RESUMEN DEL COSTO X M2 DE ESTRUCTURAS - TRIANA

UTILIDAD COSTO COSTO


ESPECIALIDAD COSTO DIRECTO G.G 0.09601728% SUB-TOTAL IGV 18% TOTAL S/.
0% S/./M2 $/M2.
Estructuras Casco (del 1° Piso a la S/. 1,088,520.54 S/. 104,516.78 S/. 1,193,037.32 S/. 214,746.72 S/. 1,407,784.04 S/. 700.83 $214.32
Azotea)
Estructuras Cota + 1.50m (2do S/. 914,610.20 S/. 87,818.38 S/. 1,002,428.58 S/. 180,437.15 S/. 1,182,865.73 S/. 1,121.90 $343.09
sotano, 1er Sotano y Semisotano

Presupuesto final de Estructuras S/. 2,003,130.74 S/. 192,335.17 S/. 2,195,465.91 S/. 395,183.86 S/. 2,590,649.77 S/. 845.77 $258.64
(todo el casco)

AT de Estructuras (m2) 3063.08 m2

RESUMEN DE AREA
TECHADA

Descripcion Area
2do Sotano 290.33
1er Sotano 386.2
Semisotano 377.81
1° Piso 266.24
2° Piso 265.51
3° Piso 265.51
4° Piso 265.51
5° Piso 265.51
6° Piso 265.51
7° Piso 265.51
Azotea 149.44
Azotea 92.98

Total Casco 3063.08 m2


S10 Página 1

Presupuesto de Estructuras Casco - Triana


Presupuesto 0103018 EDIFICIO RESIDENCIAL TRIANA
Subpresupuesto 001 ESTRUCTURAS
Cliente TALE CONSTRUCTORA SAC Costo al
Lugar LIMA - LIMA - PUEBLO LIBRE

Item Descripción Und. Metrado Precio S/. Parcial S/.

01 OBRAS PROVISIONALES 34,007.05


01.01 OFICINA DE OBRA STAFF glb 0.50 2,830.74 1,415.37
01.02 ALMACEN DE OBRA glb 0.50 2,361.99 1,181.00
01.03 CASETA DE GUARDIANIA glb 0.50 1,654.77 827.39
01.04 COMEDOR DE OBRA (capacidad 70 personas) glb 0.50 2,734.60 1,367.30

01.06 SERVICIOS HIGIENICOS DE OBRA PORTATILES mes 8.50 663.00 5,635.50

01.08 AGUA PARA LA CONSTRUCCION mes 8.50 408.00 3,468.00


01.09 ENERGIA ELECTRICA PARA LA OBRA mes 8.50 425.00 3,612.50
01.10 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y glb 1.00 6000.00 6000.00
HERRAMIENTAS
01.12 ACUERDO SINDICAL glb 1.00 5000.00 5000.00
01.13 CONSUMIBLES Y HERRAMIENTAS VARIOS glb 1.00 5500.00 5500.00

02 OBRAS PRELIMINARES 195,804.60

2.01 LIMPIEZA DURANTE LA EJECUCION DE LA OBRA glb 0.50 35,772.00 17,886.00


2.02 TRAZO Y REPLANTEO INICIAL Y DURANTE LA EJECUCION DE mes 7.00 9,676.12 67,732.84
OBRA
2.03 TRANSPORTE VERTICAL CON WINCHE ELECTRICO glb 1.00 6,751.63 6,751.63
TRANSPORTE VERTICAL CON ELEVADOR mes 6.00 5,000.00 0.00
30,000.00

2.04 EQUIPOS DE PROTECCION COLECTIVA glb 0.50 25,033.35 12,516.68


2.05 EQUIPOS DE PROTECCION INDIVIDUAL glb 0.50 17,916.90 8,958.45
2.06 SEÑALIZACION TEMPORAL DE SEGURIDAD glb 1.00 21,959.00 21,959.00
2.07 MADERA PARA PROTECCIONES COLECTIVAS glb 1.00 30,000.00 30,000.00

03 MOVIMIENTO DE TIERRAS 23,823.39

3.01 TRASLADO DE DESMONTE PARA SU ELIMINACION (MANUAL) m3 93.60 21.68 2,029.25

3.02 TRASLADO DE DESMONTE PARA SU ELIMINACION (MANUAL) hr 150.00 100.00 15,000.00

3.03 ELIMINACION MATERIAL EXCEDENTE CARGIO m3 229.07 29.66 6,794.14


MANUAL(SUBCONTRATO)
4
CONCRETO ARMADO 834,885.51

05.05 PLACAS 173,623.60


05.05.01 CONCRETO PREMEZCLADO PLACAS f'c=245 kg/cm2 m3 210.00 290.00 60,898.55

05.05.05 ACERO FY= 4200 kg/cm2 GRADO 60 EN PLACAS kg 45,090.02 2.50 112,725.05
(SUBCONTRATO)
05.06 COLUMNAS 38,182.86
05.06.01 CONCRETO PREMEZCLADO COLUMNAS f'c=245 kg/cm2 m3 50.00 290.00 14,500.00

05.06.05 ACERO FY= 4200 kg/cm2 GRADO 60 EN COLUMNAS kg 9,473.14 2.50 23,682.86
(SUBCONTRATO)
05.07 LOSAS ALIGERADAS e = 0.20 m. 145,497.97

05.07.01 CONCRETO PREMEZCLADO LOSAS ALIGERADAS f'c=210 kg/cm2 m3 150.00 274.00 41,098.90
05.07.03 ACERO FY= 4200 kg/cm2 GRADO 60 EN LOSA ALIGERADA kg 4,078.28 2.50 10,195.71
(SUBCONTRATO)
05.07.04 COLOCACION DE VIGUETAS PREFABRICADAS m2 2,186.20 3.19 6,973.98
05.07.05 COLOCACION DE BOVEDILLA DE ARCILLA 15x25x39 CM und 19,675.80 0.15 2,951.37
05.07.06 SISTEMA DE VIGUETAS PREFABRICADAS Y BOBEDILLAS m2 2,186.20 38.55 84,278.01
15x25x39 CM
05.08 LOSAS MACIZAS 29,385.89
05.08.01 CONCRETO PREMEZCLADO LOSAS MACIZAS f'c=210 kg/cm2 m3 70.00 274.00 19,180.00
05.08.03 ACERO FY= 4200 kg/cm2 GRADO 60 EN LOSA MACIZA kg 4,082.36 2.50 10,205.89
(SUBCONTRATO)
05.09 VIGAS 137,398.85
05.09.01 CONCRETO PREMEZCLADO VIGAS f'c=210 kg/cm2 m3 250.00 274.00 68,499.45
05.09.03 ACERO FY= 4200 kg/cm2 GRADO 60 EN VIGAS (SUBCONTRATO) kg 27,559.76 2.50 68,899.39
05.10 ESCALERAS 8,886.79

