Está en la página 1de 5

ANALISIS DE COSTO UNITARIO PARA PEGA DE BLOQU

06/01/2021
VOLUMEN DE BLOQUES (MT2): 3220.00 TIEMPO: 75 dias / 26 dias x mes =
RENDIMIENTO : 14.50 MT2/ DIA (1 ALB. + 0.5 PEON) @ B/. 5.90/HORA CAL. + B/. 4.39/HORA PEON
PERSONAL: 3 CAL. (43.50 MT2/ DIA) (5.90 HORA X 48 HORAS SEMANALES = B/. 283.20
2 AYUD. (4.39/HORA X 48 HORA SEMANALES= B/. 210.72 X 4.333 semanas/mes=

RENDIMIENTO TIEMPO EN DIAS COSTO X DIA DE SALARIOS DE PERSONAL


CANTIDAD MT2
DIARIO (MT2) LABORABLES PERSONAL SIN PRESTACIONES

3220.00 42.93 75.00 B/. 211.82 B/. 15,886.78

M.O. SIN
PRESTACIONES LIQUIDACIONES

SALARIOS DE VACACIONES PRIMA ANT. INDEMNIZACION 6.54


PERSONAL 9.10 % XIII MES 8.33 % 1.923 % %
B/. 15,886.78 B/. 1,445.70 B/. 1,323.37 B/. 305.50 B/. 1,039.00

DATO: 1 SACO DE CEMENTO PEGA 85 BLOQUES. (desperdicio incluido) Por lo tanto

ACTIVIDAD UNIDAD PROVEEDOR


BLOQUES DE 4" ( 38,640 BLOQUES) BLOQUE COCHEZ
CEMENTO DE PEGA (350 sacos) SACO COCHEZ
ARENA (107 yd3) YD3 COCHEZ
ANDAMIOS Y EQUIPO (14 MARCOS) GLOBAL
MANO DE OBRA
EQUIPO DE PROTECCION PERSONAL

COSTO UNITARIO : B/. 79,963.09 / 3220 MT2 = B/. 24.83


COSTO UNIT.
% X MT2
BLOQUES 40.33 B/. 10.02
CEMENTO 5.18 B/. 1.29
ARENA 1.30 B/. 0.32
ANDAMIOS Y EQUIPO 1.34 B/. 0.33
SALARIOS + E.P.P. 36.14 B/. 8.97
UTILIDAD 13.04 B/. 3.24
97.32 B/. 24.17
O PARA PEGA DE BLOQUES DE 3", 4" Y 6"

PO: 75 dias / 26 dias x mes = 2.8846153846154 MESES


9/HORA PEON
x 4.333 semanas/mes = B/. 1,227.11 X 3 cal. = B/. 3,681.32 B/.3681.32 X 2.8846 MESES =

B/. 913.05 X 2 ayud.= B/. 1,826.10 B/. 1826.10 X 2.8846 MESES =

TOTAL M.O.
PRESTACIONES (70 %)
(SALARIOS+ PREST.)

B/. 11,120.74 B/. 27,007.52

DESCUENTOS AL TRABAJADOR
APORTACION PATRONAL
SEG. SOC. SEG. EDUC. RIESGOS PROF.
I.S.R. 2.90 % SEG.SOC. 9.75 % SEG. EDUC. 1.25 PATRONAL PATRONAL 4.089 %
% 12.25 % 1.5 %
B/. 307.96 B/. 1,548.96 B/. 198.58 B/. 1,946.13 B/. 238.30 B/. 649.61

38640 bloq./ 85 bloq.x saco = 454.6 sacos de cem.

COSTO UNIT. CANTIDAD COSTO TOTAL


B/. 0.78 38640.00 B/. 30,139.20
B/. 8.50 455.00 B/. 3,867.50
B/. 48.50 20.00 B/. 970.00
B/. 1,000.00 1.00 B/. 1,000.00
B/. 27,007.52
B/. 2,000.00
B/. 64,984.22
ITBMS (7 %) B/. 4,548.90
B/. 69,533.12
UTILIDAD (15 %) B/. 10,429.97
GRAN TOTAL B/. 79,963.09
NOTA: Costo unitario sin fianzas, seguros, gastos de oficina de campo ,
salarios administrativos, luz,agua, etc.
B/. 10,619.18
B/. 5,267.59

TOTALES MANO DE
OBRA
B/. 24,889.89

También podría gustarte