HOSPITAL DANIEL ALCIDES CARRION -HUANCAYO-

Código Ud Resumen ud cantidad precio / m2 costo parcial


T DRYWALL
1.01.2 m2 TABIQUE DRYWALL 11,5 cm 2 CARAS ST 1/2". TOTAL M2 1,841.20

MATERIAL

clavos p/ fijación de 1" cto 0.020 2.370 0.047


tornillo 6x1 punta fina mill 0.037 6.930 0.256
tornillo 7x7/16 punta fina mill 0.005 5.790 0.029
fulminante marron cal 22 cto 0.020 5.710 0.114
esquinero metalico lineal ud 0.080 3.050 0.244
riel de 3 5/8" x 0,045 x 3 mt ud 0.285 5.330 1.519
parante de 3 5/8" x 0,045 x 3 mt ud 1.007 6.710 6.757
pasta p/junta de planchas de drywall ( 1 balde ) kg 1.200 1.545 1.855
cinta malla ml 2.000 0.063 0.127
lana de fibra de vidrio fiberglass de 3 1/2" ( 1 rollo ) m2 1.007 5.279 5.316
placa de yeso 1/2" ST ud 0.707 24.240 17.138

total materiales 33.40


M.O.

mano de obra de instalación m2 1.000 20.000 20.000

total M.O. 20.00

EQUIPOS Y HERRAMIENTAS

5% s/ M.O. % 0.005 20.000 0.100


total equipos y herramientas 0.100

TOTAL ITEM 53.50

1.01.3 m2 TABIQUE DE CEMENTO SUPERBORD (fibrocemento) 10 TOTAL M2 1,841.20


mm 2 CARAS

MATERIAL

clavos p/ fijación de 1" cto 0.020 2.370 0.047


tornillo 6x1 punta fina mill 0.037 6.930 0.256
tornillo 7x7/16 punta fina mill 0.005 5.790 0.029
fulminante marron cal 22 cto 0.020 5.710 0.114
esquinero metalico lineal ud 0.080 3.050 0.244
riel de 3 5/8" x 0,045 x 3 mt ud 0.285 5.330 1.519
parante de 3 5/8" x 0,045 x 3 mt ud 1.007 6.710 6.757
pasta p/junta planchas fibrocemento ( 1 balde ) kg 1.200 1.545 1.855
cinta malla ml 2.000 0.063 0.127
lana de fibra de vidrio fiberglass de 3 1/2" ( 1 rollo ) m2 1.007 5.279 5.316
plancha DURABORD (fibrocemento) 10 mm ud 0.707 51.820 36.637

total materiales 52.90


M.O.
mano de obra de instalación m2 1.000 20.000 20.000

total M.O. 20.00

EQUIPOS Y HERRAMIENTAS

5% s/ M.O. % 0.005 20.000 0.100

total equipos y herramientas 0.100

TOTAL ITEM 73.00


HOSPITAL DANIEL ALCIDES CARRION -HUANCAYO-BLOQUE A
Código Ud Resumen ud cantidad precio / m2 costo parcial
FCR FALSO CIELO RASO

FCR1 m2 CIELO RASO METALICO CON BALDOSA DE FIBRA MINERAL TOTAL M2 1,480.26
0,60x0,60 m, SUSPENDIDA DE PERFILERIA METALICA DE ACERO
GALVANIZADO PREPINTADA, OWA COSMOS para descuelgües
aproximados de 1,00 m.

