transporte? (kg/sm)
3/8" 9.5 21.30 0.213 0.00119 0.013472412 NO
4 4.75 18.47 0.185 0.00119 0.006736206 NO
10 2 15.27 0.153 0.00119 0.002836297 NO
40 0.425 10.05 0.100 0.00119 0.000602713 SI 0.050 0.005
200 0.07 13.42 0.134 0.00119 0.000099270 SI 0.231 0.031
Ʃ= 0.036
Mes= ABRIL
Qmes= 0.011 (m3/s)
TAMIZ Se Produce gsi
% RET. a, b, n q (m3/sm) qc (m3/sm) gs (kg/sm)
Nominal (mm) Transporte? (kg/sm)
3/8" 9.5 21.30 0.213 0.00046 0.013472412 NO
4 4.75 18.47 0.185 0.00046 0.006736206 NO
10 2 15.27 0.153 0.00046 0.002836297 NO
40 0.425 10.05 0.100 0.00046 0.000602713 NO
200 0.07 13.42 0.134 0.00046 0.000099270 SI 0.076 0.010
Ʃ= 0.010
Mes= MAYO
Qmes= 0.003 (m3/s)
TAMIZ Se Produce gsi
% RET. a, b, n q (m3/sm) qc (m3/sm) gs (kg/sm)
Nominal (mm) Transporte? (kg/sm)
3/8" 9.5 21.30 0.213 0.00011 0.013472412 NO
4 4.75 18.47 0.185 0.00011 0.006736206 NO
10 2 15.27 0.153 0.00011 0.002836297 NO
40 0.425 10.05 0.100 0.00011 0.000602713 NO
200 0.07 13.42 0.134 0.00011 0.000099270 SI 0.002 0.000
Ʃ= 0.000
Mes= JUNIO
Qmes= 0.002 (m3/s)
TAMIZ Se Produce gsi
% RET. a, b, n q (m3/sm) qc (m3/sm) gs (kg/sm)
Nominal (mm) Transporte? (kg/sm)
3/8" 9.5 21.30 0.213 0.00010 0.013472412 NO
4 4.75 18.47 0.185 0.00010 0.006736206 NO
10 2 15.27 0.153 0.00010 0.002836297 NO
40 0.425 10.05 0.100 0.00010 0.000602713 NO
200 0.07 13.42 0.134 0.00010 0.000099270 NO
Ʃ= 0.000
Mes= JULIO
Qmes= 0.002 (m3/s)
TAMIZ Se Produce gsi
% RET. a, b, n q (m3/sm) qc (m3/sm) gs (kg/sm)
Nominal (mm) Transporte? (kg/sm)
3/8" 9.5 21.30 0.213 0.00010 0.013472412 NO
4 4.75 18.47 0.185 0.00010 0.006736206 NO
10 2 15.27 0.153 0.00010 0.002836297 NO
40 0.425 10.05 0.100 0.00010 0.000602713 NO
200 0.07 13.42 0.134 0.00010 0.000099270 SI 0.000 0.000
Ʃ= 0.000
Mes= AGOSTO
Qmes= 0.005 (m3/s)
TAMIZ Se Produce gsi
% RET. a, b, n q (m3/sm) qc (m3/sm) gs (kg/sm)
Nominal (mm) Transporte? (kg/sm)
3/8" 9.5 21.30 0.213 0.00022 0.013472412 NO
4 4.75 18.47 0.185 0.00022 0.006736206 NO
10 2 15.27 0.153 0.00022 0.002836297 NO
40 0.425 10.05 0.100 0.00022 0.000602713 NO
200 0.07 13.42 0.134 0.00022 0.000099270 SI 0.025 0.003
Ʃ= 0.003
Mes= SEPTIEMBRE
Qmes= 0.011 (m3/s)
TAMIZ Se Produce gsi
% RET. a, b, n q (m3/sm) qc (m3/sm) gs (kg/sm)
Nominal (mm) Transporte? (kg/sm)
3/8" 9.5 21.30 0.213 0.00042 0.013472412 NO
4 4.75 18.47 0.185 0.00042 0.006736206 NO
10 2 15.27 0.153 0.00042 0.002836297 NO
40 0.425 10.05 0.100 0.00042 0.000602713 NO
200 0.07 13.42 0.134 0.00042 0.000099270 SI 0.069 0.009
Ʃ= 0.009
Mes= OCTUBRE
Qmes= 0.013 (m3/s)
TAMIZ Se Produce gsi
% RET. a, b, n q (m3/sm) qc (m3/sm) gs (kg/sm)
Nominal (mm) Transporte? (kg/sm)
3/8" 9.5 21.30 0.213 0.00053 0.013472412 NO
4 4.75 18.47 0.185 0.00053 0.006736206 NO
10 2 15.27 0.153 0.00053 0.002836297 NO
40 0.425 10.05 0.100 0.00053 0.000602713 NO
