VALORIZACION SEMANAL N° 06 DEL 02/10/2014 AL 03/10/2014

FORMULA : 01 ESTRUCTURAS
PRESUPUESTO BASE :
PRESUPUESTO CONTRATADO:

PRESUPUESTADO ACUMULADO ANTERIOR SALDO POR EJECUTAR


ITEM DESCRIPCION UND
CANTIDAD P.UNIT PARCIAL LUNES MARTES MIERCOLES JUEVES VIERNES SABADO MES ACUMULADO SEMANA ANTERIOR PARCIAL TOTAL PRECIO %
1.00.00 OBRAS PROVISIONALES 0 0.00 0.00
1.01.01 OFICINA Y ALMACEN DE MATERIALES GLB 1.00 2,117.58 2,117.58 0.00 0 0.00 0.00 0.00
1.02.00 CARTEL DE OBRA S/ESPECIFICACIONES PZA 1.00 1,055.46 1,055.46 0.00 0 0.00 0.00 0.00
2.00.00 TRABAJOS PRELIMINARES 0 0.00 0.00
2.01.01 TRANSPORTE DE EQUIPO Y MATERIALES GLB 1.00 2,530.61 2,530.61 0.00 0 0.00 0.00 0.00
3.00.00 MOVIMIENTO DE TIERRAS 0 0.00 0.00
3.01.00 EXCAVACION DE ZANJAS 0 0.00 0.00
3.01.01 EXCAVACION ZANJAS PARA CIMIENTOS CORRIDOS.H=1.5 M3 21.82 51.04 1,113.49 2.02 0 0.00 2.02 102.90
3.01.02 EXCAVACION PARA ZAPATAS H= 1.50 MT M3 127.82 63.80 8,154.90 2.81 21.93 0 2.81 24.74 1,578.41
3.01.03 EXCAVACION PARA VIGAS DE CIMENTACION H= 0.80 MT M3 8.64 63.80 550.93 13.99 5.3 0.00 19.29 1,230.70
3.02.00 RELLENOS CON MATERIAL PROPIO Y PRESTAMO 0 0.00 0.00
3.02.01 RELLENO Y COMPACTACION C/MATERIAL PROPIO M3 72.43 21.27 1,540.67 3.98 0 0.00 3.98 84.74
3.03.00 ELIMINACION DE MATERIAL EXCEDENTE 0 0.00 0.00
3.03.01 ELIMINACION DE MATERIAL EXCEDENTE M3 155.43 21.27 3,305.99 0.00 0 0.00 0.00 0.00
4.00.00 OBRAS DE CONCRETO SIMPLE 0 0.00 0.00
4.01.00 CIMIENTOS CORRIDOS 0 0.00 0.00
4.01.01 CONCRETO CIMIENTOS C:H 1:8 +30% P.G M3 8.73 203.31 1,774.16 0.00 0 0.00 0.00 0.00
4.02.00 SOLADO PARA ZAPATA 0 0.00 0.00
4.02.01 CONCRETO C:H 1:10 E= 4" SOLADO M2 78.90 60.26 4,754.57 7.05 0 0.00 7.05 424.83
4.03.00 PISOS 0 0.00 0.00
4.03.01 FALSOPISO MEZCLA 1:8 CEMENTO-HORMIGON E= 0.10 M m2 168.62 35.61 6,004.56 0.00 0 0.00 0.00 0.00
5.00.00 OBRAS DE CONCRETO ARMADO 0 0.00 0.00
5.01.00 SOBRECIMIENTO ARMADO M3 0 0.00 0.00
5.01.01 CONCRETO F'C= 175 KG/CM2 M3 6.90 469.01 3,236.17 5.22 2.61 0.00 7.83 3,672.35
5.01.02 ENCOFRADO Y DESENCOFRADO SOBRECIMIENTO ARMADO M2 65.98 27.12 1,789.49 84.64 42.32 0.00 126.96 3,443.16
5.01.03 ACERO DE REFUERZO FY= 4200 KG/CM2 SOBRECIMIENTO ARMADO
KG 318.43 0.00 295.58 134.4 0.00 429.98 0.00
5.02.00 ZAPATAS 0 0.00 0.00
5.02.01 CONCRETO F'C= 210 KG/CM2 ZAPATA M3 37.01 286.85 10,616.78 2.28 0 0.00 2.28 653.16
5.02.02 ACERO DE REFUERZO FY= 4200 KG/CM2 ZAPATA KG 906.37 3.81 3,453.26 0.00 0 0.00 0.00 0.00
5.03.00 VIGAS DE CIMENTACION 0 0.00 0.00
5.03.01 CONCRETO F'C= 210 KG/CM2 VIGAS DE CIMENTACION M3 5.42 312.97 1,695.05 2.65 0 0.00 2.65 830.62
5.03.02 ENCOFRADO Y DESENCOFRADO DE VIGA CIMENTACION. M2 36.06 49.29 1,777.20 8.15 0 0.00 8.15 401.47
5.03.03 ACERO DE REFUERZO FY= 4200 KG/CM2 VIGAS DE CIMENTACIÓN
KG 677.20 4.42 2,993.22 309.98 97.82 0.00 407.80 1,802.48
5.04.00 COLUMNAS 0 0.00 0.00
5.04.01 CONCRETO F'C=210 KG/CM2 COLUMNAS M3 23.11 469.64 10,853.62 0 0.00 0.00 0.00
5.04.02 ENCOFRADO Y DESENCOFRADO COLUMNAS M2 260.40 46.56 12,124.22 2.23 60.76 0.00 62.99 2,932.63
5.04.03 ACERO DE REFUERZO FY= 4200 KG/CM2 COLUMNAS KG 4,502.09 3.89 17,513.12 144.90 0 0.00 144.90 563.64
5.05.00 PLACAS 0.00 0 0.00 0.00 0.00
5.05.01 CONCRETO F'C=210 KG/CM2 PLACAS M3 10.33 421.44 4,353.05 0 0.00 0.00 0.00
5.05.02 ENCOFRADO Y DESENCOFRADO PLACAS M2 194.22 52.01 10,101.12 0 0.00 0.00 0.00
5.05.03 ACERO DE REFUERZO FY= 4200 KG/CM2 PLACAS KG 2,070.76 3.86 7,993.11 125.93 0 125.93 125.93 486.09
6.00.00 MUROS Y TABIQUES DE ALBAÑILERIA 0 0.00 0.00 0.00
6.01.00 MUROS DE LADRILLO KING KONG 0 0.00 0.00 0.00
6.01.01 MURO LADRILLO KK ARCILLA SOGA P/T C: A 1:4 M2 615.15 58.14 35,764.82 36.37 32.806 36.37 69.18 4,021.89
TOTAL COSTO DIRECTO 157,167.15 22,229.06
GASTOS GENERALES 15% 23,575.07
UTILIDAD 10% 15,716.72
TOTAL 196,458.94
FACTOR DE RELACION: 0.90000 176,813.05