MATERIAL
ud cantidad precio / m2 costo parcial cantidad
Utilizar en
obra
angulo perimetral (0,4 mm ), de 3 m. ud 0.22 2.07 0.455 325.66
suspensión principal (0,3 mm), 3,66 m. ud 0.46 1.26 0.580 680.92
suspensión secundaria (0,27 mm/1220), 1,22 m. ud 0.73 1.14 0.832 1,080.59
suspensión terciario (0,27 mm/1220), 1,22 m. ud 0.73 0.94 0.686 1,080.59
fulminante verde cal. 22 (caja 100 ud.) ud 0.080 5.71 0.457 118.42
kit ( clavos + ganchos ) ( caja 100 ud.) ud 0.014 13.65 0.191 20.72
alambre galvanizado # 14 ( 36 m / kg ) kg 0.020 2.80 0.056 29.61
baldosa OWA COSMOS ud 2.800 11.97 33.516 4,144.73

total materiales 36.77


M.O.

mano de obra de instalación m2 1.000 18.000 18.00

total M.O. 18.00

EQUIPOS Y HERRAMIENTAS

5% s/ M.O. % 0.005 18.000 0.09


total equipos y herramientas 0.09

TOTAL ITEM 54.86

FCR2 m2 CIELO RASO METALICO CON BALDOSA DE FIBRA MINERAL TOTAL M2 72.87
0,60x0,60 m, SUSPENDIDA DE PERFILERIA METALICA DE ACERO
GALVANIZADO PREPINTADA, OWA CONSTELLATION para
descuelgües aproximados de 1,00 m.

MATERIAL

ud cantidad precio / m2 costo parcial cantidad


Utilizar en
obra
angulo perimetral (0,4 mm ), de 3 m. ud 0.22 2.07 0.455 16.03
suspensión principal (0,3 mm), 3,66 m. ud 0.46 1.26 0.580 33.52
suspensión secundaria (0,27 mm/1220), 1,22 m. ud 0.73 1.14 0.832 53.20
suspensión terciario (0,27 mm/1220), 1,22 m. ud 0.73 0.94 0.686 53.20
fulminante verde cal. 22 (caja 100 ud.) ud 0.080 5.71 0.457 5.83
kit ( clavos + ganchos ) ( caja 100 ud.) ud 0.014 13.65 0.191 1.02
alambre galvanizado # 14 ( 36 m / kg ) kg 0.020 2.80 0.056 1.46
baldosa CONSTELLATION ud 2.800 22.18 62.104 204.04

total materiales 65.36


M.O.
mano de obra de instalación m2 1.000 18.000 18.00

total M.O. 18.00

EQUIPOS Y HERRAMIENTAS
5% s/ M.O. % 0.005 18.000 0.09
total equipos y herramientas 0.09

TOTAL ITEM 83.45

FCR3 m2 CIELO RASO METALICO CON BALDOSA DE FIBRA MINERAL TOTAL M2 272.66
0,60x0,60 m, SUSPENDIDA DE PERFILERIA METALICA DE ACERO
GALVANIZADO PREPINTADA, OWA TACLA, para descuelgües
aproximados de 1,00 m, en SSHH.

MATERIAL

ud cantidad precio / m2 costo parcial cantidad


Utilizar en
obra
angulo perimetral (0,4 mm ), de 3 m. ud 0.22 2.07 0.455 59.99
suspensión principal (0,3 mm), 3,66 m. ud 0.46 1.26 0.580 125.42
suspensión secundaria (0,27 mm/1220), 1,22 m. ud 0.73 1.14 0.832 199.04
suspensión terciario (0,27 mm/1220), 1,22 m. ud 0.73 0.94 0.686 199.04
fulminante verde cal. 22 (caja 100 ud.) ud 0.080 5.71 0.457 21.81
kit ( clavos + ganchos ) ( caja 100 ud.) ud 0.014 13.65 0.191 3.82
alambre galvanizado # 14 ( 36 m / kg ) kg 0.020 2.80 0.056 5.45
baldosa de fibra mineral OWA TACLA ud 2.800 8.84 24.752 763.45

total materiales 28.01


M.O.

mano de obra de instalación m2 1.000 18.000 18.00

total M.O. 18.00

EQUIPOS Y HERRAMIENTAS

5% s/ M.O. % 0.005 18.000 0.09


total equipos y herramientas 0.09

TOTAL ITEM 46.10

FCR4 m2 CIELO RASO CON PLACA K762 KNAUF SAFEBOARD o SIMILAR, TOTAL M2 #REF!
DE DIMENSIONES 625x2500 y e= 12,5 mm., CON SUSPENSION
METALICA, para descuelgües aprox. de 1 m.

