V A L O R I Z A C I O N No. 02
:
"MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y
PEATONAL EN LA AV. ALAMEDA TRAMO: JR. BOLIVIA - AV.
O B R A
CENTENARIO, DISTRITO DE SAN JERONIMO DE TUNAN, HUANCAYO -
JUNIN"
NOVIEMBRE 2017
FICHA TECNICA DEL PROYECTO
MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y
1 OBRA : PEATONAL EN LA AVENIDA ALAMEDA TRAMO: JR. BOLIVIA - AV.
CENTENARIO, DIST SAN JERONIMO DE TUNAN, HUANCAYO - JUNIN
2 UBICACIÓN
DEPARTAMENTO : Junin
PROVINCIA : Huancayo
DISTRITO : San Jeronimo de Tunan
3 ENTIDAD EJECUTANTE : Municipalidad Provincial de Huancayo
4 ENTIDAD QUE FINANCIA : Municipalidad Provincial de Huancayo
5 CÓDIGO DE PROYECTO : 188773
6 DEL PERFIL
6.01 SNIP : 188773
6.02 RESPONSABLE DE FORMULAR : Econ. JUAN ANTONIO TOMAS ADAUTO
6.03 RESPONSABLE APROBAR VIABILIDAD : Econ. FICOL B. LAZARO PECHO
6.04 MONTO PRESUPUESTO TOTAL : S/. 3,687,501.11
6.05 MONTO ASIGNADO : S/. 967,602.15
6.06 FECHA DE DECLARATORIA DE LA VIABILID : 16-Feb-17
6.07 COMPONENTES DEL PROYECTO DE INVERSION PUBLICA
EXPEDIENTE TECNICO : S/. 167,056.00
COSTO DIRECTO : S/. 4,366,846.00
GASTOS GENERALES ( 06 % ) : S/. 167,056.00
SUPERVISION ( 03 % ) : S/. 167,057.00
IGV ( 18 % ) : S/. 0.00
UTILIDAD : S/. 0.00
COSTO TOTAL : S/. 4,868,015.00
PLAZO DE EJECUCION DEL PROYECTO : 210 d.c.
6.08 METAS DEL PROYECTO DE INVERSION PUBLICA
●CONSTRUCCIÓN DE LA CALZADA VEHICULAR CON PAVIMENTO RÍGIDO●CONSTRUIRÁN CUENTAS ●SE CONSTRUIRÁN VEREDAS
PARA EL TRÁNSITO PEATONAL ●SARDINELES
6.09 REGISTRO DE VARIACIONES EN LA FASE DE INVERSION - OPI/DGPM
FORMATO SNIP - 16 : 25-Sep-17
DOCUMENTO SUSTENTO : OFICIO N° 082-2017-MPH/GOP-AEP
8 DE LA ENTIDAD
8.01 SUPERVISOR DE OBRA : ING. YUDITH BACA ARANA
8.02 RESIDENTE DE OBRA : ING. MARIA MILAGROS GAMARRA CENZANO
8.03 PLAZO DE EJECUCION DE OBRA : 135 DC 4-Oct-17
8.04 MODALIDAD DE EJECUCION : ADMINISTRACION DIRECTA
8.05 TOTAL PRESUPUESTO : S/. 3,687,501.11 Inc/I.G.V.
8.06 PRESUPUESTO ASIGNADO : S/. 967,602.15 Inc/I.G.V.
8.07 ENTREGA DE TERRENO : 4-Oct-17
8.08 INICIO DEL PLAZO CONTRACTUAL : 4-Oct-17
8.09 TERMINO DEL PLAZO CONTRACTUAL : 15-Feb-18
ENTIDAD: MUNICIPALIDAD PROVINCIAL DE HUANCAYO
"MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA AV. ALAMEDA TRAMO: JR. BOLIVIA - AV. CENTENARIO, DISTRITO DE SAN JERONIMO DE TUNAN, HUANCAYO -
OBRA:
JUNIN"
MONTO ASIGNADO 967,602.15
MODALIDAD: ADMINISTRACION DIRECTA FECHA INICIO OBRA 4-Oct-17
SUPERVISOR: ING. YUDITH BACA ARANA MONTO TOTAL 3,687,501.11
RESIDENTE: ING. MARIA MILAGROS GAMARRA CENZANO
RESUMEN DE VALORIZACION N° 02
NOVIEMBRE 2017
1..00 VALORIZACION NOVIEMBRE 879,112.78 126,944.52 14.44% 73,544.77 8.37% 200,489.29 22.81% 678,623.49 77.19%
O B R A "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA AV. ALAMEDA TRAMO: JR. BOLIVIA - AV. CENTENARIO, DISTRITO DE SAN JERONIMO DE TUNAN, HUANCAYO - JUNIN" Inspector ING. YUDITH BACA ARANA
ING. MARIA GAMARRA CENZANO
CONTRATISTA ADMINISTRACION DIRECTA Residente:
ENTIDAD MUNICIPALIDAD PROVINCIAL DE HUANCAYO F.Inicio: 04 de Octubre del 2017
F. Termino: 30 de Abril 2018
PRESUPUESTO AVANCE FISICO
Partida Descripción UND. VAL. ANTERIOR VAL. ACTUAL VAL. ACUMULADO SALDO DE VAL.
METRADO P.U. (S/.) Parcial (S/.) Metr. % Metr. % Metr. S/. %
Metr. S/. % S/. S/.
01.01.04 MOVILIZACION Y DESMOVILIZACION EQUIPO GLB 0.50 5,892.54 2,946.27 0.50 2,946.27 100.00% 0.00 - 0.00% 0.50 2,946.27 100.00% - - 0.00%
01.02 TRABAJOS PRELIMINARES
01.02.01 LIMPIEZA DEL TERRENO M2 3,644.78 0.53 1,931.73 0.00 - 0.00% 0.00 - 0.00% - - 0.00% 3,644.78 1,931.73 100.00%
01.02.02 LIMPIEZA Y DEFORESTACION HA 0.12 3,834.60 444.81 0.00 - 0.00% 0.00 - 0.00% - - 0.00% 0.12 444.81 100.00%
01.02.03 TRAZO, NIVELES Y REPLANTEO M2 3,810.16 0.70 2,667.11 3600.00 2,520.00 94.48% 0.00 - 0.00% 3,600.00 2,520.00 94.48% 210.16 147.11 5.52%
01.02.04
TRAZO Y REPLANTEO DURANTE LA
M2 3,810.16 0.98 3,733.96 2925.59 2,867.08 76.78% 0.00 - 0.00% 2,925.59 2,867.08 76.78% 884.57 866.88 23.22%
EJECUCION DE OBRA
01.02.05 DEMOLICION DE ALCANTARILLAS M3 6.80 45.58 309.94 6.80 309.94 100.00% 0.00 - 0.00% 6.80 309.94 100.00% - - 0.00%
01.03 MOVIMIENTO DE TIERRAS
01.03.01
CORTE DE TERRENO A NIVEL DE SUB
M3 2,479.36 12.11 30,025.05 2494.17 30,204.40 100.60% 0.00 - 0.00% 2,494.17 30,204.40 100.00% - - 0.00%
RASANTE
01.03.02
CORTE DE TERRENO A NIVEL DE MEJ. SUB
M3 673.20 12.11 8,152.45 658.39 7,973.10 97.80% 0.00 - 0.00% 658.39 7,973.10 97.80% 14.81 179.35 2.20%
RASANTE
01.03.03 EXCAVACION MANUAL M3 106.25 34.41 3,656.06 219.36 7,548.18 206.46% 0.00 - 100.00% 219.36 7,548.18 100.00% - - 0.00%
01.03.04 EXCAVACION MANUAL EN CUNETA M3 15.76 34.41 542.30 10.10 347.54 64.09% 0.00 - 0.00% 10.10 347.54 64.09% 5.66 194.76 35.91%
01.03.05 EXCAVACION MANUAL P/BADEN M3 9.96 34.41 342.72 3.84 132.13 38.55% 0.00 - 0.00% 3.84 132.13 38.55% 6.12 210.59 61.45%
01.03.06 ELIMINACION DE MATERIAL EXCEDENTE
01.03.06.01 ACARREO INTERNO DE MATERIAL M3 164.96 17.21 2,838.96 156.45 2,692.50 94.84% 0.00 - 0.00% 156.45 2,692.50 94.84% 8.51 146.46 5.16%
01.03.06.02 CARGUIO DE MATERIAL EXCEDENTE M3 3,618.00 6.19 22,395.42 3618.00 22,395.42 100.00% 0.00 - 0.00% 3,618.00 22,395.42 100.00% - - 0.00%
01.03.06.03
TRANSPORTE (ELIM DE MATERIAL
M3 3,618.00 18.07 65,377.26 3618.00 65,377.26 100.00% 0.00 - 0.00% 3,618.00 65,377.26 100.00% - - 0.00%
EXCEDENTE)
01.04 EXPLANACIONES
01.04.01
ESCARIFICADO, PERFIL Y COMP. DE
M2 3,305.00 3.81 12,592.05 3359.40 12,799.31 101.65% 0.00 - 0.00% 3,359.40 12,799.31 100.00% - - 0.00%
SUBRASANTE
01.05 OBRAS DE CONCRETO SIMPLE
01.05.01 DRENAJE
01.05.01.01
DRENAJE CUNETA ENCOFRADO Y
M2 201.68 32.93 6,641.32 75.78 2,495.44 37.57% 0.00 - 0.00% 75.78 2,495.44 37.57% 125.90 4,145.89 62.43%
DESENCOFRADO
01.05.01.02 DRENAJE CUNETA CONCRETO FC=210 KG/CM2 M3 64.60 414.78 26,794.79 26.14 10,842.35 40.46% 0.00 - 0.00% 26.14 10,842.35 40.46% 38.46 15,952.44 59.54%
01.05.02 BADEN
01.05.02.01 BADENES ENCOF Y DESENCOFRADO M2 79.67 31.75 2,529.52 30.39 964.88 38.14% 0.00 - 0.00% 30.39 964.88 38.14% 49.28 1,564.64 61.86%
