CARGA MUERTA EJE C PISO 1 Y 2

1er tramo
Ancho Alto Peso Espec. Carga
Peso propio 0.5 0.5 2.4 0.60 Tn/ml

2do tramo
Ancho Alto Peso Espec. Carga
Peso propio 0.5 0.5 2.4 0.60 Tn/ml

Alto Peso Espec. Carga


Losa = 0.16 2.4 0.384 Tn/m2
Piso term. = 0.1 Tn/m2
0.484 Tn/m2

Alto Carga Carga distr.


Wm1 2 0.484 0.97 Tn/ml

Tab = Ancho Alto Peso Espec.


0.15 3.84 1.8 1.04 Tn/m2

Wtab hor 1.04 3.9 5 0.81 Tn/ml

Wtab vert 1.04 1.1 1.14 Tn

3er tramo
Ancho Alto Peso Espec. Carga
Peso propio 0.5 0.5 2.4 0.60 Tn/ml

Alto Peso Espec. Carga


Losa = 0.16 2.4 0.384 Tn/m2
Piso term. = 0.1 Tn/m2
0.484 Tn/m2

Alto Carga Carga distr.


Wm2 2 0.484 0.97 Tn/ml

Tab = Ancho Alto Peso Espec.


0.15 3.84 1.8 1.04 Tn/m2

Wtab hor 1.04 3.9 5 0.81 Tn/ml

Wtab vert 1.04 0.6 3.9 / 5 0.49 Tn

4to tramo
Ancho Alto Peso Espec. Carga
Peso propio 0.5 0.5 2.4 0.60 Tn/ml
CARGA VIVA EJE C PISO 1 Y 2
1er tramo

Area viga = 0.5 0.2 0.10 Tn/ml

2do tramo

Lo = 0.2 Tn/m2
At = 4 0.9 4.900 m2
Ai = 4.9 2 9.8 m2
Fr = 0.344 m2
Lr = 0.2 0.344 0.069 m2

Wm1 = 0.069 2 0.14 Tn/ml

3er tramo

Lo = 0.25 Tn/m2
At = 4 0.9 4.900 m2
Ai = 4.9 2 9.8 m2
Fr = 0.430 m2
Lr = 0.25 0.430 0.107 m2

Wm1 = 0.107 2 0.21 Tn/ml

4to tramo

Area viga = 0.5 0.25 0.13 Tn/ml


CARGA MUERTA EJE C PISO 3
1er tramo
Ancho Alto Peso Espec. Carga
Peso propio 0.5 0.5 2.4 0.60 Tn/ml

2do tramo
Ancho Alto Peso Espec. Carga
Peso propio 0.5 0.5 2.4 0.60 Tn/ml

Alto Peso Espec. Carga


Losa = 0.13 2.4 0.312 Tn/m2
Piso term. = 0.1 Tn/m2
0.412 Tn/m2

Alto Carga Carga distr.


Wm1 2 0.412 0.82 Tn/ml

3er tramo
Ancho Alto Peso Espec. Carga
Peso propio 0.5 0.5 2.4 0.60 Tn/ml

Alto Peso Espec. Carga


Losa = 0.13 2.4 0.312 Tn/m2
Piso term. = 0.1 Tn/m2
0.412 Tn/m2

Alto Carga Carga distr.


Wm2 2 0.412 0.82 Tn/ml

4to tramo
Ancho Alto Peso Espec. Carga
Peso propio 0.5 0.5 2.4 0.60 Tn/ml
CARGA VIVA EJE C PISO 3
1er tramo

Area viga = 0.5 0.1 0.05 Tn/ml

2do tramo

Lo = 0.1 Tn/m2
At = 4 0.9 4.900 m2
Ai = 4.9 2 9.8 m2
Fr = 0.172 m2
Lr = 0.1 0.172 0.017 m2

Wm1 = 0.017 2 0.03 Tn/ml

3er tramo

Lo = 0.25 Tn/m2
At = 4 0.9 4.900 m2
Ai = 4.9 2 9.8 m2
Fr = 0.430 m2
Lr = 0.25 0.430 0.107 m2

Wm1 = 0.107 2 0.21 Tn/ml

4to tramo

Area viga = 0.5 0.25 0.13 Tn/ml