MATERIAL

ud cantidad precio / m2 costo parcial cantidad


Utilizar en
obra
parantes 2 1/2" ud 1.06 5.640 5.978 #REF!
clavos p/ fijación de 1" cto 0.04 2.370 0.095 #REF!
tornillo 6x1 punta fina mill 0.04 6.930 0.256 #REF!
cinta malla ml 2.00 0.063 0.127 #REF!
fulminante marrón cal 22 cto 0.04 5.710 0.228 #REF!
Cargamuertos parantes 3 5/8" ud 0.71 9.870 6.975 #REF!
Muertos parantes 3 5/8" ud 0.71 9.870 6.975 #REF!
tornillo 7x7/16 punta fina mill 0.005 6.260 0.031 #REF!
pasta p/junta de planchas de drywall ( 1 balde ) kg 0.700 2.030 1.421 #REF!
placa K762 ud 0.340 30.000 10.200 #REF!

total materiales 32.29


M.O.
mano de obra de instalación m2 1.000 18.000 18.00

total M.O. 18.00


EQUIPOS Y HERRAMIENTAS

5% s/ M.O. % 0.005 18.000 0.09


total equipos y herramientas 0.09

TOTAL ITEM 50.38

FCR5 m2 CIELO RASO CON PLACA DE YESO PANEL REY DE 3/8", DE TOTAL M2 #REF!
DIMENSIONES 1,22x2,44 m. CON SUSPENSION METALICA, para
descuelgües aproximados de 1,00 m.

MATERIAL

ud cantidad precio / m2 costo parcial cantidad


Utilizar en
obra
parantes 2 1/2" ud 1.06 5.640 5.978 #REF!
clavos p/ fijación de 1" cto 0.04 2.370 0.095 #REF!
tornillo 6x1 punta fina mill 0.04 6.930 0.256 #REF!
cinta malla ml 2.00 0.063 0.127 #REF!
fulminante marrón cal 22 cto 0.04 5.710 0.228 #REF!
Cargamuertos parantes 3 5/8" ud 0.71 9.870 6.975 #REF!
Muertos parantes 3 5/8" ud 0.71 9.870 6.975 #REF!
tornillo 7x7/16 punta fina mill 0.005 6.260 0.031 #REF!
pasta p/junta de planchas de drywall ( 1 balde ) kg 0.700 2.030 1.421 #REF!
plancha panel Rey ST de 3/8" ud 0.340 15.770 5.362 #REF!

total materiales 27.45


M.O.

mano de obra de instalación m2 1.000 18.000 18.00

total M.O. 18.00

EQUIPOS Y HERRAMIENTAS

5% s/ M.O. % 0.005 18.000 0.09


total equipos y herramientas 0.09

TOTAL ITEM 45.54

FCR6 m2 CIELO RASO CON PLACA DE YESO PANEL REY DE 3/8", DE TOTAL M2 #REF!
DIMENSIONES 1,22x2,44 m. CON SUSPENSION METALICA, para
descuelgües aproximados de 1,00 m.

MATERIAL

ud cantidad precio / m2 costo parcial cantidad


Utilizar en
obra
parantes 2 1/2" ud 1.06 5.640 5.978 #REF!
clavos p/ fijación de 1" cto 0.04 2.370 0.095 #REF!
tornillo 6x1 punta fina mill 0.04 6.930 0.256 #REF!
cinta malla ml 2.00 0.063 0.127 #REF!
fulminante marrón cal 22 cto 0.04 5.710 0.228 #REF!
Cargamuertos parantes 3 5/8" ud 0.71 9.870 6.975 #REF!
Muertos parantes 3 5/8" ud 0.71 9.870 6.975 #REF!
tornillo 7x7/16 punta fina mill 0.005 6.260 0.031 #REF!
pasta p/junta de planchas de drywall ( 1 balde ) kg 0.700 2.030 1.421 #REF!
plancha panel Rey ST de 3/8" ud 0.340 15.770 5.362 #REF!