05.10.01 CONCRETO PREMEZCLADO ESCALERA f'c=210 kg/cm2 m3 20.00 274.00 5,480.00


05.10.03 ACERO FY= 4200 kg/cm2 GRADO 60 EN ESCALERA kg 1,362.72 2.50 3,406.79
(SUBCONTRATO)
05.12 SUB CONTRATO 264,484.80
05.12.01 SC M. DE O. PARA ACERO CORRUGADO kg 95,326.61 0.85 81,027.62
SC PARA ENCOFRADO METALICO (TODO COSTO) und 1.00 183,457.18 183,457.18
05.13 EQUIPOS 8,700.00

05.13.01 EQUIPOS DE OBRA und 0.50 17,400.00 8,700.00


05.14 VARIOS 28,724.76

05.14.04 LIMPIEZA DE CUÑAS DE VACIADO m 118.92 29.85 3,549.76

05.14.06 ENCOFRADO MUERTO m2 450.00 28.00 12,600.00


05.14.07
05.14.07 DADOS DE CONCRETO EN ARMADO DE ACERO und 5,500.00 0.45 2,475.00

05.14.08 CURADO DE CONCRETO m2 0.85 0.00

05.14.09 TRATAMIENTO UNION MURO/LOSA VIGA ml 1,200.00 2.25 2,700.00

05.14.10 TECNOPOR PARA JUNTAS DE DILATACION m2 400.00 18.50 7,400.00

COSTO DIRECTO S/. 1,088,520.54


GASTOS GENERALES 09.601728% 104,516.78
UTILIDAD 0 %
----------------------

SUBTOTAL 1,193,037.32
IMPUESTO(IGV 18%) 214,746.72
===============

TOTAL PRESUPUESTO
S/. 1,407,784.04
SON: UN MILLON TRESCIENTOS SESENTA MIL, TREINTA Y SEIS MIL Y 79/100 NUEVOS SOLES
Presupuestos por Recursos - Estructuras Casco
Obra 0103019 EDIFICIO RESIDENCIAL TRIANA (Nivel +1.50) - OPTIMIZADO 23/08/17
Subpresupuesto 001 ESTRUCTURAS
Fecha
Lugar
Código Recurso Unidad Cantidad Precio S/. Parcial S/.

MANO DE OBRA

CAPATAZ hh 432.0000 23.47 10,139.04


0101010003 OPERARIO hh 480.0000 18.05 8,664.00
OPERARIO ALBAÑIL hh 432.0000 18.05 7,797.60
0101010004 OFICIAL hh 480.0000 14.85 7,128.00
0101010005 PEON hh 5,088.0000 13.32 67,772.16
01010300000004 TOPOGRAFO hh 816.0000 18.05 14,728.80
S/. 116,229.60
MATERIALES

