VOLUMEN DE BLOQUES (MT2): 3220.00 TIEMPO: 75 dias / 26 dias x mes =
RENDIMIENTO : 14.50 MT2/ DIA (1 ALB. + 0.5 PEON) @ B/. 5.90/HORA CAL. + B/. 4.39/HORA PEON
PERSONAL: 3 CAL. (43.50 MT2/ DIA) (5.90 HORA X 48 HORAS SEMANALES = B/. 283.20
2 AYUD. (4.39/HORA X 48 HORA SEMANALES= B/. 210.72 X 4.333 semanas/mes=
M.O. SIN
PRESTACIONES LIQUIDACIONES
TOTAL M.O.
PRESTACIONES (70 %)
(SALARIOS+ PREST.)
DESCUENTOS AL TRABAJADOR
APORTACION PATRONAL
SEG. SOC. SEG. EDUC. RIESGOS PROF.
I.S.R. 2.90 % SEG.SOC. 9.75 % SEG. EDUC. 1.25 PATRONAL PATRONAL 4.089 %
% 12.25 % 1.5 %
B/. 307.96 B/. 1,548.96 B/. 198.58 B/. 1,946.13 B/. 238.30 B/. 649.61
TOTALES MANO DE
OBRA
B/. 24,889.89