total materiales 27.45


M.O.

mano de obra de instalación m2 1.000 18.000 18.00

total M.O. 18.00

EQUIPOS Y HERRAMIENTAS

5% s/ M.O. % 0.005 18.000 0.09


total equipos y herramientas 0.09

TOTAL ITEM 45.54

CANTIDAD TOTAL DE MATERIALES


angulo perimetral (0,4 mm ), de 3 m. ud 401.67
suspensión principal (0,3 mm), 3,66 m. ud 839.86
suspensión secundaria (0,27 mm/1220), 1,22 m. ud 1,332.83
suspensión terciario (0,27 mm/1220), 1,22 m. ud 1,332.83
fulminante verde cal. 22 (caja 100 ud.) ud 146.06
kit ( clavos + ganchos ) ( caja 100 ud.) ud 25.56
alambre galvanizado # 14 ( 36 m / kg ) kg
baldosa OWA COSMOS ud
ud descripción ct. largo ancho alto parcial

HOSPITAL DANIEL ALCIDES II -HUANCAYO-

BLOQUE B

m2 FCR BALDOSA OWA COSMOS 60x60


h= ???????
NIVEL 1
SECTOR 1 y SECTOR 2

1 32.22 32.22
1 35.29 35.29
1 5.95 5.95
1 3.18 3.18
1 2.59 2.59
1 338.69 338.69

1 30.08 30.08
1 45.11 45.11
1 306.46 306.46
1 28.56 28.56
1 18.24 18.24
1 18.75 18.75
1 37.52 37.52
1 17.16 17.16
1 151.06 151.06
1 17.16 17.16
1 109.81 109.81
1 15 15
1 183.38 183.38
1 19.17 19.17
1 49.31 49.31
1 64.24 64.24
1 15.35 15.35
1 8.05 8.05
1 49.73 49.73
1 18.87 18.87
1 3.35 3.35
1 6.65 6.65
1 10.64 10.64
1 5.65 5.65
1 33.69 33.69
1 33.79 33.79
1 10.24 10.24
1 41.1 41.1
1 10.26 10.26
1 15.74 15.74
1792.04

NIVEL 2
SECTOR 1 y SECTOR 2

1 5.03 5.03
1 8.27 8.27
1 22.95 22.95
1 20.18 20.18
1 156.51 156.51
1 28.95 28.95
1 6.72 6.72
1 22.78 22.78
1 19.5 19.5
1 28.42 28.42
1 149.91 149.91
1 157.88 157.88
1 342.32 342.32
1 2.5 2.5

1 37.7 37.7
1 29.61 29.61

1039.23

NIVEL 3
SECTOR 1 y SECTOR 2

1 3.3 3.3
1 205.84 205.84
1 73.05 73.05
1 27.01 27.01
2 1.16 2.32
6 22.33 133.98
1 144.35 144.35
1 14.32 14.32
1 8.76 8.76
1 6.28 6.28
1 26 26
1 21.54 21.54
1 14.95 14.95
1 13.67 13.67
1 18.4 18.4
1 3.46 3.46

1 26 26
1 29.6 29.6
1 29.1 29.1

801.93

m2 FCR BALDOSA OWA CONSTELLATION 60x60


h= ???????
NIVEL 1
SECTOR 1 y SECTOR 2

2 12.36 24.72
1 8.52 8.52
1 8.17 8.17
1 8.32 8.32
1 12.07 12.07
1 12.41 12.41
1 12.33 12.33
1 14.94 14.94
1 46.48 46.48
1 14.31 14.31
1 32.48 32.48
1 57.16 57.16
1 32.33 32.33