0201030001 GASOLINA gal 64.0000 11.87 759.68


02040100010002 ALAMBRE NEGRO RECOCIDO N° 16 kg 3,000.0000 3.03 9,090.00
ALAMBRE NEGRO RECOCIDO N° 8 kg 500.0000 3.03 1,515.00
0204030001 ACERO CORRUGADO fy = 4200 kg/cm2 kg 104,859.27 2.50 262,148.18
02041200010001 GRADO
CLAVOS60
PARA MADERA CON CABEZA DE kg 1,050.0000 2.75 2,887.50
02041200010004 1"
CLAVOS PARA MADERA CON CABEZA DE 2 kg 700.0000 2.75 1,925.00
02041200010005 1/2"
CLAVOS PARA MADERA CON CABEZA DE kg 15.0000 2.75 41.25
02041200010007 3"
CLAVOS PARA MADERA CON CABEZA DE kg 6.0000 2.75 16.50
0204150003 4"
DADOS DE CONCRETO EN ARMADO DE glb 1.0000 2,475.00 2,475.00
02060100010006 ACERO
TUBERIA PVC-SAL 4" X 3 m und 8.0016 20.50 164.03
0207040001 MATERIAL GRANULAR m3 49.9200 33.90 1,692.29
0207070001 AGUA PUESTA EN OBRA m3 410.2091 5.44 2,231.54
02080100010002 TUBERIA PVC-SEL 3/4" X 3 m und 27.0089 2.25 60.77
02080200010002 CURVAS PVC-SEL 3/4" (20 mm) und 39.0000 0.25 9.75
02080300010002 UNIONES PVC-SEL 3/4" (20 mm) und 33.0000 0.23 7.59
02080400010002 CONEXIONES PVC-SEL 3/4" (20 mm) und 41.0000 0.34 13.94
0210030001 MALLA CERCADORA NARANJA rll 8.0000 33.90 271.20
02100400010005 TECNOPOR DE 2.40 x 1.20 x 2" glb 1.0000 7,400.00 7,400.00
0213010001 CEMENTO PORTLAND TIPO I (42.5 kg) bol 467.0000 15.64 7,301.82
02190100010010 CONCRETO PREMEZCLADO F'C=210 m3 6.2759 209.00 1,311.65
02190100010011 kg/cm2
CONCRETO PREMEZCLADO F'C=210 m3 493.2300 209.00 103,085.07
02190100010016 kg/cm2,
CONCRETOP57, PREMEZCLADO
S46 F'C=245 m3 266.5600 225.00 59,976.00
02190500010001 kg/cm2,
SERVICIOP67,
DES46
BOMBA PARA CONCRETO m3 766.0659 30.00 22,981.98
0222080012 PREMEZCLADO
PEGAMENTO PARA PVC 1 GLN gal 5.0000 150.00 750.00
0231010001 MADERA TORNILLO p2 3,865.9800 4.50 17,396.91
02310500010006 TRIPLAY DE 1.20X2.40 m X 4 mm und 30.0000 21.95 658.50
0231130002 MADERA CACHIMBO 4"x4"x10' und 54.0000 56.00 3,024.00
0231130003 MADERA CACHIMBO 3"x4"x8' und 27.0000 33.60 907.20
0231130004 MADERA CACHIMBO 2"x4"x10' und 21.0000 28.00 588.00
0231130005 MADERA CACHIMBO 1"x2"x10' und 36.0000 7.00 252.00
0231130006 MADERA CACHIMBO 1"x2"x8' und 36.0000 5.60 201.60
0231130007 MADERA CACHIMBO 1 1/2"x8"x10' und 126.0000 30.51 3,844.26
0231130008 MADERA CACHIMBO 2"x2"x10' und 84.0000 10.17 854.28
0231130009 MADERA CACHIMBO 2"x2"x8' und 78.0000 11.20 873.60
0231220004 PANEL OSB 9MM 1.22x2.44M und 53.0000 33.48 1,774.44
0237080001 CERRADURA PARA PUERTA INTERIOR und 2.0000 15.25 30.50
02410200010001 CINTA AISLANTE 3M rll 1.8000 5.00 9.00
02620500040008 INTERRUPTOR DOBLE DOMINO und 4.0000 11.90 47.60
02620500060009 INTERRUPTOR UNIPOLAR SIMPLE DOMINO und 1.0000 7.55 7.55
02621300010006 TOMACORRIENTE BIPOLAR DOBLE und 5.2500 12.50 65.63
02670100010005 DOMINOTIPO JOCKEY NARANJA
CASCO und 60.0000 12.71 762.60
0267010003 BARBIQUEJO und 120.0000 1.69 202.80
0267020001 LENTES DE POLICARBONATO LUNA CLARA und 360.0000 2.97 1,069.20
0267030008 PROTECTOR DE OIDOS TIPO TAPON und 360.0000 1.69 608.40
0267040007 RESPIRADORES DESCARTABLES und 720.0000 4.24 3,052.80
0267050001 GUANTES DE CUERO par 60.0000 8.65 519.00
0267050004 GUANTES DE NITRILO par 600.0000 6.19 3,714.00
0267050006 GUANTES DE JEBE par 60.0000 11.70 702.00
02670600060005 PANTALON DRILL AZUL und 120.0000 16.10 1,932.00
0267060012 POLOS und 300.0000 9.33 2,799.00
0267070001 BOTINES DE CUERO CON PUNTA DE par 180.0000 36.00 6,480.00
0267070006 ACERO
BOTINES DE JEBE CON PUNTA par 60.0000 21.20 1,272.00
0267080002 REFORZADA
ARNES CON TRES ANILLO und 60.0000 212.00 12,720.00
0267080007 SOGA DE NYLON 3/4" m 300.0000 1.90 570.00
0267100012 MANTA ARPILLERA ANCHO= 2.00 m. m 150.0000 1.60 240.00
0267110001 CINTA DE SEÑALIZACION und 16.0000 55.00 880.00
02671100040002 SEÑALES REGLAMENTARIAS 75 X 75 cm und 32.0000 20.00 640.00
0267110022 CACHACO DE CONCRETO und 40.0000 15.00 600.00
0267110023 BALAUSTRES DE METAL und 100.0000 2.75 275.00
0267110024 SARGENTOS DE METAL und 16.0000 12.85 205.60
0267110025 CASQUETE DE PVC PARA BALAUSTRES und 300.0000 1.44 432.00
0267110026 CASQUILLOS DE PVC PARA SEGURIDAD und 2,000.0000 0.43 860.00
02680500010001 CAJA DE PASE OCTOGONAL SEL 100 X 55 und 8.0000 1.50 12.00
0268060001 mm RECTANGULAR PVC
CAJA und 8.0000 1.50 12.00
02681200010002 CAJA DE PASE CUADRADA DE FIERRO und 2.5000 4.50 11.25
02683000010001 GALVANIZADO
TAPA 1 GANG DE 100x100x50 mm und 2.5000 4.50 11.25
0270010080 CABLE TW 2.5 mm2 m 157.0000 1.00 157.00
0270010083 CABLE TW 4 mm2 m 80.0000 1.50 120.00
0293010002 SISTEMA LOSA ALIGERADA ALITEC h = 20 m2 2,186.2000 39.50 86,357.09
cm.
S/. 645,867.79
EQUIPOS

0301000012 EQUIPO DE OBRA glb 1.0000 8,265.00 8,265.00


0301010006 HERRAMIENTAS MANUALES %mo 435.00
S/. 8,700.00
SUBCONTRATOS

SC PARA ENCOFRADO CASCO (Todo costo) glb 1.0000 183,457.18 183,457.18


SC M. DE O. PARA ACERO casco +1.50 kg 95,326.61 0.85 81,027.62
0401010001 ELIMINACION DE DESMONTE glb 1.0000 2,029.25 2,029.25
0402010003 ALQUILER DE BOODCATT glb 1.0000 15,000.00 15,000.00
0402010003 ELIMINACION DEL MATERIAL EXCEDENTE glb 1.0000 6,794.14 6,794.14
CARGUIO
LIMPIEZA DE CUÑAS EN VACIADO glb 1.0000 3,549.76 3,549.76
TRATAMIENTO EN UNION EN MURO/LOSA glb 1.0000 2,700.00 2,700.00
0402020003 VIGA
SC SERVICIOS HIGIENICOS PORTATILES mes 8.5000 663.00 5,635.50
0405020022 SC ENCOFRADO MUERTO m2 1.0000 12,600.00 12,600.00
0416010005 SC CONSUMO EN KWH Kwh 4,250.0000 0.35 1,466.25
SC AGUA PARA LA CONSTRUCCION mes 8.5000 408.00 3,468.00
S/. 317,727.70

Total Costo Directo Sin IGV S/.