01.05.02.02 BADENES CONCRETO FC=210 KG/CM2 M3 29.88 414.78 12,393.63 9.53 3,952.85 31.89% 0.00 - 0.00% 9.53 3,952.85 31.89% 20.35 8,440.77 68.11%
01.05.02.03 CURADO CON ARROCERAS EN BADEN M2 99.60 3.54 352.58 0.00 - 0.00% 0.00 - 0.00% - - 0.00% 99.60 352.58 100.00%
01.05.03 BOCACALLE DE CONCRETO
01.05.03.01 COMPACTACION DE BASE DE BOCACALLE M2 399.39 3.79 1,513.69 220.42 835.39 55.19% 0.00 - 0.00% 220.42 835.39 55.19% 178.97 678.30 44.81%
01.05.03.02 BOCACALLE ENCOF Y DESENCOFRADO M2 76.88 31.75 2,440.94 36.09 1,145.86 46.94% 0.00 - 0.00% 36.09 1,145.86 46.94% 40.79 1,295.08 53.06%
01.05.03.03 BOCACALLE CONCRETO FC=210 KG/CM2 M3 68.00 414.78 28,205.04 45.61 18,918.12 67.07% 0.00 - 0.00% 45.61 18,918.12 67.07% 22.39 9,286.92 32.93%
01.05.03.04
CURADO CON ARROCERAS EN
M2 399.39 3.54 1,413.84 227.92 806.84 57.07% 0.00 - 0.00% 227.92 806.84 57.07% 171.47 607.00 42.93%
ESTACIONAMIENTO
01.05.04 ESTACIONAMIENTOS
01.05.04.01
ESTACIONAMIENTO ENCOF Y
M2 135.14 31.75 4,290.70 0.00 - 0.00% 0.00 - 0.00% - - 0.00% 135.14 4,290.70 100.00%
DESENCOFRADO
01.05.04.02
ESTACIONAMIENTO CONCRETO FC=210
M3 107.09 414.78 44,418.79 0.00 - 0.00% 0.00 - 0.00% - - 0.00% 107.09 44,418.79 100.00%
KG/CM2
01.05.04.03
CURADO CON ARROCERAS EN
M2 535.46 3.54 1,895.53 0.00 - 0.00% 0.00 - 0.00% - - 0.00% 535.46 1,895.53 100.00%
ESTACIONAMIENTO
01.06 OBRAS DE CONCRETO ARMADO
01.06.01 ALCANTARILLA CAJON
01.06.01.01 TRAZO, NIVELES Y REPLANTEO M2 35.40 0.7 24.78 39.60 27.72 111.86% 0.00 - 0.00% 39.60 27.72 100.00% - - 0.00%
01.06.01.02 EXCAVACION MANUAL M3 28.35 34.41 975.52 28.35 975.52 100.00% 0.00 - 0.00% 28.35 975.52 100.00% - - 0.00%
01.06.01.03 SOLADO DE CONCRETO E=4" M3 3.54 275.39 974.88 3.54 974.88 100.00% 0.00 - 0.00% 3.54 974.88 100.00% - - 0.00%
01.06.01.04
ACERO CORRUGADO FY=4200KG/CM2 GRADO
KG 1,936.00 4.88 9,447.68 1959.27 9,561.24 101.20% 0.00 - 0.00% 1,959.27 9,561.24 100.00% - - 0.00%
60
VALORIZACION Nº 07 - MONTO ASIGNADO
DEL 01 - 30 DE ABRIL 2018
O B R A "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA AV. ALAMEDA TRAMO: JR. BOLIVIA - AV. CENTENARIO, DISTRITO DE SAN JERONIMO DE TUNAN, HUANCAYO - JUNIN" Inspector ING. YUDITH BACA ARANA
ING. MARIA GAMARRA CENZANO
CONTRATISTA ADMINISTRACION DIRECTA Residente:
ENTIDAD MUNICIPALIDAD PROVINCIAL DE HUANCAYO F.Inicio: 04 de Octubre del 2017
F. Termino: 30 de Abril 2018
PRESUPUESTO AVANCE FISICO
Partida Descripción UND. VAL. ANTERIOR VAL. ACTUAL VAL. ACUMULADO SALDO DE VAL.
METRADO P.U. (S/.) Parcial (S/.) Metr. % Metr. % Metr. S/. %
Metr. S/. % S/. S/.
01.06.01.05 ENCOFRADO DE ELEVACIONES M2 62.76 82.67 5,188.37 62.22 5,143.73 99.14% 0.00 - 0.00% 62.22 5,143.73 99.14% 0.54 44.64 0.86%
01.06.01.06 CONCRETO FC=280 KG/CM2 M3 22.28 489.98 10,916.75 25.35 12,420.99 113.78% 0.00 - 0.00% 25.35 12,420.99 100.00% - - 0.00%
01.06.01.07 JUNTAS WATER STOP M 85.80 19.22 1,649.08 68.40 1,314.65 79.72% 0.00 - 0.00% 68.40 1,314.65 79.72% 17.40 334.43 20.28%
01.06.01.08 CURADO M2 62.76 2.04 128.03 463.20 944.93 738.05% 0.00 - 100.00% 463.20 944.93 100.00% - - 0.00%
01.06.01.09 JUNTA ASFALTICA M 9.00 4.25 38.25 0.00 - 0.00% 0.00 - 0.00% - - 0.00% 9.00 38.25 100.00%
01.07 PAVIMENTOS
01.07.01 MEJORAMIENTO DE SUBRASANTE
01.07.01.01 MATERIAL P/MEJ DE SUB RASANTE M3 480.00 37.5 18,000.00 870.76 32,653.50 181.41% 0.00 - 100.00% 870.76 32,653.50 100.00% - - 0.00%
01.07.01.02
EXTENDIDO/RIEGO/COMP DE SUB BASE
M3 480.00 24.02 11,529.60 731.96 17,581.68 152.49% 0.00 - 100.00% 731.96 17,581.68 100.00% - - 0.00%
E=0.15M
01.07.02 SUB BASE GRANULAR
01.07.02.01 MATERIAL PARA SUB BASE M3 605.19 43.75 26,477.10 832.62 36,427.13 137.58% 0.00 - 0.00% 832.62 36,427.13 100.00% - - 0.00%
01.07.02.02
EXTENDIDO/RIEGO/COMP DE SUB BASE
M2 2,880.00 3.63 10,454.40 3523.19 12,789.18 122.33% 0.00 - 0.00% 3,523.19 12,789.18 100.00% - - 0.00%
E=0.20M
01.07.03 PAVIMENTO RIGIDO
01.07.03.01
ENCOFRADO Y DESENCOFRADO EN LOSAS DE
M2 211.12 38.24 8,073.23 101.24 3,871.42 47.95% 40.95 1,565.93 19.40% 142.19 5,437.35 67.35% 68.93 2,635.88 32.65%
CONCRETO
01.07.03.02 LOSA CONCRETO FC=280 KG/CM2 E=0.20M M3 504.00 489.98 246,949.92 338.58 165,897.43 67.18% 117.93 57,783.34 23.40% 456.51 223,680.77 90.58% 47.49 23,269.15 9.42%
01.07.03.03 ACABADO EN LOSAS DE CONCRETO M2 2,520.00 14.56 36,691.20 1666.44 24,263.37 66.13% 589.68 8,585.74 23.40% 2,256.12 32,849.11 89.53% 263.88 3,842.09 10.47%
01.07.03.04 CURADO CON ARROCERAS M2 2,520.00 3.54 8,920.80 1443.60 5,110.34 57.29% 589.68 2,087.47 23.40% 2,033.28 7,197.81 80.69% 486.72 1,722.99 19.31%
01.07.03.05
JUNTAS DE CONTRACCION PASADORES
UND 1,992.00 4.28 8,525.76 692.00 2,961.76 34.74% 468.00 2,003.04 23.49% 1,160.00 4,964.80 58.23% 832.00 3,560.96 41.77%
CORRUGADAS
01.07.03.06
JUNTAS LONGITUDINALES (BARRAS DE
UND 460.00 7.61 3,500.60 197.00 1,499.17 42.83% 135.00 1,027.35 29.35% 332.00 2,526.52 72.17% 128.00 974.08 27.83%
AMARRE)
01.08 JUNTAS
01.08.01 JUNTAS DE DILATACION M 1,495.31 4.25 6,355.07 0.00 - 0.00% 0.00 - 0.00% - - 0.00% 1,495.31 6,355.07 100.00%
01.09 SEÑALIZACIONES HORIZONTALES
01.09.01 PINTURA LINEAL EN SARDINEL M 350.00 10.09 3,531.50 0.00 - 0.00% 0.00 - 0.00% - - 0.00% 350.00 3,531.50 100.00%
01.09.02
PINTURA INTERMEDIA CONTINUA CENTRO DE
M 297.76 5.3 1,578.13 0.00 - 0.00% 0.00 - 0.00% - - 0.00% 297.76 1,578.13 100.00%
VIA
01.09.03 PINTURA DE SIMBOLOS - FLECHAS M2 15.52 23.13 358.98 0.00 - 0.00% 0.00 - 0.00% - - 0.00% 15.52 358.98 100.00%
01.09.04 PINTURA ZONAL CRUCE PEATONAL M2 98.40 23.44 2,306.50 0.00 - 0.00% 0.00 - 0.00% - - 0.00% 98.40 2,306.50 100.00%
01.11 ENSAYOS Y PRUEBAS DE LABORATORIO
01.11.01 ENSAYO DE DENSIDAD DE CAMPO UND 20.00 30 600.00 24.00 720.00 120.00% 0.00 - 0.00% 24.00 720.00 100.00% - - 0.00%
01.11.02
ENSAYO DE COMPACTACION DE SUELOS
UND 2.00 120 240.00 2.00 240.00 100.00% 0.00 - 0.00% 2.00 240.00 100.00% - - 0.00%
(PROCTOR MODIFICADO)
01.11.03 DISEÑO DE MEZCLAS DE CONCRETO UND 3.00 350 1,050.00 3.00 1,050.00 100.00% 0.00 - 0.00% 3.00 1,050.00 100.00% - - 0.00%