284.24

NIVEL 2
SECTOR 1 y SECTOR 2

1 16.82 16.82
1 6.28 6.28
1 14.28 14.28
1 16.75 16.75
1 13.91 13.91
1 14.09 14.09
1 14.06 14.06
1 14.31 14.31
1 17.1 17.1
1 11.27 11.27
1 15.11 15.11
1 15.6 15.6
1 14.54 14.54
1 14.77 14.77
10 14.2 142
2 13.84 27.68
1 13.9 13.9
1 13.63 13.63
1 15.4 15.4
1 15.12 15.12
1 14.92 14.92
1 14.29 14.29
1 14.67 14.67
1 14.97 14.97

485.47

NIVEL 3
SECTOR 1 y SECTOR 2

9 14.2 127.8
1 14.77 14.77
1 15 15
1 14.78 14.78
1 14.03 14.03
1 14.25 14.25
1 12.77 12.77
1 32.3 32.3
1 16.5 16.5
1 16.55 16.55
1 23.89 23.89
1 11.65 11.65
1 23.89 23.89
1 32.59 32.59
1 10.41 10.41
1 18.99 18.99
1 25.27 25.27
1 15.96 15.96
1 16.18 16.18

457.58

m2 FCR BALDOSA OWA TACLA 60x60


h= ???????
NIVEL 1
SECTOR 1 y SECTOR 2

4 3 12
1 6.1 6.1
1 3.33 3.33
2 6.12 12.24
2 2.46 4.92
1 5.47 5.47
1 3 3
1 7.7 7.7
1 16.74 16.74
1 19.42 19.42
1 91.62 91.62
1 12.44 12.44
1 11.7 11.7
1 2.52 2.52
1 12.24 12.24
1 11.72 11.72
1 11.85 11.85
1 38.82 38.82
1 4.28 4.28
1 10.02 10.02
1 13.12 13.12
1 6 6
1 19 19
1 5.18 5.18
1 12.36 12.36
1 8.31 8.31
1 13.85 13.85
1 8.31 8.31
1 5.45 5.45
1 5.49 5.49
1 10.24 10.24
1 6.3 6.3
1 6.74 6.74
1 12.36 12.36
1 3.48 3.48

1 12.29 12.29
1 17.74 17.74

464.35

NIVEL 2
SECTOR 1 y SECTOR 2

1 6.67 6.67
1 32.99 32.99
2 7.88 15.76
1 8.31 8.31
1 6.79 6.79
1 6.97 6.97
1 11.44 11.44
1 17.31 17.31
1 3.48 3.48
1 14.92 14.92
1 14.44 14.44

139.08

NIVEL 3
SECTOR 1 y SECTOR 2

1 4.66 4.66
1 14.38 14.38
1 14.64 14.64
1 3.64 3.64
1 4.14 4.14
1 4.26 4.26
1 7.12 7.12
1 4.18 4.18
1 3.34 3.34
1 6.09 6.09
1 5.85 5.85
1 9.64 9.64
1 9.45 9.45
1 6.97 6.97
1 3.18 3.18
1 2.81 2.81
1 6.75 6.75
1 6.41 6.41
1 3.91 3.91
1 3.24 3.24
1 10.95 10.95
1 13.78 13.78
1 13.23 13.23
1 17.1 17.1
1 1.88 1.88
1 2.55 2.55
1 2.48 2.48

186.63

BLOQUE A

m2 FCR BALDOSA OWA COSMOS 60x60


h= ???????
NIVEL 1
SECTOR 1 y SECTOR 2

1 12.24 12.24
1 16.06 16.06
1 12.87 12.87
1 12.81 12.81
1 19.35 19.35
1 22.77 22.77
1 14.63 14.63
1 3.61 3.61
1 5 5
2 6.15 12.3
1 170.53 170.53
1 21.15 21.15
1 9.67 9.67
1 15.4 15.4
1 90.46 90.46
1 136.03 136.03
1 36.11 36.11
1 3.04 3.04
1 5.66 5.66
1 72.45 72.45
1 8.39 8.39
1 15.52 15.52
1 14.94 14.94
1 195.07 195.07
1 125.31 125.31
1 132.05 132.05
1 22.55 22.55
1 25.86 25.86
1 13.74 13.74
1 8.61 8.61
1 36.26 36.26
1 7.65 7.65
1 21.91 21.91
1 27.45 27.45
1 15.54 15.54
1 13.42 13.42
1 14.57 14.57
1 25.34 25.34
1 4.95 4.95
1 20.89 20.89
1 38.1 38.1