1,088,525.09
Presupuesto de Estructuras Cota + 1.50m
Presupuesto 0103018

Subpresupues 001
to
Cliente TALE CONSTRUCTORA SAC
Lugar LIMA - LIMA - PUEBLO LIBRE

Item Descripción Und. Metrado Precio S/. Parcial S/.

01 OBRAS PROVISIONALES 43,146.76

01.01 OFICINA DE OBRA glb 1.00 2,830.74 2,830.74


01.02 ALMACEN DE OBRA glb 1.00 2,361.99 2,361.99
01.03 CASETA DE GUARDIANIA glb 1.00 1,654.77 1,654.77
01.04 COMEDOR DE OBRA (capacidad 70 personas) glb 1.00 2,734.60 2,734.60
01.05 VESTUARIO PERSONAL OBRERO (capacidad 70 personas) glb 1.00 3,512.66 3,512.66

01.06 SERVICIOS HIGIENICOS DE OBRA PORTATILES mes 4.50 663.00 2,983.50


01.07 CERCO METALICO DE OBRA DE 2.50 m. ALTURA m 14.05 400.00 5,620.00
01.08 AGUA PARA LA CONSTRUCCION mes 4.50 408.00 1,836.00
01.09 ENERGIA ELECTRICA PARA LA OBRA mes 4.50 425.00 1,912.50
01.10 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS, OBRAS glb 1.00 6000.00 6,000.00
PROVISIONALES DE INICIO
01.11 MONTAJE Y DESMONTAJE DE ESCALERA DE ACCESO glb 1.00 1200.00 1,200.00

01.12 ACUERDO SINDICAL glb 1.00 5000.00 5,000.00


01.13 CONSUMIBLES Y HERRAMIENTAS VARIOS glb 1.00 5500.00 5,500.00
02 OBRAS PRELIMINARES 156,231.12

02.01 LIMPIEZA DEL TERRENO MANUAL m2 384.00 3.23 1,240.32


02.02 DEMOLICION CONSTRUCCION EXISTENTE glb 1.00 21,186.44 21,186.44
02.03 LIMPIEZA DURANTE LA EJECUCION DE LA OBRA glb 1.00 35,772.00 35,772.00
02.04 TRAZO Y REPLANTEO INICIAL Y DURANTE LA EJECUCION DE mes 4.50 9,676.12 43,542.54
OBRA
02.05 TRANSPORTE VERTICAL CON WINCHE ELECTRICO mes 0.00 11,889.34 0.00

02.06 EQUIPOS DE PROTECCION COLECTIVA glb 0.50 25,033.35 12,516.68


02.07 EQUIPOS DE PROTECCION INDIVIDUAL glb 0.50 17,916.90 8,958.45
02.08 SEÑALIZACION TEMPORAL DE SEGURIDAD glb 1.00 33,014.69 33,014.69
03 MOVIMIENTO DE TIERRAS 161,048.47
03.01 EXCAVACION MASIVA EN BANCO (inc. eliminación) m3 2,900.00 21.19 61,451.00
03.02 EXCAV. ZAPATAS MAT. SUELTO H=1.00 M m3 126.47 52.29 6,613.12
03.03 RELLENO COMPACTADO A MANO CON MATERIAL PROPIO m3 261.94 18.32 4,798.74

03.04 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO m3 47.15 67.64 3,189.23


(AFIRMADO)
03.05 TRASLADO DE DESMONTE PARA SU ELIMINACION (MANUAL) m3 93.60 21.68 2,029.25

03.06 RELLENO CON MATERIAL GRANULAR PARA ENCOFRADO MUROS hm 306.00 186.44 57,050.64
ANCLADOS

03.07 PERFILADO DE MURO PANTALLA m2 608.90 13.65 8,311.49


03.09 DEMOLICION DE CACHIMBA (INC. MARTILLO) ml 264.00 13.65 3,603.60
03.10 PLATAFORMA PARA TRAZO DE MURO PANTALLA ml 264.00 13.65 3,603.60

03.11 PICADO PARA ANCLADO DE VIGUETAS, VIGAS DE LA LOSA DE L ml 264.00 13.65 3,603.60
03.12 ELIMINACION MATERIAL EXCEDENTE CARGIO m3 229.07 29.66 6,794.22
MANUAL(SUBCONTRATO)
04 CONCRETO SIMPLE 19,870.62

04.01 PAÑETEO MORTERO EN MURO PANTALLA m3 608.90 9.09 5,534.90


04.02 CONCRETO SOLADO MEZCLA 1:10 CEMENTO-HORMIGON e=0.20 m2 205.33 47.28 9,708.00
m.
04.03 CONCRETO SUBZAPATAS 1:12 + 30% P.G. m3 38.59 119.92 4,627.71
04.04 CONCRETO FALSO PISO MEZCLA 1:8 CEMENTO-HORMIGON e=4" m2 0.00 29.92 0.00

05
CONCRETO ARMADO 534,313.24

05.01 ZAPATAS 20,164.47


05.01.01 CONCRETO PREMEZCLADO ZAPATAS f'c=210 kg/cm2 m3 51.22 269.00 13,778.18

05.01.03 ACERO FY= 4200 kg/cm2 GRADO 60 EN ZAPATAS kg 3,225.40 1.98 6,386.29
(SUBCONTRATO)
05.02 VIGA DE CIMENTACION 945.24
05.02.01 CONCRETO PREMEZCLADO VIGA DE CIMENTACION f'c=210 m3 1.87 269.00 503.03
kg/cm2
05.02.03 ACERO FY= 4200 kg/cm2 GRADO 60 EN VIGA DE CIMENTACION kg 216.77 2.04 442.21
(SUBCONTRATO)

05.03 CIMIENTOS 8,446.09


05.03.01 CONCRETO PREMEZCLADO CIMENTACIONES f'c=210 kg/cm2 m3 21.78 269.00 5,858.82

05.03.03 ACERO FY= 4200 kg/cm2 GRADO 60 EN CIMINETOS kg 1,287.20 2.01 2,587.27
(SUBCONTRATO)
05.04 MUROS DE CONTENCION 101,493.56
05.04.01 CONCRETO PREMEZCLADO MURO DE CONTENCION f'c=245 m3 143.88 285.00 41,005.80
kg/cm2
05.04.02 CONCRETO PREMEZCLADO MURO DE CONTENCION f'c=280 m3 80.75 298.00 24,063.50
kg/cm2
05.04.03 ACERO FY= 4200 kg/cm2 GRADO 60 EN MUROS DE CONTENCION kg 18,121.52 2.01 36,424.26
(SUBCONTRATO)
05.05 PLACAS 16,782.61
05.05.01 CONCRETO PREMEZCLADO PLACAS f'c=245 kg/cm2 m3 15.37 285.00 4,380.45