01.11.04 ENSAYO DE RESISTENCIA A LA COMPRESION UND 12.00 25 300.00 9.00 225.00 75.00% 0.00 - 0.00% 9.00 225.00 75.00% 3.00 75.00 25.00%
01.12.01 COSTOS AMBIENTALES GLB 0.50 500 250.00 0.00 - 0.00% 0.00 - 0.00% - - 0.00% 0.50 250.00 100.00%
01.14 VARIOS
01.14.01 RECONEXION DE PUNTOS DE AGUA PTO 18.00 39.68 714.24 16.00 634.88 88.89% 0.00 - 0.00% 16.00 634.88 88.89% 2.00 79.36 11.11%
01.14.02 RECONEXION DE CAJA MEDIDOR DE AGUA UND 18.00 49.18 885.24 0.00 - 0.00% 0.00 - 0.00% - - 0.00% 18.00 885.24 100.00%
01.14.03 RECONEXION DE PUNTOS DE DESAGUE PTO 18.00 180.91 3,256.38 12.00 2,170.92 66.67% 0.00 - 0.00% 12.00 2,170.92 66.67% 6.00 1,085.46 33.33%
01.14.04
RECONEXION DE CAJA DE REGISTRO DE
UND 18.00 69.18 1,245.24 0.00 - 0.00% 0.00 - 0.00% - - 0.00% 18.00 1,245.24 100.00%
DESAGUE
01.14.05 ENCIMADO DE BUZONES UND 4.00 613.47 2,453.88 4.00 2,453.88 100.00% 0.00 - 0.00% 4.00 2,453.88 100.00% - - 0.00%
01.14.06 ALINEAMIENTO DE POSTES DE LUZ UND 3.00 1800 5,400.00 0.00 - 0.00% 0.00 - 0.00% - - 0.00% 3.00 5,400.00 100.00%
01.14.08 PLACA RECORDATORIA UND 1.00 337.79 337.79 0.00 - 0.00% 0.00 - 0.00% - - 0.00% 1.00 337.79 100.00%
01.14.09 LIMPIEZA FINAL DE OBRA M2 4,769.22 0.53 2,527.69 0.00 - 0.00% 0.00 - 0.00% - - 0.00% 4,769.22 2,527.69 100.00%
02 ACERA PEATONAL 141,392.65
02 ACERA PEATONAL
02.01 TRABAJOS PRELIMINARES
02.01.01 LIMPIEZA DEL TERRENO M2 241.85 0.53 128.18 0.00 - 0.00% 0.00 - 0.00% - - 0.00% 241.85 128.18 100.00%
02.01.02 TRAZO, NIVELES Y REPLANTEO DE VEREDAS M2 241.85 0.70 169.30 0.00 - 0.00% 0.00 - 0.00% - - 0.00% 241.85 169.30 100.00%
02.01.03
TRAZO Y REPLANTEO DURANTE LA
M2 241.85 0.98 237.01 43.26 42.39 17.89% 0.00 - 0.00% 43.26 42.39 17.89% 198.59 194.62 82.11%
EJECUCION DE OBRA
02.01.04 DEMOLICION DE VEREDAS EXISTENTES M3 12.52 192.82 2,414.11 12.52 2,414.11 100.00% 0.00 - 0.00% 12.52 2,414.11 100.00% -
VALORIZACION Nº 07 - MONTO ASIGNADO
DEL 01 - 30 DE ABRIL 2018
O B R A "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA AV. ALAMEDA TRAMO: JR. BOLIVIA - AV. CENTENARIO, DISTRITO DE SAN JERONIMO DE TUNAN, HUANCAYO - JUNIN" Inspector ING. YUDITH BACA ARANA
ING. MARIA GAMARRA CENZANO
CONTRATISTA ADMINISTRACION DIRECTA Residente:
ENTIDAD MUNICIPALIDAD PROVINCIAL DE HUANCAYO F.Inicio: 04 de Octubre del 2017
F. Termino: 30 de Abril 2018
PRESUPUESTO AVANCE FISICO
Partida Descripción UND. VAL. ANTERIOR VAL. ACTUAL VAL. ACUMULADO SALDO DE VAL.
METRADO P.U. (S/.) Parcial (S/.) Metr. % Metr. % Metr. S/. %
Metr. S/. % S/. S/.
02.01.05 DEMOLICION DE SARDINEL EXISTENTES M3 5.15 172.08 886.21 1.35 232.31 26.21% 0.00 - 0.00% 1.35 232.31 26.21% 3.80 653.90 73.79%
02.02 MOVIMIENTO DE TIERRAS
02.02.01 EXCAVACION MANUAL P/VEREDA Y MARTILLO M3 4.11 34.41 141.43 0.00 - 0.00% 0.00 - 0.00% - - 0.00% 4.11 141.43 100.00%
02.02.03
EXCAVACION MANUAL P/SARDINEL
M3 7.68 35.08 269.41 3.15 110.50 41.02% 0.00 - 0.00% 3.15 110.50 41.02% 4.53 158.91 58.98%
PERALTADO
02.02.04 EXCAVACION MANUAL P/SARDINEL DE JARDIN M3 6.20 35.08 217.50 3.44 120.68 55.49% 0.00 - 0.00% 3.44 120.68 55.49% 2.76 96.82 44.51%
02.02.06 ELIMINACION DE MATERIAL
02.02.06.01 ACARREO MANUAL DE MATERIAL DE CORTE M3 29.70 17.21 511.14 21.45 369.15 72.22% 0.00 - 0.00% 21.45 369.15 72.22% 8.25 141.98 27.78%
02.02.06.02 CARGUIO DE MATERIAL EXCEDENTE M3 29.70 5.16 153.25 12.38 63.88 41.68% 0.00 - 0.00% 12.38 63.88 41.68% 17.32 89.37 58.32%
447.28
02.02.06.03 TRANSPORTE (ELIM DE MATERIAL EXCEDENTE) M3 29.70 15.06 12.38 186.44 41.68% 0.00 - 0.00% 12.38 186.44 41.68% 17.32 260.84 58.32%
02.03.01
SARDINEL PERALTADO - ENCOFRADO Y
M2 317.00 42.76 13,554.92 138.20 5,909.43 43.60% 0.00 - 0.00% 138.20 5,909.43 43.60% 178.80 7,645.49 56.40%
DESENCOFRADO
02.03.02
SARDINEL PERALTADO - CONCRETO FC=175
M3 37.50 412.20 15,457.50 18.25 7,522.65 48.67% 0.00 - 0.00% 18.25 7,522.65 48.67% 19.25 7,934.85 51.33%
KG/CM2
02.04 SARDINEL DE JARDIN
02.04.01 SARDINEL DE JARDIN TIPO I
02.04.01.01 MATERIAL PARA BASE DE JARDIN M3 81.87 43.75 3,581.81 0.00 - 0.00% 0.00 - 0.00% - - 0.00% 81.87 3,581.81 100.00%
02.04.01.02
RELLENO Y COMPACTACION - BASE DE
M2 511.71 24.02 12,291.27 0.00 - 0.00% 0.00 - 0.00% - - 0.00% 511.71 12,291.27 100.00%
JARDIN
02.04.01.03
SARDINEL DE JARDIN - ENCOFRADO Y
M2 443.66 42.76 18,970.90 79.11 3,382.74 17.83% 0.00 - 0.00% 79.11 3,382.74 17.83% 364.55 15,588.16 82.17%
DESENCOFRADO
02.04.01.04
ACERO CORRUGADO FY=4200KG/CM2 GRADO
KG 1,200.00 4.88 5,856.00 714.42 3,486.37 59.54% 100.80 491.90 8.40% 815.22 3,978.27 67.93% 384.78 1,877.73 32.07%
60
02.04.01.05
SARDINEL DE JARDIN - CONCRETO FC=175
M3 70.35 412.20 28,998.27 15.64 6,446.81 22.23% 0.00 - 0.00% 15.64 6,446.81 22.23% 54.71 22,551.46 77.77%
KG/CM2
02.04.01.06 CURADO M2 386.36 2.04 788.17 64.71 132.01 16.75% 0.00 - 0.00% 64.71 132.01 16.75% 321.65 656.17 83.25%
02.04.01.07 ENCHAPE DE GRANITO PULIDO M2 320.21 63.18 20,230.87 0.00 - 0.00% 0.00 - 0.00% - - 0.00% 320.21 20,230.87 100.00%
02.06 SARDINEL DE VEREDA
02.06.01 SARDINEL - ENCOFRADO Y DESENCOFRADO M2 128.11 42.76 5,477.98 0.00 - 0.00% 0.00 - 0.00% - - 0.00% 128.11 5,477.98 100.00%
02.06.02 SARDINEL - CONCRETO FC=175 KG/CM2 M3 20.55 412.20 8,470.71 0.00 - 0.00% 0.00 - 0.00% - - 0.00% 20.55 8,470.71 100.00%
02.06.03 CURADO M2 136.99 2.04 279.46 0.00 - 0.00% 0.00 - 0.00% - - 0.00% 136.99 279.46 100.00%
02.09 JUNTAS
02.09.01 JUNTAS DE DILATACION M 266.20 4.25 1,131.35 0.00 - 0.00% 0.00 - 0.00% - - 0.00% 266.20 1,131.35 100.00%
02.16 ENSAYOS Y PRUEBAS DE LABORATORIO
150.00
02.16.04 ENSAYO DE RESISTENCIA A LA COMPRESION UND 6.00 25.00 0.00 - 0.00% 0.00 - 0.00% - - 0.00% 6.00 150.00 100.00%
02.18 VARIOS
317.46
02.18.01 CONEXIÓN A RED MATRIZ PTO 6.00 52.91 0.00 - 0.00% 0.00 - 0.00% - - 0.00% 6.00 317.46 100.00%
141.15
02.18.04 LIMPIEZA FINAL DE OBRA M2 266.32 0.53 0.00 - 0.00% 0.00 - 0.00% - - 0.00% 266.32 141.15 100.00%
COSTO DIRECTO TOTAL 879,112.78 574,988.69 65.41% 73,544.77 8.37% 648,533.46 73.77% S/. 270,656.07 26.23%
COSTO DIRECTO TOTAL 0.00 0.00 #DIV/0! 0.00 #DIV/0! 0.00 #DIV/0! 0.00 #DIV/0!