1480.26

m2 FCR BALDOSA OWA CONSTELLATION 60x60


h= ???????
NIVEL 1
SECTOR 1 y SECTOR 2

1 10.29 10.29
1 13.26 13.26
1 49.32 49.32

72.87

m2 FCR BALDOSA OWA TACLA 60x60


h= ???????
NIVEL 1
SECTOR 1 y SECTOR 2

1 2.23 2.23
1 6.3 6.3
1 12.27 12.27
1 12.8 12.8
1 2.94 2.94
1 6.5 6.5
1 3.84 3.84
1 5.46 5.46
1 6.6 6.6
1 8.17 8.17
1 4.05 4.05
1 3.52 3.52
1 23.31 23.31
1 17.13 17.13
1 19.13 19.13
1 10.39 10.39
1 4.28 4.28
1 17.74 17.74
1 14.29 14.29
4 3 12
1 11.59 11.59
1 2.92 2.92
1 2.7 2.7
1 3.06 3.06
1 3.03 3.03
1 3.24 3.24
1 3.6 3.6
1 7.1 7.1
2 3.6 7.2
1 17.6 17.6
1 17.67 17.67

272.66
total
3633.20
1227.29
790.06
HOSPITAL DANIEL ALCIDES CARRION -HUANCAYO-BLOQUE A
Código Ud Resumen ud cantidad precio / m2 costo parcial
FCR FALSO CIELO RASO

FCR1 m2 CIELO RASO METALICO CON BALDOSA DE FIBRA MINERAL TOTAL M2 3,633.20
0,60x0,60 m, SUSPENDIDA DE PERFILERIA METALICA DE ACERO
GALVANIZADO PREPINTADA, OWA COSMOS para descuelgües
aproximados de 1,00 m.

MATERIAL
ud cantidad precio / m2 costo parcial cantidad
Utilizar en
obra
angulo perimetral (0,4 mm ), de 3 m. ud 0.22 2.07 0.455 799.30
suspensión principal (0,3 mm), 3,66 m. ud 0.46 1.26 0.580 1,671.27
suspensión secundaria (0,27 mm/1220), 1,22 m. ud 0.73 1.14 0.832 2,652.24
suspensión terciario (0,27 mm/1220), 1,22 m. ud 0.73 0.94 0.686 2,652.24
fulminante verde cal. 22 (caja 100 ud.) ud 0.080 5.71 0.457 290.66
kit ( clavos + ganchos ) ( caja 100 ud.) ud 0.014 13.65 0.191 50.86
alambre galvanizado # 14 ( 36 m / kg ) kg 0.020 2.80 0.056 72.66
baldosa OWA COSMOS ud 2.800 11.97 33.516 10,172.96

total materiales 36.77


M.O.

mano de obra de instalación m2 1.000 18.000 18.00

total M.O. 18.00

EQUIPOS Y HERRAMIENTAS

5% s/ M.O. % 0.005 18.000 0.09


total equipos y herramientas 0.09

TOTAL ITEM 54.86

FCR2 m2 CIELO RASO METALICO CON BALDOSA DE FIBRA MINERAL TOTAL M2 1,227.29
0,60x0,60 m, SUSPENDIDA DE PERFILERIA METALICA DE ACERO
GALVANIZADO PREPINTADA, OWA CONSTELLATION para
descuelgües aproximados de 1,00 m.