200 0.07 13.42 0.134 0.00053 0.000099270 SI 0.091 0.012
Ʃ= 0.012
Mes= NOVIEMBRE
Qmes= 0.020 (m3/s)
TAMIZ Se Produce gsi
% RET. a, b, n q (m3/sm) qc (m3/sm) gs (kg/sm)
Nominal (mm) Transporte? (kg/sm)
3/8" 9.5 21.30 0.213 0.00080 0.013472412 NO
4 4.75 18.47 0.185 0.00080 0.006736206 NO
10 2 15.27 0.153 0.00080 0.002836297 NO
40 0.425 10.05 0.100 0.00080 0.000602713 SI 0.017 0.002
200 0.07 13.42 0.134 0.00080 0.000099270 SI 0.148 0.020
Ʃ= 0.021
Mes= DICIEMBRE
Qmes= 0.034 (m3/s)
TAMIZ Se Produce gsi
% RET. a, b, n q (m3/sm) qc (m3/sm) gs (kg/sm)
Nominal (mm) Transporte? (kg/sm)
3/8" 9.5 21.30 0.213 0.00136 0.013472412 NO
4 4.75 18.47 0.185 0.00136 0.006736206 NO
10 2 15.27 0.153 0.00136 0.002836297 NO
40 0.425 10.05 0.100 0.00136 0.000602713 SI 0.065 0.007
200 0.07 13.42 0.134 0.00136 0.000099270 SI 0.267 0.036
Ʃ= 0.042
TRANSPORTE MENSUAL DE SEDIMENTOS (Sin Corrección)
gsmes
MES MES Q (m3/s) GS (Kg/s) GSmensual (kg/mes) GSmensual (m3/mes)
(kg/sm)
ENE 31 0.0518 0.069 1.71881985 4,603,687.08 102.30
FEB 28 0.0384 0.049 1.22203038 2,956,335.90 65.70
MAR 31 0.0297 0.036 0.90064419 2,412,285.39 53.61
ABR 30 0.0115 0.010 0.25541833 662,044.32 14.71
MAY 31 0.0027 0.000 0.00699883 18,745.68 0.42
JUN 30 0.0025 0.000 Sin Transporte
JUL 31 0.0025 0.000 0.00000752 20.15 0.00
AGO 31 0.0054 0.003 0.08319654 222,833.62 4.95
SEP 30 0.0106 0.009 0.22980709 595,659.97 13.24
OCT 31 0.0132 0.012 0.30582964 819,134.12 18.20
NOV 30 0.0199 0.021 0.53739715 1,392,933.42 30.95
DIC 31 0.0340 0.042 1.05754188 2,832,520.18 62.94
Ʃ= 16,516,199.82 367.03
1.80
1.60
1.40
1.20
1.00
0.80
0.60
0.40
0.20
0.00
JUN JUL AGO SEP OCT NOV DIC ENE FEB MAR ABR MAY JUN
CURVA DE SCHOKLITSCH CORREGIDA
2.00
1.80
1.40
TRANSPORTE DE SEDIMENTOS
1.20
1.00
0.80
0.60
0.40
0.20
0.00
0 0.01 0.02 0.03 0.04 0.05 0.06
Donde:
W= Caudal sólido (m3/año), como medida de degradación de la cuenca
T= Factor de temperatura, T=((t*0,1)+1)*(1/2)
t= Temperatura media anual en (|C)
F= Área de la zona de riesgo, (km2)
P= Precipitación media anual, (mm)
Z= Factor de riesgo (Coeficiente de erosión que refleja la intensidad y extensión del fenómeno erosivo de
una cuenca y valoriza la influencia d elos factores de suelo, vegetación y relieve).
DATOS DE LA CUENCA:
Factor Z: Z= 0.08
W= 381.34 (m3/año)
PROYECTO: CONSTRUCCION SISTEMA DE RIEGO Y PRESA SENKATA ALTA
(CALAMARCA) – LA PAZ - BOLIVIA
COMUNIDAD: SENKATA ALTA
MUNICIPIO: CALAMARCA
PROVINCIA: AROMA
DEPARTAMENTO: LA PAZ
4019.5
4019.0
4018.5
ELEVACION (msnm)
4018.0
4017.5
4017.0
4016.5
4016.0
4015.5
0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 5 5.5 6 6.5 7 7.5 8 8.5 9 9.5 10 10.5 11
VOLUMEN (1000*m3)
4019.5
4019
4018.5
ELEVACIÓN (msnm)
4018
4017.5
4017
4016.5
4016
4015.5
0.00 5.00 10.00 15.00 20.00 25.00 30.00 35.00 40.00 45.00 50.00