SUBTOTAL 0.00 - - - -
FACTOR DE RELACION 0.90 0.00 - #DIV/0! - #DIV/0! - #DIV/0! - #DIV/0!
IGV (18%) 0.18 0.00 - - - -
COSTO DIRECTO TOTAL 0.00 0.00 #DIV/0! 0.00 #DIV/0! 0.00 #DIV/0! 0.00 #DIV/0!
SUBTOTAL 0.00 - - - -
FACTOR DE RELACION 0.90 0.00 - #DIV/0! - #DIV/0! - #DIV/0! - #DIV/0!
IGV (18%) 0.18 0.00 - - - -
COSTO DIRECTO TOTAL 0.00 0.00 #DIV/0! 0.00 #DIV/0! 0.00 #DIV/0! 0.00 #DIV/0!
SUBTOTAL 0.00 - - - -
FACTOR DE RELACION 0.90 0.00 - #DIV/0! - #DIV/0! - #DIV/0! - #DIV/0!
IGV (18%) 0.18 0.00 - - - -
O B R A : "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA AV. ALAMEDA TRAMO: JR. BOLIVIA - AV. CENTENARIO, DISTRITO DE SAN JE
CONTRATISTA : ADMINISTRACION DIRECTA
INSPECTOR : ING. YUDITH BACA ARANA PRONIED - MINEDU RESIDENTE: ING. MARIA MILAGROS GAMARRA CENZANO
FECHA : DEL 01 AL 30 DE NOVIEMBRE 2017
FORMULA : ESTRUCTURAS
K = 0,346 (Jr/Jo) + 0,169 (Aceror/Aceroo) + 0.131(Cem.r/Cem.o) + 0,083 (Mad.r/Mad.o) + 0,073 (A.Grur/A.Gruo) + 0,068 (Maq.r/A.Gruo) + 0,130 (G.G.Ur/G.G.Uo)
AREA GEOGRAFICA 2 (ANCASH) ESTRUCTURA
COEF. % Io
NOV '14 DIC '14 ENE '15 FEB '15 MAR '15
SIMBOLO ELEMENTO REPRESENTATIVO CODIGO I. BASE
INCID. INCID. May-14 Ir K Ir K Ir K Ir K Ir K
0 : 0
"MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA
AV. ALAMEDA TRAMO: JR. BOLIVIA - AV. CENTENARIO, DISTRITO DE SAN JERONIMO DE
O B R A : TUNAN, HUANCAYO - JUNIN"
CONTRATISTA : ADMINISTRACION DIRECTA
INSPECTOR : ING. YUDITH BACA ARANA
RESIDENTE ING. MARIA MILAGROS GAMARRA CENZANO
FECHA : DEL 01 AL 30 DE NOVIEMBRE 2017
O B R A "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA AV. ALAMEDA ING. YUDITH BACA ARANA
TRAMO: JR. BOLIVIA - AV. CENTENARIO, DISTRITO DE SAN JERONIMO DE TUNAN, HUANCAYO - JUNIN" ING. MARIA GAMARRA CENZANO
CONTRATISTA ADMINISTRACION DIRECTA
ENTIDAD MUNICIPALIDAD PROVINCIAL DE HUANCAYO 04 de Octubre del 2017
30 de Junio 2018
META FISICA 500 ML - PAVIMENTO RIGIDO
Partida Descripción UND. METRADO VAL. ACTUAL VAL. ACUMULADO SALDO DE VAL. OBSERVACIONES
EXPEDIENTE Metr. % Metr. % Metr. %
01 CALZADA VEHICULAR
01 CALZADA VEHICULAR
01.03 MOVIMIENTO DE TIERRAS
CORTE DE TERRENO A NIVEL DE SUB
01.03.01
RASANTE M3 2,479.36 24.80 1.00% 2,538.17 100.00% - 0.00%
01.03.04 EXCAVACION MANUAL EN CUNETA M3 21.51 4.00 18.60% 14.10 65.55% 7.41 34.45%
01.05 OBRAS DE CONCRETO SIMPLE
01.05.01 DRENAJE
DRENAJE CUNETA ENCOFRADO Y
01.05.01.01
DESENCOFRADO M2 257.68 37.01 14.36% 127.19 49.36% 130.49 50.64%
DRENAJE CUNETA CONCRETO FC=210
01.05.01.02
KG/CM2 M3 81.67 12.58 15.40% 43.62 53.41% 38.05 46.59%
01.05.04 ESTACIONAMIENTOS
ESTACIONAMIENTO ENCOF Y
01.05.04.01
DESENCOFRADO M2 163.54 6.26 3.83% 17.78 10.87% 145.76 89.13%
ESTACIONAMIENTO CONCRETO FC=210
01.05.04.02
KG/CM2 M3 131.89 12.24 9.28% 35.28 26.75% 96.61 73.25%
CURADO CON ARROCERAS EN
01.05.04.03
ESTACIONAMIENTO M2 659.46 57.80 8.76% 173.01 26.24% 486.45 73.76%
01.07 PAVIMENTOS
O B R A "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA AV. ALAMEDA ING. YUDITH BACA ARANA
TRAMO: JR. BOLIVIA - AV. CENTENARIO, DISTRITO DE SAN JERONIMO DE TUNAN, HUANCAYO - JUNIN" ING. MARIA GAMARRA CENZANO
CONTRATISTA ADMINISTRACION DIRECTA
ENTIDAD MUNICIPALIDAD PROVINCIAL DE HUANCAYO 04 de Octubre del 2017
30 de Junio 2018
META FISICA 500 ML - PAVIMENTO RIGIDO
Partida Descripción UND. METRADO VAL. ACTUAL VAL. ACUMULADO SALDO DE VAL. OBSERVACIONES
EXPEDIENTE Metr. % Metr. % Metr. %
02.04.01.01 MATERIAL PARA BASE DE JARDIN M3 108.94 35.92 32.97% 69.00 63.34% 39.94 36.66%
RELLENO Y COMPACTACION - BASE DE
02.04.01.02
JARDIN M2 680.91 224.48 32.97% 431.24 63.33% 249.67 36.67%
SARDINEL DE JARDIN - ENCOFRADO Y
02.04.01.03
DESENCOFRADO M2 590.53 126.39 21.40% 276.70 46.86% 313.83 53.14%
ACERO CORRUGADO FY=4200KG/CM2
02.04.01.04
GRADO 60 KG 1,460.70 579.42 39.67% 1,394.64 95.48% 66.06 4.52%
SARDINEL DE JARDIN - CONCRETO
02.04.01.05
FC=175 KG/CM2 M3 93.14 23.95 25.71% 51.48 55.27% 41.66 44.73%
02.04.01.06 CURADO M2 511.80 107.53 21.01% 233.79 45.68% 278.01 54.32%
120.00%
100%
60% 68.16%
54.40%
60.00%
50% 54.40%
REAL
40% PROGRAMADO
36.77%
40.00%
36.77%
30%
24.55%
22.42% 24.55%
20% 22.41%
20.00%
14.68%
14.68%
10%
L.P. N° : 0
"MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA AV. ALAMEDA TRAMO: JR. BOLIVIA -
O B R A : AV. CENTENARIO, DISTRITO DE SAN JERONIMO DE TUNAN, HUANCAYO - JUNIN"
CONTRATISTA : ADMINISTRACION DIRECTA
INSPECTOR : ING. YUDITH BACA ARANA
RESIDENTE ING. MARIA MILAGROS GAMARRA CENZANO
FECHA : DEL 01 AL 30 DE NOVIEMBRE 2017
MONTO CONT.(s/IGV) = C : -
ADEL. EFECT.(s/IGV) = A : #REF!
FECHA ADEL. EFECT. : #REF!