MATERIAL

ud cantidad precio / m2 costo parcial cantidad


Utilizar en
obra
angulo perimetral (0,4 mm ), de 3 m. ud 0.22 2.07 0.455 270.00
suspensión principal (0,3 mm), 3,66 m. ud 0.46 1.26 0.580 564.55
suspensión secundaria (0,27 mm/1220), 1,22 m. ud 0.73 1.14 0.832 895.92
suspensión terciario (0,27 mm/1220), 1,22 m. ud 0.73 0.94 0.686 895.92
fulminante verde cal. 22 (caja 100 ud.) ud 0.080 5.71 0.457 98.18
kit ( clavos + ganchos ) ( caja 100 ud.) ud 0.014 13.65 0.191 17.18
alambre galvanizado # 14 ( 36 m / kg ) kg 0.020 2.80 0.056 24.55
baldosa CONSTELLATION ud 2.800 22.18 62.104 3,436.41

total materiales 65.36


M.O.
mano de obra de instalación m2 1.000 18.000 18.00

total M.O. 18.00

EQUIPOS Y HERRAMIENTAS
5% s/ M.O. % 0.005 18.000 0.09
total equipos y herramientas 0.09

TOTAL ITEM 83.45

FCR3 m2 CIELO RASO METALICO CON BALDOSA DE FIBRA MINERAL TOTAL M2 790.06
0,60x0,60 m, SUSPENDIDA DE PERFILERIA METALICA DE ACERO
GALVANIZADO PREPINTADA, OWA TACLA, para descuelgües
aproximados de 1,00 m, en SSHH.

MATERIAL

ud cantidad precio / m2 costo parcial cantidad


Utilizar en
obra
angulo perimetral (0,4 mm ), de 3 m. ud 0.22 2.07 0.455 173.81
suspensión principal (0,3 mm), 3,66 m. ud 0.46 1.26 0.580 363.43
suspensión secundaria (0,27 mm/1220), 1,22 m. ud 0.73 1.14 0.832 576.74
suspensión terciario (0,27 mm/1220), 1,22 m. ud 0.73 0.94 0.686 576.74
fulminante verde cal. 22 (caja 100 ud.) ud 0.080 5.71 0.457 63.20
kit ( clavos + ganchos ) ( caja 100 ud.) ud 0.014 13.65 0.191 11.06
alambre galvanizado # 14 ( 36 m / kg ) kg 0.020 2.80 0.056 15.80
baldosa de fibra mineral OWA TACLA ud 2.800 8.84 24.752 2,212.17

total materiales 28.01


M.O.

mano de obra de instalación m2 1.000 18.000 18.00

total M.O. 18.00

EQUIPOS Y HERRAMIENTAS

5% s/ M.O. % 0.005 18.000 0.09


total equipos y herramientas 0.09

TOTAL ITEM 46.10

FCR4 m2 CIELO RASO CON PLACA K762 KNAUF SAFEBOARD o SIMILAR, TOTAL M2 0.00
DE DIMENSIONES 625x2500 y e= 12,5 mm., CON SUSPENSION
METALICA, para descuelgües aprox. de 1 m.

MATERIAL

ud cantidad precio / m2 costo parcial cantidad


Utilizar en
obra
parantes 2 1/2" ud 1.06 5.640 5.978 0.00
clavos p/ fijación de 1" cto 0.04 2.370 0.095 0.00
tornillo 6x1 punta fina mill 0.04 6.930 0.256 0.00
cinta malla ml 2.00 0.063 0.127 0.00
fulminante marrón cal 22 cto 0.04 5.710 0.228 0.00
Cargamuertos parantes 3 5/8" ud 0.71 9.870 6.975 0.00
Muertos parantes 3 5/8" ud 0.71 9.870 6.975 0.00
tornillo 7x7/16 punta fina mill 0.005 6.260 0.031 0.00
pasta p/junta de planchas de drywall ( 1 balde ) kg 0.700 2.030 1.421 0.00
placa K762 ud 0.340 30.000 10.200 0.00

total materiales 32.29


M.O.
mano de obra de instalación m2 1.000 18.000 18.00

total M.O. 18.00


EQUIPOS Y HERRAMIENTAS

5% s/ M.O. % 0.005 18.000 0.09


total equipos y herramientas 0.09

TOTAL ITEM 50.38

FCR5 m2 CIELO RASO CON PLACA DE YESO PANEL REY DE 3/8", DE TOTAL M2 0.00
DIMENSIONES 1,22x2,44 m. CON SUSPENSION METALICA, para
descuelgües aproximados de 1,00 m.