05.05.02 CONCRETO PREMEZCLADO PLACAS f'c=210 kg/cm2 m3 0.00 269.00 0.00

05.05.03 CONCRETO PREMEZCLADO PLACAS f'c=280 kg/cm2 (Aditivo m3 0.00 440.66 0.00
Impermeable)
05.05.05 ACERO FY= 4200 kg/cm2 GRADO 60 EN PLACAS kg 6,170.23 2.01 12,402.16
(SUBCONTRATO)

05.06 COLUMNAS 13,410.67


05.06.01 CONCRETO PREMEZCLADO COLUMNAS f'c=245 kg/cm2 m3 17.20 285.00 4,902.00

05.06.02 CONCRETO PREMEZCLADO COLUMNAS f'c=245 kg/cm2 (Aditivo m3 0.00 0.00


Impermeable)
05.06.03 CONCRETO PREMEZCLADO COLUMNAS f'c=280 kg/cm2 m3 0.00 0.00

05.06.05 ACERO FY= 4200 kg/cm2 GRADO 60 EN COLUMNAS kg 4,233.17 2.01 8,508.67
(SUBCONTRATO)
05.07 LOSAS ALIGERADAS e = 0.20 m. 52,655.85
05.07.01 CONCRETO PREMEZCLADO LOSAS ALIGERADAS f'c=210 kg/cm2 m3 76.13 269.00 20,478.97

05.07.03 ACERO FY= 4200 kg/cm2 GRADO 60 EN LOSA ALIGERADA kg 1,806.37 2.01 3,630.80
(SUBCONTRATO)

05.07.04 COLOCACION DE VIGUETAS PREFABRICADAS m2 645.59 3.19 2,059.43


05.07.05 COLOCACION DE BOBEDILLA DE ARCILLA 15x25x39 CM und 5,158.56 0.31 1,599.15

05.07.06 SISTEMA DE VIGUETAS PREFABRICADAS Y BOBEDILLAS m2 645.59 38.55 24,887.49


15x25x39 CM
05.08 LOSAS MACIZAS 12,205.98
05.08.01 CONCRETO PREMEZCLADO LOSAS MACIZAS f'c=210 kg/cm2 m3 32.88 269.00 8,844.72

05.08.03 ACERO FY= 4200 kg/cm2 GRADO 60 EN LOSA MACIZA kg 1,672.27 2.01 3,361.26
(SUBCONTRATO)
05.09 VIGAS 29,643.37
05.09.01 CONCRETO PREMEZCLADO VIGAS f'c=210 kg/cm2 m3 60.52 269.00 16,279.88

05.09.03 ACERO FY= 4200 kg/cm2 GRADO 60 EN VIGAS (SUBCONTRATO) kg 6,648.50 2.01 13,363.49

05.10 ESCALERAS 2,847.51


05.10.01 CONCRETO PREMEZCLADO ESCALERA f'c=210 kg/cm2 m3 7.50 269.00 2,017.50

05.10.03 ACERO FY= 4200 kg/cm2 GRADO 60 EN ESCALERA kg 412.94 2.01 830.01
(SUBCONTRATO)
05.11 CISTERNA 29,192.59
05.11.01 CONCRETO PREMEZCLADO CISTERNA f'c=245 kg/cm2 m3 72.00 285.00 20,520.00

05.11.03 ACERO FY= 4200 kg/cm2 GRADO 60 EN CISTERNA kg 4,314.72 2.01 8,672.59
(SUBCONTRATO)

05.12 SUB CONTRATO 130,613.04


05.12.01 SC M. DE O. PARA ACERO CORRUGADO kg 49,662.36 0.85 42,213.01
SC PARA ENCOFRADO METALICO (TODO COSTO) und 1.00 88,400.03 88,400.03

05.13 EQUIPOS 33,964.02


05.13.01 EQUIPOS DE OBRA und 1.00 33,964.02 33,964.02
05.14 VARIOS 57,817.79
05.14.01 ANCLAJES POSTENSADOS TEMPORALES glb 1.00 31,635.29 31,635.29
05.14.02 CAJUELAS DE TECNOPORT 2"x1.22x2.44 m. m 118.92 5.98 711.14
05.14.03 TUBERIA PVC DESAGUE 4" PARA PASES DE ANCLAJES EN und 48.00 7.78 373.44
ENCOFRADOS DE MUROS

05.14.04 LIMPIEZA DE CUÑAS DE VACIADO m 118.92 29.85 3,549.76


05.14.05 ESCALERA METALICA PARA ACCESO PERSONAL mes 3.00 1,100.00 3,300.00

05.14.06 ENCOFRADO MUERTO m2 454.88 28.00 12,736.64


05.14.07 DADOS DE CONCRETO EN ARMADO DE ACERO und 5,500.00 0.45 2,475.00
05.14.08 CURADO DE CONCRETO m2 1,200.00 2.25 2,700.00
05.14.09 TRATAMIENTO UNION MURO/LOSA VIGA ml 18.19 18.50 336.52
05.14.10 TECNOPOR EN VIGA DE CIMENTACION Y SUBZAPATAS m2 0.00

5.15 PAVIMENTO 24,130.45


05.15.01 CONCRETO f'c=175 kg/cm2 EN PAVIMENTOS m3 35.50 269.00 9,549.50
05.15.02 ENCOFRADO Y DESENCOFRADO NORMAL EN PAVIMENTOS m2 29.10 28.00 814.80