ESTRUCTURA D = V * A/C * (K / Ka-1)
VALORIZACION ADELANTO CONTRATO DEDUCCION
No. MES MONTO A C K Ka D
1 12/31/2014 - #REF! - - - -
2 1/31/2015 -
3 2/28/2015 -
4 3/31/2015 -
5 4/30/2015 -
6 5/31/2015 -
7 6/30/2015 -
8 7/31/2015 -
9 8/31/2015 -
10 9/30/2015 -
11 10/7/2015 -
SUB-TOTAL - -
1 12/31/2014 - #REF! - - - -
2 1/31/2015 -
3 2/28/2015 -
4 3/31/2015 -
5 4/30/2015 -
6 5/31/2015 -
7 6/30/2015 -
8 7/31/2015 -
9 8/31/2015 -
10 9/30/2015 -
11 10/7/2015 -
SUB-TOTAL - -
1 12/31/2014 - #REF! - - - -
2 1/31/2015 -
3 2/28/2015 -
4 3/31/2015 -
5 4/30/2015 -
6 5/31/2015 -
7 6/30/2015 -
8 7/31/2015 -
9 8/31/2015 -
10 9/30/2015 -
11 10/7/2015 -
SUB-TOTAL - -
OBRA : "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA AV. ALAMEDA TRAMO: JR. BOLIVIA - AV. CENTENARIO, DISTRITO DE SAN JERONIMO DE TUNAN, HUANCAYO - JUNIN"
UBICACIÓN : CARGUAZ -ANCASH
FECHA BASE : DICIEMBRE 2014
PROPIETARIO : MINISTERIO DE EDUCACIÓN – UNIDAD EJECUTORA 108
CONSTRUCTOR : CONTRATAS E INGENIERIA SA - SUCURSAL DEL PERU
CRONOGRAMA TOTAL
ITEM MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7 MES 8 MES 9 MES 10 MES 11
1.00 ESTRUCTURAS 134,133.991 421,949.320 1,252,256.861 1,784,712.298 1,377,274.149 751,795.078 159,887.770 50,909.703 43,062.328 21,499.988 4,096.196
2.00 ARQUITECTURA 322.581 500.000 500.000 18,709.750 172,949.382 647,031.068 709,195.708 641,085.652 770,666.904 399,917.934 52,254.113
3.00 INSTALACIONES SANITARIAS 0.000 0.000 0.000 0.000 24,305.296 77,589.982 99,090.821 86,027.615 40,112.872 14,042.566 1,712.508
4.00 INSTALACIONES ELECTRICAS 0.000 0.000 57,398.292 68,436.425 68,436.425 87,743.572 101,633.208 190,411.478 147,656.745 57,147.438 6,764.587
COSTO DIRECTO 134,456.57 422,449.32 1,310,155.15 1,871,858.47 1,642,965.25 1,564,159.70 1,069,807.51 968,434.45 1,001,498.85 492,607.93 64,827.40
GASTOS GENERALES Y UTILIDAD 15,00% 20,168.49 63,367.40 196,523.27 280,778.77 246,444.79 234,623.95 160,471.13 145,265.17 150,224.83 73,891.19 9,724.11
SUB TOTAL 154,625.06 485,816.72 1,506,678.42 2,152,637.24 1,889,410.04 1,798,783.65 1,230,278.64 1,113,699.62 1,151,723.68 566,499.12 74,551.51
FACTOR RELACION (0.90000000) 13,916.26 43,723.50 135,601.06 193,737.35 170,046.90 161,890.53 110,725.08 100,232.97 103,655.13 50,984.92 6,709.64
IGV 2,504.93 7,870.23 24,408.19 34,872.72 30,608.44 29,140.30 19,930.51 18,041.93 18,657.92 9,177.29 1,207.74
PRESUPUESTO TOTAL 16,421.19 51,593.73 160,009.25 228,610.07 200,655.34 191,030.83 130,655.59 118,274.90 122,313.05 60,162.21 7,917.38
AVANCE PARCIAL 1.28% 4.01% 12.43% 17.75% 15.58% 14.84% 10.15% 9.19% 9.50% 4.67% 0.61%
AVANCE ACUMULADO 1.28% 5.28% 17.71% 35.46% 51.05% 65.88% 76.03% 85.21% 94.71% 99.39% 100.00%
ESTRUCTURA
ITEM DESCRIPCION MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7 MES 8 MES 9 MES 10 MES 11
12.12.2014 AL 01.12.2014 AL 01.02.2015 AL 01.03.2015 AL 01.04.2015 AL 01.05.2015 AL 01.06.2015 AL 01.07.2015 AL 01.08.2015 AL 01.01.2015 AL 01.01.2015 AL
31.12.2014 31.01.2015 28.02.2015 31.03.2015 30.04.2015 31.05.2015 30.06.2015 31.07.2015 31.08.2015 30.09.2015 07.09.2015
1.00 ESTRUCTURAS 134,133.991 421,949.320 1,252,256.861 1,784,712.298 1,377,274.149 751,795.078 159,887.770 50,909.703 43,062.328 21,499.988 4,096.196
COSTO DIRECTO 134,133.99 421,949.32 1,252,256.86 1,784,712.30 1,377,274.15 751,795.08 159,887.77 50,909.70 43,062.33 21,499.99 4,096.20
GASTOS GENERALES Y UTILIDAD 15,00% 20,120.10 63,292.40 187,838.53 267,706.84 206,591.12 112,769.26 23,983.17 7,636.46 6,459.35 3,225.00 614.43
SUB TOTAL 154,254.09 485,241.72 1,440,095.39 2,052,419.14 1,583,865.27 864,564.34 183,870.94 58,546.16 49,521.68 24,724.99 4,710.63
FACTOR RELACION (0.90000000) 13,882.87 43,671.75 129,608.59 184,717.72 142,547.87 77,810.79 16,548.38 5,269.15 4,456.95 2,225.25 423.96
IGV 2,498.92 7,860.92 23,329.55 33,249.19 25,658.62 14,005.94 2,978.71 948.45 802.25 400.55 76.31
PRESUPUESTO TOTAL 16,381.79 51,532.67 152,938.14 217,966.91 168,206.49 91,816.73 19,527.09 6,217.60 5,259.20 2,625.80 500.27
AVANCE PARCIAL 1.27% 4.00% 11.88% 16.93% 13.06% 7.13% 1.52% 0.48% 0.41% 0.20% 0.04%
AVANCE ACUMULADO 1.27% 5.27% 17.15% 34.08% 47.14% 54.27% 55.79% 56.27% 56.68% 56.88% 56.92%
ARQUITECTURA
ITEM DESCRIPCION MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7 MES 8 MES 9 MES 10 MES 11
12.12.2014 AL 01.12.2014 AL 01.02.2015 AL 01.03.2015 AL 01.04.2015 AL 01.05.2015 AL 01.06.2015 AL 01.07.2015 AL 01.08.2015 AL 01.01.2015 AL 01.01.2015 AL
31.12.2014 31.01.2015 28.02.2015 31.03.2015 30.04.2015 31.05.2015 30.06.2015 31.07.2015 31.08.2015 30.09.2015 07.09.2015
2.00 ARQUITECTURA 322.581 500.000 500.000 18,709.750 172,949.382 647,031.068 709,195.708 641,085.652 770,666.904 399,917.934 52,254.113
COSTO DIRECTO 322.58 500.09 500.29 18,710.26 172,949.98 647,031.68 709,196.28 641,086.22 770,667.47 399,918.51 52,254.68
GASTOS GENERALES Y UTILIDAD 15,00% 48.39 75.01 75.04 2,806.54 25,942.50 97,054.75 106,379.44 96,162.93 115,600.12 59,987.78 7,838.20
SUB TOTAL 370.97 575.10 575.33 21,516.80 198,892.48 744,086.43 815,575.72 737,249.15 886,267.59 459,906.29 60,092.88
FACTOR RELACION (0.90000000) 33.39 51.76 51.78 1,936.51 17,900.32 66,967.78 73,401.81 66,352.42 79,764.08 41,391.57 5,408.36
IGV 6.01 9.32 9.32 348.57 3,222.06 12,054.20 13,212.33 11,943.44 14,357.53 7,450.48 973.50
PRESUPUESTO TOTAL 39.40 61.08 61.10 2,285.08 21,122.38 79,021.98 86,614.14 78,295.86 94,121.61 48,842.05 6,381.86
AVANCE PARCIAL 0.00% 0.00% 0.00% 0.18% 1.64% 6.14% 6.73% 6.08% 7.31% 3.79% 0.50%
AVANCE ACUMULADO 0.00% 0.01% 0.01% 0.19% 1.83% 7.97% 14.69% 20.77% 28.08% 31.88% 32.37%
INSTALACIONES SANITARIAS
ITEM DESCRIPCION MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7 MES 8 MES 9 MES 10 MES 11
12.12.2014 AL 01.12.2014 AL 01.02.2015 AL 01.03.2015 AL 01.04.2015 AL 01.05.2015 AL 01.06.2015 AL 01.07.2015 AL 01.08.2015 AL 01.01.2015 AL 01.01.2015 AL
31.12.2014 31.01.2015 28.02.2015 31.03.2015 30.04.2015 31.05.2015 30.06.2015 31.07.2015 31.08.2015 30.09.2015 07.09.2015
3.00 INSTALACIONES SANITARIAS 0.000 0.000 0.000 0.000 24,305.296 77,589.982 99,090.821 86,027.615 40,112.872 14,042.566 1,712.508
COSTO DIRECTO 0.00 0.00 0.00 0.00 24,305.33 77,590.12 99,091.04 86,027.88 40,113.23 14,042.92 1,712.84
GASTOS GENERALES Y UTILIDAD 15,00% 0.00 0.00 0.00 0.00 3,645.80 11,638.52 14,863.66 12,904.18 6,016.98 2,106.44 256.93
SUB TOTAL 0.00 0.00 0.00 0.00 27,951.13 89,228.64 113,954.70 98,932.06 46,130.21 16,149.36 1,969.77
FACTOR RELACION (0.90000000) 0.00 0.00 0.00 0.00 2,515.60 8,030.58 10,255.92 8,903.89 4,151.72 1,453.44 177.28
IGV 0.00 0.00 0.00 0.00 452.81 1,445.50 1,846.07 1,602.70 747.31 261.62 31.91
PRESUPUESTO TOTAL 0.00 0.00 0.00 0.00 2,968.41 9,476.08 12,101.99 10,506.59 4,899.03 1,715.06 209.19
AVANCE PARCIAL 0.00% 0.00% 0.00% 0.00% 0.23% 0.74% 0.94% 0.82% 0.38% 0.13% 0.02%
AVANCE ACUMULADO 0.00% 0.00% 0.00% 0.00% 0.23% 0.97% 1.91% 2.72% 3.10% 3.24% 3.25%
INSTALACIONES ELECTRICAS
ITEM DESCRIPCION MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7 MES 8 MES 9 MES 10 MES 11
12.12.2014 AL 01.12.2014 AL 01.02.2015 AL 01.03.2015 AL 01.04.2015 AL 01.05.2015 AL 01.06.2015 AL 01.07.2015 AL 01.08.2015 AL 01.01.2015 AL 01.01.2015 AL