MATERIAL

ud cantidad precio / m2 costo parcial cantidad


Utilizar en
obra
parantes 2 1/2" ud 1.06 5.640 5.978 0.00
clavos p/ fijación de 1" cto 0.04 2.370 0.095 0.00
tornillo 6x1 punta fina mill 0.04 6.930 0.256 0.00
cinta malla ml 2.00 0.063 0.127 0.00
fulminante marrón cal 22 cto 0.04 5.710 0.228 0.00
Cargamuertos parantes 3 5/8" ud 0.71 9.870 6.975 0.00
Muertos parantes 3 5/8" ud 0.71 9.870 6.975 0.00
tornillo 7x7/16 punta fina mill 0.005 6.260 0.031 0.00
pasta p/junta de planchas de drywall ( 1 balde ) kg 0.700 2.030 1.421 0.00
plancha panel Rey ST de 3/8" ud 0.340 15.770 5.362 0.00

total materiales 27.45


M.O.

mano de obra de instalación m2 1.000 18.000 18.00

total M.O. 18.00

EQUIPOS Y HERRAMIENTAS

5% s/ M.O. % 0.005 18.000 0.09


total equipos y herramientas 0.09

TOTAL ITEM 45.54

FCR6 m2 CIELO RASO CON PLACA DE YESO PANEL REY DE 3/8", DE TOTAL M2 0.00
DIMENSIONES 1,22x2,44 m. CON SUSPENSION METALICA, para
descuelgües aproximados de 1,00 m.

MATERIAL

ud cantidad precio / m2 costo parcial cantidad


Utilizar en
obra
parantes 2 1/2" ud 1.06 5.640 5.978 0.00
clavos p/ fijación de 1" cto 0.04 2.370 0.095 0.00
tornillo 6x1 punta fina mill 0.04 6.930 0.256 0.00
cinta malla ml 2.00 0.063 0.127 0.00
fulminante marrón cal 22 cto 0.04 5.710 0.228 0.00
Cargamuertos parantes 3 5/8" ud 0.71 9.870 6.975 0.00
Muertos parantes 3 5/8" ud 0.71 9.870 6.975 0.00
tornillo 7x7/16 punta fina mill 0.005 6.260 0.031 0.00
pasta p/junta de planchas de drywall ( 1 balde ) kg 0.700 2.030 1.421 0.00
plancha panel Rey ST de 3/8" ud 0.340 15.770 5.362 0.00

total materiales 27.45


M.O.

mano de obra de instalación m2 1.000 18.000 18.00

total M.O. 18.00

EQUIPOS Y HERRAMIENTAS

5% s/ M.O. % 0.005 18.000 0.09


total equipos y herramientas 0.09

TOTAL ITEM 45.54

CANTIDAD TOTAL DE MATERIALES - BLOQUE A Cant. Parcial P. unitario Parcial


angulo perimetral (0,4 mm ), de 3 m. ud 1,243.12 2.07 2,573.26
suspensión principal (0,3 mm), 3,66 m. ud 2,599.25 1.26 3,275.06
suspensión secundaria (0,27 mm/1220), 1,22 m. ud 4,124.90 1.14 4,702.39
suspensión terciario (0,27 mm/1220), 1,22 m. ud 4,124.90 0.94 3,877.41
fulminante verde cal. 22 (caja 100 ud.) ud 452.04 5.71 2,581.17
kit ( clavos + ganchos ) ( caja 100 ud.) ud 79.11 13.65 1,079.82
alambre galvanizado # 14 ( 36 m / kg ) kg 113.01 2.80 316.43
baldosa OWA COSMOS ud 10,172.96 11.97 121,770.33
baldosa CONSTELLATION ud 3,436.41 22.18 76,219.62
baldosa de fibra mineral OWA TACLA ud 2,212.17 8.84 19,555.57
Total 235,951.05