05.15.03 JUNTAS DE DILATACION Y CONTRACCION (C/TECNOPOR) EN ml 127.20 14.50 1,844.40


PAVIMENTOS

05.15.04 SELLADO DE JUNTAS (C/ALQUITRAN + ARENA FINA) EN ml 127.20 12.00 1,526.40


PAVIMENTOS

05.15.05 CURADO DE CONCRETO EN PAVIMENTOS m2 915.89 0.85 778.51

05.15.06 ACABADO DE PISO DE PAVIMENTOS CON ALISADORA EN m2 915.89 10.50 9,616.85


SOTANOS

COSTO DIRECTO S/. 914,610.20


GASTOS GENERALES 09.601728% 87,818.38

UTILIDAD 0 %

----------------------------------

SUBTOTAL 1,002,428.59

IMPUESTO(IGV 18%) 180,437.15

=======================

TOTAL PRESUPUESTO
S/. 1,182,865.73

SON: UN MILLON CIENTO OCHENTA Y DOS MIL, OCHOCIENTOS SESENTA Y CINCO Y 73/100 NUEVOS SOLES
Presupuestos por Recursos - Estrcturas Cota + 1.50m

Obra 0103019 EDIFICIO RESIDENCIAL TRIANA (Nivel +1.50) - OPTIMIZADO 23/08/17


Subpresupuesto 001 ESTRUCTURAS
Fecha
Lugar
Código Recurso Unidad Cantidad Precio S/. Parcial S/.

MANO DE OBRA

0101010003 OPERARIO hh 1,584.0000 18.05 28,591.20


OPERARIO ALBAÑIL hh 384.0000 18.05 6,931.20
0101010004 OFICIAL hh 768.0000 14.85 11,404.80
0101010005 PEON hh 6,336.0000 13.32 84,395.52
01010300000004 TOPOGRAFO hh 768.0000 18.05 13,862.40

145,185.12
MATERIALES

0201030001 GASOLINA gal 64.0000 11.87 759.68


02010300010001 GASOLINA 84 OCTANOS gal 0.0000 11.87 0.00
02040100010002 ALAMBRE NEGRO RECOCIDO N° 16 kg 3,000.0000 2.75 8,250.00
ALAMBRE NEGRO RECOCIDO N° 8 kg 600.0000 3.75 2,250.00
0204030001 ACERO CORRUGADO fy = 4200 kg/cm2 kg 49,662.36 2.12 105,284.21
GRADO 60
02041200010001 CLAVOS PARA MADERA CON CABEZA DE kg 21.0000 2.75 57.75
02041200010004 1"
CLAVOS PARA MADERA CON CABEZA DE 2 kg 14.0000 2.75 38.50
02041200010005 1/2"
CLAVOS PARA MADERA CON CABEZA DE kg 15.0000 2.75 41.25
3"
02041200010007 CLAVOS PARA MADERA CON CABEZA DE kg 6.0000 2.75 16.50
0204150003 4"
MALLA TEJIDA OLIMPICA GLAVANIZADA m 75.0000 13.98 1,048.50
a=2.00 m., COCADA 2 1/2" Y ALAMBRE N° 12

02060100010006 TUBERIA PVC-SAL 4" X 3 m und 8.0016 20.50 164.03


0207010006 PIEDRA GRANDE DE 8" m3 114.4410 40.15 4,594.81
0207030001 HORMIGON m3 292.6880 38.14 11,163.12
0207040001 MATERIAL GRANULAR m3 49.9200 33.90 1,692.29
0207070001 AGUA PUESTA EN OBRA m3 410.2091 5.44 2,231.54
02080100010002 TUBERIA PVC-SEL 3/4" X 3 m und 27.0089 2.25 60.77
02080200010002 CURVAS PVC-SEL 3/4" (20 mm) und 39.0000 0.25 9.75
02080300010002 UNIONES PVC-SEL 3/4" (20 mm) und 33.0000 0.23 7.59
02080400010002 CONEXIONES PVC-SEL 3/4" (20 mm) und 41.0000 0.34 13.94
0210030001 MALLA CERCADORA NARANJA rll 8.0000 33.90 271.20
02100400010005 TECNOPOR DE 2.40 x 1.20 x 2" pln 80.0000 24.58 1,966.40
0210110001 TECHO FLEXIFORTE ROJO 3.05m.x1.10 m., und 7.0000 31.27 218.89
0213010001 E=1.2 mm. PORTLAND TIPO I (42.5 kg)
CEMENTO bol 2,272.0000 15.64 35,524.07
0217030001 VENTANA DE ALUMINIO SISTEMA NOVA und 0.0000 195.25 0.00
CON CRISTAL CRUDO 6mm.