31.12.2014 31.01.2015 28.02.2015 31.03.2015 30.04.2015 31.05.2015 30.06.2015 31.07.2015 31.08.2015 30.09.2015 07.09.2015
4.00 INSTALACIONES ELECTRICAS 0.000 0.000 57,398.292 68,436.425 68,436.425 87,743.572 101,633.208 190,411.478 147,656.745 57,147.438 6,764.587
COSTO DIRECTO 0.00 0.00 57,398.29 68,436.43 68,436.43 87,743.59 101,633.24 190,411.51 147,656.78 57,147.47 6,764.62
GASTOS GENERALES Y UTILIDAD 15,00% 0.00 0.00 8,609.74 10,265.46 10,265.46 13,161.54 15,244.99 28,561.73 22,148.52 8,572.12 1,014.69
SUB TOTAL 0.00 0.00 66,008.03 78,701.89 78,701.89 100,905.13 116,878.23 218,973.24 169,805.30 65,719.59 7,779.31
FACTOR RELACION (0.90000000) 0.00 0.00 5,940.72 7,083.17 7,083.17 9,081.46 10,519.04 19,707.59 15,282.48 5,914.76 700.14
IGV 0.00 0.00 1,069.33 1,274.97 1,274.97 1,634.66 1,893.43 3,547.37 2,750.85 1,064.66 126.03
PRESUPUESTO TOTAL 0.00 0.00 7,010.05 8,358.14 8,358.14 10,716.12 12,412.47 23,254.96 18,033.33 6,979.42 826.17
AVANCE PARCIAL 0.00% 0.00% 0.54% 0.65% 0.65% 0.83% 0.96% 1.81% 1.40% 0.54% 0.06%
AVANCE ACUMULADO 0.00% 0.00% 0.54% 1.19% 1.84% 2.67% 3.64% 5.44% 6.85% 7.39% 7.45%
TOTAL PRESUPUESTO
ITEM DESCRIPCION MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7 MES 8 MES 9 MES 10 MES 11
12.12.2014 AL 01.12.2014 AL 01.02.2015 AL 01.03.2015 AL 01.04.2015 AL 01.05.2015 AL 01.06.2015 AL 01.07.2015 AL 01.08.2015 AL 01.01.2015 AL 01.01.2015 AL
31.12.2014 31.01.2015 28.02.2015 31.03.2015 30.04.2015 31.05.2015 30.06.2015 31.07.2015 31.08.2015 30.09.2015 07.09.2015
RESUMEN 134,456.572 422,449.320 1,310,155.153 1,871,858.473 1,642,965.251 1,564,159.700 1,069,807.506 968,434.448 1,001,498.849 492,607.927 64,827.404
COSTO DIRECTO 134,456.57 422,449.32 1,310,155.16 1,871,858.48 1,642,965.27 1,564,159.73 1,069,807.54 968,434.50 1,001,498.92 492,608.00 64,827.48
GASTOS GENERALES Y UTILIDAD 15,00% 20,168.49 63,367.40 196,523.27 280,778.77 246,444.79 234,623.96 160,471.13 145,265.18 150,224.84 73,891.20 9,724.12
SUB TOTAL 154,625.06 485,816.72 1,506,678.43 2,152,637.25 1,889,410.06 1,798,783.69 1,230,278.67 1,113,699.68 1,151,723.76 566,499.20 74,551.60
FACTOR RELACION (0.90000000) 13,916.26 43,723.50 135,601.06 193,737.35 170,046.91 161,890.53 110,725.08 100,232.97 103,655.14 50,984.93 6,709.64
IGV 2,504.93 7,870.23 24,408.19 34,872.72 30,608.44 29,140.30 19,930.51 18,041.93 18,657.93 9,177.29 1,207.74
PRESUPUESTO TOTAL 16,421.19 51,593.73 160,009.25 228,610.07 200,655.35 191,030.83 130,655.59 118,274.90 122,313.07 60,162.22 7,917.38
AVANCE PARCIAL 1.28% 4.01% 12.43% 17.75% 15.58% 14.84% 10.15% 9.19% 9.50% 4.67% 0.61%
AVANCE ACUMULADO 1.28% 5.28% 17.71% 35.46% 51.05% 65.88% 76.03% 85.21% 94.71% 99.39% 100.00%
TOTAL
6,001,577.682
-
3,413,133.091
-
342,881.660
-
785,628.170
10,543,220.60
1,581,483.09
12,124,703.69
1,091,223.33
196,420.20
1,287,643.53
TOTAL
6,001,577.682
-
6,001,577.68
900,236.65
6,901,814.33
621,163.29
111,809.39
732,972.68
TOTAL
3,413,133.091
-
3,413,133.09
511,969.96
3,925,103.05
353,259.27
63,586.67
416,845.94
TOTAL
342,881.660
-
342,881.66
51,432.25
394,313.91
35,488.25
6,387.89
41,876.14
TOTAL
785,628.170
785,628.17
117,844.23
903,472.40
81,312.52
14,636.25
95,948.77
TOTAL
10,543,220.603
10,543,220.60
1,581,483.09
12,124,703.69
1,091,223.33
196,420.20
1,287,643.53
8 VIAJES MAS 31/11/2017 40
10 VIAJES 11/2/2017
156 15 2340
40
14
2500 15 166
138
28
967602.2 100%
111158.73 0.11488061
11.49%
1207602.15 100%
105838.77 0.08764374
8.76%
3687501.11 100%
804507.55 0.21817147
21.82%
1207602.15 100%
804507.55 0.66620248
66.62%
10/4/2017
6/30/2018
269
26 15 390
10
15 8 120
29
21.6 23
98.4 26
49.2 26
10 40
492 11
155
18 15 270
8
2160
388.8
1771.2
885.6
METRADOS FALTANTES POR EJECUTAR PROG 0+000 a 0+400 / MONTO ASIGNADO
METRADOS REALES HASTA EL 11/04/2018
O B R A "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA AV. ALAMEDA TRAMO: JR. BOLIVIA Inspector ING. YUDITH BACA ARANA
- AV. CENTENARIO, DISTRITO DE SAN JERONIMO DE TUNAN, HUANCAYO - JUNIN" ING. MARIA GAMARRA CENZANO
CONTRATISTA ADMINISTRACION DIRECTA Residente:
ENTIDAD MUNICIPALIDAD PROVINCIAL DE HUANCAYO F.Inicio: 04 de Octubre del 2017
F. Termino: 20 de Mayo 2018
PRESUPUESTO EXPEDIENTE TECNICO METRADOS FALTANTES POR EJECUTAR PROG 0+000 a 0+400
Partida Descripción UND. METRADO PROG VAL. ACUMULADO SALDO DE VAL.
P.U. (S/.) Parcial (S/.) Metr. % Metr. S/. %
0+000 a 0+400 S/.
01.01.04 MOVILIZACION Y DESMOVILIZACION EQUIPO GLB 0.50 5,892.54 2,946.27 0.50 2,946.27 100.00% - - 0.00%
01.02 TRABAJOS PRELIMINARES
01.02.01 LIMPIEZA DEL TERRENO M2 3,644.78 0.53 1,931.73 - - 0.00% 3,644.78 1,931.73 100.00%
01.02.02 LIMPIEZA Y DEFORESTACION HA 0.12 3,834.60 444.81 - - 0.00% 0.12 444.81 100.00%
01.02.03 TRAZO, NIVELES Y REPLANTEO M2 3,810.16 0.70 2,667.11 3,600.00 2,520.00 94.48% 210.16 147.11 5.52%
01.02.04
TRAZO Y REPLANTEO DURANTE LA
M2 3,810.16 0.98 3,733.96 2,925.59 2,867.08 76.78% 884.57 866.88 23.22%
EJECUCION DE OBRA
01.02.05 DEMOLICION DE ALCANTARILLAS M3 6.80 45.58 309.94 6.80 309.94 100.00% - - 0.00%
01.03 MOVIMIENTO DE TIERRAS
01.03.01
CORTE DE TERRENO A NIVEL DE SUB
M3 2,479.36 12.11 30,025.05 2,494.17 30,204.40 100.00% - - 0.00%
RASANTE
01.03.02
CORTE DE TERRENO A NIVEL DE MEJ. SUB
M3 673.20 12.11 8,152.45 658.39 7,973.10 97.80% 14.81 179.35 2.20%
RASANTE
01.03.03 EXCAVACION MANUAL M3 106.25 34.41 3,656.06 219.36 7,548.18 100.00% - - 0.00%
01.03.04 EXCAVACION MANUAL EN CUNETA M3 15.76 34.41 542.30 10.10 347.54 64.09% 5.66 194.76 35.91%
01.03.05 EXCAVACION MANUAL P/BADEN M3 9.96 34.41 342.72 3.84 132.13 38.55% 6.12 210.59 61.45%
01.03.06 ELIMINACION DE MATERIAL EXCEDENTE
01.03.06.01 ACARREO INTERNO DE MATERIAL M3 164.96 17.21 2,838.96 156.45 2,692.50 94.84% 8.51 146.46 5.16%
01.03.06.02 CARGUIO DE MATERIAL EXCEDENTE M3 3,618.00 6.19 22,395.42 3,618.00 22,395.42 100.00% - - 0.00%
01.03.06.03
TRANSPORTE (ELIM DE MATERIAL
M3 3,618.00 18.07 65,377.26 3,618.00 65,377.26 100.00% - - 0.00%
EXCEDENTE)
01.04 EXPLANACIONES
01.04.01
ESCARIFICADO, PERFIL Y COMP. DE
M2 3,305.00 3.81 12,592.05 3,359.40 12,799.31 100.00% - - 0.00%
SUBRASANTE
01.05 OBRAS DE CONCRETO SIMPLE
01.05.01 DRENAJE
01.05.01.01
DRENAJE CUNETA ENCOFRADO Y
M2 201.68 32.93 6,641.32 75.78 2,495.44 37.57% 125.90 4,145.89 62.43%
DESENCOFRADO
01.05.01.02
DRENAJE CUNETA CONCRETO FC=210
M3 64.60 414.78 26,794.79 26.14 10,842.35 40.46% 38.46 15,952.44 59.54%
KG/CM2
01.05.02 BADEN
01.05.02.01 BADENES ENCOF Y DESENCOFRADO M2 79.67 31.75 2,529.52 30.39 964.88 38.14% 49.28 1,564.64 61.86%
01.05.02.02 BADENES CONCRETO FC=210 KG/CM2 M3 29.88 414.78 12,393.63 9.53 3,952.85 31.89% 20.35 8,440.77 68.11%
METRADOS FALTANTES POR EJECUTAR PROG 0+000 a 0+400 / MONTO ASIGNADO
METRADOS REALES HASTA EL 11/04/2018
O B R A "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA AV. ALAMEDA TRAMO: JR. BOLIVIA Inspector ING. YUDITH BACA ARANA
- AV. CENTENARIO, DISTRITO DE SAN JERONIMO DE TUNAN, HUANCAYO - JUNIN" ING. MARIA GAMARRA CENZANO
CONTRATISTA ADMINISTRACION DIRECTA Residente:
ENTIDAD MUNICIPALIDAD PROVINCIAL DE HUANCAYO F.Inicio: 04 de Octubre del 2017
F. Termino: 20 de Mayo 2018
PRESUPUESTO EXPEDIENTE TECNICO METRADOS FALTANTES POR EJECUTAR PROG 0+000 a 0+400
Partida Descripción UND. METRADO PROG VAL. ACUMULADO SALDO DE VAL.
