PART. DENOMINACION CANT. LARGO ANCHO ALTURA SUBTOTAL TOTAL UNID.
1.00.00 OBRAS PROVISIONALES
1.01.00 CARTEL DE OBRA 1 3.60 2.40 8.64 8.64 M2
1.02.00 ALMACEN DE OBRA 1 4.00 3.00 12.00 12.00 M2

2.00.00 OBRAS PRELIMINARES


2.01.00 LIMPIEZA PRELIMINAR DE OBRA MANUAL 1 142.00 1.00 142.00 142.00 M2
2.02.00 TRAZO NIVEL Y REPLANTEO PRELIMINAR 1 142.00 1.00 142.00 142.00 M2

3.00.00 MOVIMIENTO DE TIERRA


3.01.00 EXCAVACION MANUAL EN ROCA SUELTA
EJES A y I 2 25.00 0.50 1.10 27.50
EJES 1 y 4 2 13.00 0.50 1.10 14.30 41.80 M3
3.02.00 RELLENO Y COMPACT. MATERIAL PROPIO MANUAL
EJES A y I 1 25.00 0.35 0.20 1.75
EJE 1y 5 1 13.00 0.35 0.20 0.91
2.66 M3
3.03.00 ACARREO MATERIAL DE EXCAVACIONES 1 2.66 3.19 3.19 M3

4.00.00 OBRAS DE CONCRETO SIMPLE


4.01.00 CONCRETO 1:10+30%P.G. CIMIENTO CORRIDO
EJES A y I 2 25.00 0.50 0.90 22.50
EJES 1 y 5 2 13.00 0.50 0.90 11.70 34.20 M3

5.00.00 OBRAS DE CONCRETO ARMADO


5.01.00 SOBRECIMIENTO
5.01.01 CONCRETO F'c=175 Kg/cm2 SOBRECIMIENTO
EJES A y I 2 25.00 0.15 0.35 2.63
EJE 1 y 5 1 13.00 0.15 0.35 0.68
3.31 M3
5.01.03 ENCOFRADO Y DESENCOFRADO SOBRECIMIENTO
EJES A y J 2 26.00 0.30 15.60
EJE 1 Y 4 2 13.00 0.30 7.80
23.40 M2
5.02.00 COLUMNAS
5.02.01 CONCRETO F'c=175 Kg/cm2 COLUMNAS
COLUMNA C1 3 0.40 0.25 2.35 0.71
COLUMNA C2 18 0.40 0.15 2.35 2.54
COLUMNA C3 3 0.40 0.15 2.35 0.42
3 0.25 0.15 2.35 0.26 3.93 M3
5.02.02 ACERO DE REFUERZO F'y=4200 Kg/cm2
ø1/2" COLUMNA C1 12 3.85 48.51
ø3/8" COLUMNA C1 6 3.85 12.01
ø1/4" ESTRIBOS 57 1.25 18.53
ø1/2" COLUMNA C2 72 3.85 291.06
ø1/4" ESTRIBOS 342 1.05 93.37
ø1/2" COLUMNA C3 12 3.85 48.51
ø3/8" COLUMNA C3 12 3.85 24.02
ø1/4" ESTRIBOS 114 1.05 31.12 567.13 Kg
5.02.03 ENCOFRADO Y DESENCOFRADO COLUMNAS
COLUMNA C1 3 1.30 2.00 7.80
COLUMNA C2 40 0.80 2.00 64.00
COLUMNA C3 3 1.30 2.00 7.80 79.60 M2
5.03.00 VIGAS
5.03.01 CONCRETO F'c=175 Kg/cm2 VIGAS
VIGA VS, EJES A y I 2 25.40 0.15 0.20 1.52
VIGA VS, EJE 1Y 5 2 13.40 0.15 0.20 0.80
2.33 M3
5.03.02 ACERO DE REFUERZO F'y=4200 Kg/cm2
ø3/8" VIGA V-S, EJES A y I 4 25.00 52.00
ø1/4" ESTRIBOS 250 0.77 50.05
ø3/8" VIGA V-S, EJE 1Y 5 4 13.00 27.04
HOJA DE METRADOS
OBRA: HECHO POR : THALIA PINEDA
PROPIETARIO: REVISADO POR :
FECHA : JUNIO 2021
PART. DENOMINACION CANT. LARGO ANCHO ALTURA SUBTOTAL TOTAL UNID.
ø1/4" ESTRIBOS 120 0.77 24.02

153.11 Kg
5.03.03 ENCOFRADO Y DESENCOFRADO VIGAS
VIGA VS, EJES A y I 2 25.00 0.20 10.00
VIGA VS, EJE 1Y 5 2 13.00 0.20 5.20
15.20 M2

6.00.00 MUROS Y TABIQUES


6.01.00 MURO LADRILLO ARCILLA KK SOGA, 2CV Mo.Co. 1:5
EJE A 1 21.40 2.00 42.80
EJE A PUERTA 1 17.45 2.00 34.90
EJE 1 - 5 2 11.00 2.00 44.00 121.70 M2

7.00.00 REVOQUES Y ENLUCIDOS


7.01.00 TARRAJEO Co. FROTACHADO SOBRECIMIENTO
EJE A Y I 1 25.00 0.15 3.75
EJE AYG 1 20.10 0.15 3.02
EJE 1Y 5 2 13.00 0.15 3.90
10.67 M2
7.02.00 TARRAJEO Co. FROTACHADO COLUMNAS
COLUMNA C1 3 1.15 2.00 6.90
COLUMNA C2 (AMBAS CARAS) 18 0.80 2.00 28.80
COLUMNA C3 3 1.30 2.00 7.80 43.50 M2
7.03.00 TARRAJEO Co. FROTACHADO VIGAS
VIGA VS, EJE A Y I 2 25.00 0.20 10.00
VIGA VS, EJE 1-5 2 13.00 0.20 5.20

15.20 M2

8.00.00 CARPINTERIA METALICA


8.01.00 PUERTA PERFIL Fe. PL. Ao. CONTRAPLACADA
PUERTA DE ACCESO VEHICULAR 1 3.20 2.30 7.36
PUERTA DE ACCESO PEATONAL 1 1.20 2.30 2.76 10.12 M2

9.00.00 PINTURA
9.01.00 PINTURA LATEX SOBRECIMIENTO
EJE A Y I 1 25.00 0.15 3.75
EJE A Y G 1 20.10 0.15 3.02
EJE 1-5 2 13.00 0.15 3.90
10.67 M2
9.02.00 PINTURA LATEX COLUMNAS
COLUMNA C1 3 1.15 2.00 6.90
COLUMNA C2 (AMBAS CARAS) 18 0.80 2.00 28.80
COLUMNA C3 3 1.30 2.00 7.80 43.50 M2
9.03.00 PINTURA LATEX VIGAS
VIGA VS, EJE A Y I 2 25.00 0.20 10.00
VIGA VS, EJE 1-5 2 13.00 0.20 5.20
15.20 M2
9.04.00 PINTURA ESMALTE CARPINTERIA METALICA
PUERTA DE ACCESO VEHICULAR 2 3.20 2.30 14.72
PUERTA DE ACCESO PEATONAL 2 1.20 2.30 5.52 20.24 M2
3.85-0.5-0.40 2.95
2.95/0.20 14 ESTRIBOS
14+5 19

19X3 57

19X18 342

19X6 114

25-0.5-0.40 24.1 13-0.5-0.40 12.1


24.10/0.20 120 ESTRIBOS 12.10/0.20 120 ESTRIBOS
120+5 125 120+5 60

125X2 250 60X2 120