ALADINO VI FECHA 6/12/2020 AL 12/12/2020

RECUPERACIÓN DE LOS SERVICIOS ECOSISTÉMICOS DE LA PARTE MEDIA DE LA QUEBRADA CHACTANI DE LA


CUENCA ILPA AFECTADA POR LOS PASIVOS AMBIENTALES MINEROS
CONTRATO GL-C-013-2020 REPORTE DE AVANCE FISICO - CURVA S - DATA DATE - SEMANA 18
DE LA EX UNIDAD MINERA ALADINO VI, EN EL DISTRITO MAÑAZO, PROVINCIA DE PUNO, DEPARTAMENTO DE PUNO. CODIGO WR 018

Inicio Semana 01 Semana 02 Semana 03 Semana 04 Semana 05 Semana 06 Semana 07 Semana 08 Semana 09 Semana 10 Semana 11 Semana 12 Semana 13 Semana 14 Semana 15 Semana 16 Semana 17 Semana 18 Semana 19 Semana 20 Semana 21
AVANCE FISÍCO %
WBS DESCRIPCIÓN PPTO TOTAL PROYECTADO: S/. PESO ( % ) DESVIACIÓN % Inicio 10-Ago-20 16-Ago-20 23-Ago-20 30-Ago-20 6-Set-20 13-Set-20 20-Set-20 27-Set-20 4-Oct-20 11-Oct-20 18-Oct-20 25-Oct-20 1-Nov-20 8-Nov-20 15-Nov-20 22-Nov-20 29-Nov-20 6-Dic-20 13-Dic-20 20-Dic-20 27-Dic-20
PROG REAL Inicio 15-Ago-20 22-Ago-20 29-Ago-20 5-Set-20 12-Set-20 19-Set-20 26-Set-20 3-Oct-20 10-Oct-20 17-Oct-20 24-Oct-20 31-Oct-20 7-Nov-20 14-Nov-20 21-Nov-20 28-Nov-20 5-Dic-20 12-Dic-20 19-Dic-20 26-Dic-20 2-Ene-21

1.00 OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES S/1,263,412.52 5.88% 86.24% 54.14% -32.09%

2.00 MINA .

LÍNEA BASE CONTRACTUAL % LB01 - CURVA S - ASAP (SCHEDULE )


2.01 BOCAMINAS S/195,586.77 0.91% 0.00% 0.00% 0.00%

2.02 CHIMENEA/PIQUE S/82,943.22 0.39% 0.00% 0.00% 0.00% ACTUAL - AVANCE FISICO REAL % LB01 - CURVA S - ALAP (PERFORMANCE)
14.43%

2.03 TRINCHERA S/17,041.32 0.08% 0.00% 0.00% 0.00%


.
2.04 MEDIA BARRETA S/14,768.21 0.07% 0.00% 0.00% 0.00%

2.05 TAJO S/13,076.26 0.06% 0.00% 0.00% 0.00%

3.00 INSTALACIONES DE PROCESAMIENTO

3.01 PLANTA DE PROCESAMIENTO S/51,374.82 0.24% 0.00% 97.55% 97.55%

4.00 OTRAS INFRAESTRUCTURAS RELACIONADAS CON EL PROYECTO

4.01 CAMPAMENTOS, OFICINAS Y TALLERES S/74,938.05 0.35% 0.00% 43.11% 43.11%


8.48%

5.00 INSTALACIONES PARA EL MANEJO DE RESIDUOS

5.01 DESMONTE DE MINA S/1,332,061.34 6.19% 2.56% 0.33% -2.24%

5.02 DEPOSITO DE RELAVES S/9,468,765.98 44.03% 3.55% 6.74% 3.19%

5.03 DEPOSITO DE MATERIAL EXCEDENTE (DME ID 565 PROYECTADO) S/8,265,087.69 38.44% 2.23% 19.93% 17.70%

6.00 MEDIDAS Y MANEJO AMBIENTAL DURANTE LA OBRA

6.01 PROGRAMA DE MEDIDAS PREVENTIVAS, CORRECTIVAS Y/O MITIGACION S/268,209.90 1.25% 25.53% 30.47% 4.93%

6.02 PROGRAMA DE MANEJO DE RESIDUOS S/176,460.00 0.82% 25.53% 22.19% -3.34%

6.03 PROGRAMA DE MONITOREO AMBIENTAL S/38,013.06 0.18% 25.53% 0.00% -25.53%

6.04 PROGRAMA DE SALUD Y SEGURIDAD S/150,520.35 0.70% 28.01% 36.12% 8.11%

6.05 PROGRAMA DE EDUCACION AMBIENTAL S/56,000.00 0.26% 23.08% 0.00% -23.08%

6.06 ACONDICIONAMIENTO DE AREAS INTERVENIDAS S/35,006.53 0.16% 0.00% 0.00% 0.00%

COSTO TOTAL (s/.) S/21,503,266.02 100.00% 8.48% 14.43% 5.95%

LÍNEA BASE CONTRACTUAL % LB01 - CURVA S - ASAP (SCHEDULE ) 0.00% 0.33% 1.19% 2.10% 2.33% 2.66% 2.89% 3.27% 3.80% 4.31% 4.83% 5.40% 5.97% 6.52% 6.95% 7.29% 7.63% 8.00% 8.48% 9.50% 10.60% 11.75%
LINEA BASE CONTRACTUAL % LB01 - SEMANAL 0.00% 0.33% 0.87% 0.91% 0.23% 0.33% 0.23% 0.38% 0.54% 0.50% 0.53% 0.57% 0.57% 0.55% 0.43% 0.34% 0.34% 0.37% 0.48% 1.02% 1.10% 1.15%
ACTUAL - AVANCE FISICO REAL % LB01 - CURVA S - ALAP (PERFORMANCE) 0.00% 0.22% 0.22% 0.37% 0.57% 1.02% 1.68% 2.01% 3.19% 3.74% 4.62% 5.15% 6.18% 6.65% 7.89% 9.18% 10.18% 13.61% 14.43%
ACTUAL - AVANCE FISICO REAL % LB01 - SEMANAL 0.00% 0.22% 0.00% 0.15% 0.20% 0.45% 0.66% 0.33% 1.18% 0.54% 0.89% 0.53% 1.03% 0.47% 1.24% 1.29% 1.00% 3.43% 0.82%

0.00% -0.11% -0.97% -1.74% -1.76% -1.64% -1.21% -1.26% -0.61% -0.57% -0.21% -0.25% 0.22% 0.13% 0.94% 1.89% 2.55% 5.61% 5.95%
CON RESPECTO A LÍNEA BASE CONTRACTUAL:

SPI 0.00 0.68 0.19 0.17 0.24 0.38 0.58 0.61 0.84 0.87 0.96 0.95 1.04 1.02 1.14 1.26 1.33 1.70 1.70
STATUS
ESTADO INICIO RETRASO RETRASO RETRASO RETRASO RETRASO RETRASO RETRASO RETRASO RETRASO RETRASO RETRASO OK OK OK OK OK OK OK