P.U. (S/.) Parcial (S/.) Metr. % Metr. S/. %
0+000 a 0+400 S/.
01.05.02.03 CURADO CON ARROCERAS EN BADEN M2 99.60 3.54 352.58 - - 0.00% 99.60 352.58 100.00%
01.05.03 BOCACALLE DE CONCRETO
01.05.03.01 COMPACTACION DE BASE DE BOCACALLE M2 399.39 3.79 1,513.69 220.42 835.39 55.19% 178.97 678.30 44.81%
01.05.03.02 BOCACALLE ENCOF Y DESENCOFRADO M2 76.88 31.75 2,440.94 36.09 1,145.86 46.94% 40.79 1,295.08 53.06%
01.05.03.03 BOCACALLE CONCRETO FC=210 KG/CM2 M3 68.00 414.78 28,205.04 45.61 18,918.12 67.07% 22.39 9,286.92 32.93%
01.05.03.04
CURADO CON ARROCERAS EN
M2 399.39 3.54 1,413.84 227.92 806.84 57.07% 171.47 607.00 42.93%
ESTACIONAMIENTO
01.05.04 ESTACIONAMIENTOS
01.05.04.01
ESTACIONAMIENTO ENCOF Y
M2 135.14 31.75 4,290.70 - - 0.00% 135.14 4,290.70 100.00%
DESENCOFRADO
01.05.04.02
ESTACIONAMIENTO CONCRETO FC=210
M3 107.09 414.78 44,418.79 - - 0.00% 107.09 44,418.79 100.00%
KG/CM2
01.05.04.03
CURADO CON ARROCERAS EN
M2 535.46 3.54 1,895.53 - - 0.00% 535.46 1,895.53 100.00%
ESTACIONAMIENTO
01.06 OBRAS DE CONCRETO ARMADO
01.06.01 ALCANTARILLA CAJON
01.06.01.01 TRAZO, NIVELES Y REPLANTEO M2 35.40 0.7 24.78 39.60 27.72 100.00% - - 0.00%
01.06.01.02 EXCAVACION MANUAL M3 28.35 34.41 975.52 28.35 975.52 100.00% - - 0.00%
01.06.01.03 SOLADO DE CONCRETO E=4" M3 3.54 275.39 974.88 3.54 974.88 100.00% - - 0.00%
01.06.01.04
ACERO CORRUGADO FY=4200KG/CM2 GRADO
KG 1,936.00 4.88 9,447.68 1,959.27 9,561.24 100.00% - - 0.00%
60
01.06.01.05 ENCOFRADO DE ELEVACIONES M2 62.76 82.67 5,188.37 62.22 5,143.73 99.14% 0.54 44.64 0.86%
01.06.01.06 CONCRETO FC=280 KG/CM2 M3 22.28 489.98 10,916.75 25.35 12,420.99 100.00% - - 0.00%
01.06.01.07 JUNTAS WATER STOP M 85.80 19.22 1,649.08 68.40 1,314.65 79.72% 17.40 334.43 20.28%
01.06.01.08 CURADO M2 62.76 2.04 128.03 463.20 944.93 100.00% - - 0.00%
01.06.01.09 JUNTA ASFALTICA M 9.00 4.25 38.25 - - 0.00% 9.00 38.25 100.00%
01.07 PAVIMENTOS
01.07.01 MEJORAMIENTO DE SUBRASANTE
01.07.01.01 MATERIAL P/MEJ DE SUB RASANTE M3 480.00 37.5 18,000.00 870.76 32,653.50 100.00% - - 0.00%
01.07.01.02
EXTENDIDO/RIEGO/COMP DE SUB BASE
M3 480.00 24.02 11,529.60 731.96 17,581.68 100.00% - - 0.00%
E=0.15M
01.07.02 SUB BASE GRANULAR
01.07.02.01 MATERIAL PARA SUB BASE M3 605.19 43.75 26,477.10 832.62 36,427.13 100.00% - - 0.00%
01.07.02.02
EXTENDIDO/RIEGO/COMP DE SUB BASE
M2 2,880.00 3.63 10,454.40 3,523.19 12,789.18 100.00% - - 0.00%
E=0.20M
01.07.03 PAVIMENTO RIGIDO
01.07.03.01
ENCOFRADO Y DESENCOFRADO EN LOSAS DE
M2 211.12 38.24 8,073.23 142.19 5,437.35 67.35% 68.93 2,635.88 32.65%
CONCRETO
01.07.03.02 LOSA CONCRETO FC=280 KG/CM2 E=0.20M M3 504.00 489.98 246,949.92 456.51 223,680.77 90.58% 47.49 23,269.15 9.42%
METRADOS FALTANTES POR EJECUTAR PROG 0+000 a 0+400 / MONTO ASIGNADO
METRADOS REALES HASTA EL 11/04/2018
O B R A "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA AV. ALAMEDA TRAMO: JR. BOLIVIA Inspector ING. YUDITH BACA ARANA
- AV. CENTENARIO, DISTRITO DE SAN JERONIMO DE TUNAN, HUANCAYO - JUNIN" ING. MARIA GAMARRA CENZANO
CONTRATISTA ADMINISTRACION DIRECTA Residente:
ENTIDAD MUNICIPALIDAD PROVINCIAL DE HUANCAYO F.Inicio: 04 de Octubre del 2017
F. Termino: 20 de Mayo 2018
PRESUPUESTO EXPEDIENTE TECNICO METRADOS FALTANTES POR EJECUTAR PROG 0+000 a 0+400
Partida Descripción UND. METRADO PROG VAL. ACUMULADO SALDO DE VAL.
P.U. (S/.) Parcial (S/.) Metr. % Metr. S/. %
0+000 a 0+400 S/.