02190100010010 CONCRETO PREMEZCLADO F'C=210 kg/cm2 m3 6.2759 215.00 1,349.31


02190100010011 CONCRETO PREMEZCLADO F'C=210 m3 287.5600 209.00 60,100.04
02190100010016 kg/cm2,
CONCRETOP57, PREMEZCLADO
S46 F'C=245 m3 72.0000 225.00 16,200.00
kg/cm2, P67, PREMEZCLADO
02190100010024 CONCRETO S46 F'C=245 m3 176.4500 225.00 39,701.25
02190100010025 kg/cm2,
CONCRETOP67, PREMEZCLADO
S46 F'C=280 m3 80.7500 238.00 19,218.50
kg/cm2, P67,
02190500010001 SERVICIO DES46
BOMBA PARA CONCRETO m3 630.0000 30.00 18,900.00
0222080012 PREMEZCLADO
PEGAMENTO PARA PVC 1 GLN gal 5.0000 150.00 750.00
0231010001 MADERA TORNILLO p2 1,288.6600 4.50 5,798.97
02310500010006 TRIPLAY DE 1.20X2.40 m X 4 mm und 10.0000 21.95 219.50
0231130002 MADERA CACHIMBO 4"x4"x10' und 18.0000 56.00 1,008.00
0231130003 MADERA CACHIMBO 3"x4"x8' und 9.0000 33.60 302.40
0231130004 MADERA CACHIMBO 2"x4"x10' und 7.0000 28.00 196.00
0231130005 MADERA CACHIMBO 1"x2"x10' und 12.0000 7.00 84.00
0231130006 MADERA CACHIMBO 1"x2"x8' und 12.0000 5.60 67.20
0231130007 MADERA CACHIMBO 1 1/2"x8"x10' und 42.0000 30.51 1,281.42
0231130008 MADERA CACHIMBO 2"x2"x10' und 28.0000 10.17 284.76
0231130009 MADERA CACHIMBO 2"x2"x8' und 26.0000 11.20 291.20
0231130010 MADERA CACHIMBO 1 1/2"x10"x10' und 16.0000 52.50 840.00
0231190002 MADERA PINO 1"x8"x10' und 8.0000 23.65 189.20
0231190003 MADERA PINO 2"x2"x8' und 58.0000 9.33 541.14
0231190004 MADERA PINO 1"x2"x8' und 9.0000 4.49 40.41
0231190005 MADERA PINO 2"x3"x10' und 50.0000 21.00 1,050.00
0231220002 PUERTA MDF 90x207cm. + MARCO DE PINO und 2.0000 182.20 364.40
33x60x213 cm. + CERRADURA BLINDADA +
BISAGRA CAPUCHINA 3"x3"
0231220003 PUERTA MDF 65x207cm. + MARCO DE PINO und 2.0000 156.78 313.56
33x60x213 cm. + CERRADURA BLINDADA +
BISAGRA CAPUCHINA 3"x3"
0231220004 PANEL OSB 9MM 1.22x2.44M und 53.0000 33.48 1,774.44
0237030001 CERRADURA PARA PUERTA PRINCIPAL und 1.0000 40.68 40.68
0237080001 CERRADURA PARA PUERTA INTERIOR und 2.0000 15.25 30.50
02410200010001 CINTA AISLANTE 3M rll 1.8000 5.00 9.00
02620500040008 INTERRUPTOR DOBLE DOMINO und 4.0000 11.90 47.60
02620500060009 INTERRUPTOR UNIPOLAR SIMPLE DOMINO und 1.0000 7.55 7.55
02621300010006 TOMACORRIENTE BIPOLAR DOBLE und 5.2500 12.50 65.63
DOMINOTIPO JOCKEY NARANJA
02670100010005 CASCO und 30.0000 12.71 381.30
0267010003 BARBIQUEJO und 60.0000 1.69 101.40
0267020001 LENTES DE POLICARBONATO LUNA CLARA und 180.0000 2.97 534.60
0267030008 PROTECTOR DE OIDOS TIPO TAPON und 180.0000 1.69 304.20
0267040007 RESPIRADORES DESCARTABLES und 360.0000 4.24 1,526.40
0267050001 GUANTES DE CUERO par 30.0000 8.65 259.50
0267050004 GUANTES DE NITRILO par 300.0000 6.19 1,857.00
0267050006 GUANTES DE JEBE par 30.0000 11.70 351.00
02670600060005 PANTALON DRILL AZUL und 60.0000 16.10 966.00
0267060012 POLOS und 150.0000 9.33 1,399.50
0267070001 BOTINES DE CUERO CON PUNTA DE par 90.0000 36.00 3,240.00
0267070006 ACERO DE JEBE CON PUNTA
BOTINES par 30.0000 21.20 636.00
0267080002 REFORZADA
ARNES CON TRES ANILLO und 30.0000 212.00 6,360.00
0267080007 SOGA DE NYLON 3/4" m 150.0000 1.90 285.00
0267100012 MANTA ARPILLERA ANCHO= 2.00 m. m 75.0000 1.60 120.00
0267110001 CINTA DE SEÑALIZACION und 8.0000 55.00 440.00
0267110004 SEÑALES DE OBLIGACION, PREVENCION, und 100.0000 2.55 255.00
PROHIBICION E INFORMACION SURTIDA

02671100040002 SEÑALES REGLAMENTARIAS 75 X 75 cm und 16.0000 20.00 320.00


0267110022 CACHACO DE CONCRETO und 20.0000 15.00 300.00
0267110023 BALAUSTRES DE METAL und 50.0000 2.75 137.50
0267110024 SARGENTOS DE METAL und 8.0000 12.85 102.80
0267110025 CASQUETE DE PVC PARA BALAUSTRES und 150.0000 1.44 216.00
0267110026 CASQUILLOS DE PVC PARA SEGURIDAD und 1,000.0000 0.43 430.00
02680500010001 CAJA DE PASE OCTOGONAL SEL 100 X 55 und 8.0000 1.50 12.00
0268060001 mm
CAJA RECTANGULAR PVC und 8.0000 1.50 12.00
02681200010002 CAJA DE PASE CUADRADA DE FIERRO und 2.5000 4.50 11.25
GALVANIZADO DE 100x100x50 mm

02683000010001 TAPA 1 GANG und 2.5000 4.50 11.25


0270010080 CABLE TW 2.5 mm2 m 157.0000 1.00 157.00
0270010083 CABLE TW 4 mm2 m 80.0000 1.50 120.00
0293010002 SISTEMA LOSA ALIGERADA ALITEC h = 20 m2 882.4900 40.88 36,071.78
cm.
64%

403,649.92
EQUIPOS

0301000012 EQUIPO TOGRAFICO mes 4.5000 1,255.00 5,647.50

0301010006 HERRAMIENTAS MANUALES %mo 1,627.74

03010600020008 REGLA DE MADERA PINO 2" X 4" X 10' und 16.5120 19.78 326.61
0301100003 COMPACTADORA DE PLANCHA día 2.1350 155.60 332.21
0301140009 MARTILLO ELECTRICO día 135.0000 58.50 7,897.50
03012900010002 VIBRADOR DE CONCRETO 4 HP 1.25" hm 86.6720 7.40 641.37
03012900030001 MEZCLADORA DE CONCRETO 11 P3 (23 HP) hm 115.7419 27.14 3,141.24
0301340001 ANDAMIO METALICO día 60.0000 8.65 519.00
03013800010006 PUNTAS PARA MARTILLO HILTI und 16.0000 80.00 1,280.00
WINCHE DE 5.5 HP CIMAX und 1.0000 2,669.49 2,669.49
LAPTOP LEVONO CORE I5 8 GB 1 TB 15'6 " und 2.0000 3,203.40 6,406.80
LAPTOP HP CORE I3 4 GB 1 TB 15'6 " und 2.0000 1,118.64 2,237.28
IMPRESORA MULTIFUNCIONAL HP CON und 1.0000 576.27 576.27
WIFI
TALADRO PERCU GSB 16 und 1.0000 228.73 0.00
AMOLADORA 4" und 1.0000 203.39 203.39
AMOLADORA 4" und 1.0000 457.63 457.63
33,964.02
SUBCONTRATOS