01.07.03.03 ACABADO EN LOSAS DE CONCRETO M2 2,520.00 14.56 36,691.20 2,256.12 32,849.11 89.53% 263.88 3,842.09 10.47%
01.07.03.04 CURADO CON ARROCERAS M2 2,520.00 3.54 8,920.80 2,033.28 7,197.81 80.69% 486.72 1,722.99 19.31%
01.07.03.05
JUNTAS DE CONTRACCION PASADORES
UND 1,992.00 4.28 8,525.76 1,160.00 4,964.80 58.23% 832.00 3,560.96 41.77%
CORRUGADAS
01.07.03.06
JUNTAS LONGITUDINALES (BARRAS DE
UND 460.00 7.61 3,500.60 332.00 2,526.52 72.17% 128.00 974.08 27.83%
AMARRE)
01.08 JUNTAS
01.08.01 JUNTAS DE DILATACION M 1,495.31 4.25 6,355.07 - - 0.00% 1,495.31 6,355.07 100.00%
01.09 SEÑALIZACIONES HORIZONTALES
01.09.01 PINTURA LINEAL EN SARDINEL M 350.00 10.09 3,531.50 - - 0.00% 350.00 3,531.50 100.00%
01.09.02
PINTURA INTERMEDIA CONTINUA CENTRO DE
M 297.76 5.3 1,578.13 - - 0.00% 297.76 1,578.13 100.00%
VIA
01.09.03 PINTURA DE SIMBOLOS - FLECHAS M2 15.52 23.13 358.98 - - 0.00% 15.52 358.98 100.00%
01.09.04 PINTURA ZONAL CRUCE PEATONAL M2 98.40 23.44 2,306.50 - - 0.00% 98.40 2,306.50 100.00%
01.11 ENSAYOS Y PRUEBAS DE LABORATORIO
01.11.01 ENSAYO DE DENSIDAD DE CAMPO UND 20.00 30 600.00 24.00 720.00 100.00% - - 0.00%
01.11.02
ENSAYO DE COMPACTACION DE SUELOS
UND 2.00 120 240.00 2.00 240.00 100.00% - - 0.00%
(PROCTOR MODIFICADO)
01.11.03 DISEÑO DE MEZCLAS DE CONCRETO UND 3.00 350 1,050.00 3.00 1,050.00 100.00% - - 0.00%
01.11.04 ENSAYO DE RESISTENCIA A LA COMPRESION UND 12.00 25 300.00 9.00 225.00 75.00% 3.00 75.00 25.00%
01.12.01 COSTOS AMBIENTALES GLB 0.50 500 250.00 - - 0.00% 0.50 250.00 100.00%
01.14 VARIOS
01.14.01 RECONEXION DE PUNTOS DE AGUA PTO 18.00 39.68 714.24 16.00 634.88 88.89% 2.00 79.36 11.11%
01.14.02 RECONEXION DE CAJA MEDIDOR DE AGUA UND 18.00 49.18 885.24 - - 0.00% 18.00 885.24 100.00%
01.14.03 RECONEXION DE PUNTOS DE DESAGUE PTO 18.00 180.91 3,256.38 12.00 2,170.92 66.67% 6.00 1,085.46 33.33%
01.14.04
RECONEXION DE CAJA DE REGISTRO DE
UND 18.00 69.18 1,245.24 - - 0.00% 18.00 1,245.24 100.00%
DESAGUE
01.14.05 ENCIMADO DE BUZONES UND 4.00 613.47 2,453.88 4.00 2,453.88 100.00% - - 0.00%
01.14.06 ALINEAMIENTO DE POSTES DE LUZ UND 3.00 1800 5,400.00 - - 0.00% 3.00 5,400.00 100.00%
01.14.08 PLACA RECORDATORIA UND 1.00 337.79 337.79 - - 0.00% 1.00 337.79 100.00%
01.14.09 LIMPIEZA FINAL DE OBRA M2 4,769.22 0.53 2,527.69 - - 0.00% 4,769.22 2,527.69 100.00%
02 ACERA PEATONAL 141,392.65
02 ACERA PEATONAL
02.01 TRABAJOS PRELIMINARES
02.01.01 LIMPIEZA DEL TERRENO M2 241.85 0.53 128.18 - - 0.00% 241.85 128.18 100.00%
02.01.02 TRAZO, NIVELES Y REPLANTEO DE VEREDAS M2 241.85 0.70 169.30 - - 0.00% 241.85 169.30 100.00%
METRADOS FALTANTES POR EJECUTAR PROG 0+000 a 0+400 / MONTO ASIGNADO
METRADOS REALES HASTA EL 11/04/2018
O B R A "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA AV. ALAMEDA TRAMO: JR. BOLIVIA Inspector ING. YUDITH BACA ARANA
- AV. CENTENARIO, DISTRITO DE SAN JERONIMO DE TUNAN, HUANCAYO - JUNIN" ING. MARIA GAMARRA CENZANO
CONTRATISTA ADMINISTRACION DIRECTA Residente:
ENTIDAD MUNICIPALIDAD PROVINCIAL DE HUANCAYO F.Inicio: 04 de Octubre del 2017
F. Termino: 20 de Mayo 2018
PRESUPUESTO EXPEDIENTE TECNICO METRADOS FALTANTES POR EJECUTAR PROG 0+000 a 0+400
Partida Descripción UND. METRADO PROG VAL. ACUMULADO SALDO DE VAL.
P.U. (S/.) Parcial (S/.) Metr. % Metr. S/. %
0+000 a 0+400 S/.
02.01.03
TRAZO Y REPLANTEO DURANTE LA
M2 241.85 0.98 237.01 43.26 42.39 17.89% 198.59 194.62 82.11%
EJECUCION DE OBRA
02.01.04 DEMOLICION DE VEREDAS EXISTENTES M3 12.52 192.82 2,414.11 12.52 2,414.11 100.00% -
METRADOS FALTANTES POR EJECUTAR PROG 0+000 a 0+400 / MONTO ASIGNADO
METRADOS REALES HASTA EL 11/04/2018
O B R A "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA AV. ALAMEDA TRAMO: JR. BOLIVIA Inspector ING. YUDITH BACA ARANA
- AV. CENTENARIO, DISTRITO DE SAN JERONIMO DE TUNAN, HUANCAYO - JUNIN" ING. MARIA GAMARRA CENZANO
CONTRATISTA ADMINISTRACION DIRECTA Residente:
ENTIDAD MUNICIPALIDAD PROVINCIAL DE HUANCAYO F.Inicio: 04 de Octubre del 2017
F. Termino: 20 de Mayo 2018
PRESUPUESTO EXPEDIENTE TECNICO METRADOS FALTANTES POR EJECUTAR PROG 0+000 a 0+400
Partida Descripción UND. METRADO PROG VAL. ACUMULADO SALDO DE VAL.
P.U. (S/.) Parcial (S/.) Metr. % Metr. S/. %
0+000 a 0+400 S/.
02.01.05 DEMOLICION DE SARDINEL EXISTENTES M3 5.15 172.08 886.21 1.35 232.31 26.21% 3.80 653.90 73.79%
02.02 MOVIMIENTO DE TIERRAS
02.02.01 EXCAVACION MANUAL P/VEREDA Y MARTILLO M3 4.11 34.41 141.43 - - 0.00% 4.11 141.43 100.00%
02.02.03
EXCAVACION MANUAL P/SARDINEL
M3 7.68 35.08 269.41 3.15 110.50 41.02% 4.53 158.91 58.98%
PERALTADO
02.02.04 EXCAVACION MANUAL P/SARDINEL DE JARDIN M3 6.20 35.08 217.50 3.44 120.68 55.49% 2.76 96.82 44.51%
02.02.06 ELIMINACION DE MATERIAL
02.02.06.01 ACARREO MANUAL DE MATERIAL DE CORTE M3 29.70 17.21 511.14 21.45 369.15 72.22% 8.25 141.98 27.78%
02.02.06.02 CARGUIO DE MATERIAL EXCEDENTE M3 29.70 5.16 153.25 12.38 63.88 41.68% 17.32 89.37 58.32%
447.28
02.02.06.03 TRANSPORTE (ELIM DE MATERIAL EXCEDENTE) M3 29.70 15.06 12.38 186.44 41.68% 17.32 260.84 58.32%
02.03.01
SARDINEL PERALTADO - ENCOFRADO Y
M2 317.00 42.76 13,554.92 138.20 5,909.43 43.60% 178.80 7,645.49 56.40%
DESENCOFRADO
02.03.02
SARDINEL PERALTADO - CONCRETO FC=175
M3 37.50 412.20 15,457.50 18.25 7,522.65 48.67% 19.25 7,934.85 51.33%
KG/CM2
02.04 SARDINEL DE JARDIN
02.04.01 SARDINEL DE JARDIN TIPO I
02.04.01.01 MATERIAL PARA BASE DE JARDIN M3 81.87 43.75 3,581.81 - - 0.00% 81.87 3,581.81 100.00%
02.04.01.02
RELLENO Y COMPACTACION - BASE DE
M2 511.71 24.02 12,291.27 - - 0.00% 511.71 12,291.27 100.00%
JARDIN
02.04.01.03
SARDINEL DE JARDIN - ENCOFRADO Y
M2 443.66 42.76 18,970.90 79.11 3,382.74 17.83% 364.55 15,588.16 82.17%
DESENCOFRADO
02.04.01.04
ACERO CORRUGADO FY=4200KG/CM2 GRADO
KG 1,200.00 4.88 5,856.00 815.22 3,978.27 67.93% 384.78 1,877.73 32.07%
60
02.04.01.05
SARDINEL DE JARDIN - CONCRETO FC=175
M3 70.35 412.20 28,998.27 15.64 6,446.81 22.23% 54.71 22,551.46 77.77%
KG/CM2
02.04.01.06 CURADO M2 386.36 2.04 788.17 64.71 132.01 16.75% 321.65 656.17 83.25%
02.04.01.07 ENCHAPE DE GRANITO PULIDO M2 320.21 63.18 20,230.87 - - 0.00% 320.21 20,230.87 100.00%
02.06 SARDINEL DE VEREDA
02.06.01 SARDINEL - ENCOFRADO Y DESENCOFRADO M2 128.11 42.76 5,477.98 - - 0.00% 128.11 5,477.98 100.00%
02.06.02 SARDINEL - CONCRETO FC=175 KG/CM2 M3 20.55 412.20 8,470.71 - - 0.00% 20.55 8,470.71 100.00%
02.06.03 CURADO M2 136.99 2.04 279.46 - - 0.00% 136.99 279.46 100.00%
02.09 JUNTAS
02.09.01 JUNTAS DE DILATACION M 266.20 4.25 1,131.35 - - 0.00% 266.20 1,131.35 100.00%
02.16 ENSAYOS Y PRUEBAS DE LABORATORIO
O B R A "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA AV. ALAMEDA TRAMO: JR. BOLIVIA Inspector ING. YUDITH BACA ARANA
- AV. CENTENARIO, DISTRITO DE SAN JERONIMO DE TUNAN, HUANCAYO - JUNIN" ING. MARIA GAMARRA CENZANO
CONTRATISTA ADMINISTRACION DIRECTA Residente:
ENTIDAD MUNICIPALIDAD PROVINCIAL DE HUANCAYO F.Inicio: 04 de Octubre del 2017
F. Termino: 20 de Mayo 2018
PRESUPUESTO EXPEDIENTE TECNICO METRADOS FALTANTES POR EJECUTAR PROG 0+000 a 0+400
Partida Descripción UND. METRADO PROG VAL. ACUMULADO SALDO DE VAL.
P.U. (S/.) Parcial (S/.) Metr. % Metr. S/. %
0+000 a 0+400 S/.
150.00
02.16.04 ENSAYO DE RESISTENCIA A LA COMPRESION UND 6.00 25.00 - - 0.00% 6.00 150.00 100.00%
02.18 VARIOS
317.46
02.18.01 CONEXIÓN A RED MATRIZ PTO 6.00 52.91 - - 0.00% 6.00 317.46 100.00%
141.15
02.18.04 LIMPIEZA FINAL DE OBRA M2 266.32 0.53 - - 0.00% 266.32 141.15 100.00%