SC PARA ENCOFRADO MUROS ANCLADOS glb 1.0000 31,849.54 31,849.54


(Todo
SC costo)
PARA ENCOFRADO CIMENT Y SÓTS glb 1.0000 56,550.49 56,550.49
SC M. DE O. PARA ACERO muro anclado kg 17,861.50 0.85 15,182.28
SC M. DE O. PARA ACERO casco +1.50 kg 29,574.61 0.85 25,138.42
0401010001 SC DEMOLICION Y ELIMINACION glb 1.0000 21,186.44 21,186.44
0402010003 SC CERCO METALICO DE OBRA DE 2.50 m. glb 1.0000 3,971.19 3,971.19
0402010003 DE
SC LATURA
CERCO Malla Rachell m 60.0000 67.80 4,068.00
SC SUMINISTRO E INSTALACION DE glb 1.0000 906.78 906.78
BARANDAS CONHOJA
SC CONVERTIR TUBOFIJA
REDONDO
A HOJA glb 1.0000 211.86 211.86
CORREDIZA
SC EXAMENES MEDICOS OCUPACIONALES glb 1.0000 540.00 540.00
SC TOPOGRAFIA TRAZO Y REPLANTEO glb 1.0000 1,625.00 1,625.00
SC TOPOGRAFIA TRAZOS MURO glb 1.0000 450.00 450.00
PANTALLA
SC INSTALACIONES ELECTRICAS glb 1.0000 530.00 530.00
PROVISIONALES
SC FUMIGACION glb 1.0000 500.00 500.00
0402020003 SC SERVICIOS HIGIENICOS PORTATILES mes 12.0000 271.18 3,254.16
0403010003 SC EXCAVACION MASIVA m3 2,900.0000 24.00 69,600.00
0403020001 SC RELLENO CON MATERIAL GRANULAR hm 306.0000 170.00 52,020.00
PARA ENCOFRADO MUROS ANCLADOS

0403030001 SC ELIMINACION DE MATERIAL m3 151.0500 29.66 4,480.14


0405020022 EXCEDENTE CONMUERTO
SC ENCOFRADO VOLQUETES m2 88.5000 28.00 2,478.00
0411040007 SC ESCALERA METALICA PARA ACCESO mes 3.0000 1,020.28 3,060.84
0416010005 PERSONAL
SC CONSUMO EN KWH Kwh 4,250.0000 0.50 2,125.00
0430010001 SC ANCLAJES POSTENSADOS glb 1.0000 32,083.00 32,083.00
TEMPORALES

331,811.14

Total Costo Directo Sin IGV S/.


914,610.20
RESUM
ESTRUCTURA CIM SOT2 SOT1
CIMENT MURO 1,287.20
ZAPATAS 3,320.41
VIGA-CIMENTA 216.77
CISTERNA 4,608.66
COLUMNAS 1,835.27 1,406.67
PLACAS 1,086.45 842.10
VIGAS 1,760.99 2,560.05
ALIGERADA 436.18 673.90
MACIZA 557.42 557.42
ESCALERAS 137.65 137.65
9,433.04 5,813.96 6,177.78

TOTAL ACERO CASCO 115,054.92 kg


MURO PANTALLA 18,120.51 kg
TOTAL ACERO TRIANA 133,175.43 kg

ADICIONAL -1 . PUNTO ANCLAJE 1975.06 kg


ADICIONAL -2. LOSAS Y POZOS SOTANO 4789.2452 kg
ADICIONAL -3. MUROS M-6/ M-7 2822.9845 kg

TOTAL ACERO FINAL 142,762.72 kg

137323.613
47436.11
89887.503
RESUMEN
SS PISO 1 PISO 2 PISO 3 PISO 4 PISO 5 PISO 6 PISO 7

1,449.02 1,111.22 1,111.22 1,111.22 1,111.22 1,111.22 1,111.22 1,111.22


4,975.11 5,506.70 5,506.70 5,506.70 5,506.70 5,506.70 5,506.70 5,467.02
2,499.85 3,279.97 3,387.12 3,404.51 3,404.51 3,404.51 3,404.51 3,347.05
696.29 520.98 520.98 520.98 520.98 520.98 520.98 515.22
557.42 354.62 354.62 354.62 354.62 354.62 354.62 1,199.21
137.65 137.65 137.65 137.65 137.65 137.65 137.65 412.94
10,315.35 10,911.14 11,018.29 11,035.68 11,035.68 11,035.68 11,035.68 12,052.66

49,860.64

ACERO SOTANOS COTA +1.50 47436.11 kg


ACERO CASCO CASCO 95,326.61 kg
AZOTEA
1,287.20
3,320.41
216.77
4,608.66
833.41 13,302.92
2,483.73 47,894.58
1,422.13 31,875.21
66.40 5,513.90
384.30 5,383.50
1,651.78
5,189.97 115,054.92
Resumen de Concreto de toda la Torre (8 pis
Descripcion Unidad Tipo de Concreto 1° Piso 2° Piso 3° Piso 4° Piso
Columnas m3 245#67B 4.80 4.80 4.80 4.80
Placas m3 245#67B 24.93 24.93 24.93 24.93
Vigas m3 210#57B 29.48 29.48 29.48 29.48
Losa Aligera m3 210#57B 18.02 18.02 18.02 18.02
Losa Maciza m3 210#57B 6.00 6.00 6.00 6.00
Escalera m3 210#57B 2.00 2.00 2.00 2.00

Total 210#57 460.00


Total 245#67 255.00
toda la Torre (8 pisos)
5° Piso 6° Piso 7° Piso Azotea Total
4.80 4.80 4.80 3.60 37.20
24.93 24.93 24.93 14.14 188.65
29.48 29.48 29.48 18.82 225.18
18.02 18.02 13.47 4.47 126.06
6.00 6.00 6.00 6.00 48.00
2.00 2.00 2.00 